CN218850264U - Temporary hoisting point tool for single piles laid by submarine cables - Google Patents

Temporary hoisting point tool for single piles laid by submarine cables Download PDF

Info

Publication number
CN218850264U
CN218850264U CN202222628734.7U CN202222628734U CN218850264U CN 218850264 U CN218850264 U CN 218850264U CN 202222628734 U CN202222628734 U CN 202222628734U CN 218850264 U CN218850264 U CN 218850264U
Authority
CN
China
Prior art keywords
groove steel
steel sheet
hoisting point
fixedly connected
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222628734.7U
Other languages
Chinese (zh)
Inventor
苏志龙
张其
熊涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Baosheng Changfei Offshore Engineering Co ltd
Original Assignee
Baosheng Changfei Offshore Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Baosheng Changfei Offshore Engineering Co ltd filed Critical Baosheng Changfei Offshore Engineering Co ltd
Priority to CN202222628734.7U priority Critical patent/CN218850264U/en
Application granted granted Critical
Publication of CN218850264U publication Critical patent/CN218850264U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses a submarine cable lays interim hoisting point frock of single pile, including the single groove steel sheet, the one end fixedly connected with mounting panel of single groove steel sheet, the mounting hole has all been seted up to the left and right sides of mounting panel, the other end fixedly connected with roof of single groove steel sheet, the front end fixedly connected with reinforcing plate of single groove steel sheet, the equal fixedly connected with lug in both sides of single groove steel sheet. The utility model designs the single-groove steel plate, which is fixed on the single pile when needed, and the pulley is hung on the single pile to be used as a temporary hoisting point, so that the submarine cable pulls the single pile platform along with the traction steel wire rope, thereby saving the waiting time, shortening the project construction period and saving the construction cost; the application range is large, and the fan can be applied to the basis of a fan without a fan tower; the bending radius of the submarine cable is met when the certain height is reached; the installation and the disassembly are convenient.

Description

Temporary hoisting point tool for single piles for laying submarine cables
Technical Field
The utility model relates to a submarine cable lays technical field, specifically is a submarine cable lays interim hoisting point frock of single pile.
Background
The general construction process of present sea cable laying fan platform adopts after waiting the fan installation, and the tower section of thick bamboo is worn by the fan platform of going on of cable ship again, and current technical scheme limitation is stronger, and when the use of reality, the fan installation ship of a wind field construction usefulness drops into limitedly, adds the construction progress requirement, and the progress that lays the sea cable requires highly to lead to holistic work efficiency to hang down, lead to the construction progress slow, inconvenient people use, and the practicality is low. In view of the related technical problems, no effective solution has been proposed at present.
SUMMERY OF THE UTILITY MODEL
Aiming at the problems in the related art, the utility model provides a temporary hoisting point tool for laying a single pile of a submarine cable, which aims to overcome the technical problems in the prior related art, the utility model aims to design a single-groove steel plate, fix the single pile when needed, hang a pulley on the single pile, and use the single pile as a temporary hoisting point to enable the submarine cable to drag a single pile platform along with a traction steel wire rope, thereby saving the waiting time, being capable of constructing in advance, shortening the project construction period and saving the construction cost; the application range is large, and the fan can be applied to the basis of a fan without a fan tower; reaching a certain height to meet the bending radius of the submarine cable; the installation and the disassembly are convenient.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a sea cable lays interim hoisting point frock of single pile, includes the single groove steel sheet, the one end fixedly connected with mounting panel of single groove steel sheet, the mounting hole has all been seted up to the left and right sides of mounting panel, the other end fixedly connected with roof of single groove steel sheet, the front end fixedly connected with reinforcing plate of single groove steel sheet, the equal fixedly connected with lug in both sides of single groove steel sheet.
Preferably, the single-groove steel plate is arranged in a rectangular structure.
Preferably, the reinforcing plate is provided with a plurality of reinforcing plates which are arranged at equal intervals.
Preferably, the mounting plate, the top plate, the reinforcing plate and the lifting lug are all made of metal materials.
Preferably, the outer surfaces of the mounting plate, the top plate, the reinforcing plate and the lifting lug are coated with anti-corrosion layers.
Preferably, the height of the single-channel steel plate 1 is greater than 2m.
Compared with the prior art, the beneficial effects of the utility model are that:
the utility model relates to a submarine cable lays single pile temporary hoisting point frock, through setting up single groove steel sheet and single pile structure through the bolt fastening, simple firm, easy dismounting, through hanging the pulley on the lug of single groove steel sheet, as temporary hoisting point, make the submarine cable drag the single pile platform along with drawing wire rope, save latency, can be under construction in advance, shorten project construction period, practice thrift construction cost; the application range is large, and the fan can be applied to the basis of a fan without a fan tower; reach a certain height, satisfy the bending radius of submarine cable.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention.
In the reference symbols: 1. a single-groove steel plate; 2. mounting a plate; 3. mounting holes; 4. a top plate; 5. a reinforcing plate; 6. and (7) lifting lugs.
Detailed Description
The technical solution in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention.
Examples
Please refer to fig. 1, the utility model provides a technical scheme of temporary hoisting point frock of sea cable laying single pile: the utility model provides a sea cable lays interim hoisting point frock of single pile, including single groove steel sheet 1, single groove steel sheet 1's one end fixedly connected with mounting panel 2, mounting hole 3 has all been seted up to the left and right sides of mounting panel 2, it is concrete, mounting panel 2 is fixed through bolt and single pile structure, it is simple firm, improve single groove steel sheet 1's stability, single groove steel sheet 1's other end fixedly connected with roof 4, single groove steel sheet 1's front end fixedly connected with reinforcing plate 5, it is concrete, reinforcing plate 5 is provided with three and equidistance setting, reinforcing plate 5 effectively improves single groove steel sheet 1's fastness, the equal fixedly connected with lug 6 in single groove steel sheet 1's both sides.
Referring to fig. 1, further, the single-channel steel plate 1 is arranged in a rectangular structure.
Referring to fig. 1, further, a plurality of reinforcing plates 5 are disposed at equal intervals.
In this embodiment, reinforcing plate 5 is provided with and the equidistance setting, and reinforcing plate 5 can improve the structural strength of single flute steel sheet 1, satisfies the requirement of dragging indeformable.
Further, the mounting plate 2, the top plate 4, the reinforcing plate 5 and the lifting lug 6 are all made of metal materials.
In the present embodiment, the mounting plate 2, the top plate 4, the reinforcing plate 5 and the lifting lugs 6 are made of steel materials.
Further, the outer surfaces of the mounting plate 2, the top plate 4, the reinforcing plate 5 and the lifting lug 6 are coated with anti-corrosion layers.
In the embodiment, the anti-corrosion layer is arranged, so that the mounting plate 2, the top plate 4, the reinforcing plate 5 and the lifting lug 6 are effectively prevented from being corroded by external impurities, and the service life of the mounting plate 2, the top plate 4, the reinforcing plate 5 and the lifting lug 6 is prolonged.
Further, the height of the single-channel steel plate 1 is more than 2m.
Specifically, the utility model discloses a theory of operation and use flow: the single-groove steel plate 1 is fixed with a single-pile structure through bolts, the single-groove steel plate is simple and stable, the stability of the single-groove steel plate 1 is improved, a pulley is hung on the single-groove steel plate and used as a temporary hoisting point, a submarine cable is pulled to a single-pile platform along with a pull steel wire rope, specifically, the steel wire rope is threaded from a single-pile J-shaped pipe and is bound and connected with a submarine cable head, the submarine cable is made to pass through the J-shaped pipe through a winch on a ship and arrives at the single-pile platform, the submarine cable is pulled to be in place according to the design allowance of the submarine cable, the waiting time is saved, the construction can be carried out in advance, the project construction period is shortened, and the construction cost is saved; the application range is large, and the fan can be applied to the basis of a fan without a fan tower; the bending radius of the submarine cable is met when the certain height is reached; the installation and the disassembly are convenient.
In the description of the present invention, it is to be understood that the terms "coaxial", "bottom", "one end", "top", "middle", "other end", "upper", "one side", "top", "inner", "front", "center", "both ends", and the like, indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, and do not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be construed as limiting the present invention.
In the present invention, unless otherwise expressly stated or limited, the terms "mounted," "disposed," "connected," "fixed," "screwed" and the like are to be construed broadly, e.g., as meaning fixedly connected, detachably connected, or integrally formed; can be mechanically or electrically connected; they may be directly connected or indirectly connected through an intermediate medium, and may be connected through the inside of two elements or in an interaction relationship between two elements, unless otherwise specifically defined, and the specific meaning of the above terms in the present invention will be understood by those skilled in the art according to specific situations.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a sea cable lays interim hoisting point frock of single pile, its characterized in that, includes single groove steel sheet (1), one end fixedly connected with mounting panel (2) of single groove steel sheet (1), mounting hole (3) have all been seted up to the left and right sides of mounting panel (2), the other end fixedly connected with roof (4) of single groove steel sheet (1), front end fixedly connected with reinforcing plate (5) of single groove steel sheet (1), the equal fixedly connected with lug (6) in both sides of single groove steel sheet (1).
2. A temporary hoisting point tool for laying a single sea cable according to claim 1, wherein the single-groove steel plate (1) is arranged in a rectangular structure.
3. A temporary hoisting point tooling for laying sea cables as claimed in claim 1 wherein said reinforcing plates (5) are provided in several and equidistant positions.
4. A temporary hoisting point tooling for laying of sea cable mono-pile according to claim 1, characterized in that the mounting plate (2), the top plate (4), the reinforcing plate (5) and the lifting lug (6) are made of metal material.
5. A temporary hoisting point tooling for laying of sea cable mono-piles according to claim 1, characterized in that the outer surfaces of the mounting plate (2), the top plate (4), the reinforcing plate (5) and the lifting lugs (6) are coated with anti-corrosion layers.
6. A temporary hoisting point tooling for laying of sea cable mono-pile according to claim 1 characterized in that the height of the mono-channel steel plate (1) is more than 2m.
CN202222628734.7U 2022-10-08 2022-10-08 Temporary hoisting point tool for single piles laid by submarine cables Active CN218850264U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222628734.7U CN218850264U (en) 2022-10-08 2022-10-08 Temporary hoisting point tool for single piles laid by submarine cables

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222628734.7U CN218850264U (en) 2022-10-08 2022-10-08 Temporary hoisting point tool for single piles laid by submarine cables

Publications (1)

Publication Number Publication Date
CN218850264U true CN218850264U (en) 2023-04-11

Family

ID=87303268

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222628734.7U Active CN218850264U (en) 2022-10-08 2022-10-08 Temporary hoisting point tool for single piles laid by submarine cables

Country Status (1)

Country Link
CN (1) CN218850264U (en)

Similar Documents

Publication Publication Date Title
CN102444086B (en) Cable hanging system for inclined stay cable of bridge and cable hanging method for inclined stay cable of bridge
CN218850264U (en) Temporary hoisting point tool for single piles laid by submarine cables
CN201195661Y (en) Permanent deflection-proof sheet metal sling
CN202324567U (en) Moving type large-scale operation platform
CN100460740C (en) Integrated convex stretching type cable bridge frame for ship and marine engineering
CN211521362U (en) Aluminum profile lifting device
CN211338608U (en) Novel roof hangs balance arm and upper bracket connection structure
CN205953335U (en) Shape mould of preapring for an unfavorable turn of events is hoisted in equipment of electrolysis trough bottom plate
WO2022099759A1 (en) Corrosion-resistant endless sling
CN213450691U (en) Assembled wind power tower cylinder with wing wall
CN210396223U (en) Photovoltaic power plant shaft tower reinforcing apparatus
CN203079591U (en) Crane wall-attaching steel-structure switch connection support
CN111217274A (en) A hang in midair hoist that is used for assembled buckling restrained steel plate wall quick, high-efficient assembly
CN207846838U (en) A kind of prefabricated panel playing partition
CN207920108U (en) A kind of hanger structure of roof color steel plate lifting
CN202337633U (en) Lifting appliance for furnace door
CN201729565U (en) Combination pulley block lifting appliance device
CN211667294U (en) Horseshoe-shaped pipeline supporting piece
CN217148253U (en) Column pipeline hoisting device
CN220184250U (en) Concrete pole coupling mechanism
CN206466882U (en) A kind of specialty lifting wall lifting device
CN212315461U (en) Assembled PC component propelling movement fluid pressure type lift installation multiplexer utensil
CN211393459U (en) Cable installation device of construction elevator
CN212101742U (en) Jack-up gin pole suitable for water conservancy construction
CN203411256U (en) Non-dragging independent mast device for hoisting rigid steel pile

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant