CN218764521U - Heated air circulation's heating tunnel furnace - Google Patents

Heated air circulation's heating tunnel furnace Download PDF

Info

Publication number
CN218764521U
CN218764521U CN202223384112.0U CN202223384112U CN218764521U CN 218764521 U CN218764521 U CN 218764521U CN 202223384112 U CN202223384112 U CN 202223384112U CN 218764521 U CN218764521 U CN 218764521U
Authority
CN
China
Prior art keywords
heating
furnace body
furnace
several
circulation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202223384112.0U
Other languages
Chinese (zh)
Inventor
崔琰勇
岳现锋
张炎华
王立新
李育新
杨梦可
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Huike New Energy Co ltd
Original Assignee
Anhui Huike New Energy Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Huike New Energy Co ltd filed Critical Anhui Huike New Energy Co ltd
Priority to CN202223384112.0U priority Critical patent/CN218764521U/en
Application granted granted Critical
Publication of CN218764521U publication Critical patent/CN218764521U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Tunnel Furnaces (AREA)

Abstract

本实用新型提供一种热风循环的加热隧道炉,包括:底板;炉体,炉体固定于底板的顶部,炉体的两侧均开设有敞口;物料输送带,物料输送带设置于炉体的内部,且物料输送带的两端通过两个敞口延伸至炉体的外部;若干个循环加热框,若干个循环加热框均固定于炉体的内部。本实用新型提供的热风循环的加热隧道炉,通过循环加热框两侧的导热翅片进行热量导出,进一步对物料输送带的位置进行加热,充分的对余热气体进行利用,而且通过两组交叉设置的倾斜挡板,可以提高其气体在循环加热框内部流动的时间,进而提高换热充足性,不仅具有热风循环的功能,而且具有多次余热利用的功能,提高了加热隧道炉的节能环保性能。

Figure 202223384112

The utility model provides a heating tunnel furnace with hot air circulation, comprising: a bottom plate; a furnace body, the furnace body is fixed on the top of the bottom plate, and openings are opened on both sides of the furnace body; a material conveyor belt is arranged on the furnace body The inside of the furnace body, and the two ends of the material conveyor belt extend to the outside of the furnace body through two openings; several circulating heating frames, and several circulating heating frames are fixed inside the furnace body. The hot air circulation heating tunnel furnace provided by the utility model conducts heat export through the heat conduction fins on both sides of the circulation heating frame, further heats the position of the material conveyor belt, and fully utilizes the waste heat gas, and through two sets of cross settings The inclined baffle can increase the time for the gas to flow inside the circulating heating frame, thereby improving the adequacy of heat exchange. It not only has the function of hot air circulation, but also has the function of multiple waste heat utilization, which improves the energy-saving and environmental protection performance of the heating tunnel furnace .

Figure 202223384112

Description

一种热风循环的加热隧道炉A heating tunnel furnace with hot air circulation

技术领域technical field

本实用新型涉及加热隧道炉领域,尤其涉及一种热风循环的加热隧道炉。The utility model relates to the field of heating tunnel furnaces, in particular to a heating tunnel furnace with hot air circulation.

背景技术Background technique

隧道炉是通过热的传导、对流、辐射完成食品烘烤的隧道式机械设备;烘烤室为一狭长的隧道,隧道内有一条连续运转的输送系统。食品烤制时,食品通过输送链板、钢带或网带与电热元件或直燃燃烧棒之间产生相对运动,从而完成均匀烘烤和输送的工作。The tunnel furnace is a tunnel-type mechanical device that completes food baking through heat conduction, convection, and radiation; the baking chamber is a long and narrow tunnel, and there is a continuously operating conveying system in the tunnel. When the food is baked, the relative movement between the food through the conveying chain plate, steel belt or mesh belt and the electric heating element or the direct-fired combustion rod is completed, so as to complete the work of uniform baking and conveying.

在进行食品或其他物料的加热处理时,一般需要用到相应的隧道炉,通过隧道炉不仅可连续生产,而且生产效率高,节省人力,烘烤品质稳定。When heating food or other materials, it is generally necessary to use a corresponding tunnel furnace. Through the tunnel furnace, not only can continuous production be achieved, but also the production efficiency is high, manpower is saved, and the baking quality is stable.

相关技术中,现有的隧道炉在对物料进行加热时,一般采用高温气体流动的方式进行加热为了提高其隧道炉的节能性,一般加热后的余热气体,会采用循环的方式进行收集利用,然而现有的隧道炉的高温气体流动后,会通过管线迅速排出,气流在炉内的时间较多,不能充分起到换热作用,进而无法充分对气流中的高温进行利用。In the related technology, when the existing tunnel furnace heats the material, it generally adopts the way of high-temperature gas flow for heating. In order to improve the energy saving performance of the tunnel furnace, generally the waste heat gas after heating will be collected and utilized in a circular manner. However, after the high-temperature gas in the existing tunnel furnace flows, it will be quickly discharged through the pipeline, and the airflow spends a long time in the furnace, which cannot fully perform the heat exchange function, and thus cannot fully utilize the high temperature in the airflow.

因此,有必要提供一种热风循环的加热隧道炉解决上述技术问题。Therefore, it is necessary to provide a heating tunnel furnace with hot air circulation to solve the above technical problems.

实用新型内容Utility model content

本实用新型提供一种热风循环的加热隧道炉,解决了气流在炉内的时间较多,无法充分对气流中的高温进行利用,以至于不能充分起到换热作用的问题。The utility model provides a heating tunnel furnace with hot air circulation, which solves the problem that the airflow stays in the furnace for a long time, and the high temperature in the airflow cannot be fully utilized, so that the heat exchange function cannot be fully performed.

为解决上述技术问题,本实用新型提供的热风循环的加热隧道炉包括:In order to solve the above-mentioned technical problems, the heating tunnel furnace for hot air circulation provided by the utility model includes:

底板;floor;

炉体,所述炉体固定于所述底板的顶部,所述炉体的两侧均开设有敞口;A furnace body, the furnace body is fixed on the top of the bottom plate, and both sides of the furnace body are opened with openings;

物料输送带,所述物料输送带设置于所述炉体的内部,且物料输送带的两端通过两个敞口延伸至炉体的外部;A material conveyor belt, the material conveyor belt is arranged inside the furnace body, and the two ends of the material conveyor belt extend to the outside of the furnace body through two openings;

若干个循环加热框,若干个循环加热框均固定于所述炉体的内部,且若干个循环加热框均位于物料输送带的内部;A plurality of circulation heating frames, the several circulation heating frames are all fixed inside the furnace body, and the several circulation heating frames are all located inside the material conveyor belt;

加热组件,所述加热组件设置于所述炉体的顶部;a heating assembly, the heating assembly is arranged on the top of the furnace body;

循环组件,所述循环组件设置于所述炉体的内部,且所述加热组件、循环组件和若干个循环加热框通过管线连接;A circulation assembly, the circulation assembly is arranged inside the furnace body, and the heating assembly, circulation assembly and several circulation heating frames are connected by pipelines;

其中,所述循环加热框的两侧均固定连接有导热翅片,所述循环加热框内壁的顶部和底部均固定连接有交叉设置的倾斜挡板。Wherein, heat conduction fins are fixedly connected to both sides of the circulating heating frame, and inclined baffles arranged crosswise are fixedly connected to the top and bottom of the inner wall of the circulating heating frame.

优选的,所述底板顶部的两侧均通过支架转动连接有传送辊,两个传送辊通过物料输送带传动连接。Preferably, both sides of the top of the bottom plate are rotatably connected to conveying rollers through brackets, and the two conveying rollers are connected through a material conveying belt.

优选的,其中一个支架上固定连接有电机,所述电机的输出轴与该支架上的传送辊固定连接。Preferably, a motor is fixedly connected to one of the supports, and the output shaft of the motor is fixedly connected to the conveying roller on the support.

优选的,所述加热组件包括若干个固定于所述炉体正面的U型管,若干个U型管的一端分别与若干个循环加热框的内部连通,若干个U型管的另一端与炉体的内部连通,所述炉体的背面固定连接有排出管,所述排出管通过若干个支管与若干个循环加热框的内部连通。Preferably, the heating assembly includes several U-shaped tubes fixed on the front of the furnace body, one end of the several U-shaped tubes communicates with the interior of several circulating heating frames, and the other end of the several U-shaped tubes communicates with the inside of the furnace body. The interior of the furnace body is connected, and the back of the furnace body is fixedly connected with a discharge pipe, and the discharge pipe communicates with the interior of several circulating heating frames through several branch pipes.

优选的,所述加热组件包括固定于所述炉体顶部的加热箱,以及设置于炉体内壁两侧之间的均风板,所述均风板和加热箱通过若干个通管连通,所述炉体的背面固定连接有吸泵,所述吸泵的出气口和吸气口分别通过管道与加热箱和排出管的内部连通。Preferably, the heating assembly includes a heating box fixed on the top of the furnace body, and an air equalizing plate arranged between two sides of the inner wall of the furnace, and the air equalizing plate and the heating box are communicated through several through pipes, so that The back side of the furnace body is fixedly connected with a suction pump, and the gas outlet and suction port of the suction pump communicate with the inside of the heating box and the discharge pipe respectively through pipelines.

优选的,所述均风板的两侧分别滑动连接于所述炉体内壁的两侧。Preferably, the two sides of the air equalizing plate are respectively slidably connected to the two sides of the inner wall of the furnace.

优选的,所述炉体内壁的顶部转动连接有双向丝杆,所述双向丝杆两端的外表面均螺纹连接有螺纹块,所述螺纹块的底部和均风板的顶部之间铰接有连接杆,所述双向丝杆的一端贯穿炉体并延伸至炉体的外部。Preferably, the top of the inner wall of the furnace is rotatably connected with a two-way screw rod, the outer surfaces of both ends of the two-way screw rod are screwed with threaded blocks, and the bottom of the threaded block and the top of the air distribution plate are hinged to connect Rod, one end of the two-way screw rod passes through the furnace body and extends to the outside of the furnace body.

与相关技术相比较,本实用新型提供的热风循环的加热隧道炉具有如下有益效果:Compared with related technologies, the hot air circulation heating tunnel furnace provided by the utility model has the following beneficial effects:

本实用新型提供一种热风循环的加热隧道炉,通过加热组件可以对物料输送带上的物料进行加热处理,而且通过循环组件的设置,可以加热后的气体排至到若干个循环加热框中,通过循环加热框两侧的导热翅片进行热量导出,进一步对物料输送带的位置进行加热,充分的对余热气体进行利用,而且通过两组交叉设置的倾斜挡板,可以提高其气体在循环加热框内部流动的时间,进而提高换热充足性,不仅具有热风循环的功能,而且具有多次余热利用的功能,提高了加热隧道炉的节能环保性能。The utility model provides a heating tunnel furnace with hot air circulation. The material on the material conveyor belt can be heated through the heating assembly, and the heated gas can be discharged into several circulation heating frames through the setting of the circulation assembly. The heat is exported through the heat conduction fins on both sides of the circulating heating frame, and the position of the material conveyor belt is further heated to fully utilize the waste heat gas, and through two sets of cross-set inclined baffles, it can improve the circulation heating of the gas. It not only has the function of hot air circulation, but also has the function of multiple waste heat utilization, which improves the energy saving and environmental protection performance of the heating tunnel furnace.

附图说明Description of drawings

图1为本实用新型提供的热风循环的加热隧道炉的第一实施例的结构示意图;Fig. 1 is the structural representation of the first embodiment of the heating tunnel furnace of hot air circulation provided by the utility model;

图2为图1所示的热风循环的加热隧道炉的结构后视图;Fig. 2 is the rear view of the structure of the heating tunnel furnace of hot air circulation shown in Fig. 1;

图3为图1所示的热风循环的加热隧道炉的结构剖视图;Fig. 3 is the structural sectional view of the heating tunnel furnace of hot air circulation shown in Fig. 1;

图4为图3所示的循环加热框的截面侧视图;Fig. 4 is a cross-sectional side view of the circulating heating frame shown in Fig. 3;

图5为本实用新型提供的热风循环的加热隧道炉的第二实施例的结构示意图。Fig. 5 is a schematic structural view of the second embodiment of the hot air circulation heating tunnel furnace provided by the present invention.

图中标号:1、底板;2、炉体;3、物料输送带;4、循环加热框;41、导热翅片;42、倾斜挡板;5、传送辊;6、电机;7、U型管;8、排出管;9、加热箱;10、均风板;11、吸泵;12、双向丝杆;13、螺纹块;14、连接杆。Labels in the figure: 1. Bottom plate; 2. Furnace body; 3. Material conveyor belt; 4. Circulating heating frame; 41. Heat conduction fin; 42. Inclined baffle; 5. Conveying roller; 6. Motor; 7. U-shaped 8. Discharge pipe; 9. Heating box; 10. Evening plate; 11. Suction pump; 12. Two-way screw rod; 13. Thread block; 14. Connecting rod.

具体实施方式Detailed ways

下面结合附图和实施方式对本实用新型作进一步说明。Below in conjunction with accompanying drawing and embodiment the utility model is further described.

第一实施例first embodiment

请结合参阅图1、图2、图3、图4,其中,图1为本实用新型提供的热风循环的加热隧道炉的第一实施例的结构示意图;图2为图1所示的热风循环的加热隧道炉的结构后视图;图3为图1所示的热风循环的加热隧道炉的结构剖视图;图4为图3所示的循环加热框的截面侧视图。热风循环的加热隧道炉包括:Please refer to Fig. 1, Fig. 2, Fig. 3, Fig. 4 in conjunction, wherein, Fig. 1 is the structural representation of the first embodiment of the heating tunnel furnace of the hot air circulation provided by the utility model; Fig. 2 is the hot air circulation shown in Fig. 1 The rear view of the structure of the heating tunnel furnace; Fig. 3 is a cross-sectional view of the structure of the heating tunnel furnace shown in Fig. 1; Fig. 4 is a cross-sectional side view of the circulating heating frame shown in Fig. 3 . The heating tunnel furnace with hot air circulation includes:

底板1;bottom plate 1;

炉体2,炉体2固定于底板1的顶部,炉体2的两侧均开设有敞口;The furnace body 2, the furnace body 2 is fixed on the top of the bottom plate 1, and both sides of the furnace body 2 are provided with openings;

物料输送带3,物料输送带3设置于炉体2的内部,且物料输送带3的两端通过两个敞口延伸至炉体2的外部;The material conveyor belt 3 is arranged inside the furnace body 2, and the two ends of the material conveyor belt 3 extend to the outside of the furnace body 2 through two openings;

若干个循环加热框4,若干个循环加热框4均固定于炉体2的内部,且若干个循环加热框4均位于物料输送带3的内部;A plurality of circulating heating frames 4 are fixed inside the furnace body 2, and several circulating heating frames 4 are located inside the material conveyor belt 3;

加热组件,加热组件设置于炉体2的顶部;heating assembly, the heating assembly is arranged on the top of the furnace body 2;

循环组件,循环组件设置于炉体2的内部,且加热组件、循环组件和若干个循环加热框4通过管线连接;A circulation assembly, the circulation assembly is arranged inside the furnace body 2, and the heating assembly, the circulation assembly and several circulation heating frames 4 are connected by pipelines;

其中,循环加热框4的两侧均固定连接有导热翅片41,循环加热框4内壁的顶部和底部均固定连接有交叉设置的倾斜挡板42;Wherein, heat conduction fins 41 are fixedly connected to both sides of the circulating heating frame 4, and inclined baffles 42 arranged crosswise are fixedly connected to the top and bottom of the inner wall of the circulating heating frame 4;

通过加热组件可以对物料输送带3上的物料进行加热处理,而且通过循环组件的设置,可以加热后的气体排至到若干个循环加热框4中;The material on the material conveyor belt 3 can be heated through the heating component, and the heated gas can be discharged into several circulation heating frames 4 through the setting of the circulation component;

通过循环加热框4两侧的导热翅片41进行热量导出,进一步对物料输送带3的位置进行加热,充分的对余热气体进行利用;The heat is exported through the heat conduction fins 41 on both sides of the circulating heating frame 4, further heating the position of the material conveyor belt 3, and fully utilizing the waste heat gas;

通过两组交叉设置的倾斜挡板42,可以提高其气体在循环加热框4内部流动的时间,进而提高换热充足性,不仅具有热风循环的功能,而且具有多次余热利用的功能,提高了加热隧道炉的节能环保性能。Through two sets of inclined baffles 42 arranged crosswise, the time for the gas to flow inside the circulating heating frame 4 can be increased, thereby improving the adequacy of heat exchange. It not only has the function of hot air circulation, but also has the function of multiple waste heat utilization, which improves the Energy saving and environmental protection performance of heating tunnel furnace.

底板1顶部的两侧均通过支架转动连接有传送辊5,两个传送辊5通过物料输送带3传动连接;Both sides of the top of the bottom plate 1 are connected to the transmission roller 5 through the rotation of the bracket, and the two transmission rollers 5 are connected through the transmission of the material conveyor belt 3;

通过两个传送辊5的旋转,可以带动物料输送带3进行旋转运动,通过物料输送带3的旋转运动,即可带动需要加热的物料输送至炉体2的内部,进行加热处理。Through the rotation of the two conveying rollers 5, the material conveyor belt 3 can be driven to rotate. Through the rotation of the material conveyor belt 3, the material to be heated can be driven to be transported to the inside of the furnace body 2 for heating treatment.

其中一个支架上固定连接有电机6,电机6的输出轴与该支架上的传送辊5固定连接;One of the brackets is fixedly connected with a motor 6, and the output shaft of the motor 6 is fixedly connected with the transmission roller 5 on the bracket;

电机6与外界的电源和控制开关连接,为正反转电动机,采用现有技术的连接方式和编码方式进行设置,用于带动其中一个传送辊5进行旋转,进而带动物料输送带3进行旋转运动。The motor 6 is connected with an external power source and a control switch, and is a positive and negative motor, which is set by using the connection method and coding method of the prior art, and is used to drive one of the conveying rollers 5 to rotate, and then to drive the material conveyor belt 3 to rotate .

加热组件包括若干个固定于炉体2正面的U型管7,若干个U型管7的一端分别与若干个循环加热框4的内部连通,若干个U型管7的另一端与炉体2的内部连通,炉体2的背面固定连接有排出管8,排出管8通过若干个支管与若干个循环加热框4的内部连通;The heating assembly includes several U-shaped tubes 7 fixed on the front of the furnace body 2, one end of the several U-shaped tubes 7 communicates with the interior of several circulating heating frames 4, and the other end of the several U-shaped tubes 7 connects with the furnace body 2. The internal communication of the furnace body 2 is fixedly connected with a discharge pipe 8, and the discharge pipe 8 communicates with the interior of several circulating heating frames 4 through several branch pipes;

通过U型管7的设置,用于将炉体2内部加热后的气体排至的若干个循环加热框4中,通过加热框4对物料输送带3上的物料进行二次加热,充分的余热气体进行利用,而且利用后的气体排至到排出管8中,等待加热组件的收集。Through the arrangement of the U-shaped tube 7, it is used to discharge the heated gas inside the furnace body 2 into several circulating heating frames 4, and the materials on the material conveyor belt 3 are reheated through the heating frame 4, so that sufficient waste heat The gas is utilized, and the utilized gas is discharged into the discharge pipe 8, waiting for the collection of the heating assembly.

加热组件包括固定于炉体2顶部的加热箱9,以及设置于炉体2内壁两侧之间的均风板10,均风板10和加热箱9通过若干个通管连通,炉体2的背面固定连接有吸泵11,吸泵11的出气口和吸气口分别通过管道与加热箱9和排出管8的内部连通;The heating assembly includes a heating box 9 fixed on the top of the furnace body 2, and an air uniform plate 10 arranged between both sides of the inner wall of the furnace body 2. The air uniform plate 10 and the heating box 9 are communicated through several through pipes. The back side is fixedly connected with a suction pump 11, and the air outlet and suction port of the suction pump 11 communicate with the inside of the heating box 9 and the discharge pipe 8 through pipes respectively;

通过吸泵11的设置,可以将排出管8内部的余热气体进行吸收,并且排至到加热箱9中进行循环加热,加热后的气体通过管道排至到均风板10中,通过均风板10均匀排出,对物料输送带3上的物料进行加热处理。Through the setting of the suction pump 11, the waste heat gas inside the discharge pipe 8 can be absorbed, and discharged to the heating box 9 for circulation heating, the heated gas is discharged to the air uniform plate 10 through the pipeline, and passed 10 is evenly discharged, and the material on the material conveyor belt 3 is heated.

本实用新型提供的热风循环的加热隧道炉的工作原理如下:The working principle of the heating tunnel furnace with hot air circulation provided by the utility model is as follows:

通过吸泵11的启动,可以将排出管8内部的余热气体进行吸收,并且排至到加热箱9中进行循环加热,加热后的气体通过管道排至到均风板10中,通过均风板10均匀排出,对物料输送带3上的物料进行加热处理,加热处理后的余热气体通过若干个U型管7排至到若干个循环加热框4中,通过循环加热框4两侧的导热翅片41进行热量导出,进一步对物料输送带3的位置进行加热,充分的对余热气体进行利用,并且通过两组交叉设置的倾斜挡板42,可以提高其气体在循环加热框4内部流动的时间,进而提高换热时间的充足性,换热后的气体,再次排进排出管8中,等待抽取。By starting the suction pump 11, the waste heat gas inside the discharge pipe 8 can be absorbed and discharged into the heating box 9 for circulation heating. 10 is evenly discharged, and the material on the material conveyor belt 3 is heated. After the heat treatment, the waste heat gas is discharged into several circulating heating frames 4 through several U-shaped tubes 7, and passes through the heat conducting fins on both sides of the circulating heating frame 4. The sheet 41 conducts heat export, further heats the position of the material conveyor belt 3, fully utilizes the waste heat gas, and through two sets of inclined baffles 42 arranged crosswise, the time for the gas to flow inside the circulating heating frame 4 can be increased , and further improve the adequacy of the heat exchange time, and the gas after heat exchange is discharged into the discharge pipe 8 again, waiting to be extracted.

第二实施例second embodiment

请结合参阅图5,基于本申请的第一实施例提供的热风循环的加热隧道炉,本申请的第二实施例提出另一种热风循环的加热隧道炉。第二实施例仅仅是第一实施例优选的方式,第二实施例的实施对第一实施例的单独实施不会造成影响。Please refer to FIG. 5 , based on the hot air circulation heating tunnel furnace provided in the first embodiment of the present application, the second embodiment of the present application proposes another hot air circulation heating tunnel furnace. The second embodiment is only a preferred mode of the first embodiment, and the implementation of the second embodiment will not affect the independent implementation of the first embodiment.

具体的,本申请的第二实施例提供的热风循环的加热隧道炉的不同之处在于,均风板10的两侧分别滑动连接于炉体2内壁的两侧;Specifically, the difference of the heating tunnel furnace with hot air circulation provided in the second embodiment of the present application is that both sides of the air equalizing plate 10 are respectively slidably connected to both sides of the inner wall of the furnace body 2;

通过均风板10采用滑动的方式连接,便于均风板10上下的运动,与物料输送带3之间的间距进行调节,而且通管采用伸缩软管。The air equalizing plate 10 is connected in a sliding manner, which facilitates the up and down movement of the air equalizing plate 10, and the distance between the air equalizing plate 10 and the material conveyor belt 3 is adjusted, and the duct adopts a telescopic hose.

炉体2内壁的顶部转动连接有双向丝杆12,双向丝杆12两端的外表面均螺纹连接有螺纹块13,螺纹块13的底部和均风板10的顶部之间铰接有连接杆14,双向丝杆12的一端贯穿炉体2并延伸至炉体2的外部;The top of the inner wall of the furnace body 2 is rotatably connected with a two-way screw rod 12, and the outer surfaces of both ends of the two-way screw rod 12 are screwed with a threaded block 13, and a connecting rod 14 is hinged between the bottom of the threaded block 13 and the top of the air distribution plate 10, One end of the two-way screw rod 12 runs through the furnace body 2 and extends to the outside of the furnace body 2;

通过手部对双向丝杆12的旋转,可以带动两个螺纹块13相对或相离方向运动,进而可以带动两个连接杆14扇形驱动,最终可以带动均风板10上下运动,对物料输送带3之间的距离进行调节,进而提高其加热效果。Through the rotation of the two-way screw rod 12 by the hand, the two threaded blocks 13 can be driven to move relative to or away from each other, and then the two connecting rods 14 can be driven to fan-shaped drive, and finally the air equalizing plate 10 can be driven to move up and down, and the material conveyor belt 3 to adjust the distance, thereby improving its heating effect.

以上仅为本实用新型的实施例,并非因此限制本实用新型的专利范围,凡是利用本实用新型说明书及附图内容所作的等效结构或等效流程变换,或直接或间接运用在其它相关的技术领域,均同理包括在本实用新型的专利保护范围内。The above are only embodiments of the present utility model, and are not intended to limit the patent scope of the present utility model. Any equivalent structure or equivalent flow conversion made by using the specification of the utility model and the contents of the accompanying drawings, or directly or indirectly used in other relevant Technical fields are all included in the scope of patent protection of the utility model in the same way.

Claims (7)

1.一种热风循环的加热隧道炉,其特征在于,包括:1. A heating tunnel furnace for hot air circulation, characterized in that it comprises: 底板(1);bottom plate (1); 炉体(2),所述炉体(2)固定于所述底板(1)的顶部,所述炉体(2)的两侧均开设有敞口;A furnace body (2), the furnace body (2) is fixed on the top of the bottom plate (1), and both sides of the furnace body (2) are provided with openings; 物料输送带(3),所述物料输送带(3)设置于所述炉体(2)的内部,且物料输送带(3)的两端通过两个敞口延伸至炉体(2)的外部;A material conveyor belt (3), the material conveyor belt (3) is arranged inside the furnace body (2), and the two ends of the material conveyor belt (3) extend to the furnace body (2) through two openings external; 若干个循环加热框(4),若干个循环加热框(4)均固定于所述炉体(2)的内部,且若干个循环加热框(4)均位于物料输送带(3)的内部;A plurality of circulation heating frames (4), the plurality of circulation heating frames (4) are all fixed inside the furnace body (2), and the several circulation heating frames (4) are all located inside the material conveyor belt (3); 加热组件,所述加热组件设置于所述炉体(2)的顶部;a heating assembly, the heating assembly is arranged on the top of the furnace body (2); 循环组件,所述循环组件设置于所述炉体(2)的内部,且所述加热组件、循环组件和若干个循环加热框(4)通过管线连接;A circulation assembly, the circulation assembly is arranged inside the furnace body (2), and the heating assembly, circulation assembly and several circulation heating frames (4) are connected by pipelines; 其中,所述循环加热框(4)的两侧均固定连接有导热翅片(41),所述循环加热框(4)内壁的顶部和底部均固定连接有交叉设置的倾斜挡板(42)。Wherein, both sides of the circulating heating frame (4) are fixedly connected with heat conduction fins (41), and the top and bottom of the inner wall of the circulating heating frame (4) are fixedly connected with inclined baffles (42) arranged crosswise. . 2.根据权利要求1所述的热风循环的加热隧道炉,其特征在于,所述底板(1)顶部的两侧均通过支架转动连接有传送辊(5),两个传送辊(5)通过物料输送带(3)传动连接。2. The heating tunnel furnace of hot air circulation according to claim 1, characterized in that, both sides of the top of the bottom plate (1) are connected with transfer rollers (5) through bracket rotation, and the two transfer rollers (5) pass through Material conveying belt (3) transmission connection. 3.根据权利要求2所述的热风循环的加热隧道炉,其特征在于,其中一个支架上固定连接有电机(6),所述电机(6)的输出轴与该支架上的传送辊(5)固定连接。3. The heating tunnel furnace of hot air circulation according to claim 2, characterized in that, a motor (6) is fixedly connected to one of the supports, and the output shaft of the motor (6) is connected to the conveying roller (5) on the support. ) fixed connection. 4.根据权利要求1所述的热风循环的加热隧道炉,其特征在于,所述加热组件包括若干个固定于所述炉体(2)正面的U型管(7),若干个U型管(7)的一端分别与若干个循环加热框(4)的内部连通,若干个U型管(7)的另一端与炉体(2)的内部连通,所述炉体(2)的背面固定连接有排出管(8),所述排出管(8)通过若干个支管与若干个循环加热框(4)的内部连通。4. The heating tunnel furnace with hot air circulation according to claim 1, characterized in that, the heating assembly comprises several U-shaped tubes (7) fixed on the front of the furnace body (2), and several U-shaped tubes One end of (7) communicates with the inside of several circulating heating frames (4) respectively, and the other end of several U-shaped pipes (7) communicates with the inside of the furnace body (2), and the back of the furnace body (2) is fixed A discharge pipe (8) is connected, and the discharge pipe (8) communicates with the interior of several circulation heating frames (4) through several branch pipes. 5.根据权利要求4所述的热风循环的加热隧道炉,其特征在于,所述加热组件包括固定于所述炉体(2)顶部的加热箱(9),以及设置于炉体(2)内壁两侧之间的均风板(10),所述均风板(10)和加热箱(9)通过若干个通管连通,所述炉体(2)的背面固定连接有吸泵(11),所述吸泵(11)的出气口和吸气口分别通过管道与加热箱(9)和排出管(8)的内部连通。5. The heating tunnel furnace with hot air circulation according to claim 4, characterized in that, the heating assembly comprises a heating box (9) fixed on the top of the furnace body (2), and is arranged on the furnace body (2) The air uniform plate (10) between the two sides of the inner wall, the air uniform plate (10) and the heating box (9) are connected through several through pipes, and the back of the furnace body (2) is fixedly connected with a suction pump (11 ), the gas outlet and the suction port of the suction pump (11) communicate with the inside of the heating box (9) and the discharge pipe (8) through pipelines respectively. 6.根据权利要求5所述的热风循环的加热隧道炉,其特征在于,所述均风板(10)的两侧分别滑动连接于所述炉体(2)内壁的两侧。6. The heating tunnel furnace with hot air circulation according to claim 5, characterized in that, the two sides of the air equalizing plate (10) are respectively slidably connected to the two sides of the inner wall of the furnace body (2). 7.根据权利要求6所述的热风循环的加热隧道炉,其特征在于,所述炉体(2)内壁的顶部转动连接有双向丝杆(12),所述双向丝杆(12)两端的外表面均螺纹连接有螺纹块(13),所述螺纹块(13)的底部和均风板(10)的顶部之间铰接有连接杆(14),所述双向丝杆(12)的一端贯穿炉体(2)并延伸至炉体(2)的外部。7. The heating tunnel furnace with hot air circulation according to claim 6, characterized in that, the top of the inner wall of the furnace body (2) is rotatably connected with a two-way screw rod (12), and the two-way screw rod (12) at both ends A threaded block (13) is threaded on the outer surface, and a connecting rod (14) is hinged between the bottom of the threaded block (13) and the top of the air uniform plate (10), and one end of the two-way screw rod (12) It runs through the furnace body (2) and extends to the outside of the furnace body (2).
CN202223384112.0U 2022-12-16 2022-12-16 Heated air circulation's heating tunnel furnace Expired - Fee Related CN218764521U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202223384112.0U CN218764521U (en) 2022-12-16 2022-12-16 Heated air circulation's heating tunnel furnace

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202223384112.0U CN218764521U (en) 2022-12-16 2022-12-16 Heated air circulation's heating tunnel furnace

Publications (1)

Publication Number Publication Date
CN218764521U true CN218764521U (en) 2023-03-28

Family

ID=85683145

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202223384112.0U Expired - Fee Related CN218764521U (en) 2022-12-16 2022-12-16 Heated air circulation's heating tunnel furnace

Country Status (1)

Country Link
CN (1) CN218764521U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117925990A (en) * 2024-03-18 2024-04-26 内蒙古丰洲材料有限公司 Double-vehicle-position tunnel furnace

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117925990A (en) * 2024-03-18 2024-04-26 内蒙古丰洲材料有限公司 Double-vehicle-position tunnel furnace

Similar Documents

Publication Publication Date Title
CN105423749A (en) Energy-saving type split double-layer roller way electrical kiln for permanent magnetic ferrite sintering
CN106440732A (en) A food drying device
CN108951262A (en) A kind of energy-saving drying device for paper making equipment
CN103820963A (en) Setting machine with drying oven
CN203642642U (en) High-temperature heat pump reversible circulation drying machine
CN206832013U (en) A kind of textile cloth energy-saving dryer
CN218846849U (en) Energy-saving efficient continuous green brick roasting production kiln
CN208620749U (en) A kind of roller drying device
CN209443113U (en) A kind of induction aramid fiber continuous heat heating path
CN114438827B (en) A device and method for improving the foundation of the fan box in the drying part of the pulp machine
CN215302636U (en) Heat conversion circulating air tunnel furnace
CN215002911U (en) Ceramic roller high-temperature heating furnace
CN212035860U (en) Baking equipment for producing sea sedge crisp chips
CN209512456U (en) A double-sided automatic drying production line for ceramic bowls
CN223929359U (en) A tunnel furnace energy management system device
CN222406666U (en) Airflow circulation structure of rubber production drying equipment
CN222617530U (en) Energy-saving daily-use ceramic kiln
CN207180441U (en) A kind of heating furnace heat pipe type waste heat reclaiming device
CN207922784U (en) A kind of solid feed processing drying unit
CN207741531U (en) A kind of cycle baking oven for producing coil of strip
CN207113452U (en) A kind of heated-air circulation oven applied to pickling Treatment of Sludge
CN107388762B (en) Composite pollution-free drying device
CN208269640U (en) An infrared tunnel furnace
CN112079558A (en) Gas-electric hybrid heating furnace tempering furnace and heating method thereof
CN214132599U (en) A special drying furnace for oil pipes

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20230328