CN218758687U - Steel formwork for building - Google Patents

Steel formwork for building Download PDF

Info

Publication number
CN218758687U
CN218758687U CN202223015567.5U CN202223015567U CN218758687U CN 218758687 U CN218758687 U CN 218758687U CN 202223015567 U CN202223015567 U CN 202223015567U CN 218758687 U CN218758687 U CN 218758687U
Authority
CN
China
Prior art keywords
fixed
connecting plate
close
spliced pole
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202223015567.5U
Other languages
Chinese (zh)
Inventor
狄旭胜
蒋传艳
陈汉生
何宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Sheyu Construction Engineering Co ltd
Original Assignee
Anhui Sheyu Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Sheyu Construction Engineering Co ltd filed Critical Anhui Sheyu Construction Engineering Co ltd
Priority to CN202223015567.5U priority Critical patent/CN218758687U/en
Application granted granted Critical
Publication of CN218758687U publication Critical patent/CN218758687U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model belongs to the technical field of building templates, specifically disclose a steel formwork for building, including building steel formwork, the position that the building steel formwork back is close to one side is equipped with the spliced pole, is provided with the fixed slot on the spliced pole, and the position that the building steel formwork back is close to the opposite side is equipped with the connecting plate with the fixed slot mutual adaptation, evenly is provided with a plurality of fixed jacks on the connecting plate; be provided with the mount on the spliced pole, one side that the spliced pole is close to the mount is rotated and is connected with the screw rod, the screw rod passes the mount and is connected with the knob, threaded connection has the board of supporting on the screw rod, one side that the board is close to the spliced pole evenly is provided with a plurality ofly and the fixed inserted bar of the mutual adaptation of fixed jack, fixed inserted bar passes the spliced pole and inserts the fixed connection board in fixed jack, insert the fixed jack on the connecting plate through the fixed inserted bar that will support on the board, alright fix the connecting plate in the fixed slot, thereby link together two building steel templates, it is very convenient.

Description

Steel formwork for building
Technical Field
The utility model relates to a building templates technical field specifically is a steel template for building.
Background
The steel form is used for concrete placement fashioned steel form, except that the steel form has wooden form in addition, plywood template etc., current steel form when the installation, generally first with the steel form module, piece together, then utilize billet and bolt to be in the same place two steel form modules are fixed, but this kind of fixed mode is very loaded down with trivial details, when the installation, need use a plurality of bolts to lock the billet on two steel form modules, just can realize the connection of two steel form modules, the installation can waste staff's a large amount of operating time, and follow-up if need demolish it, when maintaining the change, still need demolish a large amount of screws, just can demolish the steel form, work efficiency has seriously been reduced.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a steel formwork for building to solve the problem that proposes among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: a steel formwork for construction comprises a steel formwork for construction, wherein a connecting column is arranged at a position, close to one side, of the back surface of the steel formwork for construction, a fixing groove is formed in the connecting column, a connecting plate matched with the fixing groove is arranged at a position, close to the other side, of the back surface of the steel formwork for construction, and a plurality of fixing insertion holes are uniformly formed in the connecting plate; be provided with the mount on the spliced pole, one side that the spliced pole is close to the mount is rotated and is connected with the screw rod, the screw rod passes the mount and is connected with the knob, threaded connection has the board of supporting on the screw rod, one side that the board is close to the spliced pole evenly is provided with a plurality ofly and the fixed inserted bar of the mutual adaptation of fixed jack, fixed inserted bar passes the spliced pole and inserts the fixed connection board in fixed jack, insert the fixed jack on the connecting plate through the fixed inserted bar that will support on the board, alright fix the connecting plate in the fixed slot, thereby link together two building steel templates, it is very convenient.
Preferably, one side of the abutting plate, which is close to the fixing frame, is symmetrically provided with positioning rods, and the positioning rods penetrate through the fixing frame and are connected with positioning blocks.
Preferably, the position of keeping away from the spliced pole at the building steel form back evenly is provided with a plurality of first screw.
Preferably, the connecting plate is provided with a plurality of connecting holes corresponding to first screw holes in the side edge of the fixed jack, and the first screw holes are used for installing the connecting plate.
Preferably, a bolt is arranged in the connecting hole, the bolt is screwed into the first screw hole to fix the connecting plate, and when the connecting plate is arranged in the first screw hole, the connecting plate is parallel to the building steel template.
Preferably, one side that the connecting plate is close to first screw evenly is provided with a plurality of second screws, and the second screw is the same with the quantity and the specification homogeneous phase of first screw, and the connecting hole on second screw and the connecting plate corresponds, can align connecting hole and second screw on the connecting plate, then utilizes the bolt to fix it for the connecting plate is the vertical state with the building steel form, is used for connecting the building steel form of corner.
Compared with the prior art, the beneficial effects of the utility model are that: the utility model discloses an insert the connecting plate in the fixed slot, then rotatory screw rod, utilize the screw rod to push down the backup plate, insert the fixed jack on the connecting plate through the fixed inserted bar that will support on the plate, alright fix the connecting plate in the fixed slot, thereby link together two building steel form, it is very convenient, only need the reverse rotation screw rod when needing to demolish, up push up the backup plate, take out the fixed inserted bar on the backup plate from fixed slot, thereby cancel building steel form's fixed, alright directly unpack building steel form apart, the novel operation of this use is very simple, and can realize quick assembly disassembly, the operating time of staff has been saved, thereby work efficiency has been improved.
Drawings
FIG. 1 is a schematic view of the three-dimensional structure of the present invention;
FIG. 2 is a schematic side view of the present invention;
fig. 3 is the schematic diagram of the connection plate dismantling structure of the present invention.
In the figure: 1. building a steel template; 2. connecting columns; 3. a fixed mount; 4. a connecting plate; 5. fixing the jack; 6. a bolt; 7. a resisting plate; 8. connecting holes; 9. positioning a rod; 10. a screw; 11. a knob; 12. positioning a block; 13. fixing grooves; 14. fixing the inserted rod; 15. a first screw hole; 16. and a second screw hole.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "vertical", "upper", "lower", "horizontal", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed in a specific orientation, and be operated, and thus should not be construed as limiting the present invention.
In the description of the present invention, it should also be noted that, unless otherwise explicitly specified or limited, the terms "disposed," "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning either a fixed connection, a removable connection, or an integral connection; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood according to specific situations by those skilled in the art.
Referring to fig. 1-3, the present invention provides a technical solution: a steel formwork for construction comprises a steel formwork 1 for construction, wherein a connecting column 2 is arranged at a position, close to one side, of the back surface of the steel formwork 1 for construction, a fixing groove 13 is formed in the connecting column 2, a connecting plate 4 matched with the fixing groove 13 is arranged at a position, close to the other side, of the back surface of the steel formwork 1 for construction, and a plurality of fixing insertion holes 5 are uniformly formed in the connecting plate 4; be provided with mount 3 on spliced pole 2, one side that spliced pole 2 is close to mount 3 is rotated and is connected with screw rod 10, and screw rod 10 passes mount 3 and is connected with knob 11, and threaded connection has on the screw rod 10 and supports board 7, supports board 7 and evenly is provided with a plurality of fixed inserted bars 14 with the mutual adaptation of fixed jack 5 in one side that is close to spliced pole 2, and fixed inserted bar 14 passes spliced pole 2 and inserts and establish fixed connection board 4 in fixed jack 5.
Furthermore, positioning rods 9 are symmetrically arranged on one side of the abutting plate 7 close to the fixing frame 3, and the positioning rods 9 penetrate through the fixing frame 3 and are connected with positioning blocks 12.
Further, the position of the back of the building steel formwork 1 far away from the connecting column 2 is evenly provided with a plurality of first screw holes 15.
Furthermore, a plurality of connecting holes 8 corresponding to first screw holes 15 are formed in the side edge of the fixing insertion hole 5 on the connecting plate 4, and the first screw holes 15 are used for installing the connecting plate 4.
Further, a bolt 6 is arranged in the connecting hole 8, the bolt 6 is screwed into the first screw hole 15 to fix the connecting plate 4, and when the connecting plate 4 is installed in the first screw hole 15, the connecting plate 4 is parallel to the building steel formwork 1.
Further, one side that connecting plate 4 is close to first screw 15 evenly is provided with a plurality of second screw 16, and second screw 16 is the same with first screw 15's quantity and specification homogeneous phase, and second screw 16 corresponds with connecting hole 8 on the connecting plate 4, can align connecting hole 8 on the connecting plate 4 with second screw 16, then utilizes bolt 6 to fix it for connecting plate 4 is vertical state with building steel form 1, is used for connecting the building steel form 1 of corner.
The working principle is as follows: when connecting two building steel form 1, only need insert fixed slot 13 with connecting plate 4 earlier, then rotate knob 11 with the hand, make knob 11 drive screw rod 10 and rotate, utilize screw rod 10 to promote and will support board 7 downstream, make the locating lever 9 on supporting board 7 slide on mount 3, in the fixed jack 5 on supporting board 7 on fixed inserted bar 14 inserts connecting plate 4, alright fix connecting plate 4 in fixed slot 13, thereby link together two parallel building steel form 1, high durability and convenient use.
When two perpendicular building steel form 1 need be connected, only need earlier screw out from first screw 15 with bolt 6, cancel the fixed of connecting plate 4, then align connecting plate 4 connecting hole 8 with the second screw 16 of building steel form 1, then pass bolt 6 and connect empty in screw in second screw 16, be perpendicular with connecting plate 4 and building steel form 1, then alright insert fixed slot 13 with building steel form 1 vertically connecting plate 4, then rotatory screw rod 10, insert in fixed jack 5 with fixed inserted bar 14 on the board 7 of will supporting, alright accomplish the connection of two perpendicular building steel form 1.
Only need reverse rotation screw rod 10 when needing to demolish for screw rod 10 will support 7 up pushes away, will support fixed inserted bar 14 on the board 7 and take out from fixed slot, thereby cancel building steel form 1's fixing, alright directly unpack building steel form 1 apart, this novel operation of use is very simple, and can realize quick assembly disassembly, saved staff's operating time, thereby improved work efficiency.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. A steel formwork for construction is characterized in that: the building steel formwork comprises a building steel formwork (1), wherein a connecting column (2) is arranged at a position, close to one side, of the back surface of the building steel formwork (1), a fixing groove (13) is formed in the connecting column (2), a connecting plate (4) matched with the fixing groove (13) is arranged at a position, close to the other side, of the back surface of the building steel formwork (1), and a plurality of fixing insertion holes (5) are uniformly formed in the connecting plate (4); be provided with mount (3) on spliced pole (2), one side that spliced pole (2) are close to mount (3) is rotated and is connected with screw rod (10), screw rod (10) pass mount (3) and are connected with knob (11), threaded connection has department of support (7) on screw rod (10), department of support (7) is close to one side of spliced pole (2) and evenly is provided with a plurality of fixed inserted bars (14) with fixed jack (5) looks mutual adaptation, fixed inserted bar (14) pass spliced pole (2) and insert and establish fixed connection board (4) in fixed jack (5).
2. The steel form for construction as set forth in claim 1, wherein: positioning rods (9) are symmetrically arranged on one side, close to the fixing frame (3), of the abutting plate (7), and the positioning rods (9) penetrate through the fixing frame (3) and are connected with positioning blocks (12).
3. The steel form for construction as set forth in claim 1, wherein: the back of the building steel formwork (1) is far away from the connecting column (2) and is evenly provided with a plurality of first screw holes (15).
4. The steel form for construction as claimed in claim 1, wherein: and a plurality of connecting holes (8) corresponding to the first screw holes (15) are formed in the connecting plate (4) at the side edge of the fixed insertion hole (5).
5. The steel form for construction as set forth in claim 4, wherein: and a bolt (6) is arranged in the connecting hole (8), and the bolt (6) is screwed into the first screw hole (15) to fix the connecting plate (4).
6. The steel form for construction as set forth in claim 1, wherein: one side of the connecting plate (4) close to the first screw holes (15) is uniformly provided with a plurality of second screw holes (16), and the number and the specification of the second screw holes (16) are the same as those of the first screw holes (15).
CN202223015567.5U 2022-11-11 2022-11-11 Steel formwork for building Active CN218758687U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202223015567.5U CN218758687U (en) 2022-11-11 2022-11-11 Steel formwork for building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202223015567.5U CN218758687U (en) 2022-11-11 2022-11-11 Steel formwork for building

Publications (1)

Publication Number Publication Date
CN218758687U true CN218758687U (en) 2023-03-28

Family

ID=85648993

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202223015567.5U Active CN218758687U (en) 2022-11-11 2022-11-11 Steel formwork for building

Country Status (1)

Country Link
CN (1) CN218758687U (en)

Similar Documents

Publication Publication Date Title
CN218456238U (en) Mounting structure of truss integrated form switch board
CN112459468A (en) Template for building pouring construction
CN218758687U (en) Steel formwork for building
CN212901785U (en) Outer quick-witted mounting bracket of air conditioner convenient to dismouting
CN212583226U (en) Building construction template with connect fixed knot to construct
CN215168088U (en) Combined connecting and locking device for building template
CN212224730U (en) Reinforcing apparatus for building structure
CN209799003U (en) house steel structure supporting structure
CN210032246U (en) Plate-type embedded part of glass curtain wall
CN210326088U (en) Antenna convenient to dismantle
CN216110103U (en) Road bridge construction is with combination formula fender that encloses
CN215594944U (en) Novel template of pin-connected panel
CN210032108U (en) Adjustable steel structure factory building bearing base frame
CN217379222U (en) Framework bearing structure
CN212154139U (en) Building aluminum alloy template balcony integrated configuration
CN211899829U (en) Combined top support device convenient for building
CN212200771U (en) Quick connecting device for steel frame structure
CN216011073U (en) Outer machine construction of air conditioner is with reserving fixed bolster
CN217734367U (en) Steel corbel convenient to install and dismantle
CN217841142U (en) Corrugated structure with vertical self-locking function
CN217581247U (en) Adjustable building template connecting and locking device for building construction
CN219351579U (en) Photovoltaic board convenient to dismouting
CN219773615U (en) Square column buckle
CN220953900U (en) Frame building structure convenient to install
CN214402160U (en) But quick assembly disassembly's simple and easy room of steel construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant