CN218758087U - Clean room - Google Patents

Clean room Download PDF

Info

Publication number
CN218758087U
CN218758087U CN202223162987.6U CN202223162987U CN218758087U CN 218758087 U CN218758087 U CN 218758087U CN 202223162987 U CN202223162987 U CN 202223162987U CN 218758087 U CN218758087 U CN 218758087U
Authority
CN
China
Prior art keywords
wall body
clean room
supporting plate
support plate
panel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202223162987.6U
Other languages
Chinese (zh)
Inventor
杜安
张向洲
罗震
苏双喜
何亮峰
刘力源
张龙龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SY Technology Engineering and Construction Co Ltd
Original Assignee
SY Technology Engineering and Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SY Technology Engineering and Construction Co Ltd filed Critical SY Technology Engineering and Construction Co Ltd
Priority to CN202223162987.6U priority Critical patent/CN218758087U/en
Application granted granted Critical
Publication of CN218758087U publication Critical patent/CN218758087U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Residential Or Office Buildings (AREA)

Abstract

The utility model relates to a toilet technical field, in particular to toilet, include: the ceiling rail comprises a first wall body, a ceiling rail body and a top plate assembly, wherein the first wall body is provided with a first side face and a second side face which are oppositely arranged along the thickness and used for being connected with the top face of the first side face and the top face of the second side face, the top plate assembly is installed on the top face of the first wall body through the ceiling rail body and comprises a first supporting plate and a second supporting plate which are connected with each other, the ceiling rail body is located between the first wall body and the top plate assembly, a first bonding layer is arranged at the joint between the top plate assembly and the first supporting plate, a second bonding layer is arranged at the joint between the first wall body and the second supporting plate, the gap at the joint can be effectively sealed, the service environment of a clean room is better met, and the sealing and the service life of the gap are further prolonged.

Description

Clean room
Technical Field
The utility model relates to a toilet technical field, in particular to toilet.
Background
The clean room is a specially designed room which is designed to remove the pollutants such as micro-particles, harmful air, bacteria and the like in the air within a certain space range and control the indoor temperature, cleanliness, indoor pressure, airflow velocity and airflow distribution, noise vibration, illumination and static electricity within a certain required range. The clean room is generally installed in a prefabricated manner. Because the position of clean wallboard and roof concatenation is generally on the top of toilet, and the position is higher, also only carries out the shutoff with the mode of beating to glue during the shutoff, simple shutoff like this can not satisfy the environmental requirement of toilet, and shutoff life is shorter.
SUMMERY OF THE UTILITY MODEL
The utility model discloses a toilet for the relatively poor, the shorter problem of shutoff life of shutoff leakproofness.
In order to achieve the above purpose, the utility model provides a following technical scheme:
the utility model provides a clean room, include: a first wall body, a head rail body and a roof panel assembly;
the first wall body is provided with a first side surface, a second side surface and a top surface, the first side surface and the second side surface are oppositely arranged along the thickness, the top surface is used for connecting the first side surface and the second side surface, and the top plate assembly is arranged on the top surface of the first wall body through the sky rail body;
the sky rail body comprises a first supporting plate and a second supporting plate which are connected, the first supporting plate is parallel to the first side face of the first wall body, and the second supporting plate is perpendicular to the first side face and is positioned between the first wall body and the top plate assembly;
the roof subassembly with the junction is provided with first adhesive linkage between the first backup pad, the junction is provided with the second adhesive linkage between first wall body and the second backup pad.
The utility model discloses the increase is provided with the sky rail body that is used for installing first wall body and roof subassembly, and set up the sky rail body into first backup pad and the second backup pad that has mutually perpendicular, thereby above-mentioned structure has increased the area of contact between sky rail body and first wall body and the roof subassembly to a certain extent, great area of contact can increase the area that sets up of adhesive linkage promptly, specifically do, this application is provided with first adhesive linkage between first backup pad and roof subassembly, be provided with the second adhesive linkage between second backup pad and first wall body, and then improved the stability that first wall body and roof subassembly are connected when installing to sky rail body to a certain extent, increase the adhesive linkage in the sky rail body junction of first wall body and roof subassembly installation simultaneously, can effectually seal the gap of junction, better service environment who satisfies the toilet, and then promoted the sealed service life that keeps of gap department.
Optionally, the top plate assembly includes a top plate body and a second wall body, the top plate body is vertically disposed on the second wall body, the top plate body is connected to the second wall body, and the first adhesive layer is disposed between the second wall body and the first supporting plate.
Optionally, the second wall body includes a first panel and a second panel arranged in parallel, and a filler, and the filler is disposed in an accommodating space formed between the first panel and the second panel.
Optionally, the first panel is connected to the top plate body, and a third adhesive layer is disposed at a joint between the first panel and the top plate body.
Optionally, the sky rail body still includes the third backup pad, the third backup pad is on a parallel with first side, just the third backup pad with first backup pad is connected, the third backup pad with be provided with the fourth adhesive linkage between the first side.
Optionally, the sky rail body further includes a fourth supporting plate, the fourth supporting plate is disposed on a side of the second supporting plate away from the first supporting plate, an orthographic projection of the fourth supporting plate on the first wall body is located on the second side surface, and a fifth bonding layer is disposed on the fourth supporting plate and between the fourth supporting plate and the second side surface.
Optionally, the first adhesive layer is a silica gel adhesive, and/or the second adhesive layer is a silica gel adhesive, and/or the third adhesive layer is a silica gel adhesive.
Optionally, the filler comprises fire-resistant rock wool.
Optionally, the top plate body comprises a corrugated steel plate.
Optionally, the first panel is provided with a mounting groove for mounting the top plate body.
Drawings
Fig. 1 is a schematic structural view of a clean room portion according to an embodiment of the present invention;
FIG. 2 is a schematic plan view of a clean room portion according to the present invention;
fig. 3 is a schematic structural diagram of a top plate assembly according to an embodiment of the present invention;
fig. 4 is a schematic view of the structure of the sky rail body in an embodiment provided by the present invention;
fig. 5 is a schematic view of the structure of the sky rail body in another embodiment of the present invention;
fig. 6 is a schematic view of the structure of the sky rail body in another embodiment of the present invention.
1-a first wall body, 11-a first side, 12-a second side, 13-a top, 2-a first panel, 3-a second panel, 4-a filler, 5-a roof body, 6-a sky rail body, 61-a first support plate, 62-a second support plate, 63-a third support plate, 64-a fourth support plate.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
As shown in fig. 1 to 2, an embodiment of the present invention provides a clean room, including: a first wall body 1, a head rail body 6 and a roof plate assembly;
the first wall body 1 is provided with a first side surface 11 and a second side surface 12 which are oppositely arranged along the thickness and a top surface 13 used for connecting the first side surface 11 and the second side surface 12, and the top plate component is arranged on the top surface 13 of the first wall body 1 through the sky rail body 6;
the sky rail body 6 comprises a first supporting plate 61 and a second supporting plate 62 which are connected, the first supporting plate 61 is parallel to the first side surface 11 of the first wall body 1, and the second supporting plate 62 is perpendicular to the first side surface 11 and is positioned between the first wall body 1 and the roof plate assembly;
a first adhesive layer is arranged at the joint between the top plate assembly and the first supporting plate 61, and a second adhesive layer is arranged at the joint between the first wall body 1 and the second supporting plate 62.
The utility model discloses the increase is provided with sky rail body 6 that is used for installing first wall body 1 and roof subassembly, and set up sky rail body 6 into first backup pad 61 and second backup pad 62 that have mutually perpendicular, thereby above-mentioned structure has increased the area of contact between sky rail body 6 and first wall body 1 and the roof subassembly to a certain extent, great area of contact can increase the area that sets up of adhesive linkage promptly, specifically do, this application is provided with first adhesive linkage between first backup pad 61 and roof subassembly, be provided with the second adhesive linkage between second backup pad 62 and first wall body 1, and then improved the stability of first wall body 1 and roof subassembly when installing to sky rail body 6 on to a certain extent, increase the adhesive linkage in sky rail body 6 junction of first wall body 1 and roof subassembly installation simultaneously, can effectually seal the gap of junction, better satisfy toilet's service environment, and then promoted the sealed service life that keeps of gap department.
In a possible implementation manner, as shown in fig. 3, the top plate assembly includes a top plate body 5 and a second wall body, the top plate body 5 is vertically disposed on the second wall body, and the top plate body 5 is connected with the second wall body, the first adhesive layer is disposed between the second wall body and the first supporting plate 61, in the above structure, the top plate assembly is divided into the top plate body 5 and the second wall body by the application, and the top plate body 5 is vertically disposed on the second wall body, so that when the top plate body 5 is mounted on the clean room, the normal use of the top plate body 5 is ensured, and the addition of the second wall body can effectively support the top plate assembly through the first wall body 1 after the top plate assembly is mounted on the top rail body 6, and meanwhile, the addition of the first adhesive layer can ensure the sealing performance of the connection between the top plate body 5 and the second wall body while remarkably improving the connection stability between the top plate body 5 and the second wall body, thereby improving the overall sealing performance of the clean room.
In the mode that one kind probably realized, as shown in fig. 3, filler 4 includes fire prevention rock wool, and fire prevention rock wool is with basalt as main raw materials, after high temperature melting, makes inorganic fiber by high-speed centrifugal equipment, and the while evenly adds the binder of certain proportion and dries into the big board, cuts into the rock silver according to production needs, and the rock wool is the non-burning body, and fire behavior is good to in foretell structure, this application passes through the effect of filler 4, can effectual promotion toilet overall structure's fire behavior.
In a possible implementation manner, as shown in fig. 3, the second wall body includes a first panel 2 and a second panel 3 that are arranged in parallel, and a filler 4, where the filler 4 is disposed in an accommodating space formed between the first panel 2 and the second panel 3, in the above structure, one side of the first panel 2 close to the top plate body 5 and the first side surface 11 are located on the same plane, and one side of the second panel 3 far from the top plate body 5 and the second side surface 12 are located on the same plane, that is, the thickness of the accommodating space formed between the first panel 2 and the second panel 3 is equal to the thickness of the first wall body 1, so that a smooth plane can be formed between the first wall body 1 and the second wall body, which improves the beauty of the whole structure of the clean room, and the filler 4 is added, so as to effectively improve the fire resistance of the whole structure of the clean room, and also play a certain sound insulation effect.
In a possible implementation manner, as shown in fig. 3, the first panel 2 is connected to the top panel body 5, and a third adhesive layer is disposed at a joint between the first panel 2 and the top panel body 5, in the above structure, the top panel body 5 in the present application is installed on the first panel 2, and the third adhesive layer is disposed at a joint between the top panel body 5 and the first panel 2, so that a gap existing in an installation process of the clean room is further sealed, and the whole sealing performance of the clean room is improved.
In a possible implementation, as shown in fig. 4, the head rail body 6 includes a first supporting plate 61 and a second supporting plate 62 connected, the first supporting plate 61 is parallel to the first side 11 of the first wall body 1, and the second supporting plate 62 is perpendicular to the first side 11 and is located between the first wall body 1 and the roof plate assembly;
in the structure, this application is provided with first backup pad 61 and the second backup pad 62 of connection to make first backup pad 61 and first panel 2 contact, second backup pad 62 and the top surface 13 of first wall body 1 to the contact, and be provided with first adhesive linkage between first backup pad 61 and first panel 2, be provided with the second adhesive linkage in second backup pad 62 and first wall body 1, improved the stability that first wall body 1 and roof subassembly connect when installing to day rail body 6 to a certain extent.
In a possible implementation manner, as shown in fig. 5, the head rail body 6 further includes a third supporting plate 63, the third supporting plate 63 is parallel to the first side surface 11, the third supporting plate 63 is connected to the first supporting plate 61, and a fourth adhesive layer is disposed between the third supporting plate 63 and the first side surface 11.
In the above structure, the third supporting plate 63 is additionally arranged on the basis of the original first supporting plate 61 and second supporting plate 62, and the third supporting plate 63 is arranged on the side close to the first side surface 11, and meanwhile, the third supporting plate 63 is connected with the first supporting plate 61, so that a smooth plane is formed between the first supporting plate 61 and the third supporting plate 63, that is, the section of the ceiling rail body 6 is formed into a T-shaped structure, wherein the first supporting plate 61 and the third supporting plate 63 are arranged on the side close to the first side surface 11, the contact area between the ceiling rail body 6 and the first wall body 1 is increased to a certain extent, meanwhile, the fourth bonding layer in the present application can be a silica gel adhesive, and the glue applying treatment can also be performed between the third supporting plate 63 and the first wall body 1, so that the whole sealing performance of the clean room itself is improved, and the stability of the first wall body 1 on the ceiling rail body 6 is also increased.
In a possible implementation manner, as shown in fig. 6, the sky rail body 6 further includes a fourth supporting plate 64, the fourth supporting plate 64 is disposed on a side of the second supporting plate 62 away from the first supporting plate 61, an orthographic projection of the fourth supporting plate 64 on the first wall body 1 is located on the second side surface 12, and a fifth adhesive layer is disposed between the fourth supporting plate 64 and the second side surface 12.
In the above structure, the fourth supporting plate 64 is additionally arranged on the basis of the original first supporting plate 61, the original second supporting plate 62 and the original third supporting plate 63, and the orthographic projection of the fourth supporting plate 64 on the first wall body 1 is located on the second side surface 12, that is, the fourth supporting plate 64 is arranged on one side of the second side surface 12, so that the cross section of the overall structure of the sky rail body 6 is in an h-shaped structure, the fourth supporting plate 64 acts on the first wall body 1 to face an acting force along the second side surface 12 to the first side surface 11, a fifth bonding layer is arranged in a gap between the fourth supporting plate 64 and the second side surface 12, and meanwhile, the fifth bonding layer can be a silica gel adhesive, so that the installation of the first wall body 1 and the roof plate assembly is more stable.
In a possible implementation manner, the first bonding layer is a silica gel adhesive, and/or the second bonding layer is a silica gel adhesive, and/or the third bonding layer is a silica gel adhesive, and the bonding property of the silica gel adhesive is utilized to seal the connection part of the whole clean room, and the bonding layer in the present application is a silica gel adhesive, and may be other adhesive adhesives, wherein modifications and variations to the bonding layer are within the scope of the claims of the present application and the equivalent technology, and the present application is also intended to include these modifications and variations.
In the mode that one kind probably realized, roof body 5 includes the steel buckled plate, adopts the steel buckled plate of wave type, can reach the whole radiating purpose of toilet to a certain extent.
In a possible implementation manner, a mounting groove for mounting the top plate body 5 is formed in the first panel 2, in the structure, the first panel 2 and the top plate body 5 are mounted in an inserting manner, meanwhile, the depth direction of the mounting groove extends along the direction towards the first panel 2, the shape of the mounting groove is matched with that of the top plate body 5, and the top plate body 5 is conveniently inserted into the top plate body 5.
In a possible implementation, the first panel 2 and the second panel 3 may be galvanized steel sheets and/or stainless steel sheets.
The method comprises the following operation steps: a. cutting the galvanized steel plate and/or the stainless steel plate into required shapes to meet the installation requirement; b. a sky rail body 6 is arranged between the top plate body 5 and the first wall body 1; c. coating a silica gel adhesive on the joint between the top rail body 6 and the first wall body 1; d. fixing the first wall body 1 or the second wall body on the sky rail body 6; e. fireproof rock wool is filled between the first panel 2 and the second panel 3; f. the top plate body 5 and the first panel 2 are sealed by using a silica gel adhesive.
It will be apparent to those skilled in the art that various changes and modifications may be made in the present application without departing from the spirit and scope of the application. In this way it is possible to obtain, to the extent that such modifications and variations of the present application fall within the scope of the claims and their equivalents, it is intended that the present application cover such modifications and variations.

Claims (10)

1. A clean room, comprising: a first wall body, a head rail body and a roof panel assembly;
the first wall body is provided with a first side surface, a second side surface and a top surface, the first side surface and the second side surface are oppositely arranged along the thickness, the top surface is used for connecting the first side surface and the second side surface, and the top plate assembly is installed on the top surface of the first wall body through the sky rail body;
the sky rail body comprises a first supporting plate and a second supporting plate which are connected, the first supporting plate is parallel to the first side face of the first wall body, and the second supporting plate is perpendicular to the first side face and is positioned between the first wall body and the top plate assembly;
the roof subassembly with the junction is provided with first adhesive linkage between the first backup pad, the junction is provided with the second adhesive linkage between first wall body and the second backup pad.
2. The clean room of claim 1, wherein the ceiling assembly comprises a ceiling body and a second wall body, the ceiling body is vertically disposed on the second wall body and connected to the second wall body, and the first adhesive layer is disposed between the second wall body and the first support plate.
3. The clean room of claim 2, wherein the second wall body comprises first and second panels arranged in parallel and a filler disposed in a receiving space formed between the first and second panels.
4. The clean room of claim 3, wherein the first panel is attached to the ceiling body, and a third adhesive layer is provided at a junction between the first panel and the ceiling body.
5. The clean room of any one of claims 1 to 4, wherein the top rail body further comprises a third support plate, the third support plate being parallel to the first side surface and being connected to the first support plate, a fourth adhesive layer being provided between the third support plate and the first side surface.
6. The clean room of claim 5, wherein the ceiling rail body further comprises a fourth support plate disposed on a side of the second support plate away from the first support plate, and an orthographic projection of the fourth support plate on the first wall body is located on the second side surface, and a fifth adhesive layer is disposed on the fourth support plate and between the fourth support plate and the second side surface.
7. The clean room of claim 4, wherein the first adhesive layer is a silicone adhesive, and/or the second adhesive layer is a silicone adhesive, and/or the third adhesive layer is a silicone adhesive.
8. The clean room of claim 3, wherein the filler comprises fire-resistant rock wool.
9. The clean room of claim 2, wherein the top plate body comprises a corrugated steel plate.
10. The clean room of claim 4, wherein said first panel is provided with a mounting slot for mounting said ceiling body.
CN202223162987.6U 2022-11-28 2022-11-28 Clean room Active CN218758087U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202223162987.6U CN218758087U (en) 2022-11-28 2022-11-28 Clean room

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202223162987.6U CN218758087U (en) 2022-11-28 2022-11-28 Clean room

Publications (1)

Publication Number Publication Date
CN218758087U true CN218758087U (en) 2023-03-28

Family

ID=85675946

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202223162987.6U Active CN218758087U (en) 2022-11-28 2022-11-28 Clean room

Country Status (1)

Country Link
CN (1) CN218758087U (en)

Similar Documents

Publication Publication Date Title
CN218758087U (en) Clean room
CN214275981U (en) Combined sound insulation cotton convenient to install
JPH0125855B2 (en)
CN201649499U (en) Dustfall-preventing and sound-absorbing ceiling
CN213741710U (en) Sound insulation building board for building
CN215407107U (en) Building decoration decorates with heat preservation decorative board that flame retardant efficiency is good
CN2367880Y (en) Ventilating pipe
CN217896826U (en) Coated rock wool board with noise-reducing and sound-insulating honeycomb structure
CN214789023U (en) Epoxy sealing rubber strip for manufacturing and producing electric appliances
CN211499584U (en) Combined wallboard for architectural design
CN218405899U (en) Assembly wallboard structure
CN211873524U (en) Assembled wallboard for building steel structure
CN220504227U (en) Sound insulation wall structure
CN218581502U (en) Sound-insulation invisible door
CN210857627U (en) Waterproof construction between aluminum curtain wall and glass curtain wall
CN214491845U (en) Sound-insulation noise-reduction integrated external wall insulation board
CN212579323U (en) High-efficient fire-proof type metal fiber acoustic baffle
CN215831643U (en) High-flame-retardance smokeless household appliance heat-insulating material
CN217047740U (en) Combined sound insulation cotton
CN213626251U (en) Noise-reducing sound-insulating aluminum ceiling
CN215054104U (en) Heat insulation board convenient to mount for building external wall
CN209813301U (en) Effectual tectorial membrane plastic-aluminum composite panel gives sound insulation
CN214658408U (en) Wall structure provided with decorative glass plate
CN210713495U (en) Heat-insulation wallboard
CN213509097U (en) Building curtain wall with sound insulation function