CN218724204U CN202222404752.7U CN202222404752U CN218724204U CN 218724204 U CN218724204 U CN 218724204U CN 202222404752 U CN202222404752 U CN 202222404752U CN 218724204 U CN218724204 U CN 218724204U
Authority
CN
China
Prior art keywords
fixed
rod
plate
push rod
connecting plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222404752.7U
Other languages
Chinese (zh)
Inventor
李祚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202222404752.7U priority Critical patent/CN218724204U/en
Application granted granted Critical
Publication of CN218724204U publication Critical patent/CN218724204U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The utility model discloses a soil is fixed point ware for resource measurement relates to soil resource measurement technical field. The utility model discloses a bottom plate, place the case, the subassembly advances one by one, locating component, centre gripping subassembly and spacing subassembly, the one end at bottom plate top is fixed with places the case, the second is equipped with the seat and fixes on hydraulic rod, the second motor is fixed in the second and is equipped with the inside of seat, the output of second motor runs through the second and is equipped with the diapire of seat and be connected with the third connecting plate, third connecting plate bottom is fixed with the backup pad, the bottom at the third connecting plate is fixed to second electric putter's one end, the other end of second electric putter is fixed at telescopic top, the connecting block is fixed in the backup pad, the bar pole is fixed on the grip ring, connecting rod swing joint is respectively on connecting block and bar pole. The utility model discloses a set up the centre gripping subassembly, the centre gripping subassembly can directly bore into the ground with the spud pile, has set up and has placed the case, can place the incasement and put sufficient spud pile.

Description

Soil resource measuring is with pointing device
Technical Field
The utility model belongs to the technical field of land resource measurement, especially, relate to a fixed point ware for land resource measurement.
Background
Land survey is work of measuring and drawing features such as the number of landforms in various lands by using methods such as surveying science, remote sensing technology and the like, and is important work in land management, including cadastral survey, landform survey, land utilization current situation survey, backup land resource survey and the like. The prior published document CN217155410U, a pointing device for land resource management and measurement, is provided with wheel mounting seats fixedly connected with the four corners of the bottom end of a bottom plate, universal wheels with brakes are mounted on each wheel mounting seat, a semicircular hole is formed in the front end of the bottom plate, supporting frames are symmetrically mounted on the left and right of the upper end of the bottom plate, a rotatable marker post placing mechanism is mounted on the bottom plate, the top ends of the two supporting frames are fixedly connected with a top plate, and the top plate is mounted together with a pressing mechanism. The problem of current lack can assist the mechanism of location fixed point sighting rod, lead to the degree of accuracy reduction when land resource management measures the location, reduce the measurement fixed point efficiency of pointing device is solved. However, the following disadvantages still exist in the practical use:
1. most of the existing point fixing devices for measuring soil resources are that workers insert a positioning pile into the ground along a fixed point and then dig the positioning pile into the ground by using a hammer, so that the physical power of the workers is greatly consumed, when the ground for fixing the point is hard, the positioning pile cannot be smoothly driven into the ground, and the positioning pile can be damaged due to overlarge stress in the digging process when the positioning pile is hammered;
2. most of the existing fixed point devices for measuring land resources cannot carry more positioning piles, so that the fixed point device returns to continue to perform fixed point work after the positioning piles need to be supplemented after working for a certain distance, the fixed point work of a plurality of places is generally required to be performed in a working place, the fixed point devices need to turn back and supplement the positioning piles for a plurality of times, the labor intensity of workers is increased, and the subsequent work is influenced.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a soil is pointing device for resource measurement, through having set up the centre gripping subassembly and having placed the case, solved current spud pile and needed the staff to chisel into ground and locator and can not carry sufficient spud pile problem.
In order to solve the technical problem, the utility model discloses a realize through following technical scheme:
the utility model relates to a soil is fixed point ware for resource measurement, comprising a base plate, place the case, advance the subassembly step by step, locating component, centre gripping subassembly and spacing subassembly, the one end at bottom plate top is fixed with places the case, the centre gripping subassembly is fixed on locating component, the centre gripping subassembly is equipped with the seat by the second, the second motor, the third connecting plate, a supporting plate, second electric putter, the sleeve, the connecting block, the connecting rod, bar pole and grip ring are constituteed jointly, the second is equipped with the seat and fixes on hydraulic rod, the second motor is fixed in the second and is equipped with the inside of seat, the output of second motor runs through the diapire that the second was equipped with the seat and is connected with the third connecting plate, third connecting plate bottom is fixed with the backup pad, the bottom at the third connecting plate is fixed to second electric putter's one end, the other end of second electric putter is fixed at telescopic top, the connecting block is fixed on the backup pad, the bar pole is fixed on the grip ring, the one end swing joint of connecting rod is on the connecting block, the other end swing joint of connecting rod is on the bar pole.
Further, the top of bottom plate is fixed with the subassembly that advances one by one, the subassembly that advances one by one is by advancing one by one the groove, live-rollers and spud pile constitute jointly, the groove that advances one by one is fixed at the top of bottom plate, live-rollers swing joint is on the lateral wall that advances one by one the groove, the spud pile is placed and is being placed the incasement, the staff can directly move the spud pile of placing the incasement to the groove that advances one by one as required when carrying out work, then drive the spud pile by the live-rollers and move in advancing one by one the groove, just, do not need the staff to make a round trip to carry the spud pile, staff's physical power has been saved.
Further, be fixed with spacing subassembly on the subassembly that advances, spacing subassembly is by spacing shell, first be equipped with the seat, first motor, carousel and gag lever post are constituteed jointly, spacing shell is fixed on the lateral wall in groove that advances, first be equipped with the seat and fix on spacing shell, first motor is fixed in the inside of first being equipped with the seat, the output of first motor runs through the roof of first being equipped with the seat and is connected with the carousel, the gag lever post array is on the week side of carousel, when the spud reachs spacing subassembly, the spud can be given to block by the gag lever post, first motor can rotate when needing the spud and drive carousel and gag lever post rotation, when a spud passes through spacing subassembly, first motor can stall, the gag lever post can block the spud post in the back once more, the spud through spacing subassembly can be taken the centre gripping subassembly below by the live-rollers.
Furthermore, a positioning component is fixed on the limiting component, the positioning component is composed of a support rod, a first fixing plate, a first connecting plate, a first electric push rod, a second connecting plate, a second fixing plate, a connecting rod and a hydraulic push rod, the support rod is fixed at the top of the limiting shell, the first fixing plate is fixed at the top of the support rod, the first connecting plate is fixed on the side wall of the first fixing plate, the bottom end of the first electric push rod is fixed on the side wall of the first connecting plate, the second connecting plate is fixed at the top end of the first electric push rod, the second fixing plate is fixed on the side wall of the second connecting plate, one end of the connecting rod is connected on the side wall of the second connecting plate, the other end of the connecting rod is connected at the top of the second fixing plate, the hydraulic push rod is fixed at the bottom of the second fixing plate, the hydraulic push rod on the positioning component can drive the clamping component to go up and down, the first electric push rod can drive the clamping component to accurately clamp the positioning pile, and can also send the positioning pile to a designated position,
further, be fixed with the spring on the connecting block, the one end of spring is connected on the connecting block, the other end of spring is connected on the connecting rod, the equipartition has the non slipping spur on the interior circumference side of grip ring, the spring can make the connecting rod be in open state, second electric putter drives the sleeve and removes can compress tightly the connecting rod and make the spring compression, the spring props up the connecting rod and can let the spud get into clamping component better, the antiskid on the grip ring can prevent to drive the spud and take place the landing when rotating soon, also can press from both sides the spud better.
Furthermore, the top of the bottom plate far away from one side of the clamping assembly is fixed with a movable push handle, the bottom end of the bottom plate is provided with universal wheels in an array mode, the push rod can facilitate workers to move the pointing device, and the universal wheels can be better adapted to the ground of a working place.
The utility model discloses following beneficial effect has:
1. the clamping component is arranged, when the locating pile is arranged below the clamping component, the hydraulic push rod can drive the clamping component to descend, the top end of the locating pile enters the clamping component, the second electric push rod can enable the sleeve to descend to be used for extruding the connecting rod, the locating pile is tightly clamped by the clamping ring, then the second motor can drive the locating pile to rotate fast, the locating pile is drilled into the ground, the physical force of workers can be greatly saved, and the locating pile can be drilled into the ground without damaging the locating pile when the ground is hard.
2. Set up and placed the case, can all place the incasement with sufficient spud pile before beginning work, then go to carry out fixed point work again, place the spud pile of incasement enough with all positions insert the spud pile, so just need not make a round trip to supply the spud pile, not only reduced staff's intensity of labour, still be favorable to going on of later stage work.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings used in the description of the embodiments will be briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art that other drawings can be obtained according to these drawings without creative efforts.
FIG. 1 is a schematic view of a pointer for measuring soil resources;
FIG. 2 is a front view of a soil resource measuring pointing device;
FIG. 3 is a plan view of a soil resource measuring pointing device;
FIG. 4 is a side view of a soil resource measuring pointing device;
FIG. 5 is a schematic structural diagram of a progressive assembly and a limiting assembly in the pointing device for measuring soil resources;
FIG. 6 is a schematic diagram of the positioning assembly and the holding assembly of the pointing device for measuring soil resources;
FIG. 7 is a schematic view of a holding member of a pointing device for measuring soil resources;
FIG. 8 is an enlarged view of the structure at A in FIG. 7;
fig. 9 is a schematic structural view of a sleeve in the soil resource measuring pointing device.
In the drawings, the components represented by the respective reference numerals are listed below:
1. a base plate; 2. placing a box; 3. a progressive assembly; 301. a progressive groove; 302. a rotating roller; 303. positioning the pile; 4. a positioning assembly; 401. a support bar; 402. a first fixing plate; 403. a first connecting plate; 404. a first electric push rod; 405. a second connecting plate; 406. a second fixing plate; 407. a connecting rod; 408. a hydraulic push rod; 5. a clamping assembly; 501. a second standby seat; 502. a second motor; 503. a third connecting plate; 504. a support plate; 505. a second electric push rod; 506. a sleeve; 507. connecting blocks; 508. a spring; 509. a connecting rod; 510. a bar-shaped rod; 511. a clamp ring; 512. anti-skid blocks; 6. moving the push handle; 7. a universal wheel; 8. a limiting component; 801. a limiting shell; 802. a first standby seat; 803. a first motor; 804. a turntable; 805. a limiting rod.
Detailed Description
The technical solution in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention.
Referring to fig. 1, 2, 4, 6, 7, 8 and 9, the utility model relates to a pointing device for measuring land resources, which comprises a bottom plate 1, a placing box 2, a progressive assembly 3, a progressive groove 301, a rotating roller 302, a positioning pile 303, a positioning assembly 4, a support rod 401, a first fixing plate 402, a first connecting plate 403, a first electric push rod 404, a second connecting plate 405, a second fixing plate 406, a connecting rod 407, a hydraulic push rod 408, a clamping assembly 5, a second backup base 501, a second motor 502, a third connecting plate 503, a support plate 504, a second electric push rod 505, a sleeve 506, a connecting block 507, a spring 508, a connecting rod 509, a bar-shaped rod 510, a clamping ring 511, a skid block 512, a mobile pushing hand 6, a universal wheel 7, a limiting assembly 8, a limiting shell 801, a first backup base 802, a first motor 803, a turntable 804 and a limiting rod 805, wherein the clamping assembly 5 is fixed on the positioning assembly 4, the clamping assembly 5 is composed of a second standby base 501, a second motor 502, a third connecting plate 503, a supporting plate 504, a second electric push rod 505, a sleeve 506, a connecting block 507, a connecting rod 509, a bar-shaped rod 510 and a clamping ring 511, the second standby base 501 is fixed on the hydraulic push rod 408, the second motor 502 is fixed inside the second standby base 501, the output end of the second motor 502 penetrates through the bottom wall of the second standby base 501 to be connected with the third connecting plate 503, the supporting plate 504 is fixed at the bottom of the third connecting plate 503, one end of the second electric push rod 505 is fixed at the bottom of the third connecting plate 503, the other end of the second electric push rod 505 is fixed at the top of the sleeve 506, the connecting block 507 is fixed on the supporting plate 504, the bar-shaped rod 510 is fixed on the clamping ring 511, one end of the connecting rod 509 is movably connected on the connecting block 507, the other end of the connecting rod 509 is movably connected on the bar-shaped rod 510, a spring 508 is fixed on the connecting block 507, one end of the spring 508 is connected on the connecting block 507, the other end of the spring 508 is connected on the connecting rod 509, and anti-skidding blocks 512 are uniformly distributed on the inner peripheral side surface of the clamping ring 511.
The above setting, the application is: when the positioning pile 303 moves to the lower part of the clamping mechanism, the hydraulic push rod 408 starts to extend, when the top end of the positioning pile 303 abuts against the third connecting plate 503, the hydraulic push rod 408 stops to extend, the second electric push rod 505 immediately starts to extend, the second electric push rod 505 drives the sleeve 506 to move downwards, then the sleeve 506 starts to press the connecting rod 509, the connecting rod 509 drives the bar-shaped rod 510 to start to press the clamping ring 511, the second electric push rod 505 stops extending after the clamping ring 511 tightly clamps the positioning pile 303, when the positioning pile 303 is about to reach the ground, the second motor 502 is started, the second motor 502 starts to drive the third connecting plate 503 to rotate, the third connecting plate drives the positioning pile 303 to rotate quickly, until the positioning pile 303 drills into a proper depth, the hydraulic push rod 408 stops to extend, the second motor 502 stops rotating, then the second electric push rod 505 starts to retract, the second electric push rod 505 drives the sleeve 506 to start to slowly rise, the spring 508 starts to extend slowly, the spring 508 starts to drive the connecting rod 509 to drive the bar-shaped rod 510 to slowly extend, and then the bar-shaped rod 510 starts to slowly rise, and stops when the bar-shaped rod 510 starts to slowly rise and the clamping ring 510 starts to lift.
As shown in fig. 1, 2, 3 and 5, a placing box 2 is fixed at one end of the top of a bottom plate 1, a progressive assembly 3 is fixed at the top of the bottom plate 1, the progressive assembly 3 is composed of a progressive groove 301, a rotating roller 302 and a positioning pile 303, the progressive groove 301 is fixed at the top of the bottom plate 1, the rotating roller 302 is movably connected to the side wall of the progressive groove 301, the positioning pile 303 is placed in the placing box 2, a limiting assembly 8 is fixed on the progressive assembly 3, the limiting assembly 8 is composed of a limiting shell 801, a first backup seat 802, a first motor 803, a turntable 804 and a limiting rod 805, the limiting shell 801 is fixed on the side wall of the progressive groove 301, the first backup seat 802 is fixed on the limiting shell 801, the first motor 803 is fixed in the first backup seat 802, the output end of the first motor 803 penetrates through the top wall of the first backup seat 802 to be connected with the turntable 804, the limiting rod 805 is arrayed on the peripheral side face of the turntable 804, the limiting component 8 is fixed with a positioning component 4, the positioning component 4 is composed of a support rod 401, a first fixing plate 402, a first connecting plate 403, a first electric push rod 404, a second connecting plate 405, a second fixing plate 406, a connecting rod 407 and a hydraulic push rod 408, the support rod 401 is fixed at the top of the limiting shell 801, the first fixing plate 402 is fixed at the top of the support rod 401, the first connecting plate 403 is fixed on the side wall of the first fixing plate 402, the bottom end of the first electric push rod 404 is fixed on the side wall of the first connecting plate 403, the second connecting plate 405 is fixed at the top end of the first electric push rod 404, the second fixing plate 406 is fixed on the side wall of the second connecting plate 405, one end of the connecting rod 407 is connected on the side wall of the second connecting plate 405, the other end of the connecting rod 407 is connected at the top of the second fixing plate 406, and the hydraulic push rod 408 is fixed at the bottom of the second fixing plate 406, the top of the bottom plate 1 far away from one side of the clamping component 5 is fixed with a movable push handle 6, and the bottom end of the bottom plate 1 is provided with universal wheels 7 in an array mode.
The above setting, the application is: firstly, after a worker pushes a pointing device to a designated position, a plurality of positioning piles 303 are taken out from a placing box 2 and placed into a progressive groove 301, then a rotating roller 302 in the progressive groove 301 drives the positioning piles 303 to move slowly towards a limiting component 8, when the positioning piles 303 move to the limiting component 8, a limiting rod 805 blocks the positioning piles 303, then the hydraulic push rod 408 contracts, when a clamping ring 511 is slightly higher than the positioning piles 303, the contraction of the hydraulic push rod 408 stops, then the contraction of a first electric push rod 404 starts, when a clamping component 5 moves to the tail end of the progressive groove 301, the contraction of the first electric push rod 404 stops, then a first motor 803 starts to rotate, the first motor 803 drives a rotary disc 804 to start rotating, the rotary disc 804 drives the limiting rod 805 to start rotating, when the first positioning pile 303 passes through the limiting component 8, the rotation of the first motor 803 stops immediately, then the positioning pile 303 is continuously driven by the rotating roller 302 to move slowly towards the clamping component 5, when the positioning pile 303 is clamped by the clamping ring 511, then the push rod 303 starts to extend, the first electric push rod 404 moves to the upper portion, when the hydraulic push rod 408 starts to extend, then the hydraulic push rod 408, when the hydraulic push rod 408 extends to the hydraulic push rod 408, and then the hydraulic push rod 408 to the designated position, and then starts to extend to the hydraulic push rod 408, when the clamping component 408, and the hydraulic push rod 408, and then the hydraulic push rod 408 to extend to the hydraulic push rod 408.
One specific application of this embodiment is: firstly, after a worker pushes a pointing device to a specified position, a plurality of positioning piles 303 are taken out from the placing box 2 and placed into the advancing groove 301, then the rotating roller 302 in the advancing groove 301 drives the positioning piles 303 to move slowly towards the limiting component 8, when the positioning piles 303 move to the limiting component 8, the limiting rod 805 stops the positioning piles 303, then the hydraulic push rod 408 is contracted until the clamping ring 511 is slightly higher than the positioning piles 303, then the contraction of the hydraulic push rod 408 is stopped, then the first electric push rod 404 is stopped when the clamping component 5 moves to the tail end of the advancing groove 301, then the first electric motor 803 is started to rotate, the first electric motor 803 drives the turntable 804 to rotate, the turntable 804 drives the limiting rod 805 to rotate, when the first positioning pile 303 passes through the limiting component 8, the rotation of the first electric motor 803 is stopped immediately, then the positioning piles 303 are driven by the rotating roller 302 to move slowly towards the clamping component 5, when the positioning piles move to the lower part of the clamping mechanism, when the positioning piles 303 pass through the limiting component 8, the positioning piles 303 extend, the second electric push rod 511 drives the second electric push rod 511 to extend downwards to press the clamping ring 511, then the second electric push rod 511 to press the clamping rod 505, the second electric push rod 511 to press the clamping rod 511, the second electric push rod 511 to press the clamping component 303, the positioning pile 303, the second electric push rod 505, the second electric push rod 511 to extend, the clamping rod 505, the second electric push rod 511 to press the clamping rod 505, the positioning pile 303, the second electric push rod 511 to extend, the clamping rod 505, when the positioning pile 303 moves above the designated position, the first electric push rod 404 stops extending, then the hydraulic push rod 408 starts extending, when the positioning pile 303 is about to reach the ground, the second motor 502 is started, the second motor 502 starts driving the third connecting plate 503 to rotate, the third connecting plate 503 drives the positioning pile 303 to rotate quickly, when the positioning pile 303 drills into the proper depth, the hydraulic push rod 408 stops extending, the second motor 502 stops rotating, then the second electric push rod 505 starts retracting, the second electric push rod 505 drives the sleeve 506 to slowly rise, the spring 508 starts slowly extending, the spring 508 starts driving the connecting rod 509 to slowly expand, the connecting rod 509 drives the bar 510 to start moving, the bar 510 starts driving the clamping ring 511 to slowly disengage from the positioning pile 303, when the sleeve 506 rises to the initial position, the second electric push rod 505 stops retracting, then the hydraulic push rod 408 starts retracting, the hydraulic push rod 408 drives the clamping assembly 5 to rise, when the clamping assembly 5 rises to the initial position, the hydraulic push rod 408 stops retracting, and then the positioner is pushed by the worker to go to the next working place.
The above is only the preferred embodiment of the present invention, and the present invention is not limited thereto, any technical solutions recorded in the foregoing embodiments are modified, and some technical features thereof are replaced with equivalent ones, and any modification, equivalent replacement, and improvement made thereby all belong to the protection scope of the present invention.

Claims (6)

1. The utility model provides a soil is pointing device for resource measurement, includes bottom plate (1), places case (2), advances subassembly (3), locating component (4), centre gripping subassembly (5) and spacing subassembly (8), its characterized in that: the placing box (2) is fixed at one end of the top of the bottom plate (1), the clamping component (5) is fixed on the positioning component (4), the clamping component (5) is composed of a second standby seat (501), a second motor (502), a third connecting plate (503), a supporting plate (504), a second electric push rod (505), a sleeve (506), a connecting block (507), a connecting rod (509), a bar-shaped rod (510) and a clamping ring (511), the second standby seat (501) is fixed on the hydraulic push rod (408), and the second motor (502) is fixed in the second standby seat (501), the output end of the second motor (502) penetrates through the bottom wall of the second standby seat (501) and is connected with the third connecting plate (503), the bottom of the third connecting plate (503) is fixed with the supporting plate (504), one end of the second electric push rod (505) is fixed at the bottom of the third connecting plate (503), the other end of the second electric push rod (505) is fixed at the top of the sleeve (506), the connecting block (507) is fixed on the supporting plate (504), the bar-shaped rod (510) is fixed on the clamping ring (511), one end of the connecting rod (509) is movably connected onto the connecting block (507), and the other end of the connecting rod (509) is movably connected onto the bar-shaped rod (510) .
2. The pointing device for measuring land resources according to claim 1, wherein: the top of bottom plate (1) is fixed with go forward subassembly (3) in succession, it constitutes jointly by groove (301), rotation roller (302) and spud (303) to go forward subassembly (3) in succession, it fixes to go forward groove (301) in succession the top of bottom plate (1), rotation roller (302) swing joint in the lateral wall of groove (301) in succession, spud (303) are placed place in case (2).
3. The pointing device for measuring land resources according to claim 2, wherein: the progressive assembly (3) is fixed with the limiting assembly (8), the limiting assembly (8) is composed of a limiting shell (801), a first standby seat (802), a first motor (803), a rotary disc (804) and a limiting rod (805), the limiting shell (801) is fixed on the side wall of the progressive groove (301), the first standby seat (802) is fixed on the limiting shell (801), the first motor (803) is fixed inside the first standby seat (802), the output end of the first motor (803) penetrates through the top wall of the first standby seat (802) to be connected with the rotary disc (804), and the limiting rod (805) is arrayed on the peripheral side face of the rotary disc (804).
4. The pointing device for measuring soil resources according to claim 3, wherein: the positioning assembly (4) is fixed on the limiting assembly (8), the positioning assembly (4) is composed of a supporting rod (401), a first fixing plate (402), a first connecting plate (403), a first electric push rod (404), a second connecting plate (405), a second fixing plate (406), a connecting rod (407) and a hydraulic push rod (408), the supporting rod (401) is fixed at the top of the limiting shell (801), the first fixing plate (402) is fixed at the top of the supporting rod (401), the first connecting plate (403) is fixed on the side wall of the first fixing plate (402), the bottom end of the first electric push rod (404) is fixed on the side wall of the first connecting plate (403), the second connecting plate (405) is fixed at the top end of the first electric push rod (404), the second fixing plate (406) is fixed on the side wall of the second connecting plate (405), one end of the connecting rod (407) is connected on the side wall of the second connecting plate (405), the other end of the connecting rod (407) is connected to the top of the second fixing plate (406), and the bottom of the hydraulic push rod (408) is fixed at the bottom of the second fixing plate (406).
5. The pointing device for measuring land resources according to claim 1, wherein: a spring (508) is fixed on the connecting block (507), one end of the spring (508) is connected to the connecting block (507), the other end of the spring (508) is connected to the connecting rod (509), and anti-skidding blocks (512) are uniformly distributed on the inner peripheral side surface of the clamping ring (511).
6. The pointing device for measuring land resources according to claim 1, wherein: keep away from centre gripping subassembly (5) one side the top of bottom plate (1) is fixed with removes pushing hands (6), the bottom array of bottom plate (1) has universal wheel (7).
CN202222404752.7U 2022-09-09 2022-09-09 Soil resource measures uses fixed point ware Active CN218724204U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222404752.7U CN218724204U (en) 2022-09-09 2022-09-09 Soil resource measures uses fixed point ware

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222404752.7U CN218724204U (en) 2022-09-09 2022-09-09 Soil resource measures uses fixed point ware

Publications (1)

Publication Number Publication Date
CN218724204U true CN218724204U (en) 2023-03-24

Family

ID=85633566

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222404752.7U Active CN218724204U (en) 2022-09-09 2022-09-09 Soil resource measures uses fixed point ware

Country Status (1)

Country Link
CN (1) CN218724204U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117647234A (en) * 2024-01-30 2024-03-05 菏泽市国土综合整治服务中心 Land management is measured and is used pointing device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117647234A (en) * 2024-01-30 2024-03-05 菏泽市国土综合整治服务中心 Land management is measured and is used pointing device
CN117647234B (en) * 2024-01-30 2024-04-16 菏泽市国土综合整治服务中心 Land management is measured and is used pointing device

Similar Documents

Publication Publication Date Title
CN218724204U (en) Soil resource measures uses fixed point ware
CN209911011U (en) Soil sample collection system convenient to carry
CN210483530U (en) Drilling rig for land exploration
CN116971807A (en) Tunnel excavation supporting structure and construction method
CN218204387U (en) A location mount for civil engineering
CN213774384U (en) Strutting arrangement is used in building engineering construction
CN213148370U (en) Road bridge concrete quality testing is with sample drilling equipment
CN113447300A (en) Soil sampling device for mine detection
CN219909130U (en) Stake pile driving device for river protection
CN210808192U (en) Fertilizer injection unit of fruit seedling
JP3147533B2 (en) Segment feeder
CN213683963U (en) Foundation excavating device for building construction
CN217504795U (en) Based on land engineering survey and drawing is with quick location structure
CN218467619U (en) European style centralized driving trolley
JP3084405U (en) Portable drill
CN219200926U (en) Sample sampling and extracting equipment
CN215292465U (en) Sampling drilling machine for civil investigation and construction
CN220725043U (en) Roadbed punching and sampling device
CN216647703U (en) Many topography signboard base
CN217105087U (en) Fixing structure for piling in constructional engineering
CN213391977U (en) A pile device for bridge construction
CN214196348U (en) Small guide pipe jacking device for tunnel grouting
CN218863764U (en) Measuring tool for architectural design
CN213144470U (en) Jacking and jacking block of shield tunneling machine
CN215761473U (en) Drilling rig for geotechnical engineering investigation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant