CN218714865U - Construction work platform - Google Patents

Construction work platform Download PDF

Info

Publication number
CN218714865U
CN218714865U CN202222972116.4U CN202222972116U CN218714865U CN 218714865 U CN218714865 U CN 218714865U CN 202222972116 U CN202222972116 U CN 202222972116U CN 218714865 U CN218714865 U CN 218714865U
Authority
CN
China
Prior art keywords
construction
fence frame
construction fence
frame
fixed mounting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222972116.4U
Other languages
Chinese (zh)
Inventor
王立军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jilin No1 Construction Engineering Co ltd
Original Assignee
Jilin No1 Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jilin No1 Construction Engineering Co ltd filed Critical Jilin No1 Construction Engineering Co ltd
Priority to CN202222972116.4U priority Critical patent/CN218714865U/en
Application granted granted Critical
Publication of CN218714865U publication Critical patent/CN218714865U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a construction operation platform belongs to and lifts platform equipment field, a construction operation platform, including lifting machine and the construction fence frame of fixed mounting at the lifting machine top, be located the through-hole top construction fence frame top fixed mounting has material lifting component, the inside one side fixed mounting of construction fence frame has the controller, construction fence frame both sides all are provided with the guard plate, and it makes the extension through making the construction fence frame on current construction operation platform basis to installation material lifting component's promotion motor, capstan winch, steel cable and mounting panel on construction fence frame, make this construction fence frame can utilize material lifting component directly to promote the material inside the construction fence frame of eminence, practiced thrift the time that eminence material acquireed, avoid frequently going back and forth eminence and bottom because of construction fence frame and acquire the constructor who causes to stand on construction fence frame has to have to be interrupted work, improve the convenience when this platform uses, improve work efficiency.

Description

Construction work platform
Technical Field
The utility model relates to a lift platform equipment field, more specifically say, relate to a construction work platform.
Background
The construction operation platform is used for transporting constructors to a high place to construct tools, is very wide in application in the aspects of exterior wall decoration, anticorrosion engineering, overhauling, installation and the like, and is an essential tool in house construction. In the related art, a construction work platform generally comprises a driving base of a lifting machine, a lifting arm and a work platform, and when the construction work platform is used, the lifting arm drives the work platform to lift on the driving base, so that constructors are transported to a high place to carry out work.
However, the existing construction operation platform lacks a special material lifting mechanism, when a constructor is lifted to a high position along with construction materials, if the materials are used up, the constructor is required to lower the whole operation platform to the bottommost part and then carry the materials again and enable the whole operation platform to ascend to the construction position again, the whole operation platform is repeatedly ascended and descended due to the fact that the materials are taken, convenience in use is lowered, and due to the fact that the whole operation platform ascends and descends, the constructor standing on the operation platform has to work intermittently, efficiency in construction operation is affected, and therefore the construction operation platform is provided for solving the existing problems.
SUMMERY OF THE UTILITY MODEL
1. Technical problem to be solved
Problem to exist among the prior art, an object of the utility model is to provide a construction work platform, it makes the extension with the construction fence frame on current construction work platform basis, leave the installation space of material promotion subassembly, and install the promotion motor of material promotion subassembly on the construction fence frame, the capstan winch, steel cable and handling board, make this construction fence frame can be when being in the eminence, need not to descend to the lower, utilize material promotion subassembly direct with the material promote inside the construction fence frame of eminence, be convenient for the transport of material, avoid construction fence frame need frequently come and go eminence and bottom, the time that the eminence material acquireed has been practiced thrift, avoid frequently coming and going the eminence and the bottom acquisition material and causing the constructor who stands on the construction fence frame to have to be interrupted work because of construction fence frame, improve the convenience when this platform uses, and improve work efficiency.
2. Technical scheme
In order to solve the above problems, the utility model adopts the following technical proposal.
The utility model provides a construction operation platform, includes the machine of lifting and the construction breast frame of fixed mounting at the machine of lifting top, the through-hole has been seted up to construction breast frame bottom one side, is located the through-hole top construction breast frame top fixed mounting has material lifting unit, lifting machine bottom both sides are rotated and are connected with two bracing pieces, the inside one side fixed mounting of construction breast frame has the controller, construction breast frame both sides all are provided with the guard plate, just the guard plate both sides are all rotated through the round pin axle and are connected with the connection piece, the connection piece with correspond construction breast frame bottom one side fixed welding, material lifting unit includes through screw fixed mounting be in two crossbeams at construction breast frame top, and one of them crossbeam one side fixed welding has the mounting panel, bolt fixed mounting has two promotion motors at the mounting panel top, material lifting unit still including set up in the loading and unloading board of through-hole bottom.
Further, two all fixed welding in crossbeam top has two ear seats, corresponds two rotate between the ear seat and be connected with the pivot, just pivot periphery fixed mounting has two capstans, the winding of capstan winch periphery has the steel cable, just the steel cable bottom with loading and unloading board top fixed connection.
Furthermore, the output shafts of the two lifting motors are respectively connected with one end of the corresponding rotating shaft through a coupler, and the length and the width of the loading and unloading plate are smaller than those of the through hole.
Furthermore, a set of lug plates are welded on two sides of the bottom of the lifting machine corresponding to the joint of the two support rods, pin holes are formed in one end of each support rod and one set of lug plates, and one end of each support rod is rotatably connected with the corresponding set of lug plates through a pin shaft.
Furthermore, a threaded hole is formed in the other end of the supporting rod, and a base is in threaded connection with the inside of the threaded hole.
Furthermore, one side of the top of the protection plate is rotatably connected with a hook through an angle piece, and the hook is connected with a frame corresponding to the inside of the construction hurdle frame in a hanging mode.
3. Advantageous effects
Compared with the prior art, the utility model has the advantages of:
(1) According to the scheme, the construction fence frame is extended on the basis of the existing construction operation platform, the installation space of the material lifting assembly is reserved, and the lifting motor, the winch, the steel cable and the loading and unloading plate of the material lifting assembly are installed on the construction fence frame, so that the construction fence frame can be lifted to the interior of the high construction fence frame directly by using the material lifting assembly when the construction fence frame is positioned at a high position without descending to the lowest position, the material is conveniently conveyed, frequent high-position and bottom reciprocating of the construction fence frame is avoided, the time for acquiring the material at the high position is saved, the problem that constructors standing on the construction fence frame have to work discontinuously due to the fact that the construction fence frame needs to frequently reciprocate the high position and acquire the material at the bottom is avoided, the convenience of the platform in use is improved, and the working efficiency is improved;
(2) This scheme, two bracing pieces rotate through round pin axle and auricle and machine bottom both sides of lifting and are connected, can expand when using and support the machine of lifting, increase area of contact improves stability, and can fold to the machine both sides of lifting after the use is accomplished, reduces and invades occupation of space.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention;
fig. 2 is an enlarged schematic structural view of a point a in fig. 1 according to the present invention;
FIG. 3 is a schematic structural view of the material lifting assembly of the present invention;
fig. 4 is a schematic diagram of the protection plate structure of the present invention.
The reference numbers in the figures illustrate:
1. a lifter; 101. a tab; 102. a pin shaft; 2. constructing a fence frame; 201. a through hole; 3. a material lifting assembly; 4. a support bar; 401. a base; 5. a controller; 6. a protection plate; 601. connecting sheets; 602. hooking; 7. a cross beam; 701. mounting a plate; 702. an ear mount; 8. a hoisting motor; 9. assembling and disassembling the plate; 10. a rotating shaft; 11. a winch; 12. a wire rope.
Detailed Description
The technical solution in the embodiment of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiment of the present invention; obviously, the described embodiments are only a part of the embodiments of the present invention, and not all embodiments, and all other embodiments obtained by those skilled in the art without any inventive work are within the scope of the present invention based on the embodiments of the present invention.
Example (b):
please refer to fig. 1-4, a construction work platform, including lifting machine 1 and construction hurdle frame 2 fixedly mounted at the top of lifting machine 1, through-hole 201 has been seted up to construction hurdle frame 2 bottom one side, construction hurdle frame 2 top fixed mounting that is located the through-hole 201 top has material lifting assembly 3, lifting machine 1 bottom both sides are rotated and are connected with two bracing pieces 4, construction hurdle frame 2 inside one side fixed mounting has controller 5, construction hurdle frame 2 both sides all are provided with guard plate 6, and guard plate 6 both sides all rotate through the connecting axle and are connected with connection piece 601, connection piece 601 and the corresponding construction hurdle frame 2 bottom one side fixed weld, material lifting assembly 3 includes two crossbeams 7 through screw fixed mounting at construction hurdle frame 2 top, and one of them crossbeam 7 one side fixed weld has mounting panel 701, there are two lifting motor 8 at mounting panel 701 top through bolt fixed mounting, material lifting assembly 3 still includes the loading and unloading board 9 that sets up in through-hole 201 bottom.
During the use, at first expand two bracing pieces 4, support to this construction work platform and increase the support area, prevent to take place to collapse crooked, improve the security, then will stand at the constructor and the part material at construction fence frame 2 top through the machine of lifting 1 and lift to the high department together and carry out the construction operation, after the material is used up, release the handling board 9 through the material lifting means 3 of construction fence frame 2 one side, and release the handling board 9 to the lower, place remaining material on the handling board 9 by the constructor that is located the machine of lifting 1 bottom, and start material lifting means 3 and promote the material, until the material is promoted to inside the construction fence frame 2, avoid construction fence frame 2 to drive the constructor whole and rise or descend, time saving, the convenience of use is improved.
Referring to fig. 3, two fixed welds in the top of two crossbeams 7 have two ear seats 702, correspond to rotate between two ear seats 702 and be connected with pivot 10, and pivot 10 periphery fixed mounting has two winches 11, and the winding of 11 peripheries of winches has steel cable 12, and steel cable 12 bottom and handling board 9 top fixed connection, two output shafts that promote motor 8 are connected with corresponding pivot 10 one end respectively through the shaft coupling, and the length and the width of handling board 9 are less than the length and the width of through-hole 201.
When two lifting motors 8 inside the material lifting assembly 3 are started, the winch 11 outside the corresponding two rotating shafts 10 and the rotating shaft 10 can be driven to rotate, and then the steel cable 12 is coiled or released, so that the loading and unloading plate 9 connected to the bottom of the steel cable 12 is lifted or descended, and the loading and unloading of materials are facilitated.
Referring to fig. 1 and 2, a set of lugs 101 are welded on two sides of the bottom of the lifting machine 1 corresponding to the joint of the two support rods 4, pin holes are formed in one end of each support rod 4 and the corresponding lug 101, one end of each support rod 4 is rotatably connected with the corresponding lug 101 through a pin shaft 102, a threaded hole is formed in the other end of each support rod 4, and a base 401 is in threaded connection with the inside of each threaded hole.
Two bracing pieces 4 rotate through round pin axle 102 and auricle 101 and lift 1 bottom both sides and be connected, can expand when using and support lifting machine 1, increase area of contact, improve stability, and can fold to lifting machine 1 both sides after the use is accomplished, reduce and encroach the space.
Referring to fig. 4, one side of the top of the protection plate 6 is rotatably connected with a hook 602 through a corner fitting, and the hook 602 is hooked with a frame inside the corresponding construction hurdle frame 2.
The protection area of this construction hurdle frame 2 can be increased through the guard plate 6 that sets up, prevents that article from dropping, and guard plate 6 is collapsible through couple 602 and accomodates, convenience when improving the removal.
When in use: firstly, two support rods 4 are unfolded, the construction operation platform is supported to increase the support area, the collapse and the skew are prevented, the safety is improved, then constructors and partial materials standing at the top of a construction fence frame 2 are lifted to a high position through a lifting machine 1 and are subjected to construction operation, when the materials are used up, a loading and unloading plate 9 is released through a material lifting assembly 3 on one side of the construction fence frame 2, the loading and unloading plate 9 is released to the lowest position, other materials are placed on the loading and unloading plate 9 by the constructors located at the bottom of the lifting machine 1, the materials are lifted by starting the material lifting assembly 3 until the materials are lifted to the inside of the construction fence frame 2, in the process, when two lifting motors 8 inside the material lifting assembly 3 are started, two corresponding rotating shafts 10 and winches 11 outside the rotating shafts 10 can be driven to rotate, then, the steel cables 12 are wound or released, and therefore the loading and unloading plate 9 connected to the bottom of the steel cables 12 is lifted or descended, the conveying of the materials is facilitated, the construction fence frame 2 is prevented from driving the constructors to integrally lifted or descended, the whole steel cables are saved, and the use convenience is improved.
The above description is only the preferred embodiment of the present invention; the scope of the present invention is not limited thereto. Any person skilled in the art should also be able to cover the technical scope of the present invention by replacing or changing the technical solution and the improvement concept of the present invention with equivalents and modifications within the technical scope of the present invention.

Claims (6)

1. The utility model provides a construction work platform, includes machine of lifting (1) and fixed mounting at construction hurdle frame (2) at machine of lifting (1) top, its characterized in that: through-hole (201) has been seted up to construction fence frame (2) bottom one side, is located through-hole (201) top construction fence frame (2) top fixed mounting has material lifting unit (3), machine (1) bottom both sides of lifting are rotated and are connected with two bracing pieces (4), the inside one side fixed mounting of construction fence frame (2) has controller (5), construction fence frame (2) both sides all are provided with guard plate (6), just guard plate (6) both sides are connected with connection piece (601) through all rotating through the connecting axle, connection piece (601) and correspondence construction fence frame (2) bottom one side fixed welding, material lifting unit (3) include through screw fixed mounting be in two crossbeams (7) at construction fence frame (2) top, and one of them crossbeam (7) one side fixed welding has mounting panel (701), bolt fixed mounting has two lifting motor (8) at mounting panel (701) top, material lifting unit (3) still including set up in loading and unloading board (9) of through-hole (201) bottom.
2. A construction work platform according to claim 1, characterised in that: two the equal fixed welding in crossbeam (7) top has two ear seats (702), corresponds two it is connected with pivot (10) to rotate between ear seat (702), just pivot (10) periphery fixed mounting has two capstan winches (11), capstan winch (11) periphery winding has steel cable (12), just steel cable (12) bottom with loading and unloading board (9) top fixed connection.
3. A construction work platform according to claim 2, wherein: the output shafts of the two lifting motors (8) are respectively connected with one end of the corresponding rotating shaft (10) through a coupler, and the length and the width of the loading and unloading plate (9) are smaller than those of the through hole (201).
4. A construction work platform according to claim 1, wherein: correspond two bracing piece (4) junction lift machine (1) bottom both sides all weld and have a set of auricle (101), bracing piece (4) one end and a set of the pinhole has all been seted up to auricle (101) inside, bracing piece (4) one end with correspond a set of auricle (101) inside is rotated through round pin axle (102) and is connected.
5. A construction work platform according to claim 1, characterised in that: the other end of the supporting rod (4) is provided with a threaded hole, and the threaded hole is internally and threadedly connected with a base (401).
6. A construction work platform according to claim 1, characterised in that: protection plate (6) top one side is rotated through the corner fitting and is connected with couple (602), couple (602) with correspond the inside frame of construction hurdle frame (2) articulates mutually.
CN202222972116.4U 2022-11-08 2022-11-08 Construction work platform Active CN218714865U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222972116.4U CN218714865U (en) 2022-11-08 2022-11-08 Construction work platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222972116.4U CN218714865U (en) 2022-11-08 2022-11-08 Construction work platform

Publications (1)

Publication Number Publication Date
CN218714865U true CN218714865U (en) 2023-03-24

Family

ID=85610707

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222972116.4U Active CN218714865U (en) 2022-11-08 2022-11-08 Construction work platform

Country Status (1)

Country Link
CN (1) CN218714865U (en)

Similar Documents

Publication Publication Date Title
CN218714865U (en) Construction work platform
CN213774378U (en) Assembled building safety construction platform
CN215048082U (en) Integral hoisting sling for prefabricated box girder steel reinforcement framework
CN216109600U (en) Liftable support for construction engineering construction
CN211998623U (en) Automatic loading and unloading lifting platform device
CN110182698B (en) Climbing device and self-climbing crane
CN209815543U (en) Hoisting accessory for auto repair
CN114763243A (en) Combined lifting appliance for loading and unloading steel wire rod
CN218507491U (en) Simple electric forklift capable of being hoisted
CN214243534U (en) Large-scale heavily block davit for testing platform
CN211871184U (en) Portal frame for architectural decoration
CN220223204U (en) Hoisting device
CN215048194U (en) Hoisting equipment for assembly type building construction
CN205419582U (en) Floor hoist
CN209988979U (en) Lifting adjusting device for high-tech building construction
CN212503705U (en) Assembled building element hoist device
CN214456338U (en) Novel anti-drop's material for construction lifts by crane device
CN221116788U (en) Elevator well material transportation equipment
CN214031466U (en) Improved generation hoisting device for construction machinery assembly
CN216889930U (en) Quick elevator
CN221165584U (en) Multi-hook synchronous steel wire rope hoist
CN211770091U (en) Lifting platform
CN217458499U (en) Movable lifting machine
CN210596182U (en) Portable work piece tempering cooling lift
CN212050267U (en) Hoisting frame for building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant