CN218612614U - Structural steel column iron tower welding platform - Google Patents
Structural steel column iron tower welding platform Download PDFInfo
- Publication number
- CN218612614U CN218612614U CN202223302970.6U CN202223302970U CN218612614U CN 218612614 U CN218612614 U CN 218612614U CN 202223302970 U CN202223302970 U CN 202223302970U CN 218612614 U CN218612614 U CN 218612614U
- Authority
- CN
- China
- Prior art keywords
- iron tower
- frame
- clamping member
- clamping
- steel column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/72—Wind turbines with rotation axis in wind direction
Landscapes
- Butt Welding And Welding Of Specific Article (AREA)
Abstract
The application provides a structural formula steel column iron tower welded platform can improve the production efficiency of iron tower. The application includes: the middle position of connecting the base is provided with the standing groove, install in the standing groove lifting unit, first braced frame is installed one side of connecting the base, second braced frame is installed the opposite side of connecting the base, first braced frame with install the second braced frame below the removal subassembly, first braced frame with install on the second braced frame press from both sides and get locating component, press from both sides and get locating component setting and be in lifting unit's top, welding equipment installs first braced frame with on the second braced frame, lifting unit is used for driving iron tower frame and goes up and down, cooperates press from both sides and get locating component and press from both sides iron tower frame and get fixedly, welding equipment is used for with outside steelframe welding on the iron tower frame.
Description
Technical Field
The invention mainly relates to the technical field of iron tower welding, in particular to a structural steel column iron tower welding platform.
Background
The lattice type steel column iron tower is a structure arranged on two sides of a railway and used for supporting a power supply line and providing sufficient energy for a high-speed train so that the high-speed train can stably run. Wherein, lattice formula steel column iron tower itself needs to possess stronger stability, so when production lattice formula steel column iron tower, need use many steel columns to weld, and the length of many steel columns is different, when welding the inside steel column of some iron towers on main body frame, need weld again after fixing the main body frame of iron tower.
At present, the main body frame is placed on a welding platform, after the main body frame is fixed through the welding platform, steel columns inside some iron towers are welded, but when the main body frame of the iron tower is fixed through the current welding platform, the main body frame is lifted to a certain height by external equipment, the main body frame can be fixed through the welding platform, the main body frame is lifted through the external equipment, the butt joint is not accurate, the problem of long fixing time is solved, and the production efficiency of the iron tower is reduced. Based on this, the application provides a structural formula steel column iron tower welded platform is used for solving above-mentioned problem.
SUMMERY OF THE UTILITY MODEL
In order to solve the defects of the prior art, the invention provides the structural steel column and iron tower welding platform, the iron tower frame is driven to lift through the lifting assembly, and the clamping and fixing assembly is matched to clamp and fix the iron tower frame, so that the problems that the existing main body frame needs to be lifted by external equipment, the butt joint is possibly inaccurate, and the connection and fixing time is long are effectively solved. The production efficiency of iron tower is improved.
In order to achieve the purpose, the invention is realized by the following technical scheme:
a structural formula steel column iron tower welded platform includes: the device comprises a connecting base, a lifting assembly, a first supporting frame, a second supporting frame, a clamping and positioning assembly and welding equipment;
the middle position of connecting the base is provided with the standing groove, install in the standing groove lifting unit, first braced frame is installed one side of connecting the base, second braced frame is installed the opposite side of connecting the base, first braced frame with install the second braced frame below the removal subassembly, first braced frame with install on the second braced frame press from both sides and get locating component, press from both sides and get locating component setting and be in lifting unit's top, welding equipment installs first braced frame with on the second braced frame, lifting unit is used for driving iron tower frame and goes up and down, cooperates press from both sides and get locating component and press from both sides iron tower frame and get fixedly, welding equipment is used for with outside steelframe welding on the iron tower frame.
The utility model discloses as foretell structural formula steel column iron tower welded platform, it is further, lifting unit is including supporting plate, hydraulic lifting rod and backplate, hydraulic lifting rod's bottom is installed on the standing groove, hydraulic lifting rod's lift end with it connects to support the plate bottom, the surface both sides of supporting the plate are installed the backplate.
The utility model discloses as foretell structural formula steel column iron tower welded platform, it is further, the backplate sets up press from both sides one side of getting locating component.
The utility model discloses as foretell structural formula steel column iron tower welded platform, further, press from both sides to get the locating component and include that first clamp gets, the second presss from both sides gets, the third presss from both sides gets and the fourth presss from both sides gets, first clamp get with the second presss from both sides gets and installs on the first braced frame, the third press from both sides get with the fourth presss from both sides gets and installs on the second braced frame.
The utility model provides an foretell structural formula steel column iron tower welded platform, it is further, first clamp is got including installation plate body, first telescopic link, second telescopic link, first grip block and second grip block, the installation plate body is installed on the first braced frame, be provided with the fluting on the installation plate body, first telescopic link is installed grooved top, first telescopic link with first grip block is connected, the second telescopic link is installed grooved below, the second telescopic link with the second grip block is connected, first grip block with the second grip block is in first telescopic link with be used for the fixed iron tower frame of centre gripping under the effect of second telescopic link.
The utility model discloses as foretell structural formula steel column iron tower welded platform, it is further, first press from both sides get with the second is pressed from both sides and is got and be provided with first predetermined interval between the piece, install welding equipment in the first predetermined interval.
The utility model discloses as foretell structural formula steel column iron tower welded platform, it is further, the third press from both sides get with the fourth is pressed from both sides and is got and be provided with the second between the piece and predetermine the interval, install welding equipment in the second predetermines the interval.
The utility model discloses as foretell structural formula steel column iron tower welded platform, it is further, first press from both sides get with the fourth presss from both sides to get the piece setting on same straight line, the second press from both sides get with the third presss from both sides to get the piece setting on same straight line.
The utility model discloses as foretell structural formula steel column iron tower welded platform, it is further, first braced frame with be provided with the installation member on the second braced frame, first clamp get the piece the second clamp get the piece the third clamp get the piece with the fourth clamp is got the piece and is installed on the installation member.
The utility model discloses as foretell structural formula steel column iron tower welded platform, it is further, connect the base below and install first supporting plate body and second supporting plate body.
Contrast prior art, the beneficial effects of the utility model are that:
the steel column iron tower welding platform is provided with a connecting base, a lifting assembly, a first supporting frame, a second supporting frame, a clamping and positioning assembly and welding equipment; the welding equipment comprises a base, a placing groove, a lifting assembly, a first supporting frame, a second supporting frame, a clamping positioning assembly, a welding device, a lifting assembly and a clamping positioning assembly, wherein the placing groove is formed in the middle of the base, the lifting assembly is installed in the placing groove, the first supporting frame is installed on one side of the base, the second supporting frame is installed on the other side of the base, the moving assembly is installed below the first supporting frame and the second supporting frame, the clamping positioning assembly is installed on the first supporting frame and the second supporting frame, the clamping positioning assembly is arranged above the lifting assembly in a clamping mode, the welding equipment is installed on the first supporting frame and the second supporting frame, the lifting assembly is used for driving an iron tower frame to lift, the clamping positioning assembly is matched with the clamping positioning assembly to clamp the iron tower frame, and the welding equipment is used for welding an external steel frame on the iron tower frame.
In practical application, the iron tower frame is movably placed on the lifting assembly, the iron tower frame is driven to ascend under the action of the lifting assembly, after the lifting assembly ascends to a certain height, the iron tower frame can be clamped and fixed under the action of the clamping and positioning assembly and the moving assembly, and the iron tower frame can be welded on the iron tower frame by matching with welding equipment arranged on the first supporting frame and the second supporting frame. Therefore, the problems that the existing main body frame needs to be lifted by external equipment, docking is possibly inaccurate, and the connection fixing time is long are effectively solved. The production efficiency of iron tower is improved.
Drawings
FIG. 1 is a schematic diagram of the overall structure of a steel column and iron tower welding platform of the structural formula of the present application;
FIG. 2 is another schematic view of the overall structure of the structural steel column and iron tower welding platform of the present application;
FIG. 3 is another schematic view of the overall structure of the structural steel column and iron tower welding platform of the present application;
FIG. 4 is another schematic view of the overall structure of the structural steel column and iron tower welding platform of the present application;
reference numerals shown in the drawings: 1. connecting a base; 11. a first support plate body; 12. a second support plate body; 2. a support plate; 21. a guard plate; 3. a hydraulic lifting rod; 4. a first support frame; 5. a second support frame; 51. installing a rod piece; 6. a first clamping member; 61. a first clamping plate; 62. a second clamping plate; 7. welding equipment; 8. a second gripping member; 9. a third clamping part; 91. a moving assembly; 10. and a fourth clamping member.
Detailed Description
The invention is further described with reference to the accompanying drawings and the specific embodiments. It should be understood that these examples are for illustrative purposes only and are not intended to limit the scope of the present invention. Further, it should be understood that various changes or modifications of the present invention may be made by those skilled in the art after reading the teaching of the present invention, and these equivalents also fall within the scope of the present application.
As shown in fig. 1-4, the present application provides a structural steel column and iron tower welding platform, comprising: the device comprises a connecting base 1, a lifting assembly, a first supporting frame 4, a second supporting frame 5, a clamping and positioning assembly and welding equipment 7; the intermediate position of connecting base 1 is provided with the standing groove, install in the standing groove lifting unit, first braced frame 4 is installed connect one side of base 1, second braced frame 5 is installed connect the opposite side of base 1, first braced frame 4 with install second braced frame 5 below remove subassembly 91, first braced frame 4 with install on the second braced frame 5 press from both sides and get locating component, press from both sides and get locating component setting and be in lifting unit's top, welding equipment 7 is installed first braced frame 4 with on the second braced frame 5, lifting unit is used for driving iron tower frame and goes up and down, the cooperation press from both sides and get locating component and press from both sides iron tower frame and get fixedly, welding equipment 7 is used for getting outside steelframe welding on the iron tower frame.
When the current welding platform is used for fixing the main body frame of the iron tower, the main body frame is lifted to a certain height by external equipment, so that the welding platform can be fixed to the main body frame, the main body frame is lifted by the external equipment, the problems of inaccurate butt joint and long connection fixing time exist, and the production efficiency of the iron tower is reduced. Based on this, the application provides a structural steel column iron tower welded platform, can improve the production efficiency of iron tower, and is specific, structural steel column iron tower welded platform is last to be provided with connection base 1, install first supporting plate body 11 and second supporting plate body 12 connecting base 1 below, support connecting base 1 through first supporting plate body 11 and second supporting plate body 12, thereby guarantee the stability of whole equipment, make the operation that whole equipment can be normal, be provided with the standing groove in the top of connecting base 1, do not specifically prescribe a limit to the notch area of standing groove in this application, see to set for according to actual conditions, regard as the accuracy with concrete realization.
Install lifting unit in the standing groove, install first braced frame 4 and second braced frame 5 respectively in lifting unit's both sides, all install on first braced frame 4 and second braced frame 5 and get locating component. It should be noted that, the distance between the clamping and positioning assembly and the lifting assembly is set, so that when the lifting assembly drives the iron tower frame to move up, the iron tower frame does not collide with the clamping and positioning assembly, and only after the lifting assembly moves up to a certain height, under the action of the moving assembly 91, the first supporting frame 4 and the second supporting frame 5 can be driven to move, so that the clamping and positioning assembly clamps the steel frame iron tower, and the external steel frame is welded on the iron tower frame through the welding equipment 7.
It should be noted that the moving assembly 91 may be composed of a motor and a roller, and the roller is driven by the motor to rotate, so as to realize the movement of the first supporting frame 4 and the second supporting frame 5 on the connecting base 1, and may also be completed by other assemblies, so as to be implemented specifically, and is not limited specifically herein.
Wherein, lifting unit is including supporting plate 2, hydraulic lifting rod 3 and backplate 21, and install on the standing groove hydraulic lifting rod 3's bottom, and hydraulic lifting rod 3's lift end is connected with the 2 bottoms of support plate, and backplate 21 is installed to the surface both sides of supporting plate 2.
In this application embodiment, place iron tower frame on support plate 2, carry on spacingly to iron tower frame through backplate 21 on the support plate 2, prevent that iron tower frame from rising or descending in-process to take place to drop, and backplate 21 sets up and gets one side of locating component in pressing from both sides, when backplate 21 followed support plate 2 and upwards moved promptly, backplate 21 can not take place the contact collision with centre gripping locating component.
Wherein, press from both sides and get the locating component and include that first clamp is got 6, second clamp and get 8, third clamp and get 9 and fourth clamp and get 10, first clamp get 6 with second clamp is got 8 and is installed on first braced frame 4, and third clamp is got 9 and fourth clamp and is got 10 and install on second braced frame 5.
It should be noted that the first clamping member 6, the second clamping member 8, the third clamping member 9 and the fourth clamping member 10 are of the same structure, in this application, the first clamping member 6 is taken as an example for illustration, the first clamping member 6 includes an installation plate body, a first telescopic rod, a second telescopic rod, a first clamping plate 61 and a second clamping plate 62, the installation plate body is installed on the first supporting frame 4, a slot is formed in the installation plate body, the first telescopic rod is installed above the slot, the first telescopic rod is connected with the first clamping plate 61, the second telescopic rod is installed below the slot, the second telescopic rod is connected with the second clamping plate 62, and the first clamping plate 61 and the second clamping plate 62 are used for clamping and fixing the iron tower framework under the action of the first telescopic rod and the second telescopic rod.
Wherein, first clamp get 6 with be provided with first preset interval between the second clamp get 8, install welding equipment 7 in the first preset interval, third clamp get 9 and fourth clamp get 10 between be provided with the second preset interval, install welding equipment 7 in the second preset interval. After the iron tower frame is clamped and fixed by the first clamping piece 6, the second clamping piece 8, the third clamping piece 9 and the fourth clamping piece 10, the external steel frame can be welded on the iron tower frame by the welding equipment 7.
Wherein, first clamping piece 6 and fourth clamping piece 10 set up on the collinear, and second clamping piece 8 and third clamping piece 9 set up on the collinear to make placing that iron tower steelframe can be stable on first clamping piece 6, second clamping piece 8, third clamping piece 9 and fourth clamping piece 10.
Wherein, the first supporting frame 4 and the second supporting frame 5 are provided with an installation rod member 51, and the first clamping member 6, the second clamping member 8, the third clamping member 9 and the fourth clamping member 10 are installed on the installation rod member 51.
The technical features disclosed above are not limited to the combinations with other features disclosed, and other combinations between the technical features can be performed by those skilled in the art according to the purpose of the invention to achieve the aim of the invention.
Claims (10)
1. The utility model provides a structural formula steel column iron tower welded platform which characterized in that includes: the device comprises a connecting base, a lifting assembly, a first supporting frame, a second supporting frame, a moving assembly, a clamping and positioning assembly and welding equipment;
the middle position of connecting the base is provided with the standing groove, install in the standing groove lifting unit, first braced frame is installed one side of connecting the base, second braced frame is installed the opposite side of connecting the base, first braced frame with install the second braced frame below the removal subassembly, first braced frame with install on the second braced frame press from both sides and get locating component, press from both sides and get locating component setting and be in lifting unit's top, welding equipment installs first braced frame with on the second braced frame, lifting unit is used for driving iron tower frame and goes up and down, cooperates press from both sides and get locating component and press from both sides iron tower frame and get fixedly, welding equipment is used for with outside steelframe welding on the iron tower frame.
2. The structural steel column iron tower welding platform according to claim 1, wherein the lifting assembly comprises a supporting plate, a hydraulic lifting rod and guard plates, the bottom end of the hydraulic lifting rod is mounted on the placing groove, the lifting end of the hydraulic lifting rod is connected with the bottom of the supporting plate, and the guard plates are mounted on two sides of the outer surface of the supporting plate.
3. The structural steel column pylon welding platform of claim 2, wherein the guard plate is disposed on one side of the clamping and positioning assembly.
4. The structural steel column iron tower welding platform of claim 1, wherein the clamping and positioning assembly comprises a first clamping member, a second clamping member, a third clamping member, and a fourth clamping member, the first clamping member and the second clamping member being mounted on the first support frame, the third clamping member and the fourth clamping member being mounted on the second support frame.
5. The structural steel column iron tower welding platform according to claim 4, wherein the first clamping member comprises a mounting plate body, a first telescopic rod, a second telescopic rod, a first clamping plate and a second clamping plate, the mounting plate body is mounted on the first supporting frame, a slot is formed in the mounting plate body, the first telescopic rod is mounted above the slot, the first telescopic rod is connected with the first clamping plate, the second telescopic rod is mounted below the slot, the second telescopic rod is connected with the second clamping plate, and the first clamping plate and the second clamping plate are used for clamping and fixing an iron tower frame under the action of the first telescopic rod and the second telescopic rod.
6. The structural steel column iron tower welding platform according to claim 4, wherein a first predetermined spacing is provided between the first clamping member and the second clamping member, and welding equipment is installed in the first predetermined spacing.
7. The structural steel column iron tower welding platform according to claim 4, wherein a second preset distance is arranged between the third clamping member and the fourth clamping member, and welding equipment is installed in the second preset distance.
8. The structural steel column iron tower welded platform of claim 4, wherein the first clamping member and the fourth clamping member are disposed in a same straight line, and the second clamping member and the third clamping member are disposed in a same straight line.
9. The structural steel column iron tower welding platform according to claim 4, wherein the first support frame and the second support frame are provided with mounting bars, and the first clamping member, the second clamping member, the third clamping member and the fourth clamping member are mounted on the mounting bars.
10. The structural steel column iron tower welding platform according to any one of claims 1 to 9, wherein a first support plate body and a second support plate body are mounted below the connection base.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202223302970.6U CN218612614U (en) | 2022-12-08 | 2022-12-08 | Structural steel column iron tower welding platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202223302970.6U CN218612614U (en) | 2022-12-08 | 2022-12-08 | Structural steel column iron tower welding platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN218612614U true CN218612614U (en) | 2023-03-14 |
Family
ID=85453352
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202223302970.6U Active CN218612614U (en) | 2022-12-08 | 2022-12-08 | Structural steel column iron tower welding platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN218612614U (en) |
-
2022
- 2022-12-08 CN CN202223302970.6U patent/CN218612614U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202607139U (en) | Welding jig of lower car platform | |
CN202151757U (en) | Simple jacking tool for part of automobile body | |
CN201519850U (en) | Clamping device for assembly welding of orbit vehicle side wall top side beams | |
CN210172894U (en) | Draw beam assembly welding frock | |
CN218612614U (en) | Structural steel column iron tower welding platform | |
CN113700140B (en) | High-strength self-fastening steel structure joint for energy-saving building and manufacturing method thereof | |
CN205600127U (en) | High-frequency welding machine | |
CN112894043B (en) | Follow-up tail guiding clamping device of series welding machine and clamping method thereof | |
CN212656119U (en) | Large-scale steel box girder normal position supporting method installation removal regulation location frock | |
CN215498595U (en) | Mounting structure and grinding machine of heavy part | |
CN210361134U (en) | Device is changed to shaped steel roughing mill compensating beam | |
CN213560504U (en) | AC projection welding machine | |
CN213195396U (en) | Lifting bending carrying platform for welding strip | |
CN216966820U (en) | Workpiece mounting and fixing device | |
CN209156777U (en) | A kind of steel pipe bundle straightening equipment | |
CN207358360U (en) | The spot welding process equipment of door of elevator | |
CN219053411U (en) | Crane trolley welding tool | |
CN218465426U (en) | New forms of energy battery package positioner | |
CN216648538U (en) | Stainless steel electricity core-switching piece welding position device | |
CN219005082U (en) | Stainless steel plate welding and fixing device | |
CN217253949U (en) | A assembly welding device for processing pour U type bolt | |
CN217991450U (en) | End wall equipment child | |
CN216680846U (en) | Hot riveting welding oblique welding point and vertical welding point simultaneous welding device | |
CN211780011U (en) | Industrial robot is with installation base convenient to adjust | |
CN209890168U (en) | Board trades overhauls auxiliary device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |