CN218596961U - Temporary simple enclosing structure for sloping field - Google Patents

Temporary simple enclosing structure for sloping field Download PDF

Info

Publication number
CN218596961U
CN218596961U CN202223141790.4U CN202223141790U CN218596961U CN 218596961 U CN218596961 U CN 218596961U CN 202223141790 U CN202223141790 U CN 202223141790U CN 218596961 U CN218596961 U CN 218596961U
Authority
CN
China
Prior art keywords
anchor
column
upright
rope
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202223141790.4U
Other languages
Chinese (zh)
Inventor
马兵
杜建国
耿长毅
刘相顺
孙满红
耿金康
关维敏
尚鹏超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China State Construction Xinjiang Construction Engineering Group Co ltd
Original Assignee
China State Construction Xinjiang Construction Engineering Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China State Construction Xinjiang Construction Engineering Group Co ltd filed Critical China State Construction Xinjiang Construction Engineering Group Co ltd
Priority to CN202223141790.4U priority Critical patent/CN218596961U/en
Application granted granted Critical
Publication of CN218596961U publication Critical patent/CN218596961U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/23Dune restoration or creation; Cliff stabilisation

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

The utility model relates to a fender technical field is enclosed in the protection, concretely relates to temporary simple and easy fender structure that encloses of hillside fields. The device comprises a base, a plurality of upright posts and ground anchors, wherein the base comprises mounting holes, the upright posts and fixing rods; one side of the adjacent upright post close to the slope-facing surface is provided with a fixed rope; the ground anchors are provided with a plurality of ground anchors, are arranged on one side of the upright post close to the slope-facing surface and comprise anchor holes and anchor posts; a pull rope is arranged between the anchor post and the upright post; the stay cord is wire rope, and one end fixed connection is in the stand upper end, and other end fixed connection is in the anchor post upper end. When the device is used, the vertical columns are connected into a whole by the fixing ropes, the safety net is hung to intercept small-grain-size falling rocks, and the overall strength of the simple enclosure is improved. This equipment has reduced required mechanical instrument in the massif construction, has improved the efficiency of being under construction in the massif, and the effectual construction degree of difficulty that reduces drops into with the reduction manual work for the construction progress.

Description

Temporary simple enclosing structure for sloping field
Technical Field
The utility model relates to a fender technical field is enclosed in the protection, concretely relates to temporary simple and easy fender structure that encloses of hillside fields.
Background
In recent years, hotels are more and more popular with tourists as well as are recommended by government departments when the gardens integrated with nature are built on mountains, and people, buildings and nature are the development trend of later buildings. In the construction process, steep hillside slopes have big damage to municipal roads, mountain green plants and the like of west side lower slopes inevitably such as rockfall, rock rolls and the like, and have great potential safety hazards, a protection is needed to be arranged to prevent the rock rolls from falling, the sand bags, concrete walls, steel column iron sheet barriers and the like are stacked traditionally and need to be mechanically entered, and construction in the mountain is difficult, labor efficiency is low, and the influence on the environment is great.
SUMMERY OF THE UTILITY MODEL
The utility model provides a retaining structure is simply enclosed to hillside fields temporarily to solve above-mentioned problem.
The utility model adopts the following technical scheme: a temporary simple enclosure structure for a sloping field comprises a base, a stand column and a ground anchor;
the base is provided with a plurality of bases at intervals, and each base comprises a mounting hole, a foundation column and a fixing rod; the mounting hole is arranged at a preset position; the foundation columns are steel bars, are vertically arranged and inserted into the mounting holes, and the upper ends of the foundation columns extend out of the ground by a preset length; the mounting hole is fixedly connected with the foundation column; the fixed rod is a steel bar and is arranged on the ground; the fixed rod is fixedly connected with the foundation column;
a plurality of upright posts are arranged at intervals; the upright post is a vertically arranged steel pipe, the lower end of the upright post is sleeved on the foundation post and is fixedly connected with the fixed rod; one side of the adjacent upright post close to the slope-facing surface is provided with a fixed rope; the fixed rope is a steel wire rope and is fixedly connected to the upright post; a safety net is hung on the slope surface of the fixed rope;
the ground anchors are provided with a plurality of ground anchors, are arranged on one side of the upright post close to the slope-facing surface and comprise anchor holes and anchor posts; the anchor hole is arranged at a preset position; the anchor columns are steel bars, are vertically inserted into the anchor holes, and the upper ends of the anchor columns extend out of the ground by a preset length; the anchor hole and the anchor post are fixedly connected; a pull rope is arranged between the anchor post and the upright post; the stay cord is wire rope, and one end fixed connection is in the stand upper end, and other end fixed connection is in the anchor post upper end.
Furthermore, the bases are distributed at equal intervals; steel rings which are distributed at equal intervals are welded on the upright post; the fixed rope is equipped with a plurality ofly, and the level sets up, and fixes in corresponding steel ring from top to bottom equipartition ground.
Furthermore, a reinforcing rope is fixedly connected between two adjacent upright columns; the reinforcing ropes are two and are in a cross-brace shape for drawknot.
Further, cement mortar is filled between the mounting hole and the foundation column; cement mortar is filled between the anchor hole and the anchor column.
Furthermore, the upper end of the anchor post is welded with a fixing ring; the fixed ring is formed by bending a steel bar.
Furthermore, the safety net is fixed on the upright posts and the fixing ropes in a binding mode.
The beneficial effects of the utility model are that: when this equipment uses, fixed rope connects into whole with the stand, hangs the safety net in order to intercept small-size grain diameter falling rocks, improves the bulk strength that simply encloses the fender. This equipment has reduced required mechanical instrument in the massif construction, has improved the efficiency of being under construction in the massif, and the effectual construction degree of difficulty that reduces drops into with reducing artifical for the construction progress.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings needed to be used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without inventive exercise.
Fig. 1 is a schematic structural view of an embodiment of a temporary simple barricade structure for a sloping field of the present invention;
fig. 2 is a side view of an embodiment of the present invention;
fig. 3 is a top view of an embodiment of the present invention.
In the figure: 101. a ground surface; 201. a base pillar; 301. a column; 302. fixing a rope; 303. a safety net; 304. a reinforcing cord; 305. steel rings; 401. an anchor post; 402. and pulling a rope.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
The utility model discloses an embodiment of retaining structure is simply enclosed to hillside fields temporarily, as shown in FIG. 1 to FIG. 3: a temporary simple enclosure structure for a sloping field comprises a base, a stand column 301 and a ground anchor;
a plurality of bases are arranged at intervals and comprise mounting holes, foundation columns 201 and fixing rods; the mounting holes are arranged at preset positions, the interval between every two adjacent mounting holes is 2 meters, and the diameter of each mounting hole is 50 millimeters; the foundation column 201 is a 2-meter steel bar with the diameter of 25 mm, is vertically inserted into the mounting hole, and the upper end of the foundation column extends out of the ground 101 for a preset length of 1 meter; the mounting hole is fixedly connected with the base column 201; the fixed rod is a steel bar and is arranged on the ground 101; the fixing rod is connected with the foundation column 201 through welding;
a plurality of upright posts 301 are arranged at intervals; the upright column 301 is a vertically arranged steel pipe, the lower end of which is sleeved on the base column 201 and is fixedly connected with a fixed rod; one side of the adjacent upright posts 301 close to the slope surface is provided with a fixed rope 302; the fixed rope 302 is a steel wire rope and is fixedly connected to the upright column 301; a safety net 303 is hung on the slope surface of the fixed rope 302, and the safety net 303 is a dense mesh net and is used for intercepting falling rocks with small particle sizes and improving the overall strength;
the ground anchors are multiple and arranged in multiples of the upright posts 301, are arranged on one side of the upright posts 301 close to the slope-facing surface and comprise anchor holes and anchor posts 401; the anchor hole is arranged at a preset position; the anchor posts 401 are steel bars and are vertically inserted into the anchor holes, and the upper ends of the anchor posts extend out of the ground 101 by a preset length of 500 mm; the anchor hole is fixedly connected with the anchor column 401; a pull rope 402 is arranged between the anchor column 401 and the upright column 301; stay cord 402 is wire rope, and one end fixed connection is in stand 301 upper end, and other end fixed connection is in anchor post 401 upper end. The fixed rope 302 connects the upright posts 301 into a whole, and the safety net 303 is hung to intercept small-grain-size falling rocks, so that the overall strength of the simple enclosure is improved. This equipment has reduced required mechanical instrument in the massif construction, has improved the efficiency of being under construction in the massif, and the effectual construction degree of difficulty that reduces drops into with the reduction manual work for the construction progress.
In the embodiment, the bases are distributed at equal intervals; steel rings 305 are welded on the upright column 301 and are distributed at equal intervals, wherein the interval between every two adjacent steel rings 305 is 400 mm; the fixing rope 302 adopts a 6 mm galvanized steel wire; the fixed ropes 302 are horizontally arranged and are uniformly fixed in the corresponding steel rings 305.
In this embodiment, a reinforcing rope 304 is fixedly connected between two adjacent upright posts 301; two reinforcing ropes 304 are arranged and are in a cross-brace shape for knot tying, so that the stability between the upright posts 301 is improved.
In the present embodiment, cement mortar is filled between the installation hole and the foundation column 201; cement mortar is filled between the anchor hole and the anchor column 401.
In this embodiment, the upper end of the anchor column 401 is welded with a fixing ring; the retaining ring is a rebar fold for fixedly connecting the pull cord 402.
In this embodiment, the safety net 303 is fixed on the upright 301 and the fixed rope 302 in a binding manner, so that the construction is convenient, and the method is simple and rapid.
With the combination of the above embodiments, the utility model discloses a use principle and working process as follows: when the building is carried out, the mounting holes are drilled into holes by adopting a 28-air drill, the depth of the mounting holes is 1 meter, the distance between every two holes is 2 meters, and the diameter is 5 centimeters.
After the excavation is finished, a reinforcing steel bar with the length of 2 meters and the diameter of 25 millimeters is inserted into the mounting hole, cement mortar is poured into the mounting hole, and the part leaking out of the ground 101 serves as a fixing rod to be welded with the stand column 301 through the waste reinforcing steel bar. Likewise, anchor 401 is fixed to ground 101. The fixing ropes 302 on the two upright posts 301 are 7 galvanized steel wire ropes. Then, the reinforcing ropes 304 between two adjacent upright posts 301 are in a cross-brace shape to be tied, and a safety net 303 is hung on the slope facing surface. The end of anchor 401 is tied to vertical column 301 with pull rope 402, and finally formed.
The above description is only for the preferred embodiment of the present invention, and should not be taken as limiting the invention, and any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (6)

1. The utility model provides a fender structure is simply enclosed to temporary sloping field which characterized in that: comprises a base, a vertical column (301) and a ground anchor;
the base is provided with a plurality of bases at intervals, and each base comprises a mounting hole, a base column (201) and a fixing rod; the mounting hole is arranged at a preset position; the foundation column (201) is a steel bar, is vertically arranged and inserted into the mounting hole, and the upper end of the foundation column extends out of the ground (101) by a preset length; the mounting hole is fixedly connected with the foundation column (201); the fixed rod is a steel bar and is arranged on the ground (101); the fixed rod is fixedly connected with the foundation column (201);
a plurality of upright posts (301) are arranged at intervals; the upright column (301) is a vertically arranged steel pipe, the lower end of the upright column is sleeved on the foundation column (201), and the upright column is fixedly connected with the fixed rod; one side of the adjacent upright post (301) close to the slope-facing surface is provided with a fixed rope (302); the fixed rope (302) is a steel wire rope and is fixedly connected to the upright post (301); a safety net (303) is hung on the slope surface of the fixed rope (302);
the ground anchors are arranged on one side, close to the slope-facing surface, of the upright post (301) and comprise anchor holes and anchor posts (401); the anchor hole is arranged at a preset position; the anchor columns (401) are steel bars and are vertically inserted into the anchor holes, and the upper ends of the anchor columns extend out of the ground (101) by preset lengths; the anchor hole is fixedly connected with the anchor column (401); a pull rope (402) is arranged between the anchor post (401) and the upright post (301); the pull rope (402) is a steel wire rope, one end of the pull rope is fixedly connected to the upper end of the upright post (301), and the other end of the pull rope is fixedly connected to the upper end of the anchor post (401).
2. The temporary simple fence structure for sloping fields as claimed in claim 1, wherein: the bases are distributed at equal intervals; steel rings (305) which are distributed at equal intervals are welded on the upright column (301); the fixed ropes (302) are horizontally arranged and are uniformly fixed in the corresponding steel rings (305).
3. The temporary simple fence structure for sloping fields as claimed in claim 2, wherein: a reinforcing rope (304) is fixedly connected between two adjacent upright posts (301); two reinforcing ropes (304) are arranged and are in a cross-brace shape for knotting.
4. The temporary simple fence structure for sloping fields as claimed in claim 1, wherein: cement mortar is filled between the mounting hole and the foundation column (201); cement mortar is filled between the anchor hole and the anchor post (401).
5. The temporary simple fence structure for sloping fields as claimed in claim 1, wherein: the upper end of the anchor post (401) is welded with a fixing ring; the fixed ring is formed by bending a steel bar.
6. The temporary simple fence structure for sloping fields as claimed in claim 1, wherein: the safety net (303) is fixed on the upright post (301) and the fixed rope (302) in a binding mode.
CN202223141790.4U 2022-11-25 2022-11-25 Temporary simple enclosing structure for sloping field Active CN218596961U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202223141790.4U CN218596961U (en) 2022-11-25 2022-11-25 Temporary simple enclosing structure for sloping field

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202223141790.4U CN218596961U (en) 2022-11-25 2022-11-25 Temporary simple enclosing structure for sloping field

Publications (1)

Publication Number Publication Date
CN218596961U true CN218596961U (en) 2023-03-10

Family

ID=85408082

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202223141790.4U Active CN218596961U (en) 2022-11-25 2022-11-25 Temporary simple enclosing structure for sloping field

Country Status (1)

Country Link
CN (1) CN218596961U (en)

Similar Documents

Publication Publication Date Title
CN110847195A (en) Construction method for stable treatment of side and upward slope of large-block-diameter loose rock pile body opening
CN102535490A (en) Method for dewatering foundation pit by using bored cast-in-place pile
CN107975062B (en) Steep slope embankment light combined retaining structure and construction method
JP3753170B2 (en) How to build structures useful as roads and construction scaffolds on slopes
CN206693242U (en) A kind of vertical bearing structure of suspension support beam in base pit engineering
CN218596961U (en) Temporary simple enclosing structure for sloping field
CN110805049B (en) Construction method of mountain slope ultra-thickness spray anchor permanent supporting structure
CN112681347A (en) Combined supporting structure for treating dangerous rock mass and construction method thereof
CN210104765U (en) High and large retaining structure of soft geological side slope
JP3216357U (en) Reinforcing structure for supporting fence post
CN206873459U (en) A kind of large-span steel-reinforced concrete foundation ditch support system
RU2512199C2 (en) Method to erect anti-landslide structure of combined design
CN214460568U (en) Bridge steel pipe support foundation on bedding rock face
CN111962466B (en) Large-traffic large-span levee breach plugging device
CN108005086A (en) A kind of high buttress counter pull type inclined support structure for pattern foundation pit supporting structure
CN111851510B (en) Earth rock foundation pit blasting excavation system and construction method applying same
CN208152081U (en) Cell ecological retaining wall
JP2009084864A (en) Rock fall-cum-avalanche prevention facility
RU129948U1 (en) HIGH STRENGTH GABIONS
RU2354783C1 (en) Reinforcement construction for building or facility foundation
CN221168982U (en) Matched falling-stone-preventing bent for expressway construction
CN217517600U (en) Deep foundation pit supporting structure for supporting inclined struts in pit
JP5677736B2 (en) Rock fall protection net device and rock fall protection net anchor
CN219410603U (en) Flexible snow fixation fence protection system
CN213805361U (en) Anchor rod and rock-socketed concrete combined gravity anchorage

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant