CN218562329U - Frame lattice beam anchor rod grouting plug plate - Google Patents
Frame lattice beam anchor rod grouting plug plate Download PDFInfo
- Publication number
- CN218562329U CN218562329U CN202222501031.8U CN202222501031U CN218562329U CN 218562329 U CN218562329 U CN 218562329U CN 202222501031 U CN202222501031 U CN 202222501031U CN 218562329 U CN218562329 U CN 218562329U
- Authority
- CN
- China
- Prior art keywords
- reinforcing plate
- panel
- thick liquid
- hole
- grout stopping
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 82
- 239000007788 liquid Substances 0.000 claims abstract description 47
- 238000007569 slipcasting Methods 0.000 claims abstract description 27
- 239000011440 grout Substances 0.000 claims description 32
- 229910001220 stainless steel Inorganic materials 0.000 claims description 5
- 239000010935 stainless steel Substances 0.000 claims description 5
- 238000007789 sealing Methods 0.000 claims description 4
- 239000002002 slurry Substances 0.000 claims description 4
- 238000009955 starching Methods 0.000 abstract description 12
- 230000002787 reinforcement Effects 0.000 abstract description 9
- 238000005516 engineering process Methods 0.000 abstract description 3
- 229920002472 Starch Polymers 0.000 abstract description 2
- 235000019698 starch Nutrition 0.000 abstract description 2
- 239000008107 starch Substances 0.000 abstract description 2
- 238000009434 installation Methods 0.000 description 18
- 230000000694 effects Effects 0.000 description 7
- 239000003351 stiffener Substances 0.000 description 6
- 239000011435 rock Substances 0.000 description 4
- 239000002689 soil Substances 0.000 description 4
- 238000005553 drilling Methods 0.000 description 3
- 238000004519 manufacturing process Methods 0.000 description 3
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 2
- 230000002093 peripheral effect Effects 0.000 description 2
- 230000002035 prolonged effect Effects 0.000 description 2
- 238000005728 strengthening Methods 0.000 description 2
- 238000004873 anchoring Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A10/00—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
- Y02A10/23—Dune restoration or creation; Cliff stabilisation
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
The utility model relates to a slope reinforcement technology field especially relates to sash Liang Maogan slip casting blanking plate. The technical scheme comprises the following steps: only starch the panel, first reinforcing plate and second reinforcing plate, only end the other end fixedly connected with of thick liquid panel and end the thick liquid bucket, the fixed surface of only starching the panel installs the excessive hole, and the only thick liquid panel fixed surface of excessive hole bottom is connected with the slip casting hole, the one end fixed mounting in slip casting hole has the valve of ending thick liquid, only the thick liquid bucket top is installed first reinforcing plate with the only thick liquid panel periphery of bottom, only end the thick liquid panel periphery of thick liquid bucket both sides and install the second reinforcing plate, and end and be connected through the gim peg between thick liquid panel and first reinforcing plate and the second reinforcing plate, the spacing groove has been seted up on the first reinforcing plate surface of second reinforcing plate periphery. The utility model discloses a combination of various structures makes this device can be fast effectual carry out slip casting work at the during operation, has multinomial reinforcement measure simultaneously, guarantees the steadiness ability of device, makes things convenient for personnel to use.
Description
Technical Field
The utility model relates to a slope reinforcement technology field specifically is sash Liang Maogan slip casting blanking plate.
Background
Slope reinforcement refers to a measure for improving the slope stability of an open pit mine, slope angle retaining walls are arranged under slope angles of slope crushing zones, anti-slide piles are arranged on local crushing zones or slopes, and grouting is performed on rock strata with opening joints and cracks, so that the slope stability is improved, anchor rod lattice beams are a novel slope reinforcement technology, an ideal effect is achieved on reinforcement of high-expansion soil slopes and weathered soil slopes, the anchor rod lattice beams are widely used, grouting work needs to be performed in holes during construction, the anchor rod lattice beams are very important, the existing work efficiency is not ideal, and the reinforcement structure is few, so that a lattice Liang Maogan grouting plugging plate is provided.
Through the retrieval, patent publication No. CN 213897129U discloses a soil nail support slip casting end cap for building engineering, relate to slip casting end cap technical field, including installation piece and stop device, the fixed surface of installation piece is connected with the backup pad, one side fixedly connected with embedded block of installation piece is kept away from to the backup pad, the one end that the installation piece was kept away from to the embedded block is provided with stop device, stop device is including the installation cap, the one end fixed connection of installation piece is kept away from to installation cap and embedded block, the inner wall of installation cap rotates and is connected with the closure baffle, the closure baffle is the semicircle setting, CN 213897129U work efficiency is unsatisfactory among the prior art, and reinforced structure is less, and inconvenient staff carries out dismouting use work fast, in view of this, we propose frame roof beam stock slip casting end cap board and solve present problem.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a sash Liang Maogan slip casting blanking plate to solve the problem of proposing among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: sash Liang Maogan slip casting blanking plug board, including only thick liquid panel, first reinforcing plate and second reinforcing plate, only thick liquid bucket is ended to the other end fixedly connected with of thick liquid panel, only the fixed surface of thick liquid panel installs the excessive thick liquid hole, and only thick liquid panel fixed surface of excessive thick liquid hole bottom is connected with the slip casting hole, the one end fixed mounting of slip casting hole has only to starch the valve, only thick liquid bucket top and the only thick liquid panel periphery of bottom install first reinforcing plate, only the thick liquid panel periphery of thick liquid bucket both sides is installed the second reinforcing plate, and only thick liquid panel and first reinforcing plate and second reinforcing plate between pass through the fixed bolt and be connected, the first reinforcing plate surface of second reinforcing plate periphery has seted up the spacing groove.
After the installation of body of rod reinforcing bar is accomplished in drilling, at first only end the thick liquid bucket send into downthehole at the uniform velocity along the hole axis direction, the body of rod reinforcing bar that will leak outward in step penetrates the excessive thick liquid hole, open the thick liquid valve that ends behind the slip casting jogged joint grouting pump conveyer pipe, thereby automatically, the slip casting operation carries out, can effectively guarantee slip casting pressure and closely knit degree, and can in time carry out secondary splitting slip casting after treating downthehole thick liquid initial set, make the thick liquid get into the ground crack more fully, can form whole with the rock mass anchor, guarantee anchor effect device simple manufacture simultaneously, the installation is simple and easy, it is showing to use the actual effect, can be with first reinforcing plate card on only thick liquid panel when using, afterwards, can carry out the strengthening work to only thick liquid panel's bulk strength under the spacing direction of spacing groove with the second reinforcing plate card, rotate the gim peg afterwards and fix first reinforcing plate and second reinforcing plate together on only thick liquid panel, the installation work that can easily swift device, the work efficiency of increase device, through first reinforcing plate, can carry out the strengthening work life of spacing work to only, the convenient for use of dismouting, it reduces its continuous operation cost reduction.
Preferably, the grout stopping panel on the periphery of the grout stopping barrel is internally provided with a through hole, the through hole is movably connected with an expansion bolt, and the other end of the grout stopping panel on the outer side of the through hole is fixedly provided with a vertical outer edge. After the vertical outer edge of the grout stopping panel goes deep into the slope body, the vertical outer edge of the grout stopping panel penetrates through the through hole through the expansion bolt to be connected with the ground, so that the position of the grout stopping panel is anchored, and the installation and use work of the grout stopping panel is facilitated for personnel.
Preferably, the outer side surfaces of the first reinforcing plate and the second reinforcing plate are fixedly connected with a sliding rail, the sliding rail is movably connected with a sliding block, and a reinforcing rod is fixedly installed between the sliding blocks. On can installing the device through the light with the stiffener of the slip block of slider and slide rail, the stiffener can carry out spacing reinforcement to the relative position between first reinforcing plate and the second reinforcing plate, increases the bulk strength and the stability ability of device, makes things convenient for personnel to use.
Preferably, the surfaces of the first reinforcing plate and the second reinforcing plate are fixedly connected with nameplates, and the nameplates are made of stainless steel. The specification and the attention points of the device are recorded on the nameplate, so that the nameplate is convenient for people to check, the strength and the durability of the nameplate can be guaranteed by stainless steel, and the service life of the nameplate is prolonged.
Preferably, one end of the slurry stop valve is fixedly provided with a connecting flange, and the surface of the connecting flange is movably provided with a sealing cover. The staff can carry out the slip casting work with slip casting hole and slip casting pump duct connection automation through flange, can seal protection work to it through sealed lid when not using.
Preferably, the outer sides of the first reinforcing plate and the second reinforcing plate are fixedly connected with a connecting seat, and a handle is fixedly mounted on the outer side of the connecting seat. The staff can carry out the removal dismouting use work of first reinforcing plate and second reinforcing plate through gripping the handle, and the connecting seat can firmly be fixed the handle on the device, increases the steadiness ability of device, makes things convenient for personnel to use.
Compared with the prior art, the beneficial effects of the utility model are that:
1. after the installation of body of rod reinforcing bar is accomplished in drilling, at first only end the thick liquid bucket along hole axis direction at the uniform velocity send into downthehole, penetrate the excessive thick liquid hole with outer hourglass body of rod reinforcing bar in step, treat that the perpendicular outer edge of only thick liquid panel gos deep into the sloping body after, pass the through-hole through expansion bolt and be connected with ground, thereby anchor the position of only thick liquid panel, open only thick liquid valve behind the slip casting jogged joint slip casting pump conveyer pipe, thereby carry out the slip casting operation automatically, grouting pressure and closely knit degree can be effectively guaranteed, and can in time carry out secondary splitting slip casting after treating downthehole thick liquid initial set, make the thick liquid get into the ground crack more fully, can form wholly with the stock with the rock mass anchor, ensure anchor effect simple manufacture simultaneously, the installation is simple and easy, practical application is showing, make things convenient for personnel to use.
2. Can be with first enhancement integrated circuit board when using on ending the thick liquid panel, afterwards, spacing guide at the spacing groove is down to end the second reinforcing plate card on ending the thick liquid panel, rotate the gim peg afterwards and fix first reinforcing plate and second reinforcing plate together on ending the thick liquid panel, the installation work of the device that carries on that can relax swift, increase the work efficiency of device, then install the device with the stiffener through the slip block of slider and slide rail is light on, through first reinforcing plate, can carry out spacing enhancement work to the bulk strength that ends the thick liquid panel under the cooperation of second reinforcing plate and stiffener, the life of extension fixture, easy dismounting simultaneously, make things convenient for the staff to pull it down and store transportation or a plurality of device continuous cycle use work, use cost is reduced, convenience of customers uses.
Drawings
FIG. 1 is a schematic view of a partial structure of a grout stop panel of the present invention;
fig. 2 is a perspective view of the present invention;
FIG. 3 is a front view of the present invention;
fig. 4 is a schematic view of a partial structure of the first reinforcing plate of the present invention.
In the figure: 1. a grout stopping panel; 101. a vertical outer edge; 102. a through hole; 2. a pulp stopping barrel; 3. a slurry overflow hole; 4. grouting holes; 5. a first reinforcing plate; 501. a limiting groove; 6. an expansion bolt; 7. a second reinforcing plate; 8. a nameplate; 9. a fixing bolt; 10. a connecting seat; 11. a slide rail; 12. a handle; 13. a reinforcing rod; 1301. a slider; 14. a slurry stop valve; 15. and connecting the flanges.
Detailed Description
The technical solution of the present invention will be further explained with reference to the accompanying drawings and specific embodiments.
Example one
As fig. 1, fig. 2, fig. 3 and fig. 4 show, the utility model provides a sash Liang Maogan slip casting blanking plate, including only starching panel 1, first reinforcing plate 5 and second reinforcing plate 7, only starching panel 1's other end fixedly connected with ends thick liquid bucket 2, only starching panel 1's fixed surface installs overflow hole 3, and only starching panel 1 fixed surface of overflow hole 3 bottom is connected with slip casting hole 4, the one end fixed mounting of slip casting hole 4 has only starching valve 14, only starching bucket 2 top and the only starching panel 1 periphery of bottom install first reinforcing plate 5, only starching panel 1 periphery of starching bucket 2 both sides installs second reinforcing plate 7, and only starching panel 1 and first reinforcing plate 5 and second reinforcing plate 7 between be connected through gim peg 9, second reinforcing plate 7 peripheral first reinforcing plate 5 surface has seted up spacing groove 501, only starching panel 2 peripheral only has seted up inside through-hole 102, and the inside activity inflation of through-hole 102 is connected with bolt 6, the slider 101 outside fixed mounting of second reinforcing plate 7 has only fixed surface install the slider 11 and the slider perpendicular reinforcing plate 11 and the slider outside the slider of the fixed surface is connected with the slider outside the slider 11, the slider that is connected with the slider outside the slider.
The working principle of the grouting plugging plate based on the sash Liang Maogan of the embodiment 1 is as follows: after the installation of the rod body reinforcing steel bars in the drilling hole is finished, the grout stopping barrel 2 is firstly sent into the hole at a constant speed along the axis direction of the hole, the outer leaking rod body reinforcing steel bars are synchronously penetrated into the grout overflowing hole 3, after the vertical outer edge 101 of the grout stopping panel 1 is deeply penetrated into a slope body, the vertical outer edge is penetrated through the through hole 102 through the expansion bolt 6 to be connected with the ground, so that the position of the grout stopping panel 1 is anchored, the grout stopping valve 14 is opened after the grouting hole 4 is connected with a grouting pump conveying pipe, so that the grouting operation is automatically carried out, the grouting pressure and compactness can be effectively ensured, the secondary splitting grouting can be carried out in time after the grout in the hole is initially set, so that the grout can more fully enter rock-soil cracks, the anchor rod and a rock mass can be anchored into a whole, the anchoring effect is ensured, the device is simple to manufacture, the installation is simple, the practical effect is obvious, and the use is convenient for personnel, can stop thick liquid panel 1 with first reinforcing plate 5 card when using, after that stop thick liquid panel 1 with second reinforcing plate 7 card down in spacing direction of spacing groove 501, rotate the gim peg 9 afterwards and fix first reinforcing plate 5 and second reinforcing plate 7 together on ending thick liquid panel 1, the installation work of the device that carries on that can relax swift, increase the work efficiency of device, then install the device with stiffener 13 that the slip block through slider 1301 and slide rail 11 is light, through first reinforcing plate 5, can carry out spacing reinforcement work to the bulk strength that ends thick liquid panel 1 under the cooperation of second reinforcing plate 7 and stiffener 13, the life of extension fixture, easy dismounting simultaneously, make things convenient for the staff to pull down it and store transportation or a plurality of device continuous cycle use work, use cost is reduced, convenience of customers uses.
Example two
As shown in fig. 2, fig. 3 and fig. 4, the sash Liang Maogan grouting plug board provided by the present invention further includes: first reinforcing plate 5 and the fixed surface of second reinforcing plate 7 are connected with data plate 8, and data plate 8 adopts stainless steel to make, and the one end fixed mounting of only thick liquid valve 14 has flange 15, and flange 15's surface movable mounting has sealed lid, the outside fixed connection of first reinforcing plate 5 and second reinforcing plate 7 has connecting seat 10, and the outside fixed mounting of connecting seat 10 has handle 12.
In the embodiment, as shown in fig. 2, 3 and 4, the specification and the caution items of the device are recorded on the nameplate 8, so that the nameplate can be conveniently checked by personnel, and the stainless steel material can ensure the strength and the durability of the nameplate 8, so that the service life of the nameplate is prolonged; as shown in fig. 2, 3 and 4, a worker can connect the grouting hole 4 with a grouting pump conveying pipe through the connecting flange 15 to automatically perform grouting work, and can perform sealing protection work on the grouting hole through a sealing cover when the grouting pump conveying pipe is not used; as shown in fig. 2, 3 and 4, a worker can move, disassemble and assemble the first reinforcing plate 5 and the second reinforcing plate 7 for use by holding the handle 12, the connecting seat 10 can firmly fix the handle 12 on the device, the stability of the device is improved, and the worker can use the device conveniently.
The above embodiments are merely some preferred embodiments of the present invention, and those skilled in the art can make various alternative modifications and combinations to the above embodiments based on the technical solution of the present invention and the related teachings of the above embodiments.
Claims (6)
1. Sash Liang Maogan slip casting blanking plug board is including ending thick liquid panel (1), first reinforcing plate (5) and second reinforcing plate (7), its characterized in that: the grout stopping device is characterized in that the other end of the grout stopping panel (1) is fixedly connected with a grout stopping barrel (2), the surface of the grout stopping panel (1) is fixedly provided with a grout overflowing hole (3), the surface of the grout stopping panel (1) at the bottom of the grout overflowing hole (3) is fixedly connected with a grouting hole (4), one end of the grouting hole (4) is fixedly provided with a grout stopping valve (14), the top of the grout stopping barrel (2) and the periphery of the grout stopping panel (1) at the bottom are provided with first reinforcing plates (5), the peripheries of the grout stopping panels (1) at two sides of the grout stopping barrel (2) are provided with second reinforcing plates (7), the grout stopping panels (1) are connected with the first reinforcing plates (5) and the second reinforcing plates (7) through fixing bolts (9), and the surfaces of the first reinforcing plates (5) at the periphery of the second reinforcing plates (7) are provided with limiting grooves (501).
2. The sash Liang Maogan grouting plug panel of claim 1, wherein: a through hole (102) is formed in the grout stopping panel (1) on the periphery of the grout stopping barrel (2), an expansion bolt (6) is movably connected inside the through hole (102), and a vertical outer edge (101) is fixedly installed at the other end of the grout stopping panel (1) on the outer side of the through hole (102).
3. The sash Liang Maogan grouting plug panel of claim 1, wherein: the outer side surfaces of the first reinforcing plate (5) and the second reinforcing plate (7) are fixedly connected with a sliding rail (11), a sliding block (1301) is movably connected inside the sliding rail (11), and a reinforcing rod (13) is fixedly installed between the sliding blocks (1301).
4. The sash Liang Maogan grouting plug panel of claim 1, wherein: the surface of the first reinforcing plate (5) and the surface of the second reinforcing plate (7) are fixedly connected with nameplates (8), and the nameplates (8) are made of stainless steel.
5. The sash Liang Maogan grouting plug panel of claim 1, wherein: and one end of the slurry stop valve (14) is fixedly provided with a connecting flange (15), and the surface of the connecting flange (15) is movably provided with a sealing cover.
6. The sash Liang Maogan grouting plug panel of claim 1, wherein: the outer sides of the first reinforcing plate (5) and the second reinforcing plate (7) are fixedly connected with a connecting seat (10), and a handle (12) is fixedly mounted on the outer side of the connecting seat (10).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222501031.8U CN218562329U (en) | 2022-09-21 | 2022-09-21 | Frame lattice beam anchor rod grouting plug plate |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222501031.8U CN218562329U (en) | 2022-09-21 | 2022-09-21 | Frame lattice beam anchor rod grouting plug plate |
Publications (1)
Publication Number | Publication Date |
---|---|
CN218562329U true CN218562329U (en) | 2023-03-03 |
Family
ID=85312601
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202222501031.8U Expired - Fee Related CN218562329U (en) | 2022-09-21 | 2022-09-21 | Frame lattice beam anchor rod grouting plug plate |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN218562329U (en) |
-
2022
- 2022-09-21 CN CN202222501031.8U patent/CN218562329U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN211312538U (en) | Novel deep foundation pit supporting structure | |
KR101260292B1 (en) | Grouting device and tunnel reinforce method | |
CN107542115B (en) | Underground engineering waterproof structure and construction method thereof | |
CN110258538B (en) | Soil nail reinforced buffer type manual hole digging pile and construction method thereof | |
CN102767180A (en) | Construction method for strengthening base of static-pressure anchor rod pile | |
CN107604926A (en) | Composite pile anchor supporting method | |
CN107524174A (en) | A kind of diaphragm wall I-shaped steel joint provided with water expandable waterstop | |
CN212837830U (en) | Reinforcement system for reinforcing damaged segments of shield tunnel | |
CN207525755U (en) | Composite pile anchor supporting device | |
CN218562329U (en) | Frame lattice beam anchor rod grouting plug plate | |
CN209494575U (en) | A kind of push pipe portal sealing device under low Water And Earth Pressures | |
CN106761841B (en) | Working face tailgate fractured coal grouting reinforcement method | |
CN212671206U (en) | A seal storehouse system for assembled conversion layer outer wall | |
CN208899660U (en) | A kind of full precast shear wall connection structure | |
CN114439242B (en) | Assembly type cantilever complex component optimization and hoisting reinforcement construction method | |
CN112324473B (en) | Telescopic steel pipe sheet matched with tunnel connection channel construction and installation method | |
CN212670862U (en) | Open type wall connecting box | |
CN212376670U (en) | Broken roof supporting device of underground mine | |
CN211524170U (en) | Constructional engineering frame roof beam reinforcing apparatus | |
CN211312623U (en) | Miniature steel-pipe pile body displacement monitoring devices | |
CN211038697U (en) | Underground excavation small-section tunnel construction supporting device | |
CN108914964B (en) | Urban branch underground comprehensive pipe rack construction system | |
CN210263072U (en) | High-pressure jet grouting anchor cable suitable for deep foundation pit support | |
CN202047850U (en) | Anchor-grouting integrated support plate module | |
CN210067140U (en) | Assembled integral structure stair outer shear wall grouting bin sealing structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20230303 |
|
CF01 | Termination of patent right due to non-payment of annual fee |