SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a foundation construction prevents landslide and strengthens device can strengthen the comparatively soft foundation pit periphery of soil property, can effectively prevent the emergence of landslide accident, increases supporting construction's stability.
The utility model discloses the technical scheme who takes specifically as follows:
a landslide prevention reinforcing device for foundation construction comprises fixed inserting rods and baffles arranged between the adjacent fixed inserting rods, wherein a pouring platform is inserted into the tops of the fixed inserting rods in an inserting mode;
the positioning plug-in is positioned at the top of the positioning plug-in and is connected with the side surface of the pouring platform through a cable;
the side surface of the baffle is movably provided with a fixing piece for clamping the baffle, and the fixing piece is buckled with the fixing inserted rods adjacent to the two sides;
the bottom of the fixed inserted link extends to form a plug part;
the positioning plug-in unit is characterized in that an impact bearing block is arranged on one side of the top of the positioning plug-in unit adjacent to the casting platform, a side retaining groove is formed in the bottom of the impact bearing block, a plug end is arranged at the bottom of the positioning plug-in unit, and the same side retaining groove is formed in the top of the plug end, which deviates from the side retaining groove.
And a railing fixedly connected with the pouring platform is arranged at the top of the pouring platform.
And one side of the top of the impact bearing block is provided with a first retaining ring, and one side of the pouring platform adjacent to the positioning plug-in is provided with a second retaining ring corresponding to the first retaining ring.
The positioning plug-in components are obliquely arranged relative to the fixed plug-in rods.
One side of the bottom of the plug end is arranged in a round angle mode.
The side face of the baffle is movably inserted into the fixing piece through the connecting screw rod, the connecting screw rod is located on the outer side of the fixing piece and is in threaded connection with a nut, the side edge positions of the adjacent baffles on the two sides of the fixing inserted bar are provided with clamping grooves matched with the adjacent baffles, and the side edges of the baffles are clamped inside the clamping grooves.
The top of the fixed insertion rod is provided with an insertion groove, and the bottom of the pouring platform is provided with an insertion end which is in adaptive insertion connection with the insertion groove.
The bottom end of the plug part is conical, a limiting plate perpendicular to the plug part is arranged on the side face of the bottom of the fixed inserted bar, and a plurality of raised and parallel anti-skidding teeth are arranged at the bottom of the limiting plate.
The utility model discloses the technological effect who gains does:
the utility model discloses, plug portion pegs graft with ground to combine limiting plate and antiskid tooth to mutually support, plug portion realizes the location to fixed inserted bar, and the antiskid tooth prevents the horizontal slip, and the limiting plate prevents sinking of vertical direction, and can prevent to a certain extent that fixed inserted bar from taking place the slope.
The utility model discloses, through the buckle two and the buckle one of hawser winding both sides, realize location plug-in components and pouring platform's being connected to through location plug-in components to pouring platform's tensile location, avoid pouring platform and fixed inserted bar to take place the slope, and cooperate the limiting plate to realize the location installation to fixed inserted bar and baffle.
Detailed Description
In order to make the objects and advantages of the present invention more apparent, the present invention will be described in detail with reference to the following embodiments. It is to be understood that the following text is merely illustrative of one or more specific embodiments of the invention, and is not intended to strictly limit the scope of the claims.
As shown in fig. 1-3, a landslide prevention reinforcement device for foundation construction comprises fixed insertion rods 1, positioning insertion pieces 5 and baffles 2 arranged between the adjacent fixed insertion rods 1, wherein a pouring platform 3 is inserted into the tops of the fixed insertion rods 1, and plug parts 105 are extended from the bottoms of the fixed insertion rods 1.
Wherein, the bottom end of the plug part 105 is cone-shaped, the side surface of the bottom of the fixed inserted bar 1 is provided with a limit plate 103 vertical to the fixed inserted bar, and the bottom of the limit plate 103 is provided with a plurality of convex and parallel anti-skid teeth 104.
According to the structure, in the process of installing the fixed inserted bar 1, firstly, the fixed inserted bar 1 is inserted into the side face of the foundation pit, the plug part 105 is used for extending and inserting into the ground, the fixed inserted bar 1 is preliminarily positioned through the plug part 105, then after the fixed inserted bar 1 is inserted into the limiting plate 103 and inserted into the upper surface of the ground, the limiting plate 103 is inserted into the ground in an embedded mode, the limiting plate 103 is matched with the anti-slip teeth 104 mutually, the anti-slip teeth 104 prevent transverse sliding, the limiting plate 103 prevents sinking of the vertical direction, and the fixed inserted bar 1 can be prevented from inclining to a certain degree.
As shown in fig. 1-2, a fixing member 7 for clamping the baffle 2 is movably mounted on the side surface of the baffle 2, and the fixing member 7 is fastened to the fixing inserted bar 1 adjacent to the two sides.
Further, 2 sides of the baffle are movably inserted into the fixing part 7 through the connecting screw rod 201, the connecting screw rod 201 is located outside the fixing part 7 and is connected with a nut in a threaded manner, the clamping groove 101 matched with the fixing inserting rod is formed in the positions of the two sides of the adjacent baffle 2, and the baffle 2 is clamped inside the clamping groove 101.
According to above-mentioned structure, inside the draw-in groove 101 with 2 joints of baffle in fixed inserted bar 1 side afterwards, and separate the fender through the sand and soil of baffle 2 to the side, connecting screw 201 and mounting 7 through 2 sides of baffle are connected, realize the location of baffle 2, avoid deviating from ground hole one side at baffle 2 and taking place the deflection when earth does not support, then through the threaded connection relation between adjusting nut and the connecting screw 201, realize connecting screw 201's the regulation of disassembling convenience and elasticity degree.
As shown in fig. 1-2, a railing 4 is fixedly connected to the top of the casting platform 3.
Furthermore, the top of the fixed inserting rod 1 is provided with an inserting slot 102, and the bottom of the pouring platform 3 is provided with an inserting end 302 which is inserted into the inserting slot 102 in a matching manner.
Wherein the top of the positioning plug-in 5 is connected with the side of the pouring platform 3 through a cable 6.
According to the structure, after the fixed inserting rod 1 and the baffle 2 are installed, the cement casting body pouring platform 3 is poured into the slot 102 in the top of the fixed inserting rod 1 and used for covering the tops of the fixed inserting rod 1 and the baffle 2, the railing 4 is embedded into the pouring platform 3, the second retaining ring 301 is embedded into the position, adjacent to the positioning plug-in 5, of the side face of the pouring platform 3, the second retaining ring 301 and the first retaining ring 502 are wound by the cable 6, the positioning plug-in 5 is connected with the pouring platform 3, the pouring platform 3 is prevented from inclining relative to the fixed inserting rod 1 through the positioning plug-in 5, and the fixed inserting rod 1 and the baffle 2 are positioned and installed by matching with the limiting plate 103.
As shown in fig. 1 and 4, an impact-bearing block 501 is arranged on one side of the top of the positioning plug-in 5 adjacent to the casting platform 3, a side blocking groove 504 is arranged at the bottom of the impact-bearing block 501, a plug end 503 is arranged at the bottom of the positioning plug-in 5, and the same side blocking groove 504 is also arranged on one side of the top of the plug end 503 away from the side blocking groove 504.
Furthermore, a first retaining ring 502 is arranged on one side of the top of the impact bearing block 501, and a second retaining ring 301 corresponding to the first retaining ring 502 is arranged on one side of the pouring platform 3 adjacent to the positioning insert 5.
By integrating the structure, in the process of installing the positioning plug-in 5, the plug end 503 at the bottom of the positioning plug-in 5 faces one side of the pouring platform 3, and one side of the impact bearing block 501 deviates from one side of the pouring platform 3 to start to be plugged into the ground, in the plugging process, because the two sides of the positioning plug-in 5 are both provided with the side retaining grooves 504, and the positioning plug-in 5 is integrally arranged in a round angle, the labor is saved in the plugging process.
After the inserting and positioning plug-in 5 is completed, the contact area between the surface of the side retaining groove 504 and the sand can be increased by blocking the sand by the side retaining groove 504, and the stability of the positioning plug-in 5 for stretching the pouring platform 3 is increased.
Wherein, location plug-in components 5 are the slope setting for fixed inserted bar 1, can increase the location stability after location plug-in components 5 installation.
The utility model discloses a theory of operation does:
the fixed inserted bar 1 is positioned by inserting the plug part 105 on the ground, then the limiting plate 103 is inserted on the ground in an embedded manner when the fixed inserted bar 1 is flush with the surface of the ground through the limiting plate 103, the limiting plate 103 is matched with the anti-slip tooth 104, the anti-slip tooth 104 prevents transverse slippage, the limiting plate 103 prevents sinking in the vertical direction, and the fixed inserted bar 1 can be prevented from inclining to a certain extent;
through the tensile location of location plug-in components 5 to pouring platform 3, avoid pouring platform 3 and fixed inserted bar 1 to take place the slope, and cooperate limiting plate 103 to realize the location installation to fixed inserted bar 1 and baffle 2, at the in-process of installation location plug-in components 5, make the plug end 503 of its bottom towards pouring platform 3 one side, and make and bear impact block 501 one side deviate from pouring platform 3 one side and begin to peg graft and get into ground, at the grafting in-process, because location plug-in components 5 both sides all are equipped with side retaining groove 504, and location plug-in components 5 wholly are the arc, therefore it is comparatively laborsaving at the grafting in-process.
The foregoing is only a preferred embodiment of the present invention, and it should be noted that, for those skilled in the art, a plurality of modifications and decorations can be made without departing from the principle of the present invention, and these modifications and decorations should also be regarded as the protection scope of the present invention. The structures, devices, and methods of operation of the present invention, not specifically described and illustrated, are generally practiced by those of ordinary skill in the art without specific recitation or limitation.