High pier stud construction operation platform Download PDFInfo
- Publication number
- CN218540438U CN218540438U CN202223030878.9U CN202223030878U CN218540438U CN 218540438 U CN218540438 U CN 218540438U CN 202223030878 U CN202223030878 U CN 202223030878U CN 218540438 U CN218540438 U CN 218540438U
- Authority
- CN
- China
- Prior art keywords
- outside
- construction
- plate
- high pier
- people
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Emergency Lowering Means (AREA)
Abstract
The utility model discloses a high pier stud construction operation platform, which comprises a supporting column, the mounting panel is installed to the outside bottom position department of support column, the outside welding of support column has the protection net, the slide rail is installed to the bottom of mounting panel, the outside of slide rail is rotated and is connected with the removal wheel, the inboard of removing the wheel is rotated and is installed the location axle, the dead lever is installed to the bottom of location axle, the outside of dead lever is provided with safe couple, the bottom of safe couple is connected with safe rope, can hang safe couple in the outside position department of dead lever, and people walk the operation on operation platform this moment, can drive the removal wheel in the location axle outside and remove in the outside of slide rail to make things convenient for people to walk the construction wantonly on operation platform, and need not continuous adjustment position, guarantee people's safety when reducing people's operation step, promoted the construction convenience, thereby promote the efficiency of construction.
Description
Technical Field
The utility model relates to a construction scaffold technical field specifically is a high pier stud construction operation platform.
Background
The scaffold is a working platform which is erected for ensuring the smooth proceeding of each construction process, and is divided into an outer scaffold and an inner scaffold according to the erected position, and can be divided into a wood scaffold, a bamboo scaffold and a steel pipe scaffold according to different materials, wherein different construction scaffold and working platform are required for different construction buildings, and various piers and high piers need specially-made construction scaffold, so that the construction is more convenient and safer for people, the construction quality is ensured, and the construction safety of people is protected, and the scaffold is simple and convenient;
however, when the safety rope is bound on the existing construction operation platform, the position of the hook needs to be continuously adjusted according to the position of the constructor, so that the use is very inconvenient, the steps are more, the construction efficiency is reduced, and in order to avoid the technical problems, it is necessary to provide a high pier stud construction operation platform to overcome the defects in the prior art.
SUMMERY OF THE UTILITY MODEL
The utility model provides a high pier stud construction operation platform can effectively solve the current construction operation platform that provides in the above-mentioned background art when binding safety rope, needs the position of the continuous adjustment couple in constructor's position, uses the problem that very inconvenient step is more reduced the efficiency of construction.
In order to achieve the above purpose, the utility model provides a following technical scheme: a high pier column construction operating platform comprises a support column, wherein a connecting column is installed at the top end of the support column, a connecting hole is formed in the bottom end of the support column, an installation plate is installed at the bottom of the outer side of the support column, a protection grid is welded on the outer side of the support column, a construction groove is formed in the middle of the installation plate, an inclined ladder is installed at the top end of the installation plate, and a manhole is formed in the position, corresponding to the inclined ladder, of the bottom end of the installation plate;
the bottom of mounting panel is installed the slip rail, the outside of slip rail is rotated and is connected with the removal wheel, the inboard of removing the wheel is rotated and is installed the location axle, the dead lever is installed to the bottom of location axle, the outside of dead lever is provided with safe couple, the bottom of safe couple is connected with safety rope.
Preferably, the protection grid is provided with a plurality of blocks, and the plurality of blocks of protection grid are arranged at the top of the mounting plate at equal angles.
Preferably, the connecting column has a diameter equal to the inner diameter of the connecting hole, and is slidably inserted into the connecting hole.
Preferably, the number of the moving wheels is two, the two moving wheels are symmetrically arranged on the end faces of the two sides of the sliding rail, and the other end of the safety rope is also provided with a safety hook.
Preferably, a hanging plate is arranged on one side of the protection grid, a clamping rod is installed on one side end face of the hanging plate, a limiting plate is installed on one side end face of the clamping rod, an adsorption magnet is installed on one side end face of the hanging plate, a storage groove plate is installed on one side end face of the hanging plate, and an article cavity is formed in the inner side of the storage groove plate.
Preferably, the clamping rods are arranged in two numbers, and the two clamping rods are symmetrically arranged on the end face of one side of the hanging plate.
Compared with the prior art, the beneficial effects of the utility model are that: the utility model has the advantages of being scientific and reasonable in structure, convenience safe in utilization:
1. be provided with the support column, the spliced pole, the connecting hole, the mounting panel, the protection net, the construction groove, the inclined ladder, people's hole, the slip rail, remove the wheel, the location axle, the dead lever, safe couple and safety rope, can hang the outside position department at the dead lever with safe couple, people walk the time of operation on operation platform this moment, the removal wheel that can drive the location off-axial side removes in the outside of slip rail, thereby make things convenient for people to walk the construction wantonly on operation platform, and need not continuous adjusting position, guarantee people's safety when reducing people's operation steps, construction convenience has been promoted, thereby promote the efficiency of construction.
2. Be provided with link plate, joint bar, limiting plate, adsorption magnet, put thing frid and article chamber, can insert the net of protection net inboard with joint bar and limiting plate to make things convenient for people to place the article intracavity of the inboard of putting the thing frid with the instrument that the operation needs was used, and then further make things convenient for people to carry out the construction operation, prevent that operating personnel from placing the construction apparatus and having the danger that drops on one's body, further guarantee people's construction safety.
Drawings
The accompanying drawings are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention, and together with the description serve to explain the invention and not to limit the invention.
In the drawings:
FIG. 1 is a schematic view of the present invention;
fig. 2 is a schematic view of the mounting structure of the mounting plate of the present invention;
FIG. 3 is a schematic view of the installation structure of the positioning shaft of the present invention;
FIG. 4 is a schematic view of the installation structure of the object-placing trough plate of the present invention;
reference numbers in the figures: 1. a support pillar; 2. connecting columns; 3. connecting holes; 4. mounting a plate; 5. a protection grid; 6. constructing a slot; 7. an inclined ladder; 8. a human hole; 9. a sliding rail; 10. a moving wheel; 11. positioning the shaft; 12. a fixing rod; 13. a safety hook is arranged; 14. a safety rope; 15. hanging plates; 16. a clamping and connecting rod; 17. a limiting plate; 18. adsorbing a magnet; 19. a storage trough plate; 20. an article chamber.
Detailed Description
The preferred embodiments of the present invention will be described hereinafter with reference to the accompanying drawings, and it should be understood that the preferred embodiments described herein are merely for purposes of illustration and explanation, and are not intended to limit the present invention.
The embodiment is as follows: as shown in fig. 1-4, the utility model provides a technical scheme, a high pier stud construction operation platform, including support column 1, spliced pole 2 is installed on the top of support column 1, connecting hole 3 has been seted up to the bottom of support column 1, the diameter of spliced pole 2 equals the internal diameter of connecting hole 3, spliced pole 2 slides and imbeds in the inboard of connecting hole 3, it is convenient for install the operation panel, mounting panel 4 is installed to the outside bottom position department of support column 1, the outside welding of support column 1 has protection net 5, protection net 5 is provided with a plurality of, a plurality of protection nets 5 wait the angle and install in the top position department of mounting panel 4, be favorable to protecting operating personnel's safety, construction groove 6 has been seted up to the middle part position department of mounting panel 4, inclined ladder 7 is installed on the top of mounting panel 4, the bottom of mounting panel 4 corresponds position department with inclined ladder 7 and sets up someone hole 8;
One side of protection net 5 is provided with link plate 15, and the joint pole 16 is installed to a side end surface of link plate 15, and joint pole 16 is provided with two, and two joint pole 16 symmetries are installed at a side end surface of link plate 15, are favorable to installing link plate 15, and limiting plate 17 is installed to a side end surface of joint pole 16, and adsorption magnet 18 is installed to a side end surface of link plate 15, and article chamber 20 has been seted up to article groove 19's inboard to article groove 19 is installed to a side end surface of link plate 15.
The utility model discloses a theory of operation and use flow: firstly, when a plurality of operation platforms are required to be connected, the connecting hole 3 at the bottom end of the top support column 1 is inserted into the outer side of the bottom support column 1, so that the operation platforms are connected and installed, then, when people enter the protection grid 5 for operation, the people can rapidly shuttle between each layer of operation platforms through the inclined ladder 7 and the people hole 8, and then the safety hook 13 can be hung at the outer side position of the fixed rod 12, at the moment, when people walk on the operation platforms for operation, the moving wheel 10 at the outer side of the positioning shaft 11 can be driven to move at the outer side of the sliding rail 9, so that people can conveniently walk on the operation platforms at will for construction, the position is not required to be adjusted continuously, the safety of people is ensured while the operation steps of people are reduced, the construction convenience is improved, and the construction efficiency is improved;
then, when people carry out construction operation, can insert the net inboard of protection net 5 with joint pole 16 and limiting plate 17, thereby can hang link plate 15 in the inboard position department of protection net 5, then adsorb magnet 18 in a side end face of protection net 5, thereby can fix link plate 15, place the instrument that needs the operation to use in the article chamber 20 of the inboard of putting thing frid 19 with making things convenient for people, and further make things convenient for people to carry out construction operation, prevent that operating personnel from placing the construction apparatus on one's body and have the danger that drops, further guarantee people's construction safety.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described in the foregoing embodiments, or equivalents may be substituted for elements thereof. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims (6)
1. The utility model provides a high pier stud construction operation platform, includes support column (1), its characterized in that: a connecting column (2) is installed at the top end of the supporting column (1), a connecting hole (3) is formed in the bottom end of the supporting column (1), an installation plate (4) is installed at the bottom position of the outer side of the supporting column (1), a protection grid (5) is welded to the outer side of the supporting column (1), a construction groove (6) is formed in the middle position of the installation plate (4), an inclined ladder (7) is installed at the top end of the installation plate (4), and a hole (8) is formed in the position, corresponding to the inclined ladder (7), of the bottom end of the installation plate (4);
sliding rail (9) are installed to the bottom of mounting panel (4), the outside of sliding rail (9) is rotated and is connected with and removes wheel (10), the inboard of removing wheel (10) is rotated and is installed location axle (11), dead lever (12) are installed to the bottom of location axle (11), the outside of dead lever (12) is provided with safety hook (13), the bottom of safety hook (13) is connected with safety rope (14).
2. The high pier construction operating platform according to claim 1, wherein: the protection grids (5) are provided with a plurality of blocks, and the protection grids (5) are arranged at the top of the mounting plate (4) at equal angles.
3. The high pier construction operating platform according to claim 1, wherein: the diameter of the connecting column (2) is equal to the inner diameter of the connecting hole (3), and the connecting column (2) is embedded into the inner side of the connecting hole (3) in a sliding mode.
4. The high pier construction operating platform according to claim 1, wherein: the two moving wheels (10) are symmetrically arranged on the end faces of the two sides of the sliding rail (9), and the other end of the safety rope (14) is also provided with a safety hook (13).
5. The high pier construction operating platform according to claim 1, wherein: one side of protection net (5) is provided with link plate (15), joint rod (16) are installed to a side end surface of link plate (15), limiting plate (17) are installed to a side end surface of joint rod (16), adsorption magnet (18) are installed to a side end surface of link plate (15), a side end surface of link plate (15) is installed and is put thing frid (19), article chamber (20) have been seted up to the inboard of putting thing frid (19).
6. The high pier construction operating platform according to claim 5, wherein: the number of the clamping rods (16) is two, and the two clamping rods (16) are symmetrically arranged on the end face of one side of the hanging plate (15).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202223030878.9U CN218540438U (en) | 2022-11-15 | 2022-11-15 | High pier stud construction operation platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202223030878.9U CN218540438U (en) | 2022-11-15 | 2022-11-15 | High pier stud construction operation platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN218540438U true CN218540438U (en) | 2023-02-28 |
Family
ID=85262333
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202223030878.9U Active CN218540438U (en) | 2022-11-15 | 2022-11-15 | High pier stud construction operation platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN218540438U (en) |
-
2022
- 2022-11-15 CN CN202223030878.9U patent/CN218540438U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103072893B (en) | Tool and method for overturning vertical equipment in nuclear power plant | |
CN210947655U (en) | Intelligent combined mounting frame for building | |
CN202989935U (en) | Simple device for erecting or dismantling steel braces of subway foundation pits | |
CN209620571U (en) | Contracture shear wall form frame system | |
CN214740171U (en) | Ancient building wall body hoist and mount migration device | |
CN218540438U (en) | High pier stud construction operation platform | |
CN213296374U (en) | Subway construction foundation ditch excavation supporting construction | |
CN211498507U (en) | Whole reassembling type protection rack | |
CN218438659U (en) | Iron art railing assembled enclosure and lifting device thereof | |
CN217579783U (en) | Mounting system of suspension bridge steel pull rod anchoring system | |
CN216515141U (en) | Novel cantilever construction creeping formwork device | |
CN115045409A (en) | Building earthquake-resistant structure capable of improving collapse resistance | |
CN209722771U (en) | A kind of bridge construction Hanging Basket | |
CN209874468U (en) | Construction hydraulic pressure template climbing device | |
CN110374006B (en) | Construction method for dismantling space anisotropic large-tonnage steel beam bracket | |
CN210827120U (en) | Tensioning operation platform supported by temporary anchoring platform based on prefabricated section box girder | |
CN210194435U (en) | Movable trolley for transverse prestress construction of continuous beam | |
JP3032052U (en) | Construction equipment for pier reinforcement work | |
CN218480600U (en) | Auxiliary device for hanging and installing large boiler drum | |
CN219011871U (en) | Device for attaching hanging frame | |
CN216076291U (en) | Electric self-climbing formwork | |
CN216239362U (en) | Lattice formula steel column | |
CN215830054U (en) | A positioning tool for I-steel roof beam | |
CN211281410U (en) | Construction equipment is built in marine segmentation | |
CN211548691U (en) | Assembled steel structure support |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |