CN218538329U CN202222443638.5U CN202222443638U CN218538329U CN 218538329 U CN218538329 U CN 218538329U CN 202222443638 U CN202222443638 U CN 202222443638U CN 218538329 U CN218538329 U CN 218538329U
Authority
CN
China
Prior art keywords
funnel
switching
rapid
conveying system
driving motor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222443638.5U
Other languages
Chinese (zh)
Inventor
陈家林
刘正祥
邱鸿
林丰兵
李程
万江
李闽军
朱伟
郭刚
何木光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Pangang Group Panzhihua Steel and Vanadium Co Ltd
Pangang Group Panzhihua Iron and Steel Research Institute Co Ltd
Pangang Group Xichang Steel and Vanadium Co Ltd
Original Assignee
Pangang Group Panzhihua Steel and Vanadium Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Pangang Group Panzhihua Steel and Vanadium Co Ltd filed Critical Pangang Group Panzhihua Steel and Vanadium Co Ltd
Priority to CN202222443638.5U priority Critical patent/CN218538329U/en
Application granted granted Critical
Publication of CN218538329U publication Critical patent/CN218538329U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Discharge Of Articles From Conveyors (AREA)
  • Control Of Conveyors (AREA)

Abstract

The utility model discloses a conveying system fast switch over funnel, it includes body, drive arrangement, and this body is whole for tubulose "horizontal" shape funnel, and this drive arrangement is used for the drive the body is rotatory to carry out the switching of low reaches conveyer belt. The utility model provides a conveying system fast switching funnel, which can effectively avoid the phenomenon that a three-way funnel turning plate of a belt conveying system cannot be opened or a plugboard cannot be inserted, thereby reducing the system switching time; meanwhile, the 'man' shaped funnel is changed into a 'horizontal and vertical' shaped funnel, so that the space occupation and the wear-resistant material of the funnel can be effectively reduced; greatly reduce the labor intensity of workers, improve the working environment of the workers and avoid the occurrence of safety accidents during the operations of inserting and pulling the plugboard or turning the board and the like of the workers.

Description

Conveying system fast switch over funnel
Technical Field
The utility model relates to a belt conveyor production field especially relates to a conveying system fast switch over funnel.
Background
In the arrangement of the sintering process, in order to improve the sintering production operation rate, a finished product conveying system is usually arranged into a double system, namely two conveying belts are arranged in parallel to play a role of one conveying belt for standby, only one channel is usually arranged at the upstream of the double system, and when one conveying belt in the double system goes out of order, the finished product ore is immediately switched to the other conveying belt to ensure the normal production of sintering.
In order to achieve system switching, a herringbone distribution funnel is generally arranged at the head of an upstream conveying belt of a double system, the herringbone distribution funnel is generally a three-way funnel, an inserting plate or a turning plate is arranged in the funnel, and finished ore enters different systems by inserting and pulling the inserting plate or rotating the turning plate. The manual plugging and unplugging plug board is often processed by a hand gourd, a sledge hammer and the like, the efficiency is extremely low, the safety risk is extremely high, and the production is often forced to stop due to too long time consumption.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a conveying system fast switch over funnel, it can effectively avoid belt conveyor system tee bend funnel to turn over the board and can not open or the picture peg inserts the phenomenon that can not advance, then reduce system switching time.
In order to achieve the purpose, the utility model provides the following technical scheme;
a conveying system fast switching funnel comprising a body, generally tubular funnel, driving means for driving said body in rotation for switching of the downstream conveyor belt.
Optionally, the device further comprises a support device for supporting the body and the driving device.
Optionally, the driving device comprises a driving motor, a power output end of the driving motor is connected with a chain wheel, and the chain wheel is in transmission connection with the funnel body through a chain, so that when the driving motor drives, the driving motor drives the chain wheel to rotate, and the chain wheel rotates to drive the funnel body to rotate through the chain.
Optionally, the supporting device includes a plurality of supporting rollers, and the plurality of supporting rollers support the track arranged outside the body.
Optionally, an electromagnetic induction switch is arranged outside the body, the electromagnetic induction switch is in signal connection with the driving motor, when the funnel rotates to a specified position, the electromagnetic induction switch controls the driving motor, the driving motor automatically stops, and the specified position is a position of any downstream conveying belt corresponding to the outlet of the funnel body.
Optionally, the chain wheel and the chain are externally provided with a safety protection cover, so that workers are not injured during driving.
Optionally, the body is disposed between upstream of the delivery system and downstream of the delivery system; the downstream of the conveying system comprises N conveying belts, wherein N is more than or equal to 2.
As a preferred embodiment, N =2.
Preferably, a three-way funnel is arranged between the N conveying belts corresponding to the lower part of the funnel body, and the upper part of the three-way funnel is flexibly connected with the funnel body.
Preferably, the conveying belt switching device is further provided with an operation box, and a change-over switch is arranged on the operation box so as to conveniently select and switch the conveying belt.
The utility model discloses a technological effect and advantage:
the utility model provides a pair of conveying system fast switch over funnel, it can effectively avoid belt conveying system tee bend funnel to turn over the board and can not open or the picture peg inserts the phenomenon that can not advance, reduces system switching time then.
The 'man' shaped funnel is changed into the 'horizontal' shaped funnel, so that the space occupation and the wear-resistant material of the funnel can be effectively reduced; greatly reducing the labor intensity of workers, improving the working environment of the workers and avoiding the occurrence of safety accidents during the operations of inserting and pulling plug boards or turning boards and the like of the workers.
Additional features and advantages of the invention will be set forth in the description which follows, and in part will be obvious from the description, or may be learned by the practice of the invention. The objectives and other advantages of the invention will be realized and attained by the structure particularly pointed out in the written description and claims hereof as well as the appended drawings.
Drawings
FIG. 1 is a schematic view of a finished ore when the finished ore is conveyed by a conveyor belt A;
fig. 2 is a schematic diagram of a finished ore when a conveying belt B is moved.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
For solving the not enough of prior art, the utility model discloses a conveying system fast switch over funnel. The rapid switching funnel is arranged between the upstream and the downstream of a conveying system, the upstream of the conveying system is generally provided with a channel, the downstream of the conveying system is generally arranged into a double system, namely two conveying belts are arranged in parallel to play a role of standby, and when one conveying belt in the downstream goes wrong, the finished ore is immediately switched to the other conveying belt to ensure normal sintering production.
Optionally, the downstream of the conveying system comprises N conveying belts, wherein N is more than or equal to 2.
In the following, N =2 is taken as an example, i.e. the fast switching funnel of the present invention, i.e. the fast switching between the two systems is taken as an example.
As illustrated in figures 1, 2, the fast switching funnel comprises a body, generally tubular funnel, further comprising driving means for driving said body in rotation for switching of the downstream conveyor belt, supporting means for the support of said body and driving means.
Preferably, the driving device is arranged beside the body and comprises a driving motor, a power output end of the driving motor is connected with a chain wheel, and the chain wheel is in transmission connection with the funnel body through a chain. When the driving motor drives, the driving motor drives the chain wheel to rotate, and the chain wheel rotates to drive the body to rotate through the chain.
Preferably, the supporting device comprises supporting wheels, a track is horizontally arranged on the outer ring of the upper portion of the funnel body, and three supporting wheels are arranged on a platform below the track and used for supporting the whole funnel.
Preferably, an electromagnetic induction switch is arranged at a proper position of the track and is in signal connection with the driving motor, when the funnel rotates to a specified position, the electromagnetic induction switch controls the driving motor, and the driving motor automatically stops, and the specified position is the position of any one of the conveying belts at the downstream corresponding to the outlet of the funnel body.
Preferably, the chain wheel and the chain are externally provided with a safety protection cover, so that workers are not injured during driving.
Preferably, a three-way funnel is arranged between the two corresponding conveying belts at the lower part of the funnel body, and the upper part of the three-way funnel is flexibly connected with the rotary funnel body for avoiding dust raising.
Preferably, an operation box is arranged on the site of the conveyor, a change-over switch is arranged on the operation box, when the finished ore leaves the conveyor belt A, the switch of the operation box is changed to A, and the drive motor drives the funnel body to rotate to the conveyor belt A; when finished ore needs to walk through the B system, the change-over switch is switched to B, at the moment, the driving motor drives the funnel body to rotate to the B conveying belt, and when the driving motor drives the funnel body to rotate to the B conveying belt, the electromagnetic induction switch controls the driving motor, and the driving motor stops rotating automatically.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art can still modify the technical solutions described in the foregoing embodiments or make equivalent substitutions on some technical features, and any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of the present invention.

Claims (10)

1. A rapid-switching hopper for conveying systems, characterized in that it comprises a body, which is generally tubular shaped up and down, a driving device for driving said body in rotation.
2. The rapid-switching funnel of claim 1, further comprising a support means for supporting said body and said drive means.
3. The conveying system quick switching hopper according to claim 1 or 2, wherein the driving device comprises a driving motor, a power output end of the driving motor is connected with a chain wheel, and the chain wheel is in transmission connection with the hopper body through a chain.
4. The rapid-switching funnel of claim 2, wherein the supporting means comprises a plurality of supporting rollers supporting a track disposed outside the body.
5. The rapid switching funnel of claim 3, wherein an electromagnetic switch is disposed outside the body, and the electromagnetic switch is in signal connection with the driving motor.
6. The rapid transfer hopper of claim 3, wherein a safety shield is disposed outside of said sprocket and chain.
7. A delivery system rapid switching funnel according to claim 1 or claim 2, wherein the body is disposed between upstream of the delivery system and downstream of the delivery system.
8. The rapid switching funnel of claim 7, wherein the downstream of the conveyor system comprises N conveyor belts, N ≧ 2.
9. The rapid switching funnel of claim 8, wherein a three-way funnel is disposed between the N corresponding conveyor belts at the lower part of the funnel body, and the upper part of the three-way funnel is flexibly connected to the funnel body.
10. The rapid switching funnel for the conveying system according to claim 1 or 2, further comprising an operation box, wherein a switch is disposed on the operation box.
CN202222443638.5U 2022-09-15 2022-09-15 Conveying system fast switch over funnel Active CN218538329U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222443638.5U CN218538329U (en) 2022-09-15 2022-09-15 Conveying system fast switch over funnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222443638.5U CN218538329U (en) 2022-09-15 2022-09-15 Conveying system fast switch over funnel

Publications (1)

Publication Number Publication Date
CN218538329U true CN218538329U (en) 2023-02-28

Family

ID=85272955

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222443638.5U Active CN218538329U (en) 2022-09-15 2022-09-15 Conveying system fast switch over funnel

Country Status (1)

Country Link
CN (1) CN218538329U (en)

Similar Documents

Publication Publication Date Title
CN208840624U (en) A kind of cutter device of automatic cutting steel plate
CN209333926U (en) The feeding device of quartz sand crusher
CN209905654U (en) Mattress conveying assembly line
CN203439662U (en) High-speed automatic feeder of lead frame
CN207174638U (en) A kind of multidirectional discharging rollgang
CN108907745A (en) A kind of copper bus-bar process units with Combined production line
CN218538329U (en) Conveying system fast switch over funnel
CN206232110U (en) A kind of glass transportation dolly
CN206172471U (en) Automatic send and get material processing machine
CN211413421U (en) Hot stamping automatic feeding device
CN203045543U (en) Automatic loading and unloading device of sand blasting machine
CN205771655U (en) A kind of transmission equipment
CN208963838U (en) A kind of automated warehousing conveying device
CN202321596U (en) Battery sequential arrangement conveying device
CN214140699U (en) Construction is with supplementary shedding mechanism
CN213195034U (en) Special soil automatic repair machine for soil pollution treatment
CN204751264U (en) Novel pile up neatly lead pig is carried device
CN210833074U (en) Belt transmission device and portable slag removal transmission device of heating furnace
CN208761493U (en) A kind of heat treatment automatic feed mechanism
CN209565742U (en) A kind of mine rubber band conveyer automatic tape-alternation device
CN206466660U (en) Vibrating disk feed device
CN213140292U (en) Coal feeding device of gas making furnace
CN218230534U (en) Building construction material loading machine
CN203877470U (en) Mobile three-way distribution device
CN205110413U (en) Drawbench ejection of compact hoist mechanism of convertible ejection of compact direction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20231008

Address after: 617000 Xiangyang Village, East District, Sichuan, Panzhihua

Patentee after: PANGANG GROUP PANZHIHUA STEEL & VANADIUM Co.,Ltd.

Patentee after: XICHANG STEEL VANADIUM CO.,LTD., PANGANG Group

Address before: 617000 Xiangyang Village, East District, Sichuan, Panzhihua

Patentee before: PANGANG GROUP PANZHIHUA STEEL & VANADIUM Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20231122

Address after: 617000 Xiangyang Village, East District, Sichuan, Panzhihua

Patentee after: PANGANG GROUP PANZHIHUA STEEL & VANADIUM Co.,Ltd.

Patentee after: XICHANG STEEL VANADIUM CO.,LTD., PANGANG Group

Patentee after: PANGANG GROUP PANZHIHUA IRON & STEEL RESEARCH INSTITUTE Co.,Ltd.

Address before: 617000 Xiangyang Village, East District, Sichuan, Panzhihua

Patentee before: PANGANG GROUP PANZHIHUA STEEL & VANADIUM Co.,Ltd.

Patentee before: XICHANG STEEL VANADIUM CO.,LTD., PANGANG Group