CN218523153U - Hanging bracket for factory building ceiling pipeline - Google Patents
Hanging bracket for factory building ceiling pipeline Download PDFInfo
- Publication number
- CN218523153U CN218523153U CN202221613488.1U CN202221613488U CN218523153U CN 218523153 U CN218523153 U CN 218523153U CN 202221613488 U CN202221613488 U CN 202221613488U CN 218523153 U CN218523153 U CN 218523153U
- Authority
- CN
- China
- Prior art keywords
- hanging
- factory building
- pipeline
- building ceiling
- crossbeam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Supports For Pipes And Cables (AREA)
Abstract
The utility model discloses a hanging bracket for factory building ceiling pipelines, which comprises an E-shaped hook and a crossbeam, wherein the E-shaped hook comprises a vertical rod, a first hanging beam, a second hanging beam and a bottom beam, the vertical rod is arranged in the vertical direction, the first hanging beam, the second hanging beam and the bottom beam are arranged in the horizontal direction, and sequentially from top to bottom, every 2E-shaped hooks and the crossbeam are matched for use, and the bottom beam of each 2E-shaped hooks is detachably connected with two ends of the crossbeam; the utility model provides a to harmless and firm gallows of factory building ceiling pipeline of steel construction.
Description
Technical Field
The utility model relates to a pipeline construction technical field specifically is a gallows of factory building ceiling pipeline.
Background
According to the existing steel structure factory building ceiling pipeline construction technology, aiming at the installation and construction of pipelines in a factory building, because the roof is a steel structure main beam, the construction can not be carried out according to the process of drilling the mounting bracket in the construction of a reinforced concrete structure. In conventional construction, one method is to arrange the roof pipelines in the steel structure deepening design stage and weld the bracket connecting pieces in advance in the roof girder processing stage; the other type is that after the installation of the main beam is finished, the pipeline bracket is processed and then is fixed by adopting modes such as electric welding and the like, and the steel structure is damaged by adopting the modes, so that the potential quality hazard is caused.
SUMMERY OF THE UTILITY MODEL
The utility model provides a to the harmless and firm gallows of factory building ceiling pipeline of steel construction.
To achieve the purpose, the utility model provides the following technical scheme:
the utility model provides a gallows of factory building ceiling pipeline, including E shape couple and crossbeam, E shape couple includes pole setting, first string roof beam, second string roof beam and floorbar, the vertical direction is arranged in to the pole setting, first string roof beam the second string roof beam with the horizontal direction is arranged in to the floorbar, and from last to down, every 2 in proper order E shape couple with the crossbeam matches and uses, 2E shape couple the floorbar with the detachable connection in both ends of crossbeam.
Preferably, the distance between the first hanging beam and the second hanging beam is 3-8cm, and the distance between the second hanging beam and the bottom beam is not less than the diameter of the pipeline.
Preferably, the device further comprises a clamp, and the two ends of the clamp are detachably connected with the cross beam.
Preferably, the E-shaped hook further comprises a guy cable, and two ends of the guy cable are respectively connected with the 2 first hanging beams of the E-shaped hook.
Preferably, the bottom beam is provided with a mounting hole, the cross beam is provided with a mounting hole, and the bottom beam and the cross beam are fixed through bolts.
Preferably, the clip comprises a steel cord.
The utility model discloses an installation method of gallows of factory building ceiling pipeline as follows:
s1, after the plant ceiling is installed, inserting a U-shaped opening formed by a first hanging beam and a second hanging beam of 2E-shaped hooks on a lower flange plate of I-shaped steel of the plant ceiling;
s2, connecting the E-shaped hook with the cross beam;
s3, fixing the inhaul cable on the first hanging beam of the 2E-shaped hooks, and keeping the inhaul cable in a tensioned state;
s4, placing the pipeline in a mouth-shaped space formed by the I-shaped steel, the E-shaped hook and the cross beam;
and S5, fixing two ends of the clamp on the bottom beam, and clamping the pipeline by the clamp.
Compared with the prior art, the utility model discloses beneficial effect and showing the progress and lie in:
1. the utility model discloses a gallows simple manufacture, reuse of factory building ceiling pipeline.
2. The utility model discloses a gallows installation of factory building ceiling pipeline is swift, and does not have any damage to the structure, the high quality.
Drawings
To more clearly illustrate the technical solution of the present invention, the drawings required for the embodiments of the present invention will be briefly described below.
It should be apparent that the drawings in the following description are only for some embodiments of the present invention, and that other drawings can be obtained by those skilled in the art without any inventive exercise, and the other drawings also belong to the drawings required for the embodiments of the present invention.
Fig. 1 is a use state diagram of a hanger of a factory building ceiling pipeline according to an embodiment of the present invention;
fig. 2 is a schematic structural view of an E-shaped hook of a hanger of a plant ceiling pipeline according to an embodiment of the present invention;
the number of the connecting device is 1, I-shaped steel, 2, E-shaped hooks, 3, a pipeline, 4, a hoop, 5, a cross beam, 2.1, a second hanging beam, 2.2, a vertical rod, 2.3, a bottom beam, 2.4 and a first hanging beam.
Detailed Description
In order to make the purpose, technical scheme, beneficial effect and showing the progress of the embodiment of the present invention clearer, below, will combine the embodiment of the present invention, to the technical scheme in the embodiment of the present invention is clear, completely described.
It is to be understood that all of the described embodiments are only some, and not all, of the embodiments of the invention; based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative efforts belong to the protection scope of the present invention.
It should be noted that the terms "first", "second" and "third" (if present) and the like in the description and the claims of the present invention are used for distinguishing different objects and are not used for describing a specific order. Furthermore, the terms "comprises" and any variations thereof, are intended to cover non-exclusive inclusions. For example, a process, method, system, article, or apparatus that comprises a list of steps or elements is not limited to only those steps or elements but may alternatively include other steps or elements not expressly listed or inherent to such process, method, article, or apparatus.
It is to be understood that:
in the present invention, unless otherwise explicitly specified or limited, the terms "mounted," "connected," "fixed," and the like are to be understood in a broad sense, and may be, for example, fixedly connected, detachably connected, or movably connected, or integrated; either directly or indirectly through intervening media, intangible signal, or even optical, communication between two elements, or an interaction between two elements, unless expressly limited otherwise.
The specific meaning of the above terms in the present invention can be understood according to specific situations by those of ordinary skill in the art.
It should be further noted that the following embodiments may be combined with each other, and the same or similar concepts or processes may not be repeated in some embodiments.
The technical solution of the present invention will be described in detail with reference to specific examples.
Example 1
As shown in fig. 1 and 2, a hanger for a factory building ceiling pipeline is shown, which comprises an E-shaped hook 2, a hoop 3 and a cross beam 5, wherein the E-shaped hook 2 comprises an upright rod 2.2, a first hanging beam 2.4, a second hanging beam 2.1 and a bottom beam 2.3, the upright rod 2.2 is arranged in the vertical direction, the first hanging beam 2.4, the second hanging beam 2.1 and the bottom beam 2.3 are arranged in the horizontal direction, and sequentially from top to bottom, each 2E-shaped hooks 2 and the cross beam 5 are matched for use, and the bottom beams 2.3 of the 2E-shaped hooks 2 are detachably connected with two ends of the cross beam 5. Both ends of the hoop 3 are detachably connected with a cross beam 5. The lower flange plate of the I-steel 1 is arranged between the first hanging beam 2.4 and the second hanging beam 2.1, and the clamp 3 fixes the pipeline 3 on the cross beam 5.
In this embodiment, the distance between the first hanging beam 2.4 and the second hanging beam 2.1 is 3-8cm, and the distance between the second hanging beam 2.1 and the bottom beam 2.3 is not less than the diameter of the pipeline.
In this embodiment, still include the cable that the picture is not shown, the first string roof beam of 2E shape couples is connected respectively to the both ends of cable.
In this embodiment, the bottom beam is provided with a mounting hole, the cross beam is provided with a mounting hole, and the bottom beam and the cross beam are fixed by bolts.
In this embodiment, the clip comprises a steel cable.
In this embodiment, the E-shaped hook includes an upright, a first hanging beam, a second hanging beam, and a bottom beam, all fabricated using 30 × 3 galvanized square tubes. The length of the vertical rods is arranged according to the size and the elevation of the pipeline, the hanging beams are composed of two square tubes, the length of each hanging beam is 100mm, the distance between the two hanging beams is 50-70mm, and the length of each hanging beam can be specifically adjusted according to the thickness of the flange plate of the I-shaped steel; the length of the bottom beam is 100-150mm, and phi 6 bolt holes are arranged on the side face of the bottom beam at a distance of 50mm. The upright stanchion, the hanging beam and the bottom beam are all welded and fixed.
In the embodiment, 2, the cross beam is made of 40 × 3 galvanized square pipes, and phi 6 bolt holes are arranged on the transverse side face at intervals of 50mm. The length of the cross beam is adjusted according to the size of the pipeline, but the anchoring length of the cross beam and the bottom beam of the hook is ensured to be not less than 50mm.
The method for installing the hanging bracket of the factory building ceiling pipeline comprises the following steps:
s1, after the plant ceiling is installed, inserting a U-shaped opening formed by a first hanging beam and a second hanging beam of 2E-shaped hooks into a lower flange plate of I-shaped steel of the plant ceiling;
s2, connecting the E-shaped hook with the cross beam;
s3, fixing the inhaul cable on the first hanging beam of the 2E-shaped hooks, and keeping the inhaul cable in a tensioned state;
s4, placing the pipeline in a mouth-shaped space formed by the I-shaped steel, the E-shaped hook and the cross beam;
and S5, fixing two ends of the clamp on the bottom beam, and clamping the pipeline by the clamp.
During the description of the above description:
the description of the terms "present embodiment," embodiments of the invention, "" such as "\ 8230; \ 8230"; "shown," "further improved technical sub-arrangements," etc., means that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the invention; in this specification, the schematic representations of the terms used above are not necessarily for the same embodiment or example, and the particular features, structures, materials, or characteristics described, etc., may be combined or brought together in any suitable manner in any one or more embodiments or examples; moreover, those of ordinary skill in the art may combine or combine features of the various embodiments or examples and features of the various embodiments or examples described herein without creating a contradiction.
Finally, it should be noted that:
the above embodiments are only used to illustrate the technical solution of the present invention, and not to limit the same;
although the present invention has been described in detail with reference to the foregoing embodiments, it should be understood by those skilled in the art that the technical solutions described in the foregoing embodiments may be modified or equivalent replaced by some or all of the technical features, and such modifications or replacements may not cause the essence of the corresponding technical solutions to depart from the scope of the technical solutions of the embodiments of the present invention.
Claims (6)
1. The utility model provides a gallows of factory building ceiling pipeline, a serial communication port, including E shape couple and crossbeam, E shape couple includes the pole setting, first string roof beam, second string roof beam and floorbar, the vertical direction is arranged in to the pole setting, first string roof beam the second hang the roof beam with the horizontal direction is arranged in to the floorbar, and from last to down, every 2 in proper order E shape couple with the crossbeam matches the use, 2E shape couple the floorbar with the detachable connection in both ends of crossbeam.
2. The hanging bracket for the factory building ceiling pipeline as claimed in claim 1, wherein the distance between the first hanging beam and the second hanging beam is 3-8cm, and the distance between the second hanging beam and the bottom beam is not less than the diameter of the pipeline.
3. The hanger of factory building ceiling pipelines according to claim 1, further comprising a clamp, wherein two ends of the clamp are detachably connected with the cross beam.
4. The hanging bracket of the factory building ceiling pipeline according to claim 1, further comprising a guy cable, wherein two ends of the guy cable are respectively connected with the first hanging beams of 2E-shaped hooks.
5. The hanging bracket for the factory building ceiling pipeline according to claim 1, wherein mounting holes are formed in the bottom beam, mounting holes are formed in the cross beam, and the bottom beam and the cross beam are fixed through bolts.
6. The hanger for plant ceiling piping according to claim 3, wherein said clip comprises a steel cable.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202221613488.1U CN218523153U (en) | 2022-06-27 | 2022-06-27 | Hanging bracket for factory building ceiling pipeline |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202221613488.1U CN218523153U (en) | 2022-06-27 | 2022-06-27 | Hanging bracket for factory building ceiling pipeline |
Publications (1)
Publication Number | Publication Date |
---|---|
CN218523153U true CN218523153U (en) | 2023-02-24 |
Family
ID=85237248
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202221613488.1U Active CN218523153U (en) | 2022-06-27 | 2022-06-27 | Hanging bracket for factory building ceiling pipeline |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN218523153U (en) |
-
2022
- 2022-06-27 CN CN202221613488.1U patent/CN218523153U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109113369B (en) | Safe demolition method for manual demolition of cylindrical building | |
CN218523153U (en) | Hanging bracket for factory building ceiling pipeline | |
JP2639361B2 (en) | Construction method of steel pipe / concrete composite structure pier | |
CN111795212B (en) | Suspension method and suspension structure for pipeline crossing foundation pit | |
CN212336672U (en) | I-steel overhanging bearing frame of basket pull rod for constructional engineering | |
CN112302163A (en) | Connecting device for building beam and column and manufacturing method thereof | |
CN110112681B (en) | Modular cable hoist and mount lays auxiliary device | |
CN213014358U (en) | Pipeline suspension structure | |
CN113148396A (en) | Pipeline transportation support and pipeline transportation method | |
CN210713879U (en) | Steel column verticality adjusting device | |
JP2645758B2 (en) | Construction method of suspension bridge type pipe bridge | |
CN220732206U (en) | Spliced suspension bracket structure for pipeline suspension construction | |
CN218668663U (en) | Square structure prevents a reinforced structure | |
CN216587615U (en) | Installation operation support of wall body top decorative cover layer | |
CN220301749U (en) | Scaffold door opening supporting system | |
CN221295881U (en) | Hoisting system for pipeline installation | |
CN214424005U (en) | Single-beam formwork system support | |
CN117468692A (en) | Hanging basket hanging mechanism | |
CN219703912U (en) | Assembled steel pipe welding platform | |
CN220521918U (en) | Combined type finalized steel pipe supporting temporary scaffold | |
CN215519149U (en) | Clear truss connected node of encorbelmenting of load transmission | |
CN113932068B (en) | Method for assembling overhead vibration isolation hanging bracket of spring in annular pipe gallery | |
CN218621850U (en) | A construction passageway protective structure for steel truss encircles | |
CN216338002U (en) | Soft splint generating line of taking supports reinforcing apparatus | |
CN216640293U (en) | Assembled high altitude tubular column operation platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |