CN218479204U - Retaining wall that fastness is high - Google Patents
Retaining wall that fastness is high Download PDFInfo
- Publication number
- CN218479204U CN218479204U CN202222899946.9U CN202222899946U CN218479204U CN 218479204 U CN218479204 U CN 218479204U CN 202222899946 U CN202222899946 U CN 202222899946U CN 218479204 U CN218479204 U CN 218479204U
- Authority
- CN
- China
- Prior art keywords
- top surface
- basement
- groove
- wall body
- wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
- Y02A30/24—Structural elements or technologies for improving thermal insulation
- Y02A30/244—Structural elements or technologies for improving thermal insulation using natural or recycled building materials, e.g. straw, wool, clay or used tires
Landscapes
- Retaining Walls (AREA)
Abstract
The utility model relates to a retaining wall technical field's a retaining wall that fastness is high, which comprises a base, the top surface fixed mounting of basement has the wall body, the top surface of wall body is equipped with the coping stone, two relative first logical grooves have been seted up to the top surface of coping stone, and just first logical groove runs through to the surface of basement, the equal fixed mounting in both sides of wall body has the supporting shoe, the second that runs through the coping stone and extend to basement top surface is led to the groove all seted up to the both sides in first logical groove, the third that runs through the coping stone and extend to basement top surface is seted up to the top surface of supporting shoe leads to the groove. Set up two first logical grooves that run through to basement top through the top surface that sets up the coping stone to and the second that first logical groove both sides leads to the groove and the third that the supporting shoe top surface was seted up leads to the groove, and the focus when can making basement, wall body and coping stone whole use is put at the basement, reinforcing stability, and the setting of middle empty has the antidetonation effect when can making whole use.
Description
Technical Field
The utility model relates to a retaining wall technical field especially relates to a retaining wall that fastness is high.
Background
The retaining wall is a structure for supporting roadbed filling or hillside soil and preventing the filling or the soil from deforming and destabilizing, and the part of the cross section of the retaining wall, which is directly contacted with the supported soil, is called a wall back; the part facing the wall back and being empty is called the wall surface; the part directly contacting with the foundation is called a substrate; the top surface of the wall opposite the base is called the wall top; the front end of the base is called a wall toe; the rear end of the base is called a butt.
Current retaining wall is construction convenience, generally can adopt the comparatively simple pattern of structure, generally sets up for the single face, but needs self gravity balance soil body just need increase reinforcing bar, the concrete that the support nature is stronger in the intracavity, but the structure of actual self still can influence the resistance state, for this we propose the retaining wall that a fastness is high.
SUMMERY OF THE UTILITY MODEL
To the problem, the utility model provides a retaining wall that fastness is high has the effect that increases structural stability.
The technical scheme of the utility model is that:
the utility model provides a retaining wall that fastness is high, includes the basement, the top surface fixed mounting of basement has the wall body, the top surface of wall body is equipped with the coping stone, two relative first logical grooves have been seted up to the top surface of coping stone, and just first logical groove runs through to the surface of basement, the equal fixed mounting in both sides of wall body has the supporting shoe, the second that runs through the coping stone and extend to the basement top surface is led to the groove all seted up to the both sides in first logical groove, the third that runs through the coping stone and extend to the basement top surface is seted up to the top surface of supporting shoe leads to the groove.
In a further technical scheme, the inside fixed mounting of basement has the reinforcing bar that extends to the inside of wall body, and the reinforcing bar is equipped with a plurality ofly.
In a further technical scheme, the wall body is composed of a waterproof layer, a concrete layer and a back lining layer.
In a further technical scheme, a plurality of drainage grooves are formed in two ends of the wall, and a water seepage groove is formed in the outer surface of one of the supporting blocks.
In a further technical scheme, the capping stone is made of plastic steel.
The beneficial effects of the utility model are that:
1. two first through grooves penetrating to the upper part of the base are formed in the top surface of the coping stone, second through grooves on two sides of the first through grooves and third through grooves formed in the top surface of the supporting block, so that the center of gravity of the base, a wall and the coping stone can be placed on the base when the base, the wall and the coping stone are integrally used, the stability is enhanced, and the anti-seismic effect can be achieved when the base, the wall and the coping stone are integrally used due to the arrangement of the middle space;
2. through setting up the reinforcing bar and inserting the inside of establishing at the basement to extend to the inside of wall body, can make overall structure have the stability when keeping out external force, the reinforcing bar is convenient for directly carry out fixed mounting with the basement simultaneously.
Drawings
Fig. 1 is a schematic diagram of the overall structure of the embodiment of the present invention;
FIG. 2 is a schematic side view of the embodiment of the present invention;
fig. 3 is a schematic structural view of the base and the reinforcing bars according to the embodiment of the present invention.
Description of reference numerals:
1. a substrate; 2. a wall body; 3. pressing a top stone; 4. a supporting block; 5. a first through groove; 6. a second through groove; 7. a third through groove; 8. a water seepage tank; 9. a water discharge tank; 10. and (5) reinforcing steel bars.
Detailed Description
The following describes embodiments of the present invention with reference to the drawings.
Example (b):
as shown in fig. 1-3, a retaining wall with high firmness, including a base 1, a wall body 2 is fixedly mounted on the top surface of the base 1, a coping stone 3 is arranged on the top surface of the wall body 2, two opposite first through grooves 5 are formed in the top surface of the coping stone 3, the first through grooves 5 penetrate through the surface of the base 1, supporting blocks 4 are fixedly mounted on two sides of the wall body 2, second through grooves 6 penetrating through the coping stone 3 and extending to the top surface of the base 1 are formed in two sides of each first through groove 5, third through grooves 7 penetrating through the coping stone 3 and extending to the top surface of the base 1 are formed in the top surface of each supporting block 4, the retaining wall is composed of the base 1, the wall body 2 and the coping stone 3, so that the overall stability is improved, meanwhile, the first through grooves 5, the second through grooves 6 and the third through grooves 7 are formed, and the overall shock resistance is increased.
The working principle of the above technical scheme is as follows:
when the wall body 2 is used, the base 1 is buried underground, then the wall body 2 is laid on the top surface of the base 1, then the coping stone 3 is pressed on the top surface of the wall body 2, in the stacking process, gaps among the first through groove 5, the second through groove 6 and the third through groove 7 are reserved, and the supporting block 4 is fixedly connected with the wall body 2 in an integrated mode during stacking.
In another embodiment, as shown in fig. 3, the reinforcing bars 10 extending into the wall 2 are fixedly installed inside the base 1, and the reinforcing bars 10 are provided in a plurality, so that the support of the wall 2 can be enhanced by providing the reinforcing bars 10.
In use, the wall body 2 is stacked on the top surface of the foundation 1 and fused with the reinforcing bars 10.
In another embodiment, as shown in fig. 2, the wall 2 is composed of a waterproof layer, a concrete layer and a backing layer, the combination of the substrate 1 and the wall 2 can be more consistent by arranging the wall 2, and the arrangement of the waterproof layer in the wall 2 can reduce the overall water absorption and enhance the stability.
When in use, the combination of the wall body 2 and the substrate 1 is connected through a concrete layer, and meanwhile, the reinforcing steel bars 10 are convenient to fuse in the wall body 2.
In another embodiment, as shown in fig. 1 and 2, a plurality of drainage grooves 9 are formed at both ends of the wall body 2, a water seepage groove 8 is formed on the outer surface of one of the supporting blocks 4, and by arranging the water seepage groove 8 and the drainage grooves 9, water passing through the retaining wall can be drained when the retaining wall is used, so that the retaining wall is prevented from being combined with the substrate 1, the wall body 2 and the coping stone 3 to affect the supporting strength.
When the retaining wall is manufactured, drainage grooves 9 are formed in the surfaces of the two ends of the wall body 2, and then water seepage grooves 8 are formed in one side surface of the supporting block 4.
In another embodiment, as shown in fig. 1, the capping stone 3 is made of plastic steel, and the capping stone 3 is made of plastic steel, so that when the retaining wall is used, the top surface has excellent moisture-proof and corrosion-proof effects, and the retaining wall can be used for a long time.
When in use, the coping stone 3 is pressed on the top surface of the wall body 2 for fixing.
The above embodiments only express the specific embodiments of the present invention, and the description thereof is specific and detailed, but not construed as limiting the scope of the present invention. It should be noted that, for those skilled in the art, without departing from the concept of the present invention, several variations and modifications can be made, which all fall within the scope of the present invention.
Claims (5)
1. The utility model provides a retaining wall that fastness is high, includes basement (1), its characterized in that: the top surface fixed mounting of basement (1) has wall body (2), the top surface of wall body (2) is equipped with coping stone (3), two relative first logical groove (5) have been seted up to the top surface of coping stone (3), and first logical groove (5) run through to the surface of basement (1), the equal fixed mounting in both sides of wall body (2) has supporting shoe (4), the second that runs through coping stone (3) and extend to basement (1) top surface is led to groove (6) has all been seted up to the both sides that first lead to groove (5), the third tee bend groove (7) that runs through coping stone (3) and extend to basement (1) top surface have been seted up to the top surface of supporting shoe (4).
2. A retaining wall of high firmness according to claim 1, wherein: the inside fixed mounting of basement (1) has reinforcing bar (10) that extend to wall body (2) inside, and reinforcing bar (10) are equipped with a plurality ofly.
3. A retaining wall of high firmness according to claim 1, characterised in that: the wall body (2) is composed of a waterproof layer, a concrete layer and a back lining layer.
4. A retaining wall of high firmness according to claim 1, wherein: a plurality of drainage channels (9) are formed in the two ends of the wall body (2), and a water seepage channel (8) is formed in the outer surface of one supporting block (4).
5. A retaining wall of high firmness according to claim 1, wherein: the coping stone (3) is made of plastic steel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222899946.9U CN218479204U (en) | 2022-11-01 | 2022-11-01 | Retaining wall that fastness is high |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222899946.9U CN218479204U (en) | 2022-11-01 | 2022-11-01 | Retaining wall that fastness is high |
Publications (1)
Publication Number | Publication Date |
---|---|
CN218479204U true CN218479204U (en) | 2023-02-14 |
Family
ID=85171433
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202222899946.9U Active CN218479204U (en) | 2022-11-01 | 2022-11-01 | Retaining wall that fastness is high |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN218479204U (en) |
-
2022
- 2022-11-01 CN CN202222899946.9U patent/CN218479204U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111455771B (en) | Brick road surface structure permeates water | |
CN207244654U (en) | Stake two layers of retaining wall structure of support | |
CN110397156A (en) | A kind of Prefabricated reinforced concrete is whole to pour building structure and construction method | |
CN218479204U (en) | Retaining wall that fastness is high | |
CN209816902U (en) | Road greening retaining wall | |
CN213508309U (en) | Hydraulic engineering retaining wall | |
CN210887096U (en) | Novel concrete dam reinforcement reinforced structure | |
CN210066780U (en) | Self-drainage functional soil retaining brick | |
CN210341952U (en) | Slope protection device for preventing water and soil loss | |
CN216615956U (en) | Flexibly assembled block brick for plant-growing retaining wall | |
CN208056099U (en) | A kind of civil construction retaining wall structure | |
CN213868219U (en) | Anchoring structure for newly added wall of reservoir | |
CN210177536U (en) | Reinforced earth retaining wall structure | |
CN217580271U (en) | Landscape type retaining wall brick and retaining wall | |
CN214460365U (en) | Pile foundation reinforcing apparatus for building foundation | |
CN112575736A (en) | Water conservancy slope protection structure and construction method thereof | |
CN214574128U (en) | Anti basement bottom plate structure that floats | |
CN214574036U (en) | Mountain side slope building stable structure | |
CN112982653B (en) | Construction method of mountain-based building stable structure | |
CN210066811U (en) | Municipal administration retaining wall structure | |
CN220414307U (en) | Concrete sheet pile type retaining wall structure | |
CN216075227U (en) | Prefabricated assembled road retaining wall structure | |
CN213952284U (en) | Novel flexible retaining wall | |
CN215053216U (en) | Ecological gravity type retaining wall structure | |
CN213926793U (en) | Construction joint waterproof construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |