CN218415578U - High-rise building cable laying device - Google Patents

High-rise building cable laying device Download PDF

Info

Publication number
CN218415578U
CN218415578U CN202222891755.8U CN202222891755U CN218415578U CN 218415578 U CN218415578 U CN 218415578U CN 202222891755 U CN202222891755 U CN 202222891755U CN 218415578 U CN218415578 U CN 218415578U
Authority
CN
China
Prior art keywords
cable
threaded rod
lock nut
rise building
mounting bracket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222891755.8U
Other languages
Chinese (zh)
Inventor
朱小明
高强
杨藏
董钦城
胡利彪
王宁
邹盟
林伟丰
沈启金
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN202222891755.8U priority Critical patent/CN218415578U/en
Application granted granted Critical
Publication of CN218415578U publication Critical patent/CN218415578U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Installation Of Indoor Wiring (AREA)

Abstract

The utility model discloses a high-rise building cable laying device, which comprises a mounting bracket, the surface of mounting bracket is provided with respectively can carry out the centre gripping subassembly fixed to the cable and can carry out the slip subassembly that leads to the cable, and the centre gripping subassembly comprises first semicircle splint, second semicircle splint, connecting threaded rod, first lock nut and second lock nut, and the slip subassembly comprises installing frame, supporting threaded rod, fixation nut, pulley, spacing arc and adjusting bolt. This high-rise building cable laying device will support the threaded rod and pass the bar groove to utilize fixation nut to fix the installing frame on the mounting bracket, pass the cable traction head between pulley and the spacing arc after that, when traction cable, the cable traction head can the tractive cable get into in the installing frame, thereby usable pulley and spacing arc carry out spacingly and direction to the cable, avoided that the cable can take place to rock when the tractive cable, cause the cable outside and the fricative problem of electrical shaft emergence.

Description

High-rise building cable laying device
Technical Field
The utility model relates to a cable laying technical field specifically is a high-rise building cable laying device.
Background
The well that will reserve certain cross-section from the bottom to the top among the high-rise building is called electric shaft, when laying cable, can lay the cable in electric shaft, at present, cable is when laying among the current super high-rise building, adopt hoist engine and tractive steel cable to pull the cable to electric shaft in usually, thereby accomplish and lay, nevertheless because electric shaft overlength among the high-rise building, the phenomenon of rocking takes place easily for the cable atress during the traction cable, make the cable outside take place to rub with electric shaft easily, cause the cable surface damage, influence the life of cable. Therefore, a cable laying device for high-rise buildings is provided.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a high-rise building cable laying device to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above purpose, the utility model provides a following technical scheme: the utility model provides a high-rise building cable laying device, which comprises a mounting rack, the surface of mounting bracket is provided with respectively can carry out the centre gripping subassembly fixed to the cable and can carry out the slip subassembly that leads to the cable, the centre gripping subassembly is by first semicircular clamping plate, second semicircular clamping plate, connecting thread rod, first lock nut and second lock nut constitute, the slip subassembly is by the installing frame, supporting thread pole, fixation nut, the pulley, spacing arc and adjusting bolt constitute, the quantity of spacing arc is two, the ball groove has all been seted up to the interior anchor ring of two spacing arcs, the inner wall rotation of ball groove is connected with the spin, the gliding bar groove of confession connecting thread pole and supporting thread pole is seted up on the surface of mounting bracket.
Preferably, connecting threaded rod's quantity is two, two connecting threaded rod's left end respectively with the right-hand member fixed connection of first semicircle splint and second semicircle splint, and first lock nut and second lock nut's quantity is two, and two first lock nuts and second lock nut equally divide into two sets ofly, two sets of first lock nut and second lock nut respectively with two connecting threaded rod's surperficial threaded connection.
Preferably, the opposite surfaces of the first semicircular clamping plate and the second semicircular clamping plate are respectively provided with symmetrical assembling holes.
Preferably, the right flank of installing frame and the left end fixed connection who supports the threaded rod, fixation nut's inner wall and the surperficial threaded connection who supports the threaded rod, the both ends of pulley are connected with the interior antetheca and the interior back wall rotation of installing frame respectively.
Preferably, the number of the adjusting bolts is two, the two adjusting bolts are respectively in threaded connection with the front surface and the back surface of the mounting frame, and the threaded ends of the two adjusting bolts extend to the inner wall of the mounting frame and are rotatably connected with the outer annular surfaces of the two limiting arc-shaped plates.
Preferably, the equal fixedly connected with of inner ring face of first semicircle splint and second semicircle splint antiskid rubber pad, the mounting hole has all been seted up at the front and the back of mounting bracket.
Advantageous effects
The utility model provides a high-rise building cable laying device possesses following beneficial effect:
1. this high-rise building cable laying device, install the mounting bracket equidistance in electric shaft, make supporting threaded rod pass the bar groove, and utilize fixation nut to fix the installing frame on the mounting bracket, pass the cable traction head between pulley and the spacing arc after that, when traction cable, the cable traction head can the tractive cable get into in the installing frame, thereby usable pulley and spacing arc carry out spacing and direction to the cable, avoided the cable can take place to rock when the tractive cable, cause the cable outside and electric shaft to take place frictional problem.
2. This high-rise building cable laying device, after cable traction accomplishes, unscrew fixation nut, make sliding assembly demolish from the mounting bracket, pass the bar inslot with two connecting threaded rod after that, and utilize two sets of first lock nut and second lock nut to fix first semicircle splint and second semicircle splint in the both sides of cable, utilize outside bolt to assemble first semicircle splint and second semicircle splint as an organic whole after that, thereby usable first semicircle splint and second semicircle splint carry out the centre gripping with the cable fixed, and then made things convenient for the centre gripping to the cable.
Drawings
FIG. 1 is a schematic view of the three-dimensional structure of the present invention;
FIG. 2 is a schematic view of the installation frame of the present invention;
fig. 3 is a schematic view of a front view of the first semicircular clamping plate of the present invention;
fig. 4 is a schematic view of the front view structure of the mounting rack of the present invention;
fig. 5 is the utility model discloses spacing arc splint cut open schematic structure drawing downwards.
In the figure: 1 mounting bracket, 2 first semicircle splint, 3 second semicircle splint, 4 connecting threaded rods, 5 first lock nuts, 6 second lock nuts, 7 installing frames, 8 support threaded rods, 9 fixation nuts, 10 pulleys, 11 spacing arcs, 12 adjusting bolts, 13 spin, 14 anti-skidding rubber pads.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-5, the present invention provides a technical solution: the utility model provides a high-rise building cable laying device, includes mounting bracket 1, and the surface of mounting bracket 1 is provided with respectively can be to the cable carry out the centre gripping subassembly fixed and can carry out the slip subassembly that leads to the cable.
The sliding assembly comprises installing frame 7, supporting threaded rod 8, fixation nut 9, pulley 10, spacing arc 11 and adjusting bolt 12, and the quantity of spacing arc 11 is two, and the ball groove has all been seted up to the interior anchor ring of two spacing arcs 11, and the inner wall of ball groove rotates and is connected with spin 13.
The right flank of installing frame 7 and the left end fixed connection who supports threaded rod 8, fixation nut 9's inner wall and the surperficial threaded connection who supports threaded rod 8, pulley 10's both ends rotate with the interior antetheca and the interior back wall of installing frame 7 respectively and are connected, adjusting bolt 12's quantity is two, two adjusting bolt 12 respectively with the front and the back threaded connection of installing frame 7, two adjusting bolt 12's threaded end all extends to the inner wall of installing frame 7, and rotate with the outer anchor ring of two spacing arcs 11 and be connected.
The centre gripping subassembly comprises first semicircle splint 2, second semicircle splint 3, connecting threaded rod 4, first lock nut 5 and second lock nut 6, and confession connecting threaded rod 4 and the gliding bar groove of support threaded rod 8 are seted up on the surface of mounting bracket 1, and the mounting hole has all been seted up at the front and the back of mounting bracket 1.
Install 1 equidistance of mounting bracket in electric shaft, make supporting threaded rod 8 pass the bar groove, screw up fixation nut 9, thereby can fix installing frame 7 on mounting bracket 1, pass the cable traction head between pulley 10 and the spacing arc 11 after that, when traction cable, the cable traction head can tractive cable get into in installing frame 7, rotate adjusting bolt 12 and drive the surperficial contact of spin 13 on two spacing arcs 11 and cable, thereby usable pulley 10 and spacing arc 11 carry on spacingly and the direction to the cable, avoided the cable can take place to rock when the tractive cable, cause the cable outside and the problem of electric shaft emergence friction.
Connecting threaded rod 4's quantity is two, two connecting threaded rod 4's left end respectively with the right-hand member fixed connection of first semicircle splint 2 and second semicircle splint 3, and the quantity of first lock nut 5 and second lock nut 6 is two, and two first lock nuts 5 and second lock nut 6 are equallyd divide into two sets ofly, two sets of first lock nuts 5 and second lock nut 6 respectively with two connecting threaded rod 4's surperficial threaded connection.
The pilot hole has all been seted up to the opposite face of first semicircle splint 2 and second semicircle splint 3, the equal fixedly connected with of interior anchor ring face of first semicircle splint 2 and second semicircle splint 3 anti-skidding rubber pad 14.
After the cable pulls the completion, unscrew fixation nut 9, make sliding assembly demolish from mounting bracket 1, unscrew connecting threaded rod 4 with second lock nut 6, make two connecting threaded rod 4 on first semicircle splint 2 and the second semicircle splint 3 pass the bar inslot, then twist connecting threaded rod 4 surface with second lock nut 6, thereby can fix the both sides at the cable with first semicircle splint 2 and second semicircle splint 3, utilize outside bolt to assemble first semicircle splint 2 and second semicircle splint 3 as an organic whole, thereby usable first semicircle splint 2 and second semicircle splint 3 carry out the centre gripping with the cable and fix, and then made things convenient for the centre gripping to the cable, also can install proper amount first semicircle splint 2 and second semicircle splint 3 according to the quantity of laying of cable simultaneously.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a high-rise building cable laying device, includes mounting bracket (1), its characterized in that: the utility model discloses a cable fixing device, including mounting bracket (1), the surface of mounting bracket (1) is provided with respectively and carries out the centre gripping subassembly fixed and can carry out the slip subassembly that leads to the cable, the centre gripping subassembly is by first semicircular clamping plate (2), second semicircular clamping plate (3), connecting threaded rod (4), first lock nut (5) and second lock nut (6) constitute, the slip subassembly is by installing frame (7), supporting threaded rod (8), fixation nut (9), pulley (10), spacing arc (11) and adjusting bolt (12) constitute, the quantity of spacing arc (11) is two, the ball groove has all been seted up to the interior anchor ring of two spacing arcs (11), the inner wall of ball groove rotates and is connected with spin (13), the gliding bar groove of confession connecting threaded rod (4) and supporting threaded rod (8) is seted up on the surface of mounting bracket (1).
2. A high-rise building cabling arrangement according to claim 1, wherein: the quantity of connecting threaded rod (4) is two, and the left end of two connecting threaded rod (4) is two with the right-hand member fixed connection of first semicircle splint (2) and second semicircle splint (3) respectively, and the quantity of first lock nut (5) and second lock nut (6) is two, and two sets of are equallyd divide to two first lock nut (5) and second lock nut (6), and two sets of first lock nut (5) and second lock nut (6) are respectively with the surface threaded connection of two connecting threaded rod (4).
3. A high-rise building cabling arrangement as claimed in claim 1, wherein: the opposite surfaces of the first semicircular clamping plate (2) and the second semicircular clamping plate (3) are respectively provided with symmetrical assembling holes.
4. A high-rise building cabling arrangement as claimed in claim 1, wherein: the right flank of installing frame (7) and the left end fixed connection who supports threaded rod (8), the inner wall of fixation nut (9) and the surperficial threaded connection who supports threaded rod (8), the both ends of pulley (10) are connected with the interior antetheca and interior back wall rotation of installing frame (7) respectively.
5. A high-rise building cabling arrangement according to claim 1, wherein: the number of the adjusting bolts (12) is two, the two adjusting bolts (12) are respectively in threaded connection with the front face and the back face of the mounting frame (7), and the threaded ends of the two adjusting bolts (12) extend to the inner wall of the mounting frame (7) and are rotatably connected with the outer annular faces of the two limiting arc-shaped plates (11).
6. A high-rise building cabling arrangement as claimed in claim 1, wherein: the anti-skidding rubber pads (14) are fixedly connected to the inner annular surfaces of the first semicircular clamping plate (2) and the second semicircular clamping plate (3), and mounting holes are formed in the front face and the back face of the mounting frame (1).
CN202222891755.8U 2022-11-01 2022-11-01 High-rise building cable laying device Active CN218415578U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222891755.8U CN218415578U (en) 2022-11-01 2022-11-01 High-rise building cable laying device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222891755.8U CN218415578U (en) 2022-11-01 2022-11-01 High-rise building cable laying device

Publications (1)

Publication Number Publication Date
CN218415578U true CN218415578U (en) 2023-01-31

Family

ID=85007123

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222891755.8U Active CN218415578U (en) 2022-11-01 2022-11-01 High-rise building cable laying device

Country Status (1)

Country Link
CN (1) CN218415578U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116111535A (en) * 2023-04-17 2023-05-12 国网山东省电力公司潍坊市寒亭区供电公司 Cable clamp for cable installation
CN116526391A (en) * 2023-07-04 2023-08-01 冠诚建设工程有限公司 Cable installation equipment for medical factory building construction

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116111535A (en) * 2023-04-17 2023-05-12 国网山东省电力公司潍坊市寒亭区供电公司 Cable clamp for cable installation
CN116111535B (en) * 2023-04-17 2023-07-28 国网山东省电力公司潍坊市寒亭区供电公司 Cable clamp for cable installation
CN116526391A (en) * 2023-07-04 2023-08-01 冠诚建设工程有限公司 Cable installation equipment for medical factory building construction
CN116526391B (en) * 2023-07-04 2023-09-08 冠诚建设工程有限公司 Cable installation equipment for medical factory building construction

Similar Documents

Publication Publication Date Title
CN218415578U (en) High-rise building cable laying device
CN113812051A (en) Fixing frame for mounting line pipe of Internet of things weak current engineering and using method of fixing frame
CN212626942U (en) Electric power construction cable fixer with locking structure
CN112383010B (en) Electric power wire fixing device
CN210240363U (en) Twisting cage brake device of cabling machine
CN216918297U (en) Prefabricated material hoist device is used in highway construction
CN214114506U (en) Paying-off tackle capable of adapting to paying-off direction for power transmission line construction
CN111030022B (en) Wire stockbridge damper antiskid
CN212210436U (en) Damper for high-voltage overhead line convenient to assemble
CN212276958U (en) Transformer base convenient to install
CN210404561U (en) Tightener for electric power engineering cable installation
CN214429205U (en) Consider 5G basic station and apply hanging and comprehensive energy utilization's electric power tower
CN219154677U (en) Anchor windlass integrated base
CN221353873U (en) Power clamp for suspension tension-resistant power distribution network
CN218449405U (en) Overhead cable spacer convenient to install
CN218216370U (en) Electric power cable pre-tensioning device
CN211228173U (en) Bridge jacking translation is with spacing support frame
CN112193940B (en) Spinning position adjusting device
CN220085734U (en) High-efficient stranding machine
CN217741260U (en) Fastener for tangent tower convenient to dismouting
CN219937818U (en) Cable hoop device
CN213622991U (en) Special lifting device of tunnel construction landing stage
CN218880182U (en) Combined middle wallboard suitable for suspended spindle type yarn machine
CN219018403U (en) Power line cable support frame
CN221008665U (en) Wire separating device for cable stranding machine

Legal Events

Date Code Title Description
GR01 Patent grant