CN218375728U - Construction safety management fence for building engineering - Google Patents

Construction safety management fence for building engineering Download PDF

Info

Publication number
CN218375728U
CN218375728U CN202222104203.8U CN202222104203U CN218375728U CN 218375728 U CN218375728 U CN 218375728U CN 202222104203 U CN202222104203 U CN 202222104203U CN 218375728 U CN218375728 U CN 218375728U
Authority
CN
China
Prior art keywords
groove
fixedly connected
fence
support column
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222104203.8U
Other languages
Chinese (zh)
Inventor
陈胤同
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202222104203.8U priority Critical patent/CN218375728U/en
Application granted granted Critical
Publication of CN218375728U publication Critical patent/CN218375728U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A20/00Water conservation; Efficient water supply; Efficient water use
    • Y02A20/108Rainwater harvesting

Landscapes

  • Fencing (AREA)

Abstract

The utility model belongs to the technical field of enclose and keep off, concretely relates to building engineering construction safety control rail, which comprises a fence, the water catch bowl has been installed to the below of rail, the inboard of the both ends fixed connection support column one and support column two of water catch bowl, the bottom side of the equal fixed connection rail of one end of support column one and support column two, one side of rail is seted up flutedly, the shower nozzle has been installed to one side in the recess, the other end of support column one is provided with slewing mechanism, the other end of support column two is seted up flutedly and fixed connection connecting plate two, logical groove has been seted up with support column two junctions to connecting plate two, one side of the other end fixed connection bracing piece of dead lever, the opposite side fixed connection arc elasticity buckle of rail, it encloses the fender to solve current construction, it is only simple to carry out the check with the dust, so the dust still wafts in the air, still can cause the on-the-spot dust to fly, reduce dustproof effect, and the present topography adjustment angle that encloses the fender can not be along with the construction site, the relatively poor problem of practicality.

Description

Construction safety management fence for building engineering
Technical Field
The utility model belongs to the technical field of enclose the fender, concretely relates to building engineering construction safety control rail.
Background
The building construction refers to production activities in the construction implementation stage of engineering construction, is the construction process of various buildings, and also can be a process of changing various lines on a design drawing into a real object at a specified place, and comprises foundation engineering construction, main structure construction, roofing engineering construction decoration engineering construction and the like, and the place of construction operation is called a building construction site or a construction site, and is also called a construction site.
Generally speaking, can produce a large amount of dusts when construction, common way is that keep apart dust and external world at the other baffle of setting up of job site, prevents that the dust of job site from wafting to the external world, however, the fender is enclosed in current construction, just simply carries out the check with the dust and keeps off, so the dust still wafts aloft, still can cause the dust on-spot to fly upward, reduces dustproof effect, and the fender can not be along with the topography angle of adjustment of job site now to enclose, and the practicality is relatively poor.
SUMMERY OF THE UTILITY MODEL
To above problem, the utility model aims to: the utility model provides a building engineering construction safety control rail, it encloses the fender to solve current building construction, and the simple fence that carries out with the dust keeps off, so the dust still wafts aloft, still can cause on-the-spot dust to fly upward, reduces dustproof effect, and the current fender that encloses can not be along with the topography angle of adjustment of job site, the relatively poor problem of practicality.
For the purpose of realizing above, the utility model discloses a technical scheme: building engineering construction safety control rail, including the rail, the water catch bowl has been installed to the below of rail, the inboard of both ends fixed connection support column one and support column two of water catch bowl, the bottom side of the equal fixed connection rail of one end of support column one and support column two, one side of rail is seted up flutedly, the shower nozzle has been installed to one side in the recess, the other end of support column one is provided with slewing mechanism, the other end of support column two is seted up flutedly and fixed connection connecting plate two, connecting plate two has seted up logical groove with support column two junction, the one end of the inside fixed connection electric telescopic handle two of recess, the other end fixed connection universal wheel of electric telescopic handle two, one side fixed connection dead lever's of rail one end, one side of the other end fixed connection bracing piece of dead lever, the one end of bracing piece is seted up flutedly, and the one end of the fixed connection electric telescopic handle one in the recess, the other end fixed connection universal wheel of electric telescopic handle one, the opposite side fixed connection arc elasticity buckle of rail.
The utility model has the advantages that:
dust can appear in the job site when the construction, fill up water in with the water catch bowl through the water filling port, restart the water pump makes the water in the water catch bowl advance in distributive pipe one from the inslot, carry to distributive pipe two in from distributive pipe one, and one side fixed connection shower nozzle of distributive pipe two, water is from the shower nozzle blowout, and spun water is the cascade form, the dust that carries in the air can adsorb on water promptly, along with rivers drop to the water catch bowl in, can effectively improve dustproof effect, after shower nozzle blowout rivers, rivers can directly spout on the water catch bowl, filter the water source of subsidiary dust through the filter layer, make rivers to the water catch bowl after filtering the completion in, recycle, reduce the waste of water resource.
Through the universal ball that drags messenger support column below fixed connection to support column two at fixed rotary tank internal rotation, and the spin is at spacing rotary tank two, the first internal rotation of spacing rotary tank that the rotor plate opposite side was seted up to can carry out 360 degrees adjustments to this device according to the topography to the job site of required management.
In order to allow cushioning when the fence is struck:
as a further improvement of the above technical solution: a baffle is arranged on one side of the fence, one end of a spring is fixedly connected with four corners of the inner side of the baffle, and the other end of the spring is fixedly connected with one side of the fence.
The beneficial effect of this improvement does: the springs mounted inside the baffles can cushion when the fence is impacted.
In order to effectively improve dustproof effect:
as a further improvement of the technical scheme: the utility model discloses a fence, including rail, guide plate, water sump, water inlet, delivery port, one end of below fixed connection guide plate of rail, and one side of the other end fixed connection water sump of guide plate, and one side of water sump has installed the water filling port, the delivery port has been seted up to the one end of water sump, the one end fixed connection water pump of water sump, the one end of one side fixed connection distributive pipe of water pump, the other end fixed connection distributive pipe two of distributive pipe one, and distributive pipe two installs the inside at the rail, the one end of one side fixed connection shower nozzle of distributive pipe two.
The beneficial effect of this improvement does: dust can appear in the job site when the construction, fill up water in with the water catch bowl through the water filling port, restart water pump make the water in the water catch bowl from the inslot flow in distributive pipe one, carry to distributive pipe two in from distributive pipe one, and one side fixed connection shower nozzle of distributive pipe two, water is followed the shower nozzle blowout, and spun water is the cascade form, and the dust that carries in the air can adsorb on water promptly, along with rivers drop to the water catch bowl in, can effectively improve dustproof effect.
In order to recycle, reduce the waste of water resource:
as a further improvement of the technical scheme: a filtering layer is arranged on one side, close to the lower side of the fence, of the water collecting tank, and the filtering layer is composed of a garbage filtering layer, a fine sand filtering layer and an activated carbon filtering layer.
The beneficial effect of this improvement does: after the shower nozzle blowout rivers, rivers can directly spout on the water catch bowl, filters the water source that has attached the dust through the filter layer, makes the rivers that filter after accomplishing to the water catch bowl in, recycles, reduces the waste of water resource.
In order to fix the device and adjust the device by 360 degrees:
as a further improvement of the above technical solution: the rotating mechanism is composed of a rotating plate, a second fixing rod, a universal ball, a rotating base, a first fixing rotary groove, a first limiting rotary groove, a second limiting rotary groove and a first connecting plate rolling ball, one end of the first supporting rod is fixedly connected with the second fixing rod, the universal ball is fixedly connected with the other end of the second fixing rod, a through groove is formed in one side of the rotating plate, the second fixing rod penetrates through the second fixing rod in the through groove, the second limiting rotary groove is formed in the other side of the rotating plate, a plurality of rolling balls are embedded in the second limiting rotary groove, the rolling balls are embedded into the second limiting rotary groove and the first limiting rotary groove, the diameter of each rolling ball is smaller than that of the first limiting rotary groove and that of the second limiting rotary groove, the first limiting rotary groove is formed in one side of the rotating base, the fixed rotary groove is formed in one side of the rotating base, the universal ball is placed in the first fixing rotary groove, the diameter of the universal ball is smaller than that of the fixed rotary groove, the first connecting plate is fixedly connected with the first connecting plate, threaded holes are formed in the first connecting plate, and the threaded holes are connected with ground cones.
The beneficial effect of this improvement does: when using, earlier remove this device to the assigned position, prick ground awl with the screw hole threaded connection that connecting plate one was seted up again, make and prick ground awl rotate and insert to the underground, make the rotating base with a connecting plate fixed connection fix, make support column below fixed connection's universal ball at fixed rotary trough internal rotation through dragging to support column two, and the spacing rotary trough two that the spin board opposite side was seted up, spacing rotary trough internal rotation, thereby can be according to the topography to the job site of required management, 360 degrees adjustments are carried out to this device.
In order to perform unified control on the device:
as a further improvement of the above technical solution: the control mechanism is arranged on the water collecting tank, a battery and a control chip are arranged in the control mechanism, and the control mechanism is electrically connected with the first electric telescopic rod, the second electric telescopic rod and the water pump.
The beneficial effect of this improvement does: the control mechanism is electrically connected with the electric telescopic rod I, the electric telescopic rod II and the water pump, and the device can be conveniently and uniformly controlled by installing the control mechanism.
The parts of the device not involved are the same as or can be implemented using prior art.
Drawings
Fig. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic structural view of the present invention;
fig. 3 is a schematic front view of the cross-sectional structure of the present invention;
FIG. 4 is a schematic view of the cross-sectional structure of the water collecting trough of the present invention;
FIG. 5 is a schematic view of the structure of the sprinkler head of the present invention;
fig. 6 is a schematic view of the elastic buckle structure of the present invention;
fig. 7 is a schematic view of the structure of the joint between the middle baffle and the fence;
fig. 8 is a schematic structural view of the rotating mechanism of the present invention;
fig. 9 is a schematic view of the structure of the middle rotating plate of the present invention;
in the figure: 1. a fence; 2. fixing the rod; 3. a support bar; 4. a first electric telescopic rod; 5. elastic buckle; 6. a first supporting column; 7. a rotating mechanism; 8. a second supporting column; 9. a second electric telescopic rod; 10. a second connecting plate; 11. a water collection tank; 12. a groove; 13. a baffle plate; 14. a spring; 15. a filter layer; 16. a water pump; 17. a water outlet; 18. a water injection port; 19. a first water distribution pipe; 20. a second water distribution pipe; 21. a water pipe; 22. a spray head; 23. a rotating plate; 24. a second fixing rod; 25. a universal ball; 26. rotating the base; 27. fixing the rotary groove; 28. a first limiting rotary groove; 29. a second limiting rotary groove; 30. a first connecting plate; 31. rolling a ball; 32. pricking a ground cone; 33. a control mechanism; 34. a baffle.
Detailed Description
The present invention will be described in detail below with reference to the accompanying drawings in order to make those skilled in the art better understand the technical solution of the present invention, and the description in this section is only exemplary and illustrative, and should not be construed as limiting the scope of the present invention in any way.
Example 1:
as shown in fig. 1-2, as a further optimization of the above embodiment, the construction safety management fence for building engineering includes a fence 1, a water collection tank 11 is installed below the fence 1, two ends of the water collection tank 11 are fixedly connected to inner sides of a first support column 6 and a second support column 8, one ends of the first support column 6 and the second support column 8 are fixedly connected to a bottom side of the fence 1, a groove 12 is formed in one side of the fence 1, a nozzle 22 is installed in the groove 12, the other end of the first support column 6 is provided with a rotating mechanism 7, the other end of the second support column 8 is provided with a groove and is fixedly connected to a second connecting plate 10, a through groove is formed at a joint of the second connecting plate 10 and the second support column 8, one end of a second electric telescopic rod 9 is fixedly connected to the inside of the groove, the other end of the second electric telescopic rod 9 is fixedly connected to a universal wheel, one side of the fence 1 is fixedly connected to one end of a fixing rod 2, the other end of the fixing rod 2 is fixedly connected to one side of a support rod 3, one end of the support rod 3 is provided with a groove, one end of the first electric telescopic rod 4 is fixedly connected to the other end of the groove, and the fixing clamp buckle is elastically connected to the other end of the arc-shaped fixing rod 1.
Example 2:
as shown in fig. 7, as a further optimization of the above embodiment, the construction safety management fence for building engineering includes a fence 1, a water collection tank 11 is installed below the fence 1, two ends of the water collection tank 11 are fixedly connected with inner sides of a first support column 6 and a second support column 8, one ends of the first support column 6 and the second support column 8 are fixedly connected with a bottom side of the fence 1, a groove 12 is formed in one side of the fence 1, a nozzle 22 is installed in the groove 12, the other end of the first support column 6 is provided with a rotating mechanism 7, the other end of the second support column 8 is provided with a groove and a second fixedly connected connecting plate 10, a through groove is formed at a joint of the second connecting plate 10 and the second support column 8, one end of a second electric telescopic rod 9 is fixedly connected inside the groove, the other end of the second electric telescopic rod 9 is fixedly connected with a universal wheel, one end of a fixing rod 2 is fixedly connected to one side of the fence 1, the other end of the fixing rod 2 is fixedly connected with one side of a support rod 3, one end of the support rod 3 is provided with a groove, one end of the first electric telescopic rod 4 is fixedly connected with an arc-shaped universal wheel, and the other end of the universal wheel is fixedly connected with a clamp buckle 5. A baffle 13 is arranged on one side of the fence 1, one end of a spring 14 is fixedly connected at four corners of the inner side of the baffle 13, and the other end of the spring 14 is fixedly connected with one side of the fence 1.
Example 3:
as shown in fig. 3-5, as a further optimization of the above embodiment, the construction safety management fence for building engineering includes a fence 1, a water collection tank 11 is installed below the fence 1, two ends of the water collection tank 11 are fixedly connected to inner sides of a first support column 6 and a second support column 8, one ends of the first support column 6 and the second support column 8 are fixedly connected to a bottom side of the fence 1, a groove 12 is formed in one side of the fence 1, a nozzle 22 is installed in the groove 12, the other end of the first support column 6 is provided with a rotating mechanism 7, the other end of the second support column 8 is provided with a groove and is fixedly connected to a second connecting plate 10, a through groove is formed at a joint of the second connecting plate 10 and the second support column 8, one end of a second electric telescopic rod 9 is fixedly connected to the inside of the groove, the other end of the second electric telescopic rod 9 is fixedly connected to a universal wheel, one side of the fence 1 is fixedly connected to one end of a fixing rod 2, the other end of the fixing rod 2 is fixedly connected to one side of a support rod 3, one end of the support rod 3 is provided with a groove, one end of the first electric telescopic rod 4 is fixedly connected to the other end of the groove, and the electric telescopic rod 1 is fixedly connected to the other end of the arc-shaped buckle. The lower part of rail 1 fixed connection guide plate 34's one end, and guide plate 34's other end fixed connection water catch bowl 11 one side, and water filling port 18 has been installed to one side of water catch bowl 11, delivery port 17 has been seted up to the one end of water catch bowl 11, the one end fixed connection water pump 16 of water catch bowl 11, the one end of one side fixed connection distributive pipe 19 of water pump 16, the other end fixed connection distributive pipe two 20 of distributive pipe one 19, and distributive pipe two 20 installs in the inside of rail 1, one side fixed connection shower nozzle 22's one end of distributive pipe two 20.
Example 4:
as shown in fig. 4, as a further optimization of the above embodiment, the construction safety management fence for building engineering includes a fence 1, a water collecting tank 11 is installed below the fence 1, two ends of the water collecting tank 11 are fixedly connected with inner sides of a first supporting column 6 and a second supporting column 8, one ends of the first supporting column 6 and the second supporting column 8 are fixedly connected with a bottom side of the fence 1, a groove 12 is formed in one side of the fence 1, a spray head 22 is installed in the groove 12, the other end of the first supporting column 6 is provided with a rotating mechanism 7, the other end of the second supporting column 8 is provided with a groove and a second fixedly connected connecting plate 10, a through groove is formed at a joint of the second connecting plate 10 and the second supporting column 8, one end of a second electric telescopic rod 9 is fixedly connected inside the groove, the other end of the second electric telescopic rod 9 is fixedly connected with a universal wheel, one end of a fixing rod 2 is fixedly connected to one side of the fence 1, the other end of the fixing rod 2 is fixedly connected to one side of a supporting rod 3, one end of the supporting rod 3 is provided with the groove, one end of the electric telescopic rod 4 is fixedly connected with one end of the groove, the first electric telescopic rod 4 is fixedly connected with the other end of the universal wheel, and the other end of the fence 1 is connected with an arc-shaped elastic buckle 5. A filtering layer 15 is arranged on one side, close to the lower side of the fence 1, of the water collecting tank 11, and the filtering layer 15 is composed of a garbage filtering layer, a fine sand filtering layer and an activated carbon filtering layer.
Example 5:
as shown in fig. 8-9, as a further optimization of the above embodiment, the construction safety management fence for building engineering includes a fence 1, a water collection tank 11 is installed below the fence 1, two ends of the water collection tank 11 are fixedly connected to inner sides of a first support column 6 and a second support column 8, one ends of the first support column 6 and the second support column 8 are fixedly connected to a bottom side of the fence 1, a groove 12 is formed in one side of the fence 1, a nozzle 22 is installed in the groove 12, the other end of the first support column 6 is provided with a rotating mechanism 7, the other end of the second support column 8 is provided with a groove and is fixedly connected to a second connecting plate 10, a through groove is formed at a joint of the second connecting plate 10 and the second support column 8, one end of a second electric telescopic rod 9 is fixedly connected to the inside of the groove, the other end of the second electric telescopic rod 9 is fixedly connected to a universal wheel, one side of the fence 1 is fixedly connected to one end of a fixing rod 2, the other end of the fixing rod 2 is fixedly connected to one side of a support rod 3, one end of the support rod 3 is provided with a groove, one end of the first electric telescopic rod 4 is fixedly connected to the other end of the groove, and the electric telescopic rod 1 is fixedly connected to the other end of the arc-shaped buckle. The rotating mechanism 7 comprises a rotating plate 23, a second fixing rod 24, a universal ball 25, a rotating base 26, a first fixing rotating groove 27, a first limiting rotating groove 28, a second limiting rotating groove 29 and a first connecting plate 30 rolling ball 31, the other end of the first supporting column 6 is fixedly connected with one end of the second fixing rod 24, the other end of the second fixing rod 24 is fixedly connected with the universal ball 25, one side of the rotating plate 23 is provided with a through groove, the second fixing rod 24 penetrates through the through groove, the other side of the rotating plate 23 is provided with the second limiting rotating groove 29, a plurality of rolling balls 31 are embedded in the second limiting rotating groove 29 and the first limiting rotating groove 28, the diameter of each rolling ball 31 is smaller than the width of the first limiting rotating groove 28 and the width of the second limiting rotating groove 29, the first limiting rotating groove 28 is arranged on one side of the rotating base 26, the fixed rotating groove 27 is arranged on one side of the rotating base 26, the universal ball 25 is arranged in the fixed rotating groove 27, the diameter of the universal ball 25 is smaller than the diameter of the fixed rotating groove 27, the connecting plate 26 is fixedly connected with the first connecting plate 30, and a threaded hole 32 is arranged on the connecting plate 30 and is connected with a threaded hole 32.
Example 6:
as shown in fig. 1-2, as a further optimization of the above embodiment, the construction safety management fence for building engineering includes a fence 1, a water collection tank 11 is installed below the fence 1, two ends of the water collection tank 11 are fixedly connected to inner sides of a first support column 6 and a second support column 8, one ends of the first support column 6 and the second support column 8 are fixedly connected to a bottom side of the fence 1, a groove 12 is formed in one side of the fence 1, a nozzle 22 is installed in the groove 12, the other end of the first support column 6 is provided with a rotating mechanism 7, the other end of the second support column 8 is provided with a groove and is fixedly connected to a second connecting plate 10, a through groove is formed at a joint of the second connecting plate 10 and the second support column 8, one end of a second electric telescopic rod 9 is fixedly connected to the inside of the groove, the other end of the second electric telescopic rod 9 is fixedly connected to a universal wheel, one side of the fence 1 is fixedly connected to one end of a fixing rod 2, the other end of the fixing rod 2 is fixedly connected to one side of a support rod 3, one end of the support rod 3 is provided with a groove, one end of the first electric telescopic rod 4 is fixedly connected to the other end of the groove, and the fixing clamp buckle is elastically connected to the other end of the arc-shaped fixing rod 1. A control mechanism 33 is arranged on the water collecting tank 11, a battery and a control chip are arranged in the control mechanism 33, and the control mechanism 33 is electrically connected with the first electric telescopic rod 4, the second electric telescopic rod 9 and the water pump 16.
The utility model discloses a theory of operation and use flow: when the device is used, the first electric telescopic rod 4 and the second electric telescopic rod 9 are started through the control mechanism 33, the first electric telescopic rod 4 and the second electric telescopic rod 9 are enabled to jack up the device downwards, universal wheels are arranged at the bottom ends of the first electric telescopic rod 4 and the second electric telescopic rod 9, the device can be moved to a specified position through the universal wheels, after the device reaches the specified position, the first electric telescopic rod 4 and the second electric telescopic rod 9 are retracted through the control mechanism 33, the first connecting plate 30 and the second connecting plate 10 are attached to the ground, threaded holes formed in the first connecting plate 30 and the second connecting plate 10 are in threaded connection with the ground binding cone 32, the ground binding cone 32 is enabled to be rotatably inserted into the ground, the rotating base 26 fixedly connected with the first connecting plate 30 is fixed, the universal ball 25 fixedly connected below the first supporting column 6 rotates in the fixed rotating groove 27 through dragging of the second supporting column 8, the rolling ball 31 rotates in a limiting rotary groove II 29 and a limiting rotary groove I28 which are arranged on the other side of the rotating plate 23, so that the device can be adjusted by 360 degrees according to the terrain of a construction site to be managed, the device can be embedded into another device supporting rod 3 through an arc-shaped elastic buckle 5 fixedly connected with the other side of the fence 1, dust is inevitably generated on the construction site during construction, the water is filled in the water collecting groove 11 through the water filling port 18, the water pump 16 is started to enable the water in the water collecting groove 11 to flow into the water distribution pipe I19 from the groove and to be conveyed into the water distribution pipe II 20 from the water distribution pipe I19, the spray head 22 is fixedly connected with one side of the water distribution pipe II 20, the water is sprayed out from the spray head 22, the sprayed water is in a water curtain shape, the dust carried in the air can be adsorbed on the water, the dust-proof effect can be effectively improved along with the falling of the water flow into the water collecting groove 11, and after the spray head 22 sprays the water flow, the water flow directly sprays out on the water collecting groove 11, the water source with dust attached is filtered by the filter layer 15, the filtered water flows into the water collecting tank 11 and is recycled, the waste of water resources is reduced, and the spring 14 arranged on the inner side of the baffle 13 can buffer when the fence 1 is impacted.

Claims (6)

1. Building engineering construction safety control rail, its characterized in that: comprises a fence (1), a water collecting tank (11) is arranged below the fence (1), two ends of the water collecting tank (11) are fixedly connected with the inner sides of the first supporting column (6) and the second supporting column (8), one end of each of the first support column (6) and the second support column (8) is fixedly connected with the bottom side of the rail (1), one side of the fence (1) is provided with a groove (12), one side in the groove (12) is provided with a spray head (22), the other end of the first supporting column (6) is provided with a rotating mechanism (7), the other end of the second supporting column (8) is provided with a groove and is fixedly connected with a second connecting plate (10), a through groove is arranged at the joint of the second connecting plate (10) and the second support column (8), one end of an electric telescopic rod II (9) is fixedly connected inside the groove, the other end of the electric telescopic rod II (9) is fixedly connected with a universal wheel, one side of the fence (1) is fixedly connected with one end of a fixed rod (2), the other end of the fixed rod (2) is fixedly connected with one side of the supporting rod (3), one end of the supporting rod (3) is provided with a groove, one end of an electric telescopic rod I (4) is fixedly connected in the groove, the other end of the electric telescopic rod I (4) is fixedly connected with a universal wheel, the other side of the fence (1) is fixedly connected with an arc-shaped elastic buckle (5).
2. The construction safety management fence of claim 1, wherein: a baffle (13) is arranged on one side of the fence (1), one end of a spring (14) is fixedly connected at the four corners of the inner side of the baffle (13), and the other end of the spring (14) is fixedly connected with one side of the fence (1).
3. The construction safety management fence of claim 1, wherein: the one end of below fixed connection guide plate (34) of rail (1), and one side of the other end fixed connection water catch bowl (11) of guide plate (34), and water filling port (18) have been installed to one side of water catch bowl (11), delivery port (17) have been seted up to the one end of water catch bowl (11), the one end fixed connection water pump (16) of water catch bowl (11), the one end of one side fixed connection distributive pipe (19) of water pump (16), the other end fixed connection distributive pipe two (20) of distributive pipe (19), and distributive pipe two (20) install the inside at rail (1), the one end of one side fixed connection shower nozzle (22) of distributive pipe two (20).
4. The construction safety management fence of claim 1, wherein: a filtering layer (15) is arranged on one side, close to the lower side of the fence (1), of the water collecting tank (11), and the filtering layer (15) is composed of a garbage filtering layer, a fine sand filtering layer and an activated carbon filtering layer.
5. The construction safety management fence of claim 1, wherein: the rotating mechanism (7) consists of a rotating plate (23), a second fixed rod (24), a universal ball (25), a rotating base (26), a fixed rotating groove (27), a first limiting rotating groove (28), a second limiting rotating groove (29) and a first connecting plate (30) rolling ball (31), the other end of the first supporting column (6) is fixedly connected with one end of the second fixed rod (24), the other end of the second fixed rod (24) is fixedly connected with the universal ball (25), a through groove is formed in one side of the rotating plate (23), the second fixed rod (24) penetrates through the through groove, the second limiting rotating groove (29) is formed in the other side of the rotating plate (23), a plurality of rolling balls (31) are embedded in the second limiting rotating groove (29), the rolling balls (31) are embedded into the second limiting rotating groove (29) and the first limiting rotating groove (28), the diameter of the rolling balls (31) is smaller than the width of the first limiting rotating groove (28) and the width of the second limiting rotating groove (29), the first limiting rotating groove (28) is formed in one side of the rotating base (26), the fixed rotating base (26) is provided with the diameter of the first rotating ball (27), the universal ball (25), the fixed rotating base (30) and the connecting plate (25) is connected with the universal ball (25), a threaded hole is formed in the first connecting plate (30), and the threaded hole is in threaded connection with a ground prick cone (32).
6. The construction safety management fence of claim 1, wherein: a control mechanism (33) is arranged on the water collecting tank (11), a battery and a control chip are arranged in the control mechanism (33), and the control mechanism (33) is electrically connected with the first electric telescopic rod (4), the second electric telescopic rod (9) and the water pump (16).
CN202222104203.8U 2022-08-11 2022-08-11 Construction safety management fence for building engineering Active CN218375728U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222104203.8U CN218375728U (en) 2022-08-11 2022-08-11 Construction safety management fence for building engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222104203.8U CN218375728U (en) 2022-08-11 2022-08-11 Construction safety management fence for building engineering

Publications (1)

Publication Number Publication Date
CN218375728U true CN218375728U (en) 2023-01-24

Family

ID=84964766

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222104203.8U Active CN218375728U (en) 2022-08-11 2022-08-11 Construction safety management fence for building engineering

Country Status (1)

Country Link
CN (1) CN218375728U (en)

Similar Documents

Publication Publication Date Title
CN218375728U (en) Construction safety management fence for building engineering
CN214130853U (en) Dust keeper is used in municipal works construction
CN112588047A (en) Multifunctional dust removal device and dust removal method thereof
CN207505653U (en) A kind of irrigation rig for roof greening
CN214440337U (en) Adjustable dust removal spray head assembly
CN213159965U (en) On-spot dust collector for construction
CN108905455A (en) A kind of rotatable depositing dust flusher of construction site
CN208320293U (en) The boring atomizing dust removing device of core drill
CN220571232U (en) Afforestation street tree maintenance device
CN113430976A (en) Leveling device for repairing roads and facilitating waste cleaning
CN213153308U (en) Agricultural production is with accurate irrigation equipment
CN210645639U (en) Dust collector for construction
CN219077483U (en) Flying construction device for rust removal, oil brushing and maintenance of steel structure
CN214995113U (en) Filling station's awning eaves mouth
CN215744964U (en) Large-scale hydraulic generator top cover belt cleaning device
CN209873678U (en) Watering device for building site
CN220405928U (en) Dust collector for construction waste treatment
CN220736871U (en) Building site dust collector
CN213885467U (en) Automatic watering and dust removing device for building construction
CN221031936U (en) Protection device for construction engineering construction
CN218027086U (en) Concrete maintenance machine for construction
CN211201962U (en) Coal mining machine lifting support
CN219922461U (en) Dust fall device for concrete production
CN212925925U (en) Remove convenient lane flushing machine that washing effect is good
CN220952851U (en) Concrete curing device for bridge construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant