CN218374599U - Concrete heat preservation curtain wall construction - Google Patents

Concrete heat preservation curtain wall construction Download PDF

Info

Publication number
CN218374599U
CN218374599U CN202222679246.9U CN202222679246U CN218374599U CN 218374599 U CN218374599 U CN 218374599U CN 202222679246 U CN202222679246 U CN 202222679246U CN 218374599 U CN218374599 U CN 218374599U
Authority
CN
China
Prior art keywords
concrete
concrete block
curtain wall
spread groove
adjacent
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222679246.9U
Other languages
Chinese (zh)
Inventor
蔡徐波
马聆凯
黄项飞
虞昕鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Fucheng Construction Group Co ltd
Original Assignee
Zhejiang Fucheng Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Fucheng Construction Group Co ltd filed Critical Zhejiang Fucheng Construction Group Co ltd
Priority to CN202222679246.9U priority Critical patent/CN218374599U/en
Application granted granted Critical
Publication of CN218374599U publication Critical patent/CN218374599U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/24Structural elements or technologies for improving thermal insulation
    • Y02A30/244Structural elements or technologies for improving thermal insulation using natural or recycled building materials, e.g. straw, wool, clay or used tires

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Abstract

The utility model relates to a concrete heat preservation curtain wall construction, it includes a plurality of concrete block, and is a plurality of concrete block is crisscross to be built for concrete curtain wall, is provided with a plurality of coupling assembling between two horizontal adjacent concrete block along, and has all seted up the spread groove along the end in opposite directions of two horizontal adjacent concrete block, the spread groove is along vertical extension and for dovetail or tip open-ended dovetail groove, and the spread groove of two adjacent concrete block opposite ends is the opening and sets up in opposite directions, coupling assembling joint in the spread groove of two adjacent concrete block simultaneously, the spread groove still is used for filling cement mortar, is provided with the locking piece that makes both lock mutually along between two vertical adjacent concrete block. This application has when concrete curtain builds, and cement mortar solidification process, improves the connection steadiness between two adjacent concrete block.

Description

Concrete heat preservation curtain wall construction
Technical Field
The application relates to the field of concrete curtain walls, in particular to a concrete heat-preservation curtain wall structure.
Background
Nowadays, partial concrete curtain wall is built by a plurality of concrete block usually and forms, and at this moment, in order to make concrete curtain wall have the thermal insulation performance of preferred, can set up concrete block into including the building block main part of making by the concrete to and be fixed in the heated board of building block main part one side. Under the action of the heat insulation plate, the built concrete curtain wall has better heat insulation performance.
However, in the process of building the concrete curtain wall, two adjacent concrete blocks are usually bonded by smearing cement mortar. Often, cement mortar still needs a period of time when solidifying, so that the connection stability of two adjacent concrete blocks is relatively low in the solidification process of the cement mortar, and the stability of the built concrete curtain wall in the period of time is poor.
SUMMERY OF THE UTILITY MODEL
In order when concrete curtain builds, cement mortar solidification in-process improves the connection steadiness between two adjacent concrete block, this application provides a concrete heat preservation curtain wall construction.
The application provides a concrete heat preservation curtain wall construction adopts following technical scheme:
the utility model provides a concrete heat preservation curtain wall construction, includes a plurality of concrete block, and is a plurality of concrete block is crisscross to be built for concrete curtain wall, is provided with a plurality of coupling assembling between two horizontal adjacent concrete block along, and has all seted up the spread groove along the end in opposite directions of two horizontal adjacent concrete block, the spread groove is along vertical extension and be dovetail or tip open-ended dovetail groove, and two adjacent concrete block spread grooves of end in opposite directions are the opening and set up in opposite directions, coupling assembling joint in the spread groove of two adjacent concrete block simultaneously, the spread groove still is used for filling cement mortar, is provided with the locking piece that makes both locks mutually along vertical adjacent two concrete block between.
Through adopting above-mentioned technical scheme, during the installation, when adopting cement mortar to bond two adjacent concrete blocks, connect the locking piece in two vertical adjacent concrete blocks of edge, with coupling assembling joint in the spread groove along two horizontal adjacent concrete blocks simultaneously, and cement mortar still fills in the spread groove, thereby build the back at concrete curtain, and cement mortar solidification process, adjacent concrete block receives locking piece or coupling assembling's effect, increase the connection steadiness between two adjacent concrete blocks, and then make concrete curtain wall also have the steadiness of preferred in this time quantum.
Optionally, the locking member is provided as a connecting pin, the connecting pin is connected to the concrete block below, and the connecting pin penetrates through the concrete block above.
Through adopting above-mentioned technical scheme, during the installation, when receiving cement mortar bonding along two vertical adjacent concrete block, the connecting pin can also be to following two vertical adjacent concrete block and doing the restriction, and then in cement mortar solidification process, reduces these two concrete block and takes place the possibility that slides each other, and then increases the connection steadiness between these two adjacent concrete block.
Optionally, the top of the concrete block below is provided with a mounting hole for matching with the connecting pin.
Through adopting above-mentioned technical scheme, the connecting pin can be dismantled relative below concrete block to increase the convenience of connecting pin when the installation.
Optionally, the connecting assembly includes two clamping plates and a connecting column connected to the two clamping plates, and the two clamping plates are respectively clamped and slidably connected to connecting grooves of two adjacent concrete blocks.
Through adopting above-mentioned technical scheme, during the installation, two cardboards of same coupling assembling joint respectively in two adjacent concrete block's spread groove, the spliced pole can be done to two cardboards and pull this moment to it is fixed mutually with two adjacent concrete block, thereby at cement mortar solidification's in-process, coupling assembling can increase along the connection steadiness between two horizontal adjacent concrete block.
Optionally, the connecting column includes a connecting pipe and a connecting rod, the connecting rod is inserted into the connecting pipe and is in threaded connection with the connecting pipe, and the connecting rod and the connecting pipe are respectively in one-to-one correspondence fixed connection with the two clamping plates.
Through adopting above-mentioned technical scheme, rotate the total length that the spliced pole can be adjusted to the connecting rod to can adapt to two adjacent concrete block of different clearance sizes and carry out coupling assembling's installation, improve the convenience of coupling assembling installation and concrete curtain construction.
Optionally, the clamping plate is a polygonal plate, and the side edge of the clamping plate can be clamped with two side walls of the connecting groove at the same time.
Through adopting above-mentioned technical scheme, rotate in order to adjust the back to spliced pole length mutually at connecting pipe and connecting rod, wear to locate the spread groove with the cardboard, the cardboard can be simultaneously with both sides joint of spread groove wall this moment, thereby the cardboard is difficult for taking place to rotate when the joint is in the spread groove, thereby cardboard and spliced pole when removing in the spread groove, connecting pipe and the difficult mutual rotation that takes place of connecting rod, thereby guarantee the steadiness of coupling assembling installation.
Optionally, the clamping plate is provided with a plurality of grouting channels, and the grouting channels are arranged on the outer wall of the clamping plate in an opening manner.
Through adopting above-mentioned technical scheme, cement mortar is when filling in the spread groove, and in partial cement mortar can get into the grout passageway on the cardboard, and then after cement mortar solidifies, can increase the snap-in force between cardboard and the cement mortar, increases the wholeness between cardboard and the concrete block simultaneously.
Optionally, the connecting column is connected with a traction strip, and the traction strip is arranged in a gap between two adjacent concrete blocks in the transverse direction in a penetrating manner.
Through adopting above-mentioned technical scheme, when cardboard and spliced pole need slide in the spread groove, the handheld strip that pulls of accessible is controlled to further increase the convenience of coupling assembling installation.
In summary, the present application includes at least one of the following beneficial technical effects:
1. after the concrete curtain wall is built, in the cement mortar solidification process, the adjacent concrete blocks are acted by the locking piece or the connecting assembly, so that the connection stability between the two adjacent concrete blocks is improved, and the concrete curtain wall also has better stability in the time period;
2. the connecting rod can be rotated to adjust the overall length of the connecting column, so that the connecting assembly can be mounted by adapting to two adjacent concrete blocks with different gaps, and the mounting convenience of the connecting assembly and the construction convenience of a concrete curtain wall are improved;
drawings
FIG. 1 is a schematic illustration of a partial explosion structure of an embodiment of the present application;
FIG. 2 is an enlarged schematic view of portion A of FIG. 1;
fig. 3 is an exploded view of a connector assembly according to an embodiment of the present application.
Description of reference numerals: 1. concrete building blocks; 11. connecting grooves; 2. a connecting assembly; 21. clamping a plate; 211. grouting a channel; 22. connecting columns; 221. a connecting pipe; 222. a connecting rod; 23. a traction bar; 3. a connecting pin; 31. and (7) installing holes.
Detailed Description
The present application is described in further detail below with reference to figures 1-3.
The embodiment of the application discloses concrete heat preservation curtain wall construction. Referring to fig. 1 and 2, the concrete heat-preservation curtain wall structure comprises a plurality of concrete blocks 1, and the concrete blocks 1 are constructed into the concrete curtain wall in a staggered manner. The spread groove 11 has all been seted up along the end in opposite directions of two horizontal adjacent concrete block 1, and in this embodiment, spread groove 11 is tip open-ended ladder groove and follows vertical extension, and of course, spread groove 11 also can set up to the dovetail. Meanwhile, the connecting grooves 11 at the opposite ends of two adjacent concrete blocks 1 are oppositely arranged in an opening manner. At this moment, be provided with a plurality of coupling assembling 2 along between two horizontal adjacent concrete block 1, coupling assembling 2 joint in the spread groove 11 of two adjacent concrete block 1 opposite ends simultaneously.
And, be provided with the locking piece between two concrete block 1 along vertical adjacent for the wholeness between two concrete block 1 along vertical adjacent can be increased to the locking piece.
During the installation, when adopting cement mortar to bond two adjacent concrete block 1, connect the locking piece in two vertical adjacent concrete block of edge, with coupling assembling 2 joint simultaneously in the spread groove 11 of two horizontal adjacent concrete block 1 of edge to, cement mortar still fills in spread groove 11. Therefore, after the concrete curtain wall is built, in the cement mortar solidification process, the adjacent concrete blocks 1 are acted by the locking piece or the connecting component 2, the connection stability between the two adjacent concrete blocks 1 is improved, and the concrete curtain wall is enabled to have better stability in the time period.
Referring to fig. 1, in the present embodiment, the locking member is provided as a vertically extending connecting pin 3. In two concrete blocks 1 adjacent in the vertical direction, the top of the concrete block 1 below is provided with a mounting hole 31 matched with the connecting pin 3, and the connecting pin 3 also penetrates through the concrete block 1 above.
Therefore, when the two vertically adjacent concrete blocks 1 are bonded by cement mortar, the connecting pin 3 can limit the two vertically adjacent concrete blocks 1. And then in cement mortar solidification process, reduce the possibility that these two concrete block 1 take place mutual slippage, and then increase the connection steadiness between these two adjacent concrete block 1.
And, the connecting pin 3 can also be detachable relative to the lower concrete block 1, thereby increasing the convenience of the connecting pin 3 in installation. So that the connecting pin 3 can be disassembled when the concrete building block 1 positioned at the top of the concrete curtain wall is not required to be provided with the connecting pin 3.
In other embodiments, the connecting pin 3 may also be configured as a clamping strip, the clamping strip is fixed to the concrete block 1 above, and the concrete block 1 below is provided with a clamping groove which extends horizontally and is used for clamping with the clamping strip.
Referring to fig. 2 and 3, the connecting assembly 2 includes two clamping plates 21 and a connecting column 22, wherein the two clamping plates 21 are respectively clamped and slidably connected to the connecting grooves 11 at the opposite ends of the two adjacent concrete blocks 1. The connecting column 22 is fixedly connected to the two clamping plates 21. Make cardboard 21 in the joint in spread groove 11, spliced pole 22 can do the traction to two cardboard 21 to fix two adjacent concrete block 1 mutually, thereby at the in-process that cement mortar solidifies, coupling assembling 2 can increase along the connection steadiness between two horizontal adjacent concrete block 1.
And, during the installation, cement mortar still fills in spread groove 11 for cement mortar can increase the steadiness that cardboard 21 is located spread groove 11, increases the steadiness of cardboard 21 and the 1 looks joint of concrete block in place, increases the wholeness.
Referring to fig. 2 and 3, the connection column 22 includes a connection pipe 221 and a connection rod 222, the connection rod 222 is inserted through and screwed into the connection pipe 221, and the connection rod 222 and the connection pipe 221 are respectively and fixedly connected to the two clamping plates 21 in a one-to-one correspondence manner. Make the total length that the connecting rod 222 can adjust the spliced pole 22 rotate to two adjacent concrete block 1 that adapt to different clearance sizes carry out coupling assembling 2's installation, improve the convenience of coupling assembling 2 installation and concrete curtain construction.
At this moment, set up cardboard 21 into polygonal plate, and make cardboard 21 when wearing to locate connecting groove 11, cardboard 21 can be simultaneously with connecting groove 11 both sides looks joint to cardboard 21 is difficult for taking place to rotate when the joint is in connecting groove 11, thereby cardboard 21 and spliced pole 22 when removing in connecting groove 11, connecting pipe 221 and connecting rod 222 are difficult for taking place the rotation each other, thereby guarantee the steadiness of coupling assembling 2 installation.
Referring to fig. 2 and 3, simultaneously, spliced pole 22 is connected with pulls strip 23, and in this embodiment, pull strip 23 fixed connection in connecting pipe 221, and pull strip 23 and extend towards the face of concrete block 1 for when cardboard 21 and spliced pole 22 need slide in connecting groove 11, the accessible is handheld pulls strip 23 and is controlled, thereby further increases the convenience of coupling assembling 2 installation.
Referring to fig. 2 and 3, the clamping plate 21 is provided with a plurality of grouting channels 211, the grouting channels 211 are opened on the outer wall of the clamping plate 21, and the grouting channels 211 are communicated with the connecting grooves 11. Thereby cement mortar is when filling in connecting groove 11, and in partly cement mortar can get into grout passageway 211 on the cardboard 21, and then after cement mortar solidifies, can increase the interlock between cardboard 21 and the cement mortar, increases the wholeness between cardboard 21 and the concrete block 1 simultaneously.
In other embodiments, in the connection column 22, the connection rod 222 can be further inserted into the connection pipe 221 and slidably connected to the connection rod 22, at this time, the connection column 22 further includes an adjustment pin inserted into the connection rod 222 and the connection pipe 221, and the connection rod 222 or the connection pipe 221 is provided with a plurality of adjustment holes for inserting the adjustment pin.
The implementation principle of the concrete heat preservation curtain wall structure of the embodiment of the application is as follows: during the installation, when adopting cement mortar to bond two adjacent concrete block 1, connect the locking piece in two vertical adjacent concrete block of edge, with two cardboard 21 in coupling assembling 2 joint respectively in the spread groove along two horizontal adjacent concrete block 1 to, cement mortar still fills in spread groove 11. Thereby build the back at concrete curtain, and cement mortar solidification in-process, adjacent concrete block 1 receives locking piece or coupling assembling 2's effect, increases the connection steadiness between two adjacent concrete block 1, and then makes concrete curtain equally have better steadiness in this time quantum.
The above are preferred embodiments of the present application, and the scope of protection of the present application is not limited thereto, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (8)

1. The utility model provides a concrete heat preservation curtain wall construction, includes a plurality of concrete block (1), and is a plurality of concrete block (1) is crisscross to be built into concrete curtain wall, its characterized in that: be provided with a plurality of coupling assembling (2) between two horizontal adjacent concrete block (1) along, and all seted up spread groove (11) along the end in opposite directions of two horizontal adjacent concrete block (1), spread groove (11) are along vertical extension and be dovetail or tip open-ended dovetail groove, and spread groove (11) of two adjacent concrete block (1) end in opposite directions are the opening and set up in opposite directions, coupling assembling (2) joint in spread groove (11) of two adjacent concrete block (1) simultaneously, spread groove (11) still are used for filling cement mortar, are provided with the locking piece that makes both lock mutually along vertical adjacent between two concrete block (1).
2. The concrete heat-insulating curtain wall structure as claimed in claim 1, wherein: the locking piece is set to be a connecting pin (3), the connecting pin (3) is connected to the concrete building block (1) below, and the connecting pin (3) penetrates through the concrete building block (1) above.
3. The concrete heat-insulating curtain wall structure as claimed in claim 2, wherein: the top of the concrete block (1) below is provided with a mounting hole (31) matched with the connecting pin (3).
4. The concrete heat-insulating curtain wall structure as claimed in claim 1, wherein: the connecting component (2) comprises two clamping plates (21) and connecting columns (22) connected to the two clamping plates (21) at the same time, and the two clamping plates (21) are respectively clamped and connected to connecting grooves (11) of two adjacent concrete blocks (1) in a sliding mode.
5. The concrete heat-insulating curtain wall structure as claimed in claim 4, wherein: the connecting column (22) comprises a connecting pipe (221) and a connecting rod (222), the connecting rod (222) penetrates through the connecting pipe (221) and is in threaded connection with the connecting pipe, and the connecting rod (222) and the connecting pipe (221) are respectively and fixedly connected to the two clamping plates (21) in a one-to-one correspondence mode.
6. The concrete heat-insulating curtain wall structure as claimed in claim 5, wherein: the clamping plate (21) is a polygonal plate, and the side edge of the clamping plate (21) can be clamped with two side walls of the connecting groove (11) simultaneously.
7. The concrete heat-insulating curtain wall structure as claimed in claim 4, wherein: the clamping plate (21) is provided with a plurality of grouting channels (211), and the grouting channels (211) are arranged on the outer wall of the clamping plate (21) in an opening mode.
8. The concrete heat-insulating curtain wall structure as claimed in claim 4, wherein: the connecting columns (22) are connected with traction strips (23), and the traction strips (23) penetrate through gaps between two transversely adjacent concrete blocks (1).
CN202222679246.9U 2022-10-08 2022-10-08 Concrete heat preservation curtain wall construction Active CN218374599U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222679246.9U CN218374599U (en) 2022-10-08 2022-10-08 Concrete heat preservation curtain wall construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222679246.9U CN218374599U (en) 2022-10-08 2022-10-08 Concrete heat preservation curtain wall construction

Publications (1)

Publication Number Publication Date
CN218374599U true CN218374599U (en) 2023-01-24

Family

ID=84928518

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222679246.9U Active CN218374599U (en) 2022-10-08 2022-10-08 Concrete heat preservation curtain wall construction

Country Status (1)

Country Link
CN (1) CN218374599U (en)

Similar Documents

Publication Publication Date Title
CN104746828B (en) Dovetail key suspension member and use its decorative panel dry hanging construction technique
US20050108972A1 (en) Interlocking masonry articles and methods thereof
CN111287219B (en) Prefabricated assembled cable working well and construction method thereof
CN111535477A (en) PC (polycarbonate) component for assembly type building and construction method thereof
CN213682674U (en) Indoor assembled sandwich wallboard
CN111851900A (en) Quick locking device is used in assembly building fitment construction
CN218374599U (en) Concrete heat preservation curtain wall construction
CN209243970U (en) Prefabricated components connection structure and Assembled wall panels
CN211200822U (en) Partition plate's installation clamping device
CN213509079U (en) Light gauge steel fire prevention heat preservation partition wall structure
CN109594658A (en) Prefabricated components connection structure, Assembled wall panels and its construction method
CN213682638U (en) Steel construction building assembled light wall body
CN215907107U (en) Wall keel efficient mounting structure for green building decoration construction
CN210343941U (en) Bolt wedge device for horizontal joint connection of concrete wallboard
CN113463630A (en) Be used for harbour channel port inner wall construction anchor equipment
CN204418433U (en) A kind of adjustable masonry filler wall and frame column flexible connecting structure
CN221031446U (en) Building engineering construction template fastener
CN110424621B (en) Combined building block and assembled interlocking masonry structure
CN215717684U (en) Remote transmission line iron tower installation device
CN212200494U (en) Underground continuous wall with supporting structure
CN219993094U (en) Bolt-free building template
CN215406138U (en) Steel structure framework for engineering foundation construction
CN214498030U (en) Assembled floor with connection structure
CN212000960U (en) Corridor wall structure seam seepage drainage device
CN216589469U (en) Expansion chemical anchor bolt for building wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant