CN218371080U - Line frame for electric power construction - Google Patents

Line frame for electric power construction Download PDF

Info

Publication number
CN218371080U
CN218371080U CN202222783678.4U CN202222783678U CN218371080U CN 218371080 U CN218371080 U CN 218371080U CN 202222783678 U CN202222783678 U CN 202222783678U CN 218371080 U CN218371080 U CN 218371080U
Authority
CN
China
Prior art keywords
power construction
line frame
frame
unwrapping wire
arrestment mechanism
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222783678.4U
Other languages
Chinese (zh)
Inventor
董永浩
王顺利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Kunsheng Power Engineering Co ltd
Original Assignee
Shandong Kunsheng Power Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Kunsheng Power Engineering Co ltd filed Critical Shandong Kunsheng Power Engineering Co ltd
Priority to CN202222783678.4U priority Critical patent/CN218371080U/en
Application granted granted Critical
Publication of CN218371080U publication Critical patent/CN218371080U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model belongs to the technical field of the line frame, specifically disclose a line frame for electric power construction, the camera includes a supporting plate, the upper surface of backup pad is provided with the support column, the last fixed surface connection support frame of support column, the both sides of support frame are provided with arrestment mechanism, arrestment mechanism's top sets up line frame mechanism, arrestment mechanism is promptly braked after using line frame mechanism to end. This line frame for electric power construction, after the unwrapping wire, through slider and the guide block among the removal arrestment mechanism, make the unwrapping wire bucket after the unwrapping wire is ended, can emergency braking, the arch that the runner surface set up simultaneously is a plurality of clutch blocks that the annular array arranged, and the surface of slider and guide block is provided with a plurality of resistance strip, the resistance strip is the rubber material, resistance when having increased the braking of line frame, emergency braking that can be better, effectively prevent that the workman from unwrapping wire too much, avoid receiving the line once more, the unwrapping wire time has been practiced thrift, workman work efficiency is improved.

Description

Line frame for electric power construction
Technical Field
The utility model belongs to the technical field of the line frame, a line frame for electric power construction is specifically disclosed.
Background
The cable is one of indispensable building materials in modern city construction nowadays, and in the placing process of cable, often can not leave pay off rack, and the use of pay off rack has brought a lot of facilities for receiving and releasing of cable.
In the power construction, in order to facilitate arrangement, a cable is wound on a coil holder, and then the cable is wound along with pulling and rolling to realize paying off, so that the problem that the cable is too much scattered on the ground to cause winding is solved, convenience is brought to transfer and transportation of the cable on a construction site, however, in the cable paying off process, because the weight of the cable is too heavy, the front paying off is finished, due to inertia factors, a rear coil holder rotates all the time, the front paying off is too much, and finally a worker needs to take back the wire again, so that the paying off efficiency is reduced, and adverse effects are brought to construction.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the defects existing in the prior art and providing a wire frame for power construction.
In order to achieve the purpose, the utility model provides a line frame for electric power construction, the camera includes a supporting plate, the last fixed surface of backup pad is provided with the support column, the last fixed surface joint support frame of support column, the both sides of support frame are provided with arrestment mechanism, arrestment mechanism's top sets up line frame mechanism, arrestment mechanism is using line frame mechanism to finish the back emergency braking.
In the above technical scheme, further, arrestment mechanism includes the lead screw, the side fixed mounting base of support frame, the one end and the base of lead screw rotate to be connected, servo motor's output shaft is connected to the other end of lead screw, servo motor fixed mounting is in one side of support frame, the surface cover of lead screw is equipped with screw-thread fit's slider, one side fixed connection connecting plate of slider, the one end fixed connection guide block of connecting plate, the inside slip cover of guide block is equipped with the guide arm, the both ends fixed connection supporting seat of guide arm.
In the above technical scheme, further, the thread stand mechanism includes a pay-off barrel, the two ends of the pay-off barrel are fixedly connected with the rotating wheels, the inner sides of the rotating wheels are provided with rotating shafts in a penetrating manner, the rotating wheels and the rotating shafts are in running fit through ball bearings, the inner sides of the rotating wheels are fixedly provided with connecting strips, and the two ends of the rotating shafts are in movable fit with the supporting plates.
In the above technical solution, further, the two ends of the rotating shaft are distributed and fixed with lantern rings, and the two lantern rings on each side are movably clamped on the side surface of the fixing plate.
In the above technical solution, further, a plurality of protruding friction blocks arranged in an annular array are arranged on the surface of the rotating wheel, a plurality of resistance strips are fixedly arranged on the surfaces of the sliding block and the guide block, and the resistance strips are made of rubber.
In the above technical scheme, further, the bottom of backup pad is fixed and is provided with the wheel, the wheel sets up to four altogether and distributes in the backup pad and be close to the corner.
Compared with the prior art, the utility model discloses following beneficial effect has: this line frame for electric power construction, after the unwrapping wire, through slider and the guide block among the removal arrestment mechanism, make the unwrapping wire bucket can emergency braking, the arch that the runner surface set up is a plurality of clutch blocks that the annular array was arranged simultaneously, and the surface of slider and guide block is provided with a plurality of resistance strip, the resistance strip is the rubber material, resistance when having increased the braking of line frame, emergency braking that can be better, effectively prevent that the workman from unwrapping wire too much, avoid receiving the line once more, the unwrapping wire time has been practiced thrift, workman work efficiency has been improved.
Drawings
Fig. 1 is a schematic structural view of a wire rack for power construction according to the present invention;
fig. 2 is a schematic structural view of another angle of the wire rack for power construction according to the present invention;
fig. 3 is a schematic structural view of a wire frame mechanism and a brake mechanism of a wire frame for power construction according to the present invention;
in the figure: 1. a support plate; 2. a support pillar; 3. a support frame; 4. a wheel; 5. a screw rod; 6. a base; 7. a servo motor; 8. a slider; 9. a connecting plate; 10. a guide block; 11. a guide bar; 12. a supporting seat; 13. paying off a barrel; 14. a rotating wheel; 15. a connecting strip; 16. a ball bearing; 17. a rotating shaft; 18. a collar; 19. a fixing plate; 20. a friction block; 21. a resistance strip.
Detailed Description
In order to make the aforementioned objects, features and advantages of the present invention more clearly understood, the present invention will be described in further detail with reference to the accompanying drawings and detailed description.
The wire frame for power construction shown in fig. 1-3 comprises a supporting plate 1, a supporting column 2 is fixedly arranged on the upper surface of the supporting plate 1, the supporting frame 3 is fixedly connected to the upper surface of the supporting column 2, braking mechanisms are arranged on two sides of the supporting frame 3, each braking mechanism comprises a lead screw 5, a base 6 is fixedly arranged on one side of the supporting frame 3, one end of each lead screw 5 is rotatably connected with the base 6, the other end of each lead screw 5 is connected with an output shaft of a servo motor 7, the servo motors 7 are fixedly arranged on one side of the supporting frame 3, a sliding block 8 in threaded fit is sleeved on the outer surface of each lead screw 5, a connecting plate 9 is fixedly connected to one side of each sliding block 8, one end of each connecting plate 9 is fixedly connected with a guide block 10, a guide rod 11 is inserted into the guide block 10 in a sliding manner, supporting seats 12 are fixedly connected to two ends of each guide rod 11, each guide block 10 can slide along the surface of each guide rod 11, and the stability of each connecting plate 9 during movement is improved.
The upper side of the brake mechanism is provided with the wire frame mechanism, the wire frame mechanism comprises a wire releasing barrel 13 for storing cables, two ends of the wire releasing barrel 13 are fixedly connected with rotating wheels 14, the inner sides of the rotating wheels 14 are provided with rotating shafts 17 in a penetrating mode, the rotating wheels 14 are in rotating fit with the rotating shafts 17 through ball bearings 16, connecting strips 15 are fixedly arranged on the inner sides of the rotating wheels 14, two ends of the rotating shafts 17 are in movable fit with the supporting plate 1, two lantern rings 18 are fixedly distributed at two ends of the rotating shafts 17 and are movably clamped on the side face of the fixing plate 19, the fixing plate 19 is used for supporting the wire releasing barrel 13 to rotate in work, the brake mechanism emergently brakes after the wire frame mechanism is used, a plurality of protruding friction blocks 20 distributed in an annular array mode are arranged on the surface of the rotating wheels 14, a plurality of resistance strips 21 are fixedly arranged on the surfaces of the sliding blocks 8 and the guide blocks 10, the resistance strips 21 are made of rubber materials, resistance in wire frame braking is increased, emergency braking can be better, workers can effectively prevent the excessive wire releasing, take-up again, pay-off time is saved, and work efficiency of the workers is improved.
The fixed wheel 4 that is provided with in bottom of backup pad 1, wheel 4 set up to four altogether and distribute in backup pad 1 be close to the corner, and wheel 4 surface is provided with anti-skidding line, prevents that wheel 4 from marcing the in-process wheel and skidding.
In operation, rotate unwrapping wire bucket 13 and carry out the unwrapping wire operation, after the unwrapping wire is ended, slider 8 and guide block 10 through removing among the arrestment mechanism, make unwrapping wire bucket 13 can emergency braking, the arch that 14 surfaces of runner set up simultaneously is a plurality of clutch blocks 20 that the annular array was arranged, and the surface of slider 8 and guide block 10 is provided with a plurality of resistance strip 21, resistance strip 21 is the rubber material, resistance when having increased the brake of line frame, emergency braking that can be better, prevent effectively that the workman from unwrapping wire too much, avoid receiving the line once more, the unwrapping wire time has been practiced thrift, workman work efficiency has been improved.
The foregoing shows and describes the basic principles, essential features, and advantages of the invention. It should be understood by those skilled in the art that the present invention is not limited to the above embodiments, and that all the embodiments and descriptions are provided in the present invention, and that various changes and modifications can be made without departing from the spirit and scope of the present invention, and all such changes and modifications fall within the scope of the present invention as claimed. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (6)

1. The utility model provides a line frame for electric power construction, includes backup pad (1), its characterized in that: the upper surface of backup pad (1) is fixed and is provided with support column (2), the last fixed surface of support column (2) connects support frame (3), the both sides of support frame (3) are provided with arrestment mechanism, arrestment mechanism's top sets up line frame mechanism, arrestment mechanism is using emergency braking after line frame mechanism finishes.
2. The wire rack for power construction as claimed in claim 1, wherein the brake mechanism comprises a lead screw (5), a base (6) is fixedly mounted on the side surface of the support frame (3), one end of the lead screw (5) is rotatably connected with the base (6), the other end of the lead screw (5) is connected with an output shaft of a servo motor (7), the servo motor (7) is fixedly mounted on one side of the support frame (3), a sliding block (8) in threaded fit is sleeved on the outer surface of the lead screw (5), one side of the sliding block (8) is fixedly connected with a connecting plate (9), one end of the connecting plate (9) is fixedly connected with a guide block (10), a guide rod (11) is inserted into the guide block (10) in a sliding manner, and two ends of the guide rod (11) are fixedly connected with a support base (12).
3. The wire rack for power construction according to claim 2, wherein: the coil holder mechanism comprises a pay-off barrel (13), two ends of the pay-off barrel (13) are fixedly connected with rotating wheels (14), the inner sides of the rotating wheels (14) are provided with rotating shafts (17) in a penetrating mode, the rotating wheels (14) are in running fit with the rotating shafts (17) through ball bearings (16), connecting strips (15) are fixedly arranged on the inner sides of the rotating wheels (14), and two ends of the rotating shafts (17) are in movable fit with a supporting plate (1).
4. The wire rack for power construction according to claim 3, wherein: lantern rings (18) are fixedly sleeved at the two ends of the rotating shaft (17), and the two lantern rings (18) on each side are movably clamped on the side face of the fixing plate (19).
5. The wire rack for power construction according to claim 3, wherein: the surface of runner (14) is provided with a plurality of bellied friction block (20) that are the annular array and arrange, the fixed surface of slider (8) and guide block (10) is provided with a plurality of resistance strip (21), resistance strip (21) are the rubber material.
6. The wire rack for power construction according to claim 4, wherein: the bottom of backup pad (1) is fixed and is provided with wheel (4), wheel (4) set up to four altogether and distribute in backup pad (1) be close to the corner.
CN202222783678.4U 2022-10-21 2022-10-21 Line frame for electric power construction Active CN218371080U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222783678.4U CN218371080U (en) 2022-10-21 2022-10-21 Line frame for electric power construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222783678.4U CN218371080U (en) 2022-10-21 2022-10-21 Line frame for electric power construction

Publications (1)

Publication Number Publication Date
CN218371080U true CN218371080U (en) 2023-01-24

Family

ID=84932832

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222783678.4U Active CN218371080U (en) 2022-10-21 2022-10-21 Line frame for electric power construction

Country Status (1)

Country Link
CN (1) CN218371080U (en)

Similar Documents

Publication Publication Date Title
CN105600582B (en) Cable pay-off device and use method thereof
CN206108578U (en) Fill automatic winding and unwinding devices of electric pile cable
CN218371080U (en) Line frame for electric power construction
CN214879131U (en) Submerged arc welding wire winding equipment
CN212475582U (en) Wire winding vehicle for electric power engineering
CN112027821A (en) Power transmission line winding and unwinding device for electric power facility
CN206088618U (en) Automatic take -up of charging cable
CN215797554U (en) Cable pay-off for weak current engineering that flexibility is high
CN214690704U (en) Brake disc FNC novel material rack
CN212292381U (en) Pipe laying and paying-off device for hydraulic engineering
CN212450041U (en) Uniform-winding welding wire winding device
CN211480756U (en) Positioning and arranging device for laying power line
CN211619626U (en) Unwrapping wire cable guide pulley device
CN211198230U (en) Cable drum is brake equipment for unwrapping wire
CN211110301U (en) A pay-off for electric power transmission
CN111942953A (en) Winding and arranging auxiliary tool for grounding wire of transformer substation
CN219859955U (en) Wire winding and unwinding equipment
CN219326431U (en) Coiling equipment is used in cable production
CN215213525U (en) Full-hydraulic trackless lining trolley capable of automatically winding wires
CN111891833B (en) Automatic change optical cable hank-forming machine
CN216272360U (en) Galvanized pay-off brake device
CN218619680U (en) Automatic cable take-up and pay-off equipment
CN112746509B (en) Processing technology of steel wire rope of invisible protective net
CN219525933U (en) Automatic take-up and pay-off equipment
CN219371858U (en) Support for electric power construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant