CN218318370U - Steel placing device for building construction - Google Patents

Steel placing device for building construction Download PDF

Info

Publication number
CN218318370U
CN218318370U CN202221385539.XU CN202221385539U CN218318370U CN 218318370 U CN218318370 U CN 218318370U CN 202221385539 U CN202221385539 U CN 202221385539U CN 218318370 U CN218318370 U CN 218318370U
Authority
CN
China
Prior art keywords
steel
putting
steel pipe
groove
winding rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202221385539.XU
Other languages
Chinese (zh)
Inventor
严锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202221385539.XU priority Critical patent/CN218318370U/en
Application granted granted Critical
Publication of CN218318370U publication Critical patent/CN218318370U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The utility model provides a device is put to steel for construction, the affiliated building materials equipment technical field of putting, including putting the board, put the upper surface of board and offer the groove of putting that is used for putting the steel pipe, put the board upper surface symmetry and seted up the mounting groove, and rotate between two corresponding mounting grooves around and install the fender frame that is used for sheltering from the steel pipe, the socket has all been seted up to the surface around the fender frame, it is spacing to control all to peg graft between two sockets and install and be used for restricting the activity of fender frame, the left surface mounting who puts the board has the mount, the winding rod is installed to the mount internal rotation, the front surface of winding rod runs through the front surface of mount, and the front fixed surface of winding rod is connected with the crank, the fixed surface of winding rod is connected with the tarpaulin that is used for sheltering from the steel pipe, the utility model discloses can put the steel pipe through putting the groove on the board to keep off the frame through two and spacing to the steel pipe after putting, can effectively avoid the landing, avoid having the potential safety hazard, strengthen workman's safety guarantee.

Description

Steel placing device for building construction
Technical Field
The utility model belongs to the technical field of the equipment is put to the building materials, concretely relates to device is put to steel for construction.
Background
The building construction refers to production activities in the engineering construction implementation stage, is a construction process of various buildings, and can also be a process of changing various lines on a design drawing into a real object in a specified place.
The construction steel used for construction can be generally classified into steel for steel structures and steel bars for reinforced concrete structures. The steel for steel structure mainly comprises common carbon structural steel and low alloy structural steel. The variety is shaped steel, steel pipe and steel bar. The section steel comprises angle steel, I-shaped steel and channel steel.
During construction, the standby steel pipes are generally stacked into a pyramid shape for placement, and the placed steel is easy to slide off and has potential safety hazards to passers, so that the steel placement device for construction is provided.
SUMMERY OF THE UTILITY MODEL
Generally stacked for the pyramid type is put to reserve building steel among the prior art, has easy landing, has potential safety hazard scheduling problem to the workman of crossing, the utility model provides a device is put to steel for construction can put the steel pipe through putting the groove on the board to keep off through two and put the steel pipe after putting and carry on spacingly, can effectively avoid the steel pipe landing, avoid having potential safety hazard, strengthen workman's safety guarantee. The specific technical scheme is as follows:
a steel placing device for building construction comprises a placing plate, wherein a placing groove for placing a steel pipe is formed in the upper surface of the placing plate, mounting grooves are symmetrically formed in the upper surface of the placing plate, the mounting grooves are located on the outer side of the placing groove, a blocking frame for blocking the steel pipe is rotatably mounted between the two corresponding mounting grooves in the front and back directions, sockets are formed in the front and back surfaces of the blocking frame, and limiting rods for limiting the movement of the blocking frame are inserted between the left and right sockets;
in the technical scheme, a fixing frame is installed on the left surface of the placing plate, a winding rod is rotatably installed in the fixing frame, the front end of the winding rod penetrates through the front surface of the fixing frame, a crank is fixedly connected to the front surface of the winding rod, tarpaulin used for shielding a steel pipe is fixedly connected to the outer surface of the winding rod, a plurality of through holes are formed in the outer surface of the tarpaulin, metal rings are installed in the through holes, a plurality of iron locking rods used for limiting the position of the tarpaulin are installed on the right surface of the placing plate, and the metal rings are sleeved on the outer surfaces of the corresponding iron locking rods;
in the technical scheme, the right surface of the iron locking rod is provided with a groove, two adapter columns are rotatably arranged in the groove, and a stop block used for limiting the metal ring to be separated from the iron locking rod is fixedly arranged between the two adapter columns;
in the technical scheme, the rear surfaces of the stop blocks are embedded with the magnet blocks for limiting the positions of the stop blocks, and the outer surfaces of the magnet blocks are attached to the inner surfaces of the grooves;
in the technical scheme, the lower surface of the placing plate is provided with universal wheels;
in the technical scheme, the front surface of the placing plate is provided with a hanging ring;
among the above-mentioned technical scheme, all install the stiffening rod in keeping off the frame.
The utility model discloses a device is put to steel for construction, compared with the prior art, beneficial effect is:
1. the utility model discloses can put the steel pipe through putting the groove on the board to keep off the frame through two and carry on spacingly to the steel pipe after putting, can effectively avoid the steel pipe landing, avoid having the potential safety hazard, strengthen workman's safety guarantee.
2. The utility model discloses can utilize the tarpaulin to shelter from to the steel pipe after putting, avoid receiving rainwater erosion at rainy day steel pipe and produce the rust to the hand is stained with the rust when avoiding the workman to take, influences the operation mood.
3. The utility model discloses can drive the rolling pole through the cranking bar and rotate and carry out the rolling to the tarpaulin, can be when putting or taking the steel pipe, be convenient for accomodate the tarpaulin.
Drawings
Fig. 1 is a schematic view of the structure of the present invention;
fig. 2 is a schematic diagram of the explosion structure of the present invention;
fig. 3 is a schematic rear view of the present invention;
fig. 4 is a schematic structural view of the iron locking rod of the present invention;
FIG. 5 is an enlarged view of the layout at a in FIG. 2;
fig. 6 is an enlarged view of the layout at b in fig. 2.
In fig. 1-6, wherein: 1-placing plate, 11-placing groove, 12-installing groove, 13-universal wheel, 14-iron locking rod, 141-groove, 142-adapter column, 143-stop block, 144-magnet block, 15-hanging ring, 2-stop frame, 21-socket, 22-limiting rod, 23-reinforcing rod, 3-fixing frame, 31-rolling rod, 311-crank, 32-tarpaulin, 321-through hole and 322-metal ring.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative efforts all belong to the protection scope of the present invention.
Referring to fig. 1-6, the present invention provides a technical solution: a steel placing device for building construction comprises a placing plate 1, wherein a placing groove 11 for placing a steel pipe is formed in the upper surface of the placing plate 1, mounting grooves 12 are symmetrically formed in the upper surface of the placing plate 1, the mounting grooves 12 are positioned on the outer side of the placing groove 11, a blocking frame 2 for blocking the steel pipe is rotatably mounted between two corresponding front mounting grooves 12 and two corresponding rear mounting grooves 12, inserting holes 21 are formed in the front surface and the rear surface of the blocking frame 2, limiting rods 22 for limiting the movement of the blocking frame 2 are inserted between the left inserting hole 21 and the right inserting hole 21, after the steel pipe is placed on the upper surface of the placing plate 1, the two blocking frames 2 are turned inwards to block the placed steel pipe, so that the steel pipe can be prevented from sliding off, the fixing effect of the placed steel pipe is enhanced, and the safety guarantee of workers is enhanced;
specifically, a fixed frame 3 is mounted on the left surface of a placing plate 1, a winding rod 31 is rotatably mounted in the fixed frame 3, the front end of the winding rod 31 penetrates through the front surface of the fixed frame 3, a crank 311 is fixedly connected to the front surface of the winding rod 31, a tarpaulin 32 for shielding a steel pipe is fixedly connected to the outer surface of the winding rod 31, a plurality of through holes 321 are formed in the outer surface of the tarpaulin 32, metal rings 322 are fixedly mounted in the through holes 321, a plurality of iron locking rods 14 for limiting the position of the tarpaulin 32 are welded to the right surface of the placing plate 1, the metal rings 322 are sleeved on the outer surfaces of the corresponding iron locking rods 14, the tarpaulin is mainly used for shielding the placed steel pipe, and the winding rod 31 is used for winding the tarpaulin 32 so as to facilitate the storage of the tarpaulin 32 when the tarpaulin is not used;
specifically, the right surface of the iron locking rod 14 is provided with a groove 141, two adapter columns 142 are rotatably mounted in the groove 141, a stopper 143 for limiting the metal ring 322 to be separated from the iron locking rod 14 is fixedly mounted between the two adapter columns 142, and the stopper 143 is used for stopping the metal ring 322 from being separated from the iron locking rod 14, so that the tarpaulin 32 is prevented from being opened in strong wind weather, and the shielding condition of the steel pipe is guaranteed;
specifically, the magnet blocks 144 for limiting the positions of the stoppers 143 are embedded in the rear surfaces of the stoppers 143, the outer surfaces of the magnet blocks 144 are attached to the inner surfaces of the grooves 141, and the magnet blocks 144 are adsorbed in the grooves 141 of the iron locking rods 14, so that the stoppers 143 are fixed, and the stopper 143 is prevented from rotating randomly to influence the limiting effect of the tarpaulin 32;
specifically, the universal wheels 13 are mounted on the lower surface of the placing plate 1, and the universal wheels 13 are mounted on the lower surface of the placing plate 1, so that the steel pipes can be moved to a use place for taking when being used;
specifically, the hanging ring 15 is welded on the front surface of the placing plate 1, the hanging ring 15 is matched with an external hook for use, and the hanging ring 15 is arranged on the front surface of the placing plate 1, so that the external dragging equipment can be conveniently utilized to pull the utility model to move;
particularly, all install the anchor strut 23 in keeping off frame 2, through installing anchor strut 23 in keeping off frame 2, when putting shorter steel pipe, can utilize anchor strut 23 to shelter from it, avoid its landing to influence workman's safety.
The working principle is as follows: during the use, earlier with two fender frame 2 outside upset, place the steel pipe in putting groove 11 and form and put the basement again, then according to figure 2 show put other steel pipes, put the back and shelter from the steel pipe with two fender frame 2 inside upset, then peg graft gag lever post 22 and fix fender frame 2 between two sockets 21 that correspond, then rotate dog 143, make its top put into in the recess 141, then utilize tarpaulin 32 to shield the steel pipe after will putting, and cup joint becket 322 at the surface of the iron check lock lever 14 that corresponds, it can with becket 322 spacing at the surface of iron check lock lever 14 to rotate dog 143 at last, during the steel pipe is taken, reverse operation can.

Claims (7)

1. The utility model provides a device is put to steel for construction, is including putting board (1), the upper surface of putting board (1) is offered and is used for putting groove (11) of putting of steel pipe, a serial communication port, put board (1) upper surface symmetry and seted up mounting groove (12), mounting groove (12) are located the outside of putting groove (11), and corresponding two around and rotate between mounting groove (12) and install fender frame (2) that are used for sheltering from the steel pipe, socket (21) have all been seted up on the surface around fender frame (2), control two it installs gag lever post (22) that are used for restricting fender frame (2) activity to all peg graft between socket (21).
2. The steel placing device for building construction according to claim 1, wherein a fixing frame (3) is mounted on the left surface of the placing plate (1), a winding rod (31) is rotatably mounted in the fixing frame (3), the front end of the winding rod (31) penetrates through the front surface of the fixing frame (3), a crank (311) is fixedly connected to the front surface of the winding rod (31), a tarpaulin (32) used for shielding a steel pipe is fixedly connected to the outer surface of the winding rod (31), a plurality of through holes (321) are formed in the outer surface of the tarpaulin (32), metal rings (322) are mounted in the through holes (321), a plurality of iron locking rods (14) used for limiting the positions of the tarpaulin (32) are mounted on the right surface of the placing plate (1), and the metal rings (322) are sleeved on the outer surfaces of the corresponding iron locking rods (14).
3. The steel placing device for building construction as claimed in claim 2, wherein a groove (141) is formed in the right surface of the iron locking rod (14), two adapter columns (142) are rotatably mounted in the groove (141), and a stopper (143) for limiting the metal ring (322) to be separated from the iron locking rod (14) is fixedly mounted between the two adapter columns (142).
4. The steel placing device for building construction according to claim 3, wherein a magnet block (144) for limiting the position of the stopper (143) is embedded in each rear surface of the stopper (143), and the outer surface of the magnet block (144) is attached to the inner surface of the groove (141).
5. The steel placing device for building construction according to claim 1, wherein universal wheels (13) are mounted on the lower surface of the placing plate (1).
6. The steel placing device for building construction according to claim 1, wherein a hanging ring (15) is mounted on the front surface of the placing plate (1).
7. The steel placing device for building construction according to claim 1, wherein reinforcing rods (23) are installed in the blocking frames (2).
CN202221385539.XU 2022-06-06 2022-06-06 Steel placing device for building construction Expired - Fee Related CN218318370U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221385539.XU CN218318370U (en) 2022-06-06 2022-06-06 Steel placing device for building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221385539.XU CN218318370U (en) 2022-06-06 2022-06-06 Steel placing device for building construction

Publications (1)

Publication Number Publication Date
CN218318370U true CN218318370U (en) 2023-01-17

Family

ID=84866425

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221385539.XU Expired - Fee Related CN218318370U (en) 2022-06-06 2022-06-06 Steel placing device for building construction

Country Status (1)

Country Link
CN (1) CN218318370U (en)

Similar Documents

Publication Publication Date Title
CN108951651A (en) A kind of pattern foundation pit supporting structure that stablizing effect is good
CN218318370U (en) Steel placing device for building construction
CN205857723U (en) A kind of form for construction engineering
CN203097248U (en) Integral type flexible scaffold
CN206986644U (en) A kind of tunnel track simply removes device
CN207759922U (en) Large span suspender
CN203394032U (en) Inside-cylinder climb-type operation frame
CN215160510U (en) A jib for construction elevator
CN212129863U (en) Improved tool type hanging basket for mounting cable on anti-collision wall of bridge
CN207829921U (en) A kind of push pipe is hampered quick supporting device of getting rid of poverty
CN209482687U (en) A kind of Super High exterior frame column construction operation platform
CN207312923U (en) A kind of heavy-duty steel component hanging apparatus
CN202658587U (en) Pressure steel pipe installation turntable in construction hole
CN201400964Y (en) Hook ladder for rapidly mounting color steel plate on lower roof
CN206529934U (en) A kind of fabricated shear wall edge member
CN106012830B (en) A kind of Super Long Tunnel anchor utilizes the horizontal hole in the tunnel method that laterally transhipment reinforcing pull rod is constructed
CN205978844U (en) But reuse sleeve pipe
CN206034874U (en) Elevartor shaft combination formula integrally lift up operation platform
CN216328001U (en) Dismounting tool for post insulator of booster station
CN105236290B (en) Crane with hoistable platform quickly moves erecting device
CN215291341U (en) Scaffold frame protection net piece installation fixing device
CN214061608U (en) Building construction pile driver of area assistance-localization real-time function
CN220100762U (en) Interior climbing formula well promotes protection system
CN208200200U (en) Tower crane turns round position anti-climbing device
CN216866704U (en) Manned trolley for inclined shaft construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20230117