Construction structure of walking tower crane on large platform of stadium Download PDFInfo
- Publication number
- CN218292854U CN218292854U CN202121843199.6U CN202121843199U CN218292854U CN 218292854 U CN218292854 U CN 218292854U CN 202121843199 U CN202121843199 U CN 202121843199U CN 218292854 U CN218292854 U CN 218292854U
- Authority
- CN
- China
- Prior art keywords
- tower crane
- roof beam
- track roof
- fitting
- track
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims abstract description 21
- 230000010354 integration Effects 0.000 claims abstract 2
- 229910000831 Steel Inorganic materials 0.000 claims description 23
- 239000010959 steel Substances 0.000 claims description 23
- 230000003014 reinforcing effect Effects 0.000 claims description 3
- 241000252185 Cobitidae Species 0.000 abstract 1
- 238000010586 diagram Methods 0.000 description 2
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 description 2
- 230000007547 defect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000005728 strengthening Methods 0.000 description 1
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model relates to a walking tower crane is construction structures on stadium large platform, affiliated construction technical field, the loach carrying platform comprises a supporting fram, the support frame on be equipped with a pair of track roof beam, track roof beam both ends all be equipped with the bracing. The support frame include the concrete beam, the concrete beam lower extreme be equipped with a plurality of support columns, the concrete beam on be equipped with and track roof beam looks bolted connection built-in fitting fixed, track roof beam connect the built-in fitting both ends be equipped with and be the integration and with the concrete beam and be connected the built-in fitting with bracing looks bolted connection fixed bracing. The structure has the characteristics of high structural strength, good safety and reliability and long service life. The problem of walking tower crane construction cycle length is solved.
Description
Technical Field
The utility model relates to a construction technical field, concretely relates to walking tower crane is construction structures on big platform in stadiums.
Background
With the development and prosperity of the current social economy, under the large environment of the rapid development of the building industry, a large-scale steel structure is widely applied to modern large stadiums, however, the large stadiums are usually provided with two layers of large platform structures, under the condition, a large-scale walking type tower crane is adopted as main equipment for steel structure construction, the requirements of applicability and economy are met, and meanwhile, the two layers of large platform structures are reinforced, so that the construction safety and the structure safety are ensured.
Disclosure of Invention
The invention mainly solves the defects of low structural strength, poor safety and reliability and short service life in the prior art, and provides a construction structure of a walking tower crane on a large platform of a stadium, which has the characteristics of high structural strength, good safety and reliability and long service life. The problem of walking tower crane construction cycle length is solved.
The technical problem of the invention is mainly solved by the following technical scheme:
the utility model provides a construction structures of walking tower crane on big platform in stadiums, includes the support frame, the support frame on be equipped with a pair of track roof beam, track roof beam both ends all be equipped with the bracing. The support frame comprises a concrete beam, a plurality of support columns are arranged at the lower end of the concrete beam, a track beam connection embedded part fixedly connected with the track beam through bolts is arranged on the concrete beam, and inclined strut connection embedded parts which are integrated with the concrete beam and fixedly connected with the inclined strut through bolts are arranged at two ends of the track beam connection embedded part.
Preferably, the support column comprises a support base, and a support steel column is arranged between the support base and the concrete beam.
Preferably, the supporting steel column comprises a steel pipe, connecting plates integrally welded and fixed with the steel pipe are arranged at two ends of the steel pipe, and a plurality of reinforcing ribs distributed annularly at equal intervals are arranged between the connecting plates and the steel pipe.
Preferably, a base plate is arranged between the embedded parts connected with the track beam, and clamping plates integrally welded and fixed with the base plate are arranged at two ends of the track beam.
Preferably, the supporting column is a concrete column.
The invention can achieve the following effects:
the utility model provides a walking tower crane is construction structures on big platform in stadiums compares with prior art, has structural strength height, the good and long service life's of fail safe nature characteristics. The problem of walking tower crane construction cycle length is solved.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a schematic structural diagram of the support frame of the present invention.
Fig. 3 is a schematic view of a connection structure of the track beam of the present invention.
Fig. 4 is a schematic view of the connection structure of the support column of the present invention.
Fig. 5 is a schematic structural view of the support steel column of the present invention.
In the figure: bracing 1, track roof beam 2, support frame 3, embedded part 4 is connected to the bracing, and embedded part 5 is connected to the track roof beam, concrete beam 6, support column 7, cardboard 8, backing plate 9, support steel column 10, support base 11, connecting plate 12, strengthening rib 13, steel pipe 14.
Detailed Description
The technical solution of the present invention is further specifically described below by way of examples and with reference to the accompanying drawings.
The embodiment is as follows: as shown in fig. 1-5, a construction structure of a walking tower crane on a large platform of a stadium comprises a support frame 3, a pair of track beams 2 is arranged on the support frame 3, and inclined struts 1 are arranged at two ends of each track beam 2. Support frame 3 includes concrete beam 6, and 6 lower extremes of concrete beam are equipped with 2 support columns 7 that are the symmetric form and distribute, and support column 7 includes support pedestal 11, is equipped with support steel column 10 between support pedestal 11 and concrete beam 6. The supporting steel column 10 comprises a steel pipe 14, connecting plates 12 integrally welded and fixed with the steel pipe 14 are arranged at two ends of the steel pipe 14, and 4 reinforcing ribs 13 distributed annularly at equal intervals are arranged between the connecting plates 12 and the steel pipe 14. The supporting columns 7 are concrete columns. The concrete beam 6 is provided with a track beam connection embedded part 5 which is fixedly connected with the track beam 2 through bolts, a backing plate 9 is arranged between the track beam 2 and the track beam connection embedded part 5, and clamping plates 8 which are integrally welded and fixed with the backing plate 9 are arranged at two ends of the track beam 2. And the inclined strut connecting embedded parts 4 which are integrated with the concrete beam 6 and fixedly connected with the inclined struts 1 through bolts are arranged at the two ends of the track beam connecting embedded parts 5.
To sum up, this walking tower crane is in construction structures on the big platform in stadiums, has that structural strength is high, fail safe nature is good and long service life's characteristics. The problem of walking tower crane construction cycle length is solved.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without deviating from the basic characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
In conclusion, the above description is only the specific embodiment of the present invention, but the structural features of the present invention are not limited thereto, and any person skilled in the art can make changes or modifications within the scope of the present invention.
Claims (5)
1. The utility model provides a walking tower crane constructs on big platform in stadiums which characterized in that: the device comprises a support frame (3), wherein a pair of track beams (2) are arranged on the support frame (3), and inclined struts (1) are arranged at two ends of each track beam (2); support frame (3) include concrete beam (6), concrete beam (6) lower extreme be equipped with a plurality of support columns (7), concrete beam (6) on be equipped with track roof beam (2) looks bolted connection fixed track roof beam connect built-in fitting (5), track roof beam connect built-in fitting (5) both ends be equipped with concrete beam (6) be the integration and with bracing (1) looks bolted connection fixed bracing connect built-in fitting (4).
2. The construction structure of the walking tower crane on the large platform of the stadium according to claim 1, characterized in that: the supporting column (7) comprises a supporting base (11), and a supporting steel column (10) is arranged between the supporting base (11) and the concrete beam (6).
3. The construction structure of the walking tower crane on the large platform of the stadium according to claim 2, characterized in that: the supporting steel column (10) comprises a steel pipe (14), connecting plates (12) which are integrally welded and fixed with the steel pipe (14) are arranged at two ends of the steel pipe (14), and a plurality of reinforcing ribs (13) which are distributed in an equidistant annular mode are arranged between the connecting plates (12) and the steel pipe (14).
4. The construction structure of the walking tower crane on the large platform of the stadium according to claim 1, characterized in that: track roof beam (2) and track roof beam be connected between built-in fitting (5) and be equipped with backing plate (9), track roof beam (2) both ends all be equipped with and be integrated welded fastening's cardboard (8) with backing plate (9).
5. The construction structure of the walking tower crane on the large platform of the stadium according to claim 1, characterized in that: the supporting column (7) can be a concrete column.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202121843199.6U CN218292854U (en) | 2021-08-09 | 2021-08-09 | Construction structure of walking tower crane on large platform of stadium |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202121843199.6U CN218292854U (en) | 2021-08-09 | 2021-08-09 | Construction structure of walking tower crane on large platform of stadium |
Publications (1)
Publication Number | Publication Date |
---|---|
CN218292854U true CN218292854U (en) | 2023-01-13 |
Family
ID=84803253
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202121843199.6U Active CN218292854U (en) | 2021-08-09 | 2021-08-09 | Construction structure of walking tower crane on large platform of stadium |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN218292854U (en) |
-
2021
- 2021-08-09 CN CN202121843199.6U patent/CN218292854U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105780925A (en) | Method for installation construction of truss-hanging combination system | |
CN109138454A (en) | A kind of installation method of super high-rise building outline border bandy truss | |
CN208055880U (en) | A kind of crane's major girder hoisting frame | |
CN205775852U (en) | A kind of active force conversion support for steel structure support moulding bed top | |
CN102261043B (en) | Assembled steel pipe upright post system | |
CN218292854U (en) | Construction structure of walking tower crane on large platform of stadium | |
CN112049235B (en) | High-altitude large-span cantilever structure construction platform and method | |
CN111188278A (en) | Jig frame structure, jig frame assembly and construction method | |
CN203361654U (en) | Prefabricated steel frame component | |
CN210177367U (en) | Weak support system suitable for installation of steel structure of high tower steel-concrete combined beam | |
CN214835056U (en) | Supporting device for bearing plate of sawtooth-shaped steel bar truss floor | |
CN215331674U (en) | Interim bearing structure of steel bar truss building carrier plate | |
CN212403409U (en) | Lifting platform frame based on suspended dome roof system | |
CN212507295U (en) | Overhanging steel platform | |
CN212561172U (en) | Jig frame structure, jig frame assembly and assembling structure | |
CN102996368B (en) | Engine room truss of wind generation set | |
CN112392141A (en) | Large cantilever structure for balancing insufficient end pressure weight and construction method thereof | |
CN111733714A (en) | Beam column node structure of overhead station and interval bridge | |
CN220434329U (en) | Temporary steel support for mounting oversized-section steel mast | |
CN207568206U (en) | A kind of temporary support system for annular building periphery steel construction | |
CN219839949U (en) | Lower beam bracket of ultra-high bridge cable tower | |
CN217652014U (en) | Take connected node of H shaped steel and stand of keeping flat of slope | |
CN214143242U (en) | RCS structural steel supports staple bolt combination node | |
CN214885409U (en) | Connection structure of scaffold frame and steel construction wall body encorbelments | |
CN111827574B (en) | Construction method of giant inclined truss structure of high-rise building |