CN218265335U - Convenient combination formula temporary construction guardrail - Google Patents

Convenient combination formula temporary construction guardrail Download PDF

Info

Publication number
CN218265335U
CN218265335U CN202222010436.1U CN202222010436U CN218265335U CN 218265335 U CN218265335 U CN 218265335U CN 202222010436 U CN202222010436 U CN 202222010436U CN 218265335 U CN218265335 U CN 218265335U
Authority
CN
China
Prior art keywords
couple
stand
guardrail
sleeve
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222010436.1U
Other languages
Chinese (zh)
Inventor
李顺
杨长福
关腾龙
吴亚林
权力
倪俊杰
曹博宇
许宁
段理邦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
South China Construction And Development Co ltd Of Sinohydro 14th Bureau
Original Assignee
Sinohydro Bureau 14 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 14 Co Ltd filed Critical Sinohydro Bureau 14 Co Ltd
Priority to CN202222010436.1U priority Critical patent/CN218265335U/en
Application granted granted Critical
Publication of CN218265335U publication Critical patent/CN218265335U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model discloses a convenient combination formula guardrail of constructing temporarily belongs to municipal works urban area interim traffic and dredges the field, including the stand support, the railing panel, the stand support includes stand, foot rest, couple, and the stand both sides are provided with the couple, and the bottom is provided with and is used for supporting fixed foot rest, and the railing panel includes outer frame, riser, sleeve, and the parallel arrangement has the riser in the outer frame, and both ends setting and the sleeve that the couple position corresponds, stand support and railing panel form interim continuous guardrail through couple and sleeve combination. The utility model provides a guardrail is under construction temporarily to convenient combination formula has that the cost is low, simple process, but batch production, easy and simple to handle, the installation is swift, the suggestion advantage such as striking, and the constructor of easy and simple to handle easily masters, can effectively keep apart the site operation region, and the traffic is dredged the process and can be kept stable, excellent in use effect, dredges and the construction encloses effectively to practice thrift installation time in the cover in-process in urban area municipal works traffic.

Description

Convenient combination formula temporary construction guardrail
Technical Field
The utility model belongs to municipal works urban area interim traffic is dredged the field, specifically is a convenient combination formula construction guardrail temporarily.
Background
In recent years, with the overall deployment of national ecological civilization construction, the urban rain and sewage diversion project is continuously developed at present, but the construction range of the treatment project of the confluence channel box of the old urban area is wide, the treatment project covers main and secondary main roads and main branch roads in the urban area, residential quarters, markets, schools, hospitals, local enterprises, government departments and the like are distributed on the periphery, the construction segment has large people and traffic flow, the construction range is wide, the influence range is wide, the construction has large traffic influence on the urban area, the construction has large requirement on construction enclosure, the construction is frequent, the construction period is safe and stable, and a convenient combined type temporary construction guardrail is required under the condition that the construction area can be effectively isolated from the social activity area.
SUMMERY OF THE UTILITY MODEL
The above-mentioned problem to prior art exists, the utility model provides a convenient combination formula temporary construction guardrail overcomes background traffic and dredges, and urban area road excavation construction encloses temporarily that the range is covered extensively, the demand is big, removes the problem that actual existence such as frequent, the utility model discloses a set up stand support and railing plate combined use, provide one kind and conveniently accomodate, stack neatly pleasing to the eye, install convenient, quick temporary construction guardrail.
In order to achieve the above purpose, the utility model adopts the following technical scheme: a convenient combined type temporary construction guardrail comprises a stand column bracket and a guardrail plate. The stand support include stand, foot rest, couple, the stand both sides are provided with the couple, the bottom is provided with and is used for supporting fixed foot rest, the railing board include outer frame, riser, sleeve, the parallel arrangement has the riser in the outer frame, both ends set up the sleeve that corresponds with the couple position, stand support and railing board form interim continuous guardrail through couple and sleeve combination.
Furthermore, the outer side of the vertical pipe is provided with a billboard and a skirting board.
The utility model has the advantages that:
the utility model provides a guardrail is under construction temporarily to convenient combination formula, but have the cost low, simple process, batch production, easy and simple to handle, the installation is swift, suggestion advantage such as striking, only need composite mounting to produce complete stand support and railing panel in advance and can accomplish the guardrail of being under construction and build, the constructor of easy and simple to handle easily masters, can effectively keep apart the site operation region, the traffic is dredged the process and can be kept stable, excellent in use effect, dredge and the construction encloses and cover in-process can effectively practice thrift installation time in urban area municipal works traffic.
Drawings
Figure 1 is the utility model stand sketch.
Figure 2 is a side view of the utility model stand support.
Figure 3 is a schematic view of the utility model railing panel.
In the figures 1-3, 1-column, 2-foot rest, 3-hook, 4-outer frame, 5-vertical pipe, 6-billboard, 7-skirting board, 8-sleeve.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention clearer, the following will explain in detail a preferred embodiment of the present invention with reference to the accompanying drawings to facilitate understanding of the skilled person.
As shown in fig. 1-3, the convenient combined temporary construction guardrail comprises a column support and a railing panel, wherein the column support comprises a column 1, a foot support 2 and a hook 3, and the railing panel comprises an outer frame 4, a vertical pipe 5 and a sleeve 8. In the embodiment, the column support is formed by welding 50mm 2mm rectangular pipes into a [ -shaped supporting frame 2, the upper center is welded with 50mm 2mm rectangular pipe columns 1, and U-shaped phi 10mm steel bar hooks 3 are placed on two sides of the rectangular pipe columns and fixed by welding. The rail plates are formed by welding 30mm 2mm rectangular pipes to form an outer frame 4, 200mm welding 2mm 10mm rectangular pipe vertical pipes 5 rails are arranged between the outer frame 4 at intervals, and phi 15mm 2mm steel pipe sleeves 8 are arranged at equal height positions corresponding to the upright support hooks 3 at the two ends of the outer frame and are connected in a welding mode. The outer side of the 5 vertical pipe railings can be provided with 1000mm 150mm 1mm galvanized steel plate advertising boards 6 and 1850mm 200mm 1mm galvanized steel plate skirting boards 7, enterprise signs, warning words and the like can be arranged on the advertising boards, and yellow and black warning lines are marked on the skirting boards 7.
The utility model discloses a working process: the upright post supports and the railing plates with the required number of the protection areas are manufactured in advance, the upright post supports and the railing plates with the corresponding number are combined into continuous temporary construction guardrails through the hooks 3 and the sleeves 8 before construction, the advertising boards 6 and the skirting boards 7 are installed on the outer sides of the vertical pipes 5 and the railings according to construction requirements, the advertising boards 6 can be provided with enterprise signs, warning words and the like, and yellow and black warning lines are marked on the skirting boards 7. When meeting typhoon period, can pile on the stand support and press sand bag counter weight, guarantee the firm protection of interim continuous guardrail. After the construction is accomplished, will couple 3 and sleeve 8 correspond to pull down, separately accomodate stand support and railing panel can, carry out the equipment of required length guardrail again when the construction next time.
The utility model provides a guardrail is under construction temporarily to convenient combination formula, but have the cost low, simple process, batch production, easy and simple to handle, the installation is swift, suggestion advantage such as striking, only need composite mounting to produce complete stand support and railing panel in advance and can accomplish the guardrail of being under construction and build, the constructor of easy and simple to handle easily masters, can effectively keep apart the site operation region, the traffic is dredged the process and can be kept stable, excellent in use effect, dredge and the construction encloses and cover in-process can effectively practice thrift installation time in urban area municipal works traffic.
Finally, it is noted that the above-mentioned preferred embodiments illustrate rather than limit the invention, and that, although the invention has been described in detail with reference to the above-mentioned preferred embodiments, it will be understood by those skilled in the art that various changes in form and details may be made therein without departing from the scope of the invention as defined by the appended claims.

Claims (2)

1. The utility model provides a convenient combination formula is construction guardrail temporarily which characterized in that: including the stand support, the railing panel, the stand support include stand (1), foot rest (2), couple (3), stand (1) both sides are provided with couple (3), and the bottom is provided with and is used for supporting fixed foot rest (2), the railing panel include outer frame (4), riser (5), sleeve (8), parallel arrangement has riser (5) in outer frame (4), both ends set up sleeve (8) that correspond with couple (3) position, stand support and railing panel form interim continuous guardrail through couple (3) and sleeve (8) combination.
2. A ready-to-assemble temporary construction fence according to claim 1, wherein: the outer side of the vertical pipe (5) is provided with a billboard (6) and a skirting board (7).
CN202222010436.1U 2022-08-02 2022-08-02 Convenient combination formula temporary construction guardrail Active CN218265335U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222010436.1U CN218265335U (en) 2022-08-02 2022-08-02 Convenient combination formula temporary construction guardrail

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222010436.1U CN218265335U (en) 2022-08-02 2022-08-02 Convenient combination formula temporary construction guardrail

Publications (1)

Publication Number Publication Date
CN218265335U true CN218265335U (en) 2023-01-10

Family

ID=84763735

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222010436.1U Active CN218265335U (en) 2022-08-02 2022-08-02 Convenient combination formula temporary construction guardrail

Country Status (1)

Country Link
CN (1) CN218265335U (en)

Similar Documents

Publication Publication Date Title
CA2328096C (en) Environmentally compatible archway for road building
CN110805022A (en) Mud solidification treatment device and method for matching electroosmosis well point with well point dewatering
CN218265335U (en) Convenient combination formula temporary construction guardrail
CN214497276U (en) Signboard mounting structure
CN108457148B (en) Assembled multifunctional temporary road structure and construction method thereof
CN206283215U (en) A kind of cable passageway portal structure
CN207017300U (en) A kind of corrugated steel retaining wall
CN215255114U (en) Road foundation pit safety device for municipal construction
CN205875906U (en) Portable removable barricade
CN106451271B (en) A kind of cable passageway portal structure and its installation method
CN203296470U (en) Finalization fence
CN209837881U (en) Face and build and enclose fender modularization device
CN208501735U (en) Prefabricated piping lane
CN210622379U (en) Regularization steel stair foundation ditch packway
CN210530485U (en) Building construction foundation ditch safety device
CN210737262U (en) Road plate and assembled road
CN208917865U (en) Assembled arcading barricade
AU2010101417B4 (en) A fluid storage tank
CN212984555U (en) Multifunctional foot rest for road construction
CN210002309U (en) assembled enclosure structure
CN217500503U (en) Multifunctional cover plate of underground reservoir
CN217267619U (en) Old district reforms transform and uses piping lane structure
CN214401869U (en) Municipal administration public works construction foundation support structure
CN212223674U (en) Interim door opening of bridge construction usefulness
CN210798474U (en) Make things convenient for portable guardrail of dismouting

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20230806

Address after: Floor 8, Gufeng Building, Sandong Avenue, Huadu District, Guangzhou, Guangdong 510800

Patentee after: South China Construction and Development Co.,Ltd. of Sinohydro 14th Bureau

Address before: No.192, Huancheng East Road, Guandu District, Kunming District, China (Yunnan) pilot Free Trade Zone, Kunming, Yunnan 650041

Patentee before: SINOHYDRO BUREAU 14 Co.,Ltd.

TR01 Transfer of patent right