CN218205644U - Scaffold bracket device for high-altitude installation of water-cooled wall of spiral section tube ring of boiler - Google Patents

Scaffold bracket device for high-altitude installation of water-cooled wall of spiral section tube ring of boiler Download PDF

Info

Publication number
CN218205644U
CN218205644U CN202222279881.8U CN202222279881U CN218205644U CN 218205644 U CN218205644 U CN 218205644U CN 202222279881 U CN202222279881 U CN 202222279881U CN 218205644 U CN218205644 U CN 218205644U
Authority
CN
China
Prior art keywords
fixing plate
water
spiral section
section tube
fixed plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222279881.8U
Other languages
Chinese (zh)
Inventor
颜亮
谢清文
林程
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Fujian Engineering Co Ltd
Original Assignee
PowerChina Fujian Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Fujian Engineering Co Ltd filed Critical PowerChina Fujian Engineering Co Ltd
Priority to CN202222279881.8U priority Critical patent/CN218205644U/en
Application granted granted Critical
Publication of CN218205644U publication Critical patent/CN218205644U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Furnace Housings, Linings, Walls, And Ceilings (AREA)

Abstract

The utility model discloses a scaffold puts up bracket device of boiler spiral section tube coil water-cooling wall high altitude installation belongs to scaffold puts up bracket field, and its technical scheme main points are, including the installation subassembly with bear the frame, the installation subassembly is including first fixed plate and second fixed plate, first fixed plate is wavy, pass through bolted connection between first fixed plate and the second fixed plate, a recess has been seted up to one side of bearing the frame, be provided with fixed subassembly on the recess, bear the frame with the recess homonymy is close to the position of second fixed plate is provided with places the portion, fixed subassembly is including the slider, the slider with groove connection, be provided with the layer board on the slider, the slider is kept away from the position of layer board runs through there is the spring telescopic link, the both ends of spring telescopic link respectively with the second fixed plate with bear the frame and connect. Need not to set up a plurality of steel pipes and bear fixed footboard, easy dismounting and firm reliable.

Description

Scaffold bracket device for high-altitude installation of water-cooled wall of spiral section tube ring of boiler
Technical Field
The utility model relates to a scaffold puts up the bracket field, specifically is a scaffold puts up bracket device of boiler spiral section tube coil water-cooling wall high altitude installation.
Background
In the installation of the heating surface of the water-cooled wall of the spiral section tube coil, the heating surface scattered pieces are often required to be installed at high altitude, the fins of the water-cooled wall require double-sided welding, the high-altitude installation of the water-cooled wall has high requirements on the stability and safety of erecting a scaffold, the scaffold tube cannot be directly welded on the water-cooled wall tube, the scaffold is often required to be fixed through a bracket for high-altitude erection, the scaffold pedal is stabilized on the bracket by erecting a plurality of steel tubes, the construction amount is large due to the fact that operation is repeated, the assembly and disassembly are inconvenient, and the steel tubes are not easy to fix, so that the scaffold bracket device for high-altitude installation of the water-cooled wall of the spiral section tube coil of the boiler is required to solve the problems.
SUMMERY OF THE UTILITY MODEL
To the problem that exists among the prior art, the utility model aims to provide a scaffold puts up bracket device of boiler spiral section tube coil water-cooling wall high altitude installation need not to build a plurality of steel pipes and bears fixed footboard, easy dismounting and firmly reliable.
The above technical object of the present invention can be achieved by the following technical solutions: the utility model provides a scaffold puts up bracket device of boiler spiral section tube coil water-cooling wall high altitude installation, including the installation subassembly with bear the frame, the installation subassembly is including first fixed plate and second fixed plate, first fixed plate is wavy, pass through bolted connection between first fixed plate and the second fixed plate, a recess has been seted up to one side of bearing the frame, be provided with fixed subassembly on the recess, bear the frame with the recess homonymy is close to the position of second fixed plate is provided with the portion of placing, fixed subassembly is including the slider, the slider with groove connection, be provided with the layer board on the slider, the slider is kept away from the position of layer board runs through there is the spring telescopic link, the both ends of spring telescopic link respectively with the second fixed plate with bear the frame and connect.
In some embodiments, a rubber pad is disposed on the pallet.
In some embodiments, the first fixing plate is connected with two angle iron butt clamps through bolts.
In some embodiments, the carrier and the second retainer plate in combination form a triangular shape.
In some embodiments, the first and second fixing plates are flat steel.
In some embodiments, the carrier is an angle iron.
To sum up, the utility model discloses following beneficial effect has:
the utility model discloses a fixed subassembly realizes fixed to the footboard, only needs the slip layer board to make the layer board and the increase of the distance of placing the portion, places the footboard again and can accomplish fixedly on the layer board with place the portion, and the dismouting is very convenient, need not to build a plurality of steel pipes and fixes the footboard, utilizes the second fixed plate and the cooperation that bears the frame simultaneously, forms stable fixed knot to construct, and the wavy design of first fixed plate closely laminates with the spiral section water-cooling wall, has further improved the stability of device.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
fig. 2 is a schematic view of a local mechanism of the present invention.
In the figure: 1. mounting the component; 101. a first fixing plate; 102. a second fixing plate; 2. a carrier; 21. a placement section; 3. angle iron butt clamp; 4. a fixing assembly; 41. a slider; 42. a spring telescopic rod; 43. a supporting plate.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative efforts all belong to the protection scope of the present invention.
Referring to fig. 1, a scaffold bracket device for high-altitude installation of a water-cooled wall of a boiler spiral section tube coil comprises an installation assembly 1 and a bearing frame 2, wherein the installation assembly 1 comprises a first fixing plate 101 and a second fixing plate 102, the first fixing plate 101 is in a wavy shape, the first fixing plate 101 is connected with the second fixing plate 102 through a bolt, one side of the bearing frame 2 is provided with a groove, the groove is provided with a fixing assembly 4, a placing part 21 is arranged at a position, close to the second fixing plate 102, of the same side of the bearing frame 2 and the groove, the fixing assembly 4 comprises a sliding block 41, the sliding block 41 is connected with the groove, the sliding block 41 is provided with a supporting plate 43, a position, far away from the supporting plate 43, of the sliding block 41 penetrates through a spring telescopic rod 42, two ends of the spring telescopic rod 42 are respectively connected with the second fixing plate 102 and the bearing frame 2, and the bearing frame 2 and the second fixing plate 102 are combined to form a triangular shape. When the scaffold is used, the bearing frame 2 and the second fixing plate 102 are welded together to form a tripod, then the first fixing plate 101 penetrates through the water-cooled wall of the spiral section tube coil, then the first fixing plate 101 and the water-cooled wall of the spiral section tube coil are fixed together by using the angle iron butt clamp 3, the first fixing plate 101 is prevented from sliding off the water-cooled wall of the spiral section tube coil, finally the first fixing plate 101, the water-cooled wall of the spiral section tube coil and the second fixing plate 102 are fixed together by using the connecting piece 103, namely, the scaffold bracket is built, when the scaffold is required to be built, an operator stirs the sliding block 41 in the direction far away from the second fixing plate 102, the sliding block 41 drives the supporting plate 43 to move, so that the distance between the supporting plate 43 and the placing part 21 is gradually increased until the pedal can be placed in, the pedal is fixed on the bracket, namely, the scaffold is built, when the scaffold is required to be dismounted, the operator only needs to stir the pedal in the direction far away from the second fixing plate 102, so that the distance between the supporting plate 43 and the placing part 21 is continuously increased, and then the pedal is close to the placing part 21, so that the pedal can be dismounted, and the operation is convenient; the utility model discloses only need slide block 41, make layer board 43 and place the distance increase between the portion 21 in order to place the footboard, fix the footboard, need not to build a plurality of steel pipes and come to fix the footboard, safe and reliable and easy dismounting utilize the design of the unrestrained form of first fixed plate 101 simultaneously for spiral section tube coil water-cooling wall is hugged closely to first fixed plate 101, strengthens the fixed degree of installation.
In some embodiments, a rubber pad is disposed on the supporting plate 43, and the rubber pad not only protects the supporting plate 43, but also increases friction between the pedal and the supporting plate 43, so as to further fix the pedal.
In some embodiments, edge baffles are arranged on both the supporting plate 43 and the placing part 21, the supporting plate 43 and the placing part 21 are matched to form a framework for fixing the pedal, so that the pedal can be prevented from being deviated during installation, and meanwhile, the baffles can enhance the wrapping degree of the supporting plate 43 and the placing part 21 on the pedal, and improve the fixing strength of the pedal.
In some embodiments, the first fixing plate 101 and the second fixing plate 102 are made of flat steel, and cutting is reduced for operators by using the flat steel, so that labor and material consumption is reduced.
In some embodiments, the supporting frame 2 is an angle iron, but not limited thereto, the angle iron has stable function and high strength, and the tripod formed by the second fixing plate 102 is more stable.
The present embodiment is only for explaining the present invention, and it is not limited to the present invention, and those skilled in the art can make modifications to the present embodiment without inventive contribution as required after reading the present specification, but all of them are protected by patent laws within the scope of the claims of the present invention.

Claims (6)

1. The utility model provides a scaffold puts up bracket device of high altitude installation of boiler spiral section tube coil water-cooled wall which characterized in that: comprises a mounting component (1) and a bearing frame (2);
the mounting assembly (1) comprises a first fixing plate (101) and a second fixing plate (102), wherein the first fixing plate (101) is wavy, and the first fixing plate (101) is connected with the second fixing plate (102) through a bolt;
a groove is formed in one side of the bearing frame (2), a fixing component (4) is arranged on the groove, and a placing part (21) is arranged on the same side of the groove on the bearing frame (2) and close to the second fixing plate (102);
the fixing component (4) comprises a sliding block (41), the sliding block (41) is connected with the groove, a supporting plate (43) is arranged on the sliding block (41), a spring telescopic rod (42) penetrates through a position, far away from the supporting plate (43), of the sliding block (41), and two ends of the spring telescopic rod (42) are connected with the second fixing plate (102) and the bearing frame (2) respectively.
2. The overhead scaffold bracket device for the water-cooled wall of the spiral section tube coil of the boiler according to claim 1, wherein: the supporting plate (43) is provided with a rubber pad.
3. The overhead scaffold bracket device for the water-cooled wall of the spiral section tube coil of the boiler according to claim 1, wherein: the first fixing plate (101) is connected with angle iron butt clamps (3) through bolts.
4. The high-altitude mounting scaffold bracket device for the water-cooled wall of the spiral section tube coil of the boiler as claimed in claim 1, wherein: the bearing frame (2) and the second fixing plate (102) are combined to form a triangular shape.
5. The high-altitude mounting scaffold bracket device for the water-cooled wall of the spiral section tube coil of the boiler as claimed in claim 1, wherein: the first fixing plate (101) and the second fixing plate (102) are made of flat steel.
6. The overhead scaffold bracket device for the water-cooled wall of the spiral section tube coil of the boiler according to claim 1, wherein: the bearing frame (2) is an angle iron.
CN202222279881.8U 2022-08-29 2022-08-29 Scaffold bracket device for high-altitude installation of water-cooled wall of spiral section tube ring of boiler Active CN218205644U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222279881.8U CN218205644U (en) 2022-08-29 2022-08-29 Scaffold bracket device for high-altitude installation of water-cooled wall of spiral section tube ring of boiler

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222279881.8U CN218205644U (en) 2022-08-29 2022-08-29 Scaffold bracket device for high-altitude installation of water-cooled wall of spiral section tube ring of boiler

Publications (1)

Publication Number Publication Date
CN218205644U true CN218205644U (en) 2023-01-03

Family

ID=84660683

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222279881.8U Active CN218205644U (en) 2022-08-29 2022-08-29 Scaffold bracket device for high-altitude installation of water-cooled wall of spiral section tube ring of boiler

Country Status (1)

Country Link
CN (1) CN218205644U (en)

Similar Documents

Publication Publication Date Title
CN218205644U (en) Scaffold bracket device for high-altitude installation of water-cooled wall of spiral section tube ring of boiler
CN210710345U (en) Fixing clamp for flange stamping
CN210177825U (en) House photovoltaic solar energy installation component
CN207567673U (en) Novel bridge construction main longitudinal grider hardened system
CN221337400U (en) VVER pile type dome heat exchanger take-over tool
CN108616252A (en) A kind of integral type tracking holder solar cell module mounting structure
CN217274895U (en) Supporting beam for mounting photovoltaic power generation device
CN216923431U (en) Non-welded fixing is in tuber pipe support on steel construction
CN212607604U (en) Hoisting equipment for bulb head and cone
CN217927492U (en) Riser bearing guide bracket
CN217445297U (en) Saddle plate roofing double T type photovoltaic module erection support
CN215835109U (en) Lightweight easily-assembled fixing fitting for composite insulating cross arm
CN216010746U (en) Installation structure of evacuation indicator lamp
CN214497859U (en) Assembled steel sheet concrete combination shear force wall and girder steel connection structure
CN214838887U (en) Industrial steam supply pipeline fixing device
CN215666461U (en) Elevator guide rail bracket
CN220376089U (en) Utility tunnel hoist and mount positioner
CN216999853U (en) Underground power pipe gallery for data center
CN210484805U (en) High-strength light-weight quick-assembly adjustable single-riser furnace tube hanger for tubular heating furnace
CN215772371U (en) Circuit pipeline easy to assemble
CN213900105U (en) Hydraulic jack placing support for pipe jacking construction
CN212506768U (en) Steel structure connecting piece convenient to installation
CN214662558U (en) A gallows convenient to maintain
CN221552059U (en) Novel reinforcing beam structure
CN220319158U (en) Fixed type safety support for high-altitude operation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant