CN218193652U - Auxiliary device for construction of fire-fighting vertical pipe - Google Patents

Auxiliary device for construction of fire-fighting vertical pipe Download PDF

Info

Publication number
CN218193652U
CN218193652U CN202222317230.3U CN202222317230U CN218193652U CN 218193652 U CN218193652 U CN 218193652U CN 202222317230 U CN202222317230 U CN 202222317230U CN 218193652 U CN218193652 U CN 218193652U
Authority
CN
China
Prior art keywords
fire control
fixed
locking bolt
frame
spacing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222317230.3U
Other languages
Chinese (zh)
Inventor
龚子轶
郑辉
黄谨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangxi Hongdu Fire Intelligent Engineering Co ltd
Original Assignee
Jiangxi Hongdu Fire Intelligent Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangxi Hongdu Fire Intelligent Engineering Co ltd filed Critical Jiangxi Hongdu Fire Intelligent Engineering Co ltd
Priority to CN202222317230.3U priority Critical patent/CN218193652U/en
Application granted granted Critical
Publication of CN218193652U publication Critical patent/CN218193652U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Clamps And Clips (AREA)

Abstract

The utility model discloses an auxiliary device of fire control standpipe construction belongs to construction technical field, including the base and install the fixed spacing frame in its top, base and stopper pass through traveller and spacing rack sliding contact and connect, the base frame runs through and installs the screw thread sickle card, the fixed block runs through and installs first locking bolt, first outer clamp splice is all installed relatively in the one end of fixed block medial surface to first locking bolt, two frames of the adjacent spacing rack of fixed spacing frame run through there is second locking bolt, and the second outer clamp splice is all installed relatively in the one end of fixed spacing frame medial surface to the bolt that sees the second, spacing rack toothing is connected with spacing gear. This auxiliary device of fire control standpipe construction has not only solved the problem that the installation of fire control standpipe probably inclines, and the top passes through spacing rack and limit gear's cooperation with the fire control standpipe of below simultaneously, is favorable to the installation of fire control clamp more, the effectual installation effectiveness that has improved.

Description

Auxiliary device for construction of fire-fighting vertical pipe
Technical Field
The utility model belongs to the technical field of the fire control construction, concretely relates to auxiliary device of fire control standpipe construction.
Background
According to the technical Specification for fire safety of construction engineering construction site GB50720-2011, the building height is more than 24m or the monomer volume exceeds 30000m 3 A temporary indoor fire-fighting water supply system is required to be arranged in the construction project.
Because the fire control standpipe runs through when floor and below fire control standpipe butt joint installation, adopts the manual work to hoist the fire control standpipe usually, and the interval between continuous adjustment and the below fire control standpipe still needs to guarantee constantly simultaneously that the fire control standpipe keeps perpendicular, is difficult for fixing and adjusting the installation of fire control clamp between the fire control standpipe, consequently needs auxiliary device, improves the installation effectiveness.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide an auxiliary device of fire control standpipe construction to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides an auxiliary device of fire control standpipe construction, install the fixed spacing frame in its top including base and perpendicular, the frame of base runs through to install and is used for the block to fix the screw thread sickle card at the construction reservation hole, fixed establishment is installed to the frame top surface of base, fixed establishment includes the first fixed block that the size is the same, the second fixed block, third fixed block and fourth fixed block, fixed establishment runs through there is first locking bolt, first locking bolt presses close to fixed establishment inner wall one end and installs the first outer clamp splice of fixed fire control standpipe, fourth fixed block top surface runs through perpendicularly and installs spacing rack, first fixed block, traveller is installed to second fixed block and third fixed block top surface, and the traveller runs through fixed spacing frame perpendicularly, two frame symmetries of the adjacent fixed spacing frame of spacing rack run through there is second locking bolt, the second outer clamp splice is installed to the one end of the fixed spacing frame inside casing of second locking bolt.
Preferably, the base frame horizontal direction sets up the smooth hole that runs through screw thread sickle card, and the one end threaded connection that the base inner wall was kept away from to the screw thread sickle card has the hexagon nut with base outer wall contact.
Preferably, the fixed block is transversely seted up the first screw hole that runs through first locking bolt, and first outer clamp splice is close to first locking bolt side welding and has first bearing piece, and first bearing piece and first locking bolt interference fit, and first outer clamp splice is kept away from first bearing piece one side curved surface and is installed the rubber pad with fire control standpipe flexible contact.
Preferably, the fixed limiting frame is vertically provided with a rectangular through hole and a limiting through hole for the limiting rack to penetrate through, the sliding column smoothly penetrates through the rectangular through hole, and the inner wall of one side, adjacent to the limiting through hole through which the limiting rack penetrates, is welded with a bearing ring.
Preferably, the teeth of the limiting rack are meshed with a limiting gear, a rotating shaft penetrates through the limiting gear and is in interference fit with the bearing ring, and a limiting rod penetrates through one end, far away from the bearing ring, of the rotating shaft.
Preferably, two frames of the adjacent fixed limit frame of limit rack are symmetrically provided with a second threaded hole penetrating through a second locking bolt, one side of the second outer clamping block is welded with a second bearing block, one side end of the second locking bolt is in interference fit with the second bearing block, and a rubber pad in flexible contact with the fire-fighting vertical pipe is installed on one side of the second outer clamping block far away from the second bearing block.
The utility model discloses a technological effect and advantage:
this auxiliary device of fire control standpipe construction overlaps in the fire control standpipe, fix on the reservation hole inner wall of floor through screw thread hook card block, drop the fire control standpipe to with the fire control standpipe top of below when being close the position, it makes first outer clamp splice fixed with the fire control standpipe to screw up first locking bolt, it makes the outer clamp splice of second fixed with the fire control standpipe to screw up second locking bolt again, more be favorable to the fire control standpipe to reach a vertical state, when avoiding the installation of fire control standpipe, the fire control standpipe is unstable to lead to the slope, influence the installation of sealing rubber circle.
In the operation process, when the fire control standpipe and the fire control standpipe of below were too big in the interval, rotate the gag lever post and drive limit gear, make spacing rack work, and then drive fixed spacing frame and fire control standpipe vertical movement to this reduces the interval between the fire control standpipe both ends, is favorable to the installation to the fire control clamp, has improved the installation effectiveness of fire control standpipe.
Drawings
FIG. 1 is a schematic view of the present invention;
fig. 2 is a schematic structural view of the base, the fixing block and the fixing and limiting frame of the present invention;
fig. 3 is a schematic structural view of the limit rack and the limit gear of the present invention;
fig. 4 is a schematic view of the first locking bolt and the first outer clamping block of the present invention;
FIG. 5 is a schematic view of the disassembled structure of the screw thread sickle clamp and the screw cap of the present invention;
fig. 6 is a schematic view of the second locking bolt and the second outer clamping block according to the present invention.
In the figure: 1. a base; 2. fixing a limit frame; 3. a fixing mechanism; 31. a first fixed block; 32. a second fixed block; 33. a third fixed block; 34. a fourth fixed block; 4. a traveler; 5. a limiting rack; 6. a first locking bolt; 7. a thread sickle clamp; 8. a second locking bolt; 9. smoothing holes; 10. a first threaded hole; 11. a rectangular through hole; 12. a second threaded hole; 13. a limit gear; 14. a limiting rod; 15. a rotating shaft; 16. a bearing ring; 17. a first outer clamp block; 18. a first bearing block; 19. a rubber pad; 20. a hexagonal nut; 21. a second outer clamp block; 22. a second bearing block; 23. limiting the through hole.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
The utility model provides an as shown in fig. 1-fig. 6 auxiliary device that fire control standpipe was under construction, the fire control standpipe adopts the fire control clamp connection with the fire control standpipe, and the fire control clamp has including sealing rubber circle, clamp and locking bolt, and the most comparatively rough violence of current mounting means, directly splices the fire control standpipe, can't guarantee the vertical state of fire control standpipe and the sealed situation of the sealing rubber circle of the inside of clamp and this example just uses the interval of carrying out vertical fixed and adjustable fire control standpipe to the fire control standpipe as an example:
including base 1 and the fixed spacing frame 2 of vertical installation in its top, the frame of base 1 runs through to install and is used for the block to fix at the screw thread sickle card 7 in the construction reserved hole, stretch to floor fire control reserved hole through screw thread sickle card 7, unable adjustment base 1, fixed establishment 3 is installed to the frame top surface of base 1, fixed establishment 3 includes the same first fixed block 31 of size, second fixed block 32, third fixed block 33 and fourth fixed block 34, fixed establishment 3 runs through first locking bolt 6, first outer clamp splice 17 that fixed fire control standpipe was installed to 3 inner wall one end of fixed establishment is pressed close to first locking bolt 6 carries out first step fixing to fire control standpipe, fourth fixed block 34 top surface runs through perpendicularly installs spacing rack 5, first fixed block 31, sliding column 4 is installed to second fixed block 32 and third fixed block 33 top surface, and sliding column 4 runs through fixed spacing frame 2 perpendicularly, two frames symmetry of the adjacent fixed spacing frame 2 of spacing rack 5 runs through second locking bolt 8, second locking bolt 8 presses close to the one end of fixed spacing frame 2 inside casing installs second outer clamp splice 21 and carries out second step fixing.
Smooth holes 9 penetrating through the threaded sickle clamp 7 are formed in the horizontal direction of the frame of the base 1, one end, far away from the inner wall of the base 1, of the threaded sickle clamp 7 is in threaded connection with a hexagonal nut 20 in contact with the outer wall of the base 1, the stability of the base 1 is improved or weakened through screwing and loosening the hexagonal nut 20, and the more stable the base 1 is, the more beneficial the installation of the fire-fighting standpipe is.
Fixing mechanism 3 transversely sets up first screw hole 10 that runs through first locking bolt 6, first outer clamp splice 17 has first bearing piece 18 near a side welding of first locking bolt 6, and first bearing piece 18 and first locking bolt 6 interference fit, first outer clamp splice 17 is kept away from first bearing piece 18 one side curved surface and is installed the rubber pad 19 with fire control standpipe flexible contact, 17 curved surface one side installation rubber pad 19 in first outer clamp splice, can effectually reduce the damage deformation that first outer clamp splice 17 caused to fire control standpipe extrusion.
The vertical spacing through hole 23 of seting up rectangle through hole 11 and being used for spacing rack 5 to run through of fixed spacing frame 2, traveller 4 smoothly runs through in rectangle through hole 11, and the welding of the adjacent one side inner wall of spacing through hole 23 that spacing rack 5 runs through has bearing ring 16, can reciprocate through rectangle through hole 11, spacing through hole 23, traveller 4 and spacing rack 5, makes the controllability of fire control standpipe realize.
Two frames of the adjacent fixed limit frame 2 of the limit rack 5 are symmetrically provided with a second threaded hole 12 penetrating through the second locking bolt 8, one side of the second outer clamping block 21 is welded with a second bearing block 22, one side end of the second locking bolt 8 which is symmetrical is in interference fit with the second bearing block 22, the second outer clamping block 21 is far away from one side curved surface of the second bearing block 22 and is provided with a rubber pad 19 which is in flexible contact with the fire-fighting vertical pipe, and the damage deformation caused by the extrusion of the fire-fighting vertical pipe by the second outer clamping block 21 can be effectively reduced.
Tooth meshing of spacing rack 5 is connected with limit gear 13, limit gear 13 is inside to run through have with 16 interference fit's of bearing ring pivot 15, 16 one end of bearing ring is kept away from in pivot 15 runs through and installs gag lever post 14, interval according to upper and lower fire control standpipe, through rotating gag lever post 14, drive pivot 15, then drive limit gear 13, again because the outer clamp splice of second 21 is under the fixed of fire control standpipe, spacing rack 5 meshes under limit gear 13's rotation and connects and drive the vertical removal of fire control standpipe on traveller 4, be used for adjusting the interval between the fire control standpipe of fire control standpipe and below, be convenient for the installation of fire control clamp.
The working principle is as follows:
this auxiliary device of fire control standpipe construction runs through the device inside with the fire control standpipe, passes the reservation hole of floor fire control, when the fire control standpipe is comparatively close with below fire control standpipe, arranges base 1 in the fire control in the same direction as the fire control standpipe and reserves the hole top, adjusts hexagon nut 20, makes 7 chucking fire control reservation holes of screw thread sickle card, makes base 1 reach horizontal position and fix on fire control reservation hole, plays stable effect to whole device.
Adjust first locking bolt 6, make first outer clamp splice 17 press from both sides tight fire control standpipe, advance to continue to adjust second locking bolt 8, make the outer clamp splice 21 of second further carry out vertical fixed to the fire control standpipe, solve the condition of installation fire control standpipe slope and take place.
According to the low side of top fire control standpipe and the interval on the top of below fire control standpipe, for the installation fire control clamp, rotate gag lever post 14, rotate limit gear 13, limit gear 13 drives the vertical removal of fire control standpipe is connected in the tooth meshing of limit rack 5, makes the fire control clamp reach the installation condition.
The above description is only the specific implementation manner of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art should be covered within the protection scope of the present invention in the technical scope disclosed by the present invention, according to the technical solution of the present invention and the concept of the present invention, equivalent replacement or change is added.

Claims (6)

1. The utility model provides an auxiliary device of fire control standpipe construction, includes base (1) and installs fixed spacing frame (2) in its top perpendicularly, its characterized in that: the frame of base (1) runs through to install and is used for the block to fix at screw thread sickle card (7) of the hole of reserving in the construction, fixed establishment (3) are installed to the frame top surface of base (1), fixed establishment (3) are including the same first fixed block (31), second fixed block (32), third fixed block (33) and fourth fixed block (34) of size, fixed establishment (3) run through have first locking bolt (6), first outer clamp splice (17) of fixed fire control standpipe are installed to first locking bolt (6) press close to fixed establishment (3) inner wall one end, fourth fixed block (34) top surface runs through perpendicularly and installs spacing rack (5), first fixed block (31), second fixed block (32) and third fixed block (33) top surface install traveller (4), just traveller (4) run through fixed spacing frame (2) perpendicularly, two frame symmetries of spacing rack (5) adjacent fixed spacing frame (2) have run through second locking bolt (8), the one end inner casing (2) of second locking bolt (8) are pressed close to the one end spacing clamp (21) of second outer frame (2).
2. The auxiliary device for fire control standpipe construction of claim 1, wherein: smooth hole (9) that run through screw thread sickle card (7) are seted up to base (1) frame horizontal direction, just one end threaded connection that base (1) inner wall was kept away from in screw thread sickle card (7) has hexagon nut (20) with base (1) outer wall contact.
3. The auxiliary device for fire-fighting standpipe construction, according to claim 2, is characterized in that: fixing mechanism (3) transversely offer first screw hole (10) that run through first locking bolt (6), first outer clamp splice (17) are close to first locking bolt (6) side welding and have first bearing piece (18), just first bearing piece (18) and first locking bolt (6) interference fit, first outer clamp splice (17) are kept away from first bearing piece (18) one side curved surface and are installed rubber pad (19) with fire control standpipe flexible contact.
4. The auxiliary device for fire control standpipe construction of claim 3, wherein: the fixed limiting frame (2) is vertically provided with a rectangular through hole (11) and a limiting through hole (23) for the limiting rack (5) to penetrate through, the sliding column (4) smoothly penetrates through the rectangular through hole (11), and the inner wall of one side, adjacent to the limiting through hole (23), through which the limiting rack (5) penetrates is welded with a bearing ring (16).
5. The auxiliary device for fire-fighting standpipe construction, according to claim 4, is characterized in that: the tooth meshing of spacing rack (5) is connected with limiting gear (13), limiting gear (13) inside run through have with bearing ring (16) interference fit's pivot (15), pivot (15) are kept away from bearing ring (16) one end and are run through and install gag lever post (14).
6. The auxiliary device for fire-fighting standpipe construction, according to claim 5, is characterized in that: two frame symmetries of the adjacent fixed spacing frame (2) of spacing rack (5) are seted up second screw hole (12) that run through second locking bolt (8), the welding of the outer clamp splice (21) side of second has second bearing piece (22), just the relative side of second locking bolt (8) of symmetry all with second bearing piece (22) interference fit, the outer clamp splice (21) of second is kept away from second bearing piece (22) one side curved surface and is installed rubber pad (19) with fire control standpipe flexible contact.
CN202222317230.3U 2022-08-31 2022-08-31 Auxiliary device for construction of fire-fighting vertical pipe Active CN218193652U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222317230.3U CN218193652U (en) 2022-08-31 2022-08-31 Auxiliary device for construction of fire-fighting vertical pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222317230.3U CN218193652U (en) 2022-08-31 2022-08-31 Auxiliary device for construction of fire-fighting vertical pipe

Publications (1)

Publication Number Publication Date
CN218193652U true CN218193652U (en) 2023-01-03

Family

ID=84629836

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222317230.3U Active CN218193652U (en) 2022-08-31 2022-08-31 Auxiliary device for construction of fire-fighting vertical pipe

Country Status (1)

Country Link
CN (1) CN218193652U (en)

Similar Documents

Publication Publication Date Title
CN218193652U (en) Auxiliary device for construction of fire-fighting vertical pipe
CN218438404U (en) Self-adaptive size protective railing
CN211396543U (en) Telescopic channel steel cantilever beam device
CN212050050U (en) Car guide system
CN212743330U (en) Heightening device for connection of climbing frame and building structure
CN218623500U (en) Building construction bearing structure
CN111531719A (en) Chemical grouting mixing tank with stable structure and mounting method thereof
CN213062869U (en) I-steel scaffold frame of encorbelmenting that pole setting formula is connected
CN213203823U (en) Bridge construction is with assembled bracket
CN210414436U (en) Supporting device for maintenance of sewage pipeline
CN210395735U (en) Installation and construction assembly of prefabricated shear wall
CN212028048U (en) Gear pump with protective structure
CN214462521U (en) Climbing device for mounting hydraulic formwork in building construction
CN216663771U (en) Lifting device of hydraulic creeping formwork for ultrahigh hollow thin-wall pier
CN217581129U (en) Climbing frame connecting device with anti-drop function
CN220203120U (en) Anti-drop installation device for high-altitude building curtain wall
CN212336331U (en) Bracket for hoisting steel truss for large span of large roof of archaized building
CN211173843U (en) But flood prevention device of autonomous control length based on municipal water conservancy
CN217266912U (en) Integral hydraulic pressure guardrail construction auxiliary structure of bridge
CN211764745U (en) Double-ball adjustable trailer arm
CN218406425U (en) Lifting scaffold attaches wall support off-load shore strutting arrangement
CN216785520U (en) Fall-proof pneumatic hoist hanging beam safety device
CN216476260U (en) Connecting device of climbing frame
CN214885302U (en) Assembled building safety construction platform
CN209977642U (en) Fixing device for traffic flow monitoring equipment