CN218154281U - Cyclone and outlet flue combined supporting and hanging structure - Google Patents

Cyclone and outlet flue combined supporting and hanging structure Download PDF

Info

Publication number
CN218154281U
CN218154281U CN202222483281.3U CN202222483281U CN218154281U CN 218154281 U CN218154281 U CN 218154281U CN 202222483281 U CN202222483281 U CN 202222483281U CN 218154281 U CN218154281 U CN 218154281U
Authority
CN
China
Prior art keywords
cyclone
otic placode
supporting beam
export flue
flue
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222483281.3U
Other languages
Chinese (zh)
Inventor
钱素梅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuxi Huaguang Environment and Energy Group Co Ltd
Original Assignee
Wuxi Huaguang Environment and Energy Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuxi Huaguang Environment and Energy Group Co Ltd filed Critical Wuxi Huaguang Environment and Energy Group Co Ltd
Priority to CN202222483281.3U priority Critical patent/CN218154281U/en
Application granted granted Critical
Publication of CN218154281U publication Critical patent/CN218154281U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Fluidized-Bed Combustion And Resonant Combustion (AREA)

Abstract

The utility model relates to a boiler hoist and mount part technical field specifically is a cyclone jointly hangs structure with export flue, and it can reduce the total height of boiler, thereby reduces the use of jib and reduces steel consumption, shortens product production cycle, and it includes cyclone and export flue, cyclone with it props up a supporting beam rigid layer to be provided with between the export flue, it has first otic placode to prop up supporting beam rigid layer bottom welded fastening, cyclone outer wall interval welding has the second otic placode, first otic placode with the position corresponds and connects through the connecting rod about the second otic placode, export flue side outer wall welding have support in prop up the support on the supporting beam rigid layer.

Description

Cyclone and outlet flue combined supporting and hanging structure
Technical Field
The utility model relates to a boiler hoist and mount part technical field specifically is a cyclone and export flue joint hang structure.
Background
Traditional cyclone hangs on the roof of boiler export flue top through many jibs respectively with the export flue, has increased the total height of boiler, has increased the quantity of jib to boiler steel consumption has been increased. In addition, the hanger rod needs a certain period for production, the period of product production is prolonged, and the workload of workshop production is increased.
Disclosure of Invention
In order to solve the problem that current boiler height is too high, boiler steel consumption is big, product production cycle is long, the utility model provides a cyclone jointly props up with the export flue and hangs the structure, its total height that can reduce the boiler reduces thereby the use of jib and reduces steel consumption, shortens product production cycle.
The technical scheme is as follows: the utility model provides a cyclone and export flue are jointly supported and hang structure, its includes cyclone and export flue, its characterized in that, cyclone with be provided with a supporting beam rigidity layer between the export flue, a supporting beam rigidity layer bottom welded fastening has first otic placode, cyclone outer wall interval welding has the second otic placode, first otic placode with the second otic placode is upper and lower position corresponds and is connected through the connecting rod, export flue side outer wall welding have support in support on the supporting beam rigidity layer.
The connecting rod is further characterized in that two ends of the connecting rod are respectively hinged with the first lug plate and the second lug plate through pin shafts.
Adopt the utility model discloses afterwards, cyclone and export the hanging in midair of flue and support all concentrate on a supporting beam rigidity layer, saved the jib of pulling up originally for the total height of boiler obtains reducing, and the jib replaces with ordinary connecting rod and otic placode, and processing is simple, and length also shortens in addition, has reduced the steel quantity, has shortened product production cycle.
Drawings
FIG. 1 is a schematic view of the present invention;
fig. 2 is an enlarged view ofbase:Sub>A sectionbase:Sub>A-base:Sub>A in fig. 1.
Detailed Description
See fig. 1 and fig. 2, a cyclone and outlet flue combined supporting and hanging structure comprises a cyclone 1 and an outlet flue 2, a supporting beam rigid layer 3 is arranged between the cyclone 1 and the outlet flue 2, a first lug plate 4 is welded and fixed at the bottom of the supporting beam rigid layer 3, second lug plates 5 are welded on the outer wall of the cyclone 1 at intervals, the first lug plates 4 correspond to the second lug plates 5 in the upper-lower positions and are connected through connecting rods 6, and a support 7 supported on the supporting beam rigid layer 3 is welded on the outer wall of the side face of the outlet flue 2.
Two ends of the connecting rod 6 are respectively hinged with the first lug plate 4 and the second lug plate 5 through a pin shaft 8, and the connecting rod 6 is arranged to avoid a connecting flue of the cyclone separator 1 and the hearth.
The utility model discloses on concentrating on a supporting beam rigidity layer 3 with cyclone 1's hoist and mount, export flue 2 changes the support into from hoist and mount, and at side outer wall welded support 7, support on a supporting beam rigidity layer 3, the whole height of boiler obtains reducing, and the steel quantity also significantly reduces reduce cost.

Claims (2)

1. The utility model provides a cyclone and export flue are jointly supported and hang structure, its includes cyclone and export flue, its characterized in that, cyclone with be provided with a supporting beam rigidity layer between the export flue, a supporting beam rigidity layer bottom welded fastening has first otic placode, cyclone outer wall interval welding has the second otic placode, first otic placode with the second otic placode is upper and lower position corresponds and is connected through the connecting rod, export flue side outer wall welding have support in support on the supporting beam rigidity layer.
2. The cyclone separator and outlet flue combined supporting and hanging structure as claimed in claim 1, wherein two ends of the connecting rod are respectively hinged with the first ear plate and the second ear plate through pin shafts.
CN202222483281.3U 2022-09-20 2022-09-20 Cyclone and outlet flue combined supporting and hanging structure Active CN218154281U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222483281.3U CN218154281U (en) 2022-09-20 2022-09-20 Cyclone and outlet flue combined supporting and hanging structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222483281.3U CN218154281U (en) 2022-09-20 2022-09-20 Cyclone and outlet flue combined supporting and hanging structure

Publications (1)

Publication Number Publication Date
CN218154281U true CN218154281U (en) 2022-12-27

Family

ID=84563529

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222483281.3U Active CN218154281U (en) 2022-09-20 2022-09-20 Cyclone and outlet flue combined supporting and hanging structure

Country Status (1)

Country Link
CN (1) CN218154281U (en)

Similar Documents

Publication Publication Date Title
CN201268938Y (en) Corner hanging cradle for working aloft
CN218154281U (en) Cyclone and outlet flue combined supporting and hanging structure
CN104925680B (en) A kind of method of stabilizer tower crane body
CN101665211A (en) Lifting appliance for installing last furnace shell
CN201343543Y (en) Movable hanging scaffold for installing hot blast furnace
CN204782207U (en) Supporting structure of be used for chimney steel inner tube
CN205476397U (en) Bayonet supporting platform of chimney inner tube
CN201261681Y (en) Sling for mounting RH furnace circulating pipe
CN209618648U (en) A kind of lifting lift hanger
CN201809040U (en) Mobile loading platform for hoisting coal economizer of alkali recovery boiler
CN209442510U (en) A kind of suspender for brake hub lifting
CN203568661U (en) Built-in tail-sliding lifting lug
CN214090329U (en) Roof horizontal support hanging device
CN208561432U (en) A kind of composite plate lifting stiffening device
CN212334396U (en) Upper arch type balance beam
CN212562391U (en) Hanging flower basket support device that convenient removed
CN212835455U (en) Supporting angle device for steel suspension box cofferdam lowering system
CN209760032U (en) Bottom die of truss hanging basket
CN219510289U (en) Pipeline support protection device for foundation pit side wall construction
CN206188210U (en) Gasifier drive arrangement dismouting special lifting device
CN218754763U (en) Internal support sleeve mechanism for lifting and supporting pole inverted assembly
CN217478836U (en) Be used for fluidized bed boiler drum hanging beam arrangement structure
CN212050435U (en) Pneumatic lifting device for hanging basket
CN216807892U (en) Variable cross-section tower crane section
CN220845904U (en) Hanging bridge brick for combined tin bath top cover brick structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant