CN218149148U - Face and build multi-functional assembled ground of engineering - Google Patents

Face and build multi-functional assembled ground of engineering Download PDF

Info

Publication number
CN218149148U
CN218149148U CN202221672533.0U CN202221672533U CN218149148U CN 218149148 U CN218149148 U CN 218149148U CN 202221672533 U CN202221672533 U CN 202221672533U CN 218149148 U CN218149148 U CN 218149148U
Authority
CN
China
Prior art keywords
unit plate
unit
floor
assembled
angle steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221672533.0U
Other languages
Chinese (zh)
Inventor
陈建申
朱江
王长勇
左发伟
唐海
周超
叶安波
朱雨龙
丁玉琦
梁文清
曹磊
杜丽君
吴建钢
肖亮
杨勇
雷春梅
邓如丽
高智
岑健
杨德斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 8 Engineering Group Co Ltd
Seventh Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Original Assignee
China Railway No 8 Engineering Group Co Ltd
Seventh Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 8 Engineering Group Co Ltd, Seventh Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd filed Critical China Railway No 8 Engineering Group Co Ltd
Priority to CN202221672533.0U priority Critical patent/CN218149148U/en
Application granted granted Critical
Publication of CN218149148U publication Critical patent/CN218149148U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model discloses a face multi-functional assembled ground of building engineering, including the unit plate, the unit plate is rectangle platelike structure, and rectangle platelike structure's unit plate includes long limit and minor face, and long limit and minor face handing-over department are unit plate corner, unit plate corner transversely adopts 50 equilateral angle steel indent, and the vertical 30 equilateral angle steel that adopt of unit plate corner forms vertical prefabricated breach, 50 equilateral angle steel indent and 30 equilateral angle steel form vertical prefabricated breach combination, and adjacent unit plate splices, splices the reservation pore that the concatenation edge forms the unit plate. The utility model discloses a design assembled unit template, guarantee the drainage function and the temporary line reservation on ground when satisfying the terrace sclerosis, make things convenient for the maintenance of cable; after the construction project is completed, the fabricated ground can be dismantled and transported to the next construction site for rapid laying and construction; the utilization rate of the concrete is improved, and the pollution to the environment is reduced.

Description

Face and build multi-functional assembled ground of engineering
Technical Field
The utility model relates to a technical field of building engineering construction, concretely relates to building trade faces building engineering multifunctional assembly ground.
Background
At present, in the building trade, it is big to face building engineering office area and the regional harden area of non-bearing road, and required concrete volume is great, and large tracts of land concreting terrace exists and looks for the slope difficulty, the serious condition of ponding, simultaneously because large tracts of land construction terrace monoblock is pour, reserves the pipeline difficulty, leads to interim cable arrangement confusion in the later stage work progress, if the cable arranges along the ditch, increases the cable quantity. And finally, after the construction is finished, the building engineering needs to be dismantled, the generated dust is large, the environmental pollution is large, the building slag needs to be transported outside, and the dismantling cost is large.
The utility model patent application with application number CN202021400323.7 discloses a can have enough to meet need full assembled concrete and face and build prefabricated basis of board house. Can have enough to meet need full assembled concrete and face prefabricated basis of building board house and include: a concrete foundation; one end of the first embedded part is arranged in the concrete foundation, and the other end of the first embedded part extends out of the concrete foundation and is used for connecting a wallboard; one end of the second embedded part is arranged in the concrete foundation, and the other end of the second embedded part extends out of the concrete foundation and is used for connecting a prefabricated floor slab; the first embedded parts are mutually spaced and uniformly distributed along the same direction, and the second embedded parts are mutually spaced and uniformly distributed along the same direction. The utility model discloses a through first built-in fitting, second built-in fitting pre-buried in the concrete foundation respectively to form a whole prefabricated component, the component is accomplished in producer production and processing, and the scene can directly be assembled, has realized the quick hoist and mount operation of this assembled structure system. But this application is applied to large tracts of land construction terrace monoblock and pours, and it is serious to fail to solve ponding, the difficult condition of drainage, has the reservation pipeline difficulty simultaneously, the chaotic condition of pipeline arrangement.
SUMMERY OF THE UTILITY MODEL
The utility model discloses an invention aim at provides a face and build multi-functional assembled ground of engineering to above-mentioned problem that exists, including the unit plate, the unit plate is rectangle platelike structure, and the unit plate of rectangle platelike structure includes long limit and minor face, and long limit and minor face handing-over department are unit plate corner, the unit plate corner transversely adopts 50 equilateral angle indent, and the unit plate corner is vertical to adopt 30 equilateral angle steel to form vertical prefabricated breach, 50 equilateral angle steel indent and 30 equilateral angle steel form vertical prefabricated breach combination, and adjacent unit plate concatenation, concatenation edge forms the reserve pore of unit plate. The utility model discloses a design assembled unit template, guarantee the drainage function and the temporary line reservation on ground when satisfying the terrace sclerosis, make things convenient for the maintenance of cable; after the construction project is completed, the fabricated ground can be dismantled and transported to the next construction site for rapid laying and construction; the utilization rate of the concrete is improved, and the pollution to the environment is reduced.
The utility model adopts the technical scheme as follows:
the utility model discloses a face and build multi-functional assembled ground of engineering, including the unit plate, the unit plate is rectangle platelike structure, and rectangle platelike structure's unit plate includes long limit and minor face, and long limit and minor face handing-over department are unit plate corner, the unit plate corner transversely adopts 50 equilateral angle steel indent, and the vertical adoption of unit plate corner is the vertical prefabricated breach of 30 equilateral angle steel formation, 50 equilateral angle steel indent and 30 equilateral angle steel formation vertical prefabricated breach combination, adjacent unit plate concatenation, concatenation edge forms the reservation pore of unit plate.
Furthermore, the fabricated floor comprises a plurality of unit plates which are spliced and combined, adjacent unit plates are spliced, reserved holes of the unit plates are formed at the splicing corners of the outer edges of the unit plates, and temporary cable drainage holes or drainage holes of the fabricated floor are formed in the reserved holes of the outer edges of the unit plates for use.
Furthermore, the fabricated floor comprises a plurality of unit plates which are spliced and combined, four adjacent unit plates are spliced and combined to form a single fabricated floor unit, and the middle part of the single fabricated floor unit forms a reserved hole channel of the unit plate.
Furthermore, the reserved hole channels of the unit plate blocks formed in the middle of the single fabricated ground unit are inspection holes of the fabricated ground, and the inspection holes are plugged by plastic plugs.
Furthermore, a temporary cable drainage hole or a drainage hole on the assembly type ground is formed by a reserved hole on the outer edge of the unit plate, and the drainage hole is filled with coarse sand.
Furthermore, a single-layer steel bar mesh is arranged in the unit plate block of the fabricated ground, the longitudinal and transverse spacing of the steel bar mesh is 20cm, the thickness of the protective layer is 2.5cm, and the single-layer steel bar mesh adopts HRB phi 8 type steel bars.
Furthermore, the long side and the short side of the unit plate are designed according to the proportion of 3:1, the long side of the unit plate is designed to be larger than or equal to 3000mm, and the short side of the unit plate is designed to be larger than or equal to 1000mm.
The technical effects of the utility model are as follows:
the utility model discloses a face multi-functional assembled ground of building engineering, it is convenient, swift to have the construction in building engineering faces the building engineering, shortens construction period, improves the availability factor of concrete in the building engineering simultaneously, reduce cost; assembled ground has the advantage that drainage is good, convenient maintenance, ann tears open in the use, makes things convenient for temporary works to face arranging of electric cable simultaneously.
The method comprises the following specific steps:
1. the utility model discloses a drainage problem on installation back large tracts of land ground is just considered in prefabricated phase on assembled ground, guarantees the place and in time gets rid of ponding after the rainfall or wash, and this novel ground reservation pore can regard as interim cable winding displacement hole simultaneously, conveniently faces arranging of cable in the electric construction, reduces wiring engineering volume.
2. The utility model discloses an assembled ground, after construction engineering construction was accomplished, assembled ground continued to be used as the turnover material transport to next project. The method reduces the pollution to the environment and the treatment cost of the building residues in the breaking process, effectively improves the utilization rate of the concrete, and reduces the pollution to the environment.
Drawings
FIG. 1 is a schematic view of the multifunctional assembled floor for construction works of the present invention;
FIG. 2 is a schematic cross-sectional view B-B of the multi-functional fabricated floor of the construction project;
FIG. 3 is a schematic cross-sectional view C-C of the multi-functional fabricated floor of the construction project;
FIG. 4 is a schematic view of a section A of a multi-functional fabricated floor of the construction project;
FIG. 5 is a schematic view of a unit plate structure;
the labels in the figure are: 1-unit plate, 2-50 equal-side angle steels, 3-30 equal-side angle steels, 4-reserved pore canals, 401-temporary cables, 402-drainage holes and 403-inspection holes.
Detailed Description
The present invention will be described in detail with reference to the accompanying drawings.
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention will be further described in detail with reference to the accompanying drawings and embodiments.
In this embodiment, the adopted data is a preferred scheme, but is not used to limit the present invention;
example 1
As shown in fig. 1-5, this embodiment provides a face and build multi-functional assembled ground of engineering, including the unit plate, the unit plate is rectangular plate-like structure, and the unit plate of rectangular plate-like structure includes long limit and minor face, and long limit and minor face handing-over department are unit plate corner, the unit plate corner transversely adopts 50 equilateral angle indent, and the vertical 30 equilateral angle that adopt of unit plate corner forms vertical prefabricated breach, 50 equilateral angle indent and 30 equilateral angle form vertical prefabricated breach combination, and adjacent unit plate splices, and concatenation edge forms the reserve tunnel of unit plate.
In this embodiment, the long side and the short side of the unit plate are designed in a ratio of 3:1, the long side of the unit plate is designed to be greater than or equal to 3000mm, the short side of the unit plate is designed to be greater than or equal to 1000mm, and preferably, in this embodiment, the thickness of the unit plate is set to be 100mm; the height and the width of the 50 equal-edge angle steel pressing groove are both 50mm; the height and the width of the vertical prefabricated gap formed by the 30 equal-edge angle steels are both 30mm; the long side of each unit plate is designed to be 3000mm, and the short side of each unit plate is designed to be 1000mm; the size of the single unit plate provided by the embodiment reaches 3000 × 1000mm to satisfy the use requirement of large-area pouring concrete terrace, the embodiment adopts the splicing unit plate to form the fabricated ground, and after the construction of the construction project is completed, the fabricated ground is used as a turnover material to be transferred to the next project for continuous use. Reduces the pollution to the environment and the cost for slag building treatment in the breaking process.
Example 2
As shown in fig. 1-5, this embodiment provides a face multi-functional assembled ground of building engineering, including the unit plate, the unit plate is rectangle platelike structure, and the unit plate of rectangle platelike structure includes long limit and minor face, and long limit and minor face handing-over department are unit plate corner, unit plate corner transversely adopts 50 equilateral angles indent, and the unit plate corner is vertical to adopt 30 equilateral angles to form vertical prefabricated breach, 50 equilateral angles indent and 30 equilateral angles form vertical prefabricated breach combination, and adjacent unit plate concatenation, concatenation edge forms the reservation pore of unit plate.
In this embodiment, the fabricated floor includes a plurality of unit plates, adjacent unit plates are spliced, a reserved hole of the unit plate is formed at a splicing corner of the outer edge of the unit plate, and the reserved hole of the outer edge of the unit plate forms a temporary cable drainage hole or a temporary drainage hole of the fabricated floor for use. Furthermore, a temporary cable drainage hole or a drainage hole on the fabricated ground is formed in a reserved hole in the outer edge of the unit plate, the drainage hole is filled with coarse sand, building residues can be generated in the construction process and can enter the drainage hole to cause drainage blockage, the coarse sand is arranged to fill the drainage hole to prevent the drainage hole from being blocked, and meanwhile, the drainage is ensured to be smooth.
In this embodiment, four corners of unit plate all adopt 30 equilateral angle steel vertical prefabrication a breach, as laying the back of accomplishing in the later stage, interim cable threading pilot hole with ann tears the power position open. The assembly type ground of the embodiment takes the drainage problem of the large-area ground after installation into consideration in the prefabrication period, and ensures that accumulated water is drained in time after rainfall or flushing; meanwhile, the reserved hole channel can be used as a temporary cable arrangement hole on the basis of the use of the drainage hole, so that the arrangement of cables in the temporary power construction is facilitated, and the wiring engineering quantity is reduced; when the reserved holes are used for the temporary cable arranging holes, coarse sand is not used for plugging the holes.
In this embodiment, the fabricated floor includes a plurality of unit plates, four adjacent unit plates are spliced to form a single fabricated floor unit, and the middle of the single fabricated floor unit forms a reserved hole of the unit plate. Furthermore, the reserved hole channels of the unit plate blocks formed in the middle of the single fabricated ground unit are inspection holes in the fabricated ground, the inspection holes are plugged by plastic plugs, and meanwhile, the flatness of the inspection holes is guaranteed.
In this embodiment, the inspection hole may be used for installation and inspection of a pipeline and for maintenance and repair of the pipeline, and further, the inspection hole is communicated with a temporary cable drainage hole or a drainage hole formed in a reserved hole on the outer edge of the unit plate to form an assembly-type floor, and drainage is performed on a large area of the assembly-type floor, and accumulated water on the assembly-type floor may flow through the inspection hole to the drainage hole to be drained.
Example 3
As shown in fig. 1-5, this embodiment provides a face multi-functional assembled ground of building engineering, including the unit plate, the unit plate is rectangle platelike structure, and the unit plate of rectangle platelike structure includes long limit and minor face, and long limit and minor face handing-over department are unit plate corner, unit plate corner transversely adopts 50 equilateral angles indent, and the unit plate corner is vertical to adopt 30 equilateral angles to form vertical prefabricated breach, 50 equilateral angles indent and 30 equilateral angles form vertical prefabricated breach combination, and adjacent unit plate concatenation, concatenation edge forms the reservation pore of unit plate.
In this embodiment, the unit plate is prefabricated and molded, 50 equal-edge angle steels and 30 equal-edge angle steels are adopted for prefabricating holes, the overall dimension of the wood block unit is ensured after demolding, a single-layer reinforcing mesh is arranged in the unit plate, reinforcing steel bars are arranged at the lower part of the unit plate, the longitudinal and transverse intervals of the reinforcing mesh are 20cm, the thickness of a protective layer is 2.5cm, the single-layer reinforcing mesh is made of the reinforcing steel bars with the size of HRB phi 8, and therefore reasonable stress of the fabricated ground is ensured in the using process.
In this embodiment, after the unit blocks are prefabricated, the unit blocks are transported to a construction site, the original ground is firstly leveled and rolled, the unit blocks are arranged according to the plane shape of the site, and coarse sand is laid according to the size of the unit blocks before the unit blocks are assembled according to squares. Finally, the unit plates are placed on the laid grids, and the arrangement of the drainage system and the reserved temporary power pipe network is completed.
The above description is only a preferred embodiment of the present invention and should not be construed as limiting the present invention, and any modifications, equivalent replacements, and improvements made within the spirit and principle of the present invention should be included within the scope of the present invention.

Claims (7)

1. The utility model provides a face and build multi-functional assembled ground of engineering, its characterized in that, includes unit plate (1), and unit plate (1) is rectangle platelike structure, and unit plate (1) of rectangle platelike structure is including long limit and minor face, and long limit and minor face handing-over department are unit plate (1) corner, unit plate (1) corner transversely adopts 50 equilateral angle steel (2) indent, and unit plate (1) corner is vertical to adopt 30 equilateral angle steel (3) to form vertical prefabricated breach, 50 equilateral angle steel (2) indent and 30 equilateral angle steel (3) form vertical prefabricated breach combination, and adjacent unit plate (1) splice, and concatenation edge forms reserved pore (4) of unit plate (1).
2. The temporary assembled floor of construction engineering according to claim 1, wherein the assembled floor comprises a plurality of unit plates (1) which are assembled together, adjacent unit plates (1) are assembled together, the assembled edge of the unit plate (1) forms a reserved hole (4) of the unit plate (1), and the reserved hole (4) of the unit plate (1) forms a temporary cable (401) drainage hole or a drainage hole (402) of the assembled floor.
3. The temporary construction engineering multifunctional fabricated floor as claimed in claim 2, wherein the fabricated floor comprises a plurality of unit panels (1) which are spliced and combined, four adjacent unit panels (1) are spliced and combined to form a single fabricated floor unit, and the middle part of the single fabricated floor unit forms the reserved hole (4) of the unit panel (1).
4. The multi-functional fabricated floor of temporary construction engineering according to claim 3, characterized in that the reserved hole channels (4) of the unit plates (1) formed in the middle of the single fabricated floor unit are inspection holes (403) of the fabricated floor, and the inspection holes (403) are sealed by plastic plugs.
5. The temporary assembled floor for temporary buildings according to claim 2 or 4, wherein the preformed hole (4) on the outer edge of the unit plate block (1) forms a temporary cable (401) line arranging hole or a drainage hole (402) of the assembled floor, and the drainage hole (402) is filled with coarse sand.
6. The multi-functional fabricated floor of claim 5, wherein a single-layer steel bar net is arranged in the unit slabs (1) of the fabricated floor, the longitudinal and transverse intervals of the steel bar net are 20cm, the thickness of the protective layer is 2.5cm, and the single-layer steel bar net is made of HRB phi 8 type steel bars.
7. The temporary construction engineering multifunctional fabricated floor as claimed in claim 1 or 6, wherein the long side and the short side of the unit plate block (1) are designed in proportion of 3:1, the long side size of the unit plate block (1) is designed to be greater than or equal to 3000mm, and the short side size of the unit plate block (1) is designed to be greater than or equal to 1000mm.
CN202221672533.0U 2022-06-30 2022-06-30 Face and build multi-functional assembled ground of engineering Active CN218149148U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221672533.0U CN218149148U (en) 2022-06-30 2022-06-30 Face and build multi-functional assembled ground of engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221672533.0U CN218149148U (en) 2022-06-30 2022-06-30 Face and build multi-functional assembled ground of engineering

Publications (1)

Publication Number Publication Date
CN218149148U true CN218149148U (en) 2022-12-27

Family

ID=84577716

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221672533.0U Active CN218149148U (en) 2022-06-30 2022-06-30 Face and build multi-functional assembled ground of engineering

Country Status (1)

Country Link
CN (1) CN218149148U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117286755A (en) * 2023-09-28 2023-12-26 河北交投路桥建设开发有限公司 Efficient asphalt concrete road construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117286755A (en) * 2023-09-28 2023-12-26 河北交投路桥建设开发有限公司 Efficient asphalt concrete road construction method

Similar Documents

Publication Publication Date Title
US6434900B1 (en) Prefabricated concrete wall system
US20110011018A1 (en) Modular construction mold apparatus and method for constructing concrete buildings and structures
CN108252329B (en) Assembly type comprehensive pipe gallery for bearing force of enclosure structure and construction method thereof
CN106555408A (en) The structure and construction method of underground pipe gallery
CN110295700A (en) Assembled Sloping roof construction method
CN218149148U (en) Face and build multi-functional assembled ground of engineering
CN103046578A (en) Thin wall prefabricated superposed concrete underground continuous wall
CN105714849A (en) Reverse construction method for adjacent high and low floors (bays) of basement
CN110644662A (en) Prefabricated flat slab composite slab based on stress and splitting method thereof
CN106760173B (en) Prefabricated plate at post-pouring zone of basement outer wall
CN206376277U (en) The structure of underground pipe gallery
CN110130934B (en) Construction method of urban tunnel branch junction with box-type top plate structure
CN109356126B (en) Semi-prefabricated gallery structure and gallery construction method
CN210002441U (en) Box-type top plate structure for large-span urban tunnel
CN209875164U (en) Box-type top plate structure of urban tunnel branch
CN114164978A (en) One-way multi-ribbed cavity floor module for steel structure and construction method thereof
CN214364434U (en) Assembled constructional column suitable for prefabricated wallboard of frame construction
CN210134453U (en) Integral utility tunnel of environment-friendly prefabricated assembly
CN114232865A (en) One-way multi-ribbed cavity floor module for steel structure and construction method thereof
CN211037527U (en) Take vertical connected node structure of floor is assembled to full assembled of hidden beam
CN211691450U (en) Slurry leakage prevention device for prefabricated side embedded steel bars of laminated slab beam
CN108360567A (en) The reversed construction method in precast assembly tunnel
CN211229002U (en) Prefabricated multi-rib thin-wall cavity shear wall
CN114319410A (en) Wind power generation grid-connected power equipment assembly type foundation structure and installation construction process
CN210134455U (en) Integral utility tunnel of environment-friendly prefabricated assembly

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant