CN218106608U CN202221663045.3U CN202221663045U CN218106608U CN 218106608 U CN218106608 U CN 218106608U CN 202221663045 U CN202221663045 U CN 202221663045U CN 218106608 U CN218106608 U CN 218106608U
Authority
CN
China
Prior art keywords
pole setting
pole
supporting beam
support frame
rope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221663045.3U
Other languages
Chinese (zh)
Inventor
张鹏翔
杨洪超
陈东
袁冬冬
曹怀强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Metallurgical Construction Engineering Group Co Ltd
Original Assignee
China Metallurgical Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Metallurgical Construction Engineering Group Co Ltd filed Critical China Metallurgical Construction Engineering Group Co Ltd
Priority to CN202221663045.3U priority Critical patent/CN218106608U/en
Application granted granted Critical
Publication of CN218106608U publication Critical patent/CN218106608U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Emergency Lowering Means (AREA)

Abstract

The utility model belongs to the technical field of construction and specifically relates to a temporary safety belt linkage is related to, it is including connecting rope and a plurality of support frame, a supporting beam is set up to the support frame, and the support frame butt is in the foundation ditch bottom, connect the rope and connect the top in a plurality of support frames simultaneously, the support frame includes first pole setting, second pole setting and first horizontal pole, the equal butt in the foundation ditch bottom of lower extreme of first pole setting and second pole setting, and first pole setting and second pole setting are located a supporting beam's both sides respectively, a supporting beam top is set up to first horizontal pole, and the both ends of first horizontal pole difference fixed connection in first pole setting and second pole setting, it is fixed in a plurality of first pole settings simultaneously to connect the rope. This application has the effect of the construction safety when guaranteeing constructor operation on a supporting beam.

Description

Temporary safety belt hanging device
Technical Field
The application relates to the field of building construction, in particular to a temporary safety belt hanging device.
Background
Today, the foundation ditch is in the excavation process, can set up supporting beam inside the foundation ditch usually, simultaneously, and partial supporting beam below still can be provided with the horizontally structural slab. When the foundation pit construction is carried out to a certain degree, the supporting beam is usually required to be dismantled. When the supporting beam is dismantled, the supporting beam is often cut in sections, and at the moment, a forklift or other carrying equipment is adopted to support the bottom of the supporting beam to be cut, so that the supporting beam is not easy to drop after being cut and threatens constructors.
In addition, during the process of dismantling the support beam, part of the constructors need to stand on the support beam for operation. And at this moment, be difficult to for constructor provides the hanging point that the safety belt led, and then lead to constructor to wear the safety belt after, the safety belt is difficult to fix to construction safety when making constructor operation on a supporting beam is difficult to obtain the guarantee.
Disclosure of Invention
In order to guarantee the construction safety when constructor operates on a supporting beam, this application provides a interim safety belt linkage.
The application provides a interim safety belt linkage adopts following technical scheme:
the utility model provides a temporary safety belt linkage, is including connecting rope and a plurality of support frame, the support frame is set up in a supporting beam, just the support frame butt is in the foundation ditch bottom or the structural slab of a supporting beam below, connect the rope and connect the top in a plurality of support frames simultaneously.
By adopting the technical scheme, when a constructor works on the supporting beam, the supporting frame is firstly erected on the supporting beam, and then the connecting rope is fixed on the supporting frame, so that the problem that the safety belt does not have a hanging point can be solved by the arranged connecting rope, the constructor can hang the worn safety belt on the connecting rope, and the construction safety of the constructor during working on the supporting beam is further ensured; simultaneously, a supporting beam self can also play the effect of support to the support frame, steadiness when increasing the support frame and using.
Optionally, the support frame includes first pole setting, second pole setting and first horizontal pole, the equal butt in foundation ditch bottom of lower extreme of first pole setting and second pole setting, just first pole setting and second pole setting are located a supporting beam's both sides respectively, a supporting beam top is set up to first horizontal pole, just the both ends of first horizontal pole are fixed connection in first pole setting and second pole setting respectively, first pole setting and second pole setting all are provided with a plurality of fixed pins, the fixed pin anchor is in a supporting beam or foundation ditch bottom, the connection rope is fixed in a plurality of first pole settings simultaneously.
Through adopting above-mentioned technical scheme, during the support frame installation, the first horizontal pole and the second pole setting of setting can be consolidated standing of first pole setting to guarantee the steadiness of first pole setting when standing, simultaneously, the fixed pin of setting can be to the restriction of first pole setting and second pole setting, thereby when connecting the rope and receiving the load, reduce first pole setting and second pole setting and take place the possibility of empting.
Optionally, the support frame further comprises a second cross rod, the second cross rod is located below the support beam, and two ends of the second cross rod are respectively and fixedly connected to the first vertical rod and the second vertical rod.
Through adopting above-mentioned technical scheme, the second horizontal pole can further consolidate first pole setting and second pole setting, increases the wholeness of support frame.
Optionally, a third cross bar is installed on the support frame, and the third cross bar is abutted to the lower end of the support beam.
Through adopting above-mentioned technical scheme, during the installation, the first horizontal pole and the third horizontal pole that set up can carry out the centre gripping to a supporting beam to when connecting the rope and receiving load, further reduce first pole setting and second pole setting and take place the possibility of empting.
Optionally, connecting sleeves are mounted at two ends of the third cross rod, the connecting sleeves at two ends of the third cross rod are respectively sleeved on the first vertical rod and the second vertical rod, the connecting sleeves penetrate through and are in threaded connection with tightening bolts, and the tightening bolts are abutted against the first vertical rod or the second vertical rod.
Through adopting above-mentioned technical scheme, the third horizontal pole can be relative first pole setting and the vertical slip of second pole setting when the installation, and the fastening is supported tight bolt and is locked in the position with the third horizontal pole afterwards, and then realizes carrying out the effect adjusted to the clearance between first horizontal pole and the third horizontal pole to be convenient for adapt to the supporting beam of different specifications and carry out the installation of third horizontal pole.
Optionally, first pole setting cover is established and is slided and be connected with the connecting block, the connecting block is provided with the couple that is convenient for connect the rope fixed, the connecting block is provided with the locking piece, the locking piece is used for locking the connecting block in the position.
Through adopting above-mentioned technical scheme, connect the rope when being connected with first pole setting, only need to connect the rope and bind in the couple for the couple that sets up can reduce and connect the rope and bind the possibility that appears coming off after, and the connecting block can slide first pole setting relatively, locks the connecting block in the co-altitude of first pole setting through the locking piece afterwards, thereby realizes carrying out the effect adjusted to the mounting height of connecting the rope. And then improve the convenience that the safety belt that the constructor wore is hanging and is establishing.
Optionally, the locking piece is set to be a locking bolt, the first vertical rod is provided with a plurality of fixing holes, the fixing holes are vertically distributed, and the locking bolt penetrates through the connecting block and one of the fixing holes.
Through adopting above-mentioned technical scheme, during the installation, after the connecting block slided along first pole setting, only need pass connecting block and threaded connection in the fixed orifices of position with locking bolt to can be fixed in the position at different fixed orifices places with the connecting block, realize carrying out the purpose of adjusting the mounting height of connecting the rope.
Optionally, the vertical extending limiting groove is formed in the outer wall of the first vertical rod, the connecting block is provided with a clamping portion, and the clamping portion is clamped and connected in the limiting groove in a sliding mode.
Through adopting above-mentioned technical scheme, when the connecting block slided, because joint portion and spacing groove looks joint to can do the restriction to the rotation of connecting block, and then reduce the locking bolt and take place the possibility of dislocation with the fixed orifices in first pole setting week, increase the convenience of locking bolt installation.
In summary, the present application includes at least one of the following beneficial technical effects:
1. when a constructor works on the supporting beam, the supporting frame is firstly erected on the supporting beam, and then the connecting rope is fixed on the supporting frame, so that the problem that the safety belt does not have a hanging point can be solved by the arranged connecting rope, the constructor can hang the worn safety belt on the connecting rope, and the construction safety of the constructor during working on the supporting beam is further ensured;
the connecting block can slide by first pole setting relatively, locks the connecting block in the co-altitude of first pole setting through the locking piece afterwards to the realization is to the effect of adjusting the mounting height who connects the rope. And then improve the convenience that the safety belt that constructor wore is hanging and is establishing.
Drawings
FIG. 1 is a schematic view of an installation structure of an embodiment of the present application;
FIG. 2 is a partial schematic structural view of an embodiment of the present application;
fig. 3 is an enlarged structural view of a portion a in fig. 1.
Description of the reference numerals: 1. connecting ropes; 2. a support frame; 21. a first upright stanchion; 211. a fixing hole; 212. a limiting groove; 22. a second upright stanchion; 23. a first cross bar; 24. a second cross bar; 3. a third cross bar; 31. connecting a sleeve; 32. tightly abutting against the bolt; 4. connecting blocks; 41. hooking; 42. and locking the bolt.
Detailed Description
The present application is described in further detail below with reference to figures 1-3.
The embodiment of the application discloses interim safety belt linkage. Referring to fig. 1, a temporary safety belt suspension device includes a connecting rope 1 and a plurality of support frames 2. In this embodiment, the two support frames 2 are set up to be two, the two support frames 2 are all erected on the support beam, and the support frames 2 abut against the bottom of the foundation pit, and certainly, the support frames 2 also can abut against the structural plate below the support beam. In this embodiment, the connection rope 1 is a steel wire rope, and the connection rope 1 is connected to the tops of the support frames 2 at the same time.
When constructor carries out the operation on a supporting beam, will connect earlier support frame 2 and set up in a supporting beam, will connect afterwards rope 1 and be fixed in support frame 2, preferably, set up support frame 2 in a supporting beam part section of cutting temporarily for the problem that the safety belt does not have the hanging point can be solved to the connection rope 1 that sets up. Thereby make constructor can hang the safety belt of wearing and locate and connect rope 1, and then guarantee the construction safety when constructor operates on a supporting beam. And, the support frame 2 that sets up can be to connecting rope 1 and do the support, guarantees to connect the steadiness of rope 1 when using. Simultaneously, a supporting beam self can also play the effect of support to support frame 2, the steadiness when increasing support frame 2 and using.
Referring to fig. 1, the supporting frame 2 includes a first upright 21, a second upright 22, a first cross bar 23, and a second cross bar 24. First pole setting 21 and the equal vertical extension setting of second pole setting 22, first pole setting 21 and second pole setting 22 are located a supporting beam both sides respectively, and the equal butt in foundation ditch bottom of the lower extreme of first pole setting 21 and second pole setting 22. First horizontal pole 23 sets up in a supporting beam upper end, and the both ends of first horizontal pole 23 are fixed mutually with first pole setting 21 and second pole setting 22 respectively through the fastener. And, second horizontal pole 24 is close to the foundation ditch bottom setting, and the both ends of second horizontal pole 24 are fixed mutually with first pole setting 21 and second pole setting 22 respectively through the fastener likewise.
The connecting rope 1 is connected to a plurality of first vertical rods 21 at the same time. Furthermore, the first vertical rod 21 and the second vertical rod 22 are both connected with a plurality of fixing pins, and the fixing pins are anchored at the bottom of the supporting beam or the foundation pit.
When the support frame 2 is installed, the first cross rod 23, the second cross rod 24 and the second vertical rod 22 can reinforce the standing position of the first vertical rod 21, so that the stability of the first vertical rod 21 in the standing position is guaranteed. Meanwhile, the arranged fixing pins can limit the first vertical rod 21 and the second vertical rod 22, so that the possibility of toppling over of the first vertical rod 21 and the second vertical rod 22 is reduced when the connecting rope 1 is loaded.
Referring to fig. 1 and 2, the support frame 2 is provided with a third cross bar 3, and the third cross bar 3 abuts against the lower end of the support beam. The two ends of the third cross rod 3 are both fixed with connecting sleeves 31, and the connecting sleeves 31 at the two ends of the third cross rod 3 are respectively sleeved on the first vertical rod 21 and the second vertical rod 22. The connecting sleeve 31 is inserted and connected with a plurality of tightening bolts 32 through threads, and the tightening bolts 32 are abutted against the first vertical rod 21 or the second vertical rod 22 where the connecting sleeve 31 is located.
During the installation, the first horizontal pole 23 and the third horizontal pole 3 of setting can carry out the centre gripping to a supporting beam to when connecting rope 1 and receiving load, further reduce first pole setting 21 and second pole setting 22 and take place the possibility of empting. And, third horizontal pole 3 can be relative first pole setting 21 and the vertical slip of second pole setting 22 when the installation, and the fastening is supported tight bolt 32 afterwards and is locked in the position with third horizontal pole 3 in order to realize carrying out the effect of adjusting the clearance between first horizontal pole 23 and the third horizontal pole 3 to be convenient for adapt to the supporting beam of different specifications and carry out the installation of third horizontal pole 3.
Referring to fig. 3, first pole setting 21 cover is established and is slided and be connected with connecting block 4, and connecting block 4 fixedly connected with couple 41 for connect rope 1 when being connected with first pole setting 21, only need to bind in couple 41 with connecting rope 1, and the couple 41 that sets up makes and connects difficult the droing after rope 1 binds.
Connecting block 4 is provided with the locking piece for the locking piece can lock connecting block 4 in the not co-altitude of first pole setting 21 after connecting block 4 first pole setting 21 slip relatively, thereby realizes carrying out the effect of adjusting the mounting height of connecting rope 1. And then improve the convenience that the safety belt that constructor wore is hanging and is establishing.
Referring to fig. 3, in the present embodiment, a locking member is provided as the locking bolt 42. At this time, the first vertical rod 21 is provided with a plurality of vertically distributed fixing holes 211, the locking bolt 42 simultaneously penetrates through the connecting block 4 and one of the fixing holes 211, and the locking bolt 42 is in threaded connection with the inner wall of the fixing hole 211. During installation, after the connecting block 4 slides along the first vertical rod 21, the locking bolt 42 is only required to penetrate through the connecting block 4 and be connected to the fixing hole 211 at the position through threads, so that the connecting block 4 can be fixed at the positions of different fixing holes 211, and the purpose of adjusting the installation height of the connecting rope 1 is achieved.
In other embodiments, the locking member may further include a plug pin and a pushing spring, wherein the plug pin is slidably connected to the connecting block 4, the plug pin is used to penetrate through the fixing hole 211, and two ends of the pushing spring are respectively connected to the plug pin and the connecting block 4.
Referring to fig. 3, at this time, in order to reduce the possibility that the connecting block 4 is rotated relative to the first vertical rod 21, the locking bolt 42 is misaligned with the fixing hole 211 in the circumferential direction of the first vertical rod 21. Vertical extension's spacing groove 212 is seted up to first pole setting 21 outer wall, and connecting block 4 integrated into one piece has joint portion, and joint portion card is established and is slided and connect in spacing groove 212.
Thereby when connecting block 4 slided, because joint portion and spacing groove 212 looks joint to can do the restriction to connecting block 4's rotation, and then reduce locking bolt 42 and the possibility that fixed orifices 211 took place the dislocation in first pole setting 21 week, increase the convenience of locking bolt 42 installation.
The implementation principle of the temporary safety belt suspension device in the embodiment of the application is as follows: during construction, the support frames 2 are firstly arranged on the support beams, and then the connecting ropes 1 are simultaneously fixed on the hooks 41 on the support frames 2. Thereby when constructor carries out the operation on a supporting beam, constructor can hang the safety belt of wearing and locate and connect rope 1 to give the problem of solving the safety belt and not having the hanging point, and then guarantee the construction safety of constructor when the operation on a supporting beam.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: equivalent changes in structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (8)

1. A temporary safety belt suspension, characterized in that: including connecting rope (1) and a plurality of support frame (2), a supporting beam is set up in support frame (2), just support frame (2) butt in foundation ditch bottom or the structural slab of a supporting beam below, connect rope (1) and connect in the top of a plurality of support frames (2) simultaneously.
2. A temporary seat belt suspension as claimed in claim 1, wherein: support frame (2) include first pole setting (21), second pole setting (22) and first horizontal pole (23), the equal butt in foundation ditch bottom of lower extreme of first pole setting (21) and second pole setting (22), just first pole setting (21) and second pole setting (22) are located a supporting beam's both sides respectively, a supporting beam top is set up in first horizontal pole (23), just fixed connection is in first pole setting (21) and second pole setting (22) respectively at the both ends of first horizontal pole (23), first pole setting (21) and second pole setting (22) all are provided with a plurality of fixed pins, the fixed pin anchor is in a supporting beam or foundation ditch bottom, connect rope (1) and be fixed in a plurality of first pole settings (21) simultaneously.
3. A temporary safety belt suspension arrangement as claimed in claim 2, wherein: the support frame (2) further comprises a second cross rod (24), the second cross rod (24) is located below the support beam, and two ends of the second cross rod (24) are respectively and fixedly connected to the first vertical rod (21) and the second vertical rod (22).
4. A temporary seat belt suspension as claimed in claim 2, wherein: third horizontal pole (3) are installed in support frame (2), third horizontal pole (3) butt in a supporting beam lower extreme.
5. A temporary seat belt suspension as claimed in claim 4 wherein: connecting sleeve (31) are all installed at the both ends of third horizontal pole (3), first pole setting (21) and second pole setting (22) are located in cover respectively in connecting sleeve (31) at third horizontal pole (3) both ends, connecting sleeve (31) are worn to establish and threaded connection has and supports tight bolt (32), support tight bolt (32) butt in first pole setting (21) or second pole setting (22).
6. A temporary safety belt suspension arrangement as claimed in claim 2, wherein: first pole setting (21) cover is established and is slided and be connected with connecting block (4), connecting block (4) are provided with and are convenient for connect couple (41) that rope (1) is fixed, connecting block (4) are provided with the locking piece, the locking piece is used for locking connecting block (4) in the position.
7. A temporary safety belt suspension arrangement as claimed in claim 6, wherein: the locking piece sets up to locking bolt (42), a plurality of fixed orificess (211) have been seted up in first pole setting (21), and is a plurality of vertical distribution is followed in fixed orificess (211), connecting block (4) and one of them fixed orifices (211) are worn to locate simultaneously in locking bolt (42).
8. A temporary seat belt suspension as claimed in claim 7 wherein: vertical extension's spacing groove (212) are seted up to first pole setting (21) outer wall, connecting block (4) are equipped with joint portion, joint portion card is established and is slided and connect in spacing groove (212).
CN202221663045.3U 2022-06-30 2022-06-30 Temporary safety belt hanging device Active CN218106608U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221663045.3U CN218106608U (en) 2022-06-30 2022-06-30 Temporary safety belt hanging device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221663045.3U CN218106608U (en) 2022-06-30 2022-06-30 Temporary safety belt hanging device

Publications (1)

Publication Number Publication Date
CN218106608U true CN218106608U (en) 2022-12-23

Family

ID=84514826

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221663045.3U Active CN218106608U (en) 2022-06-30 2022-06-30 Temporary safety belt hanging device

Country Status (1)

Country Link
CN (1) CN218106608U (en)

Similar Documents

Publication Publication Date Title
US11365556B1 (en) Systems and methods for supporting utility poles
CN218106608U (en) Temporary safety belt hanging device
CN113404268A (en) Basement exterior wall scaffold system and construction method thereof
CN117306831A (en) Method for erecting disc buckle type scaffold
CN217175873U (en) Assembled building used screen
CN214786169U (en) Rain-proof cover of building site
CN107178658B (en) Footstock structure of lifting rod type support and hanger
CN216157227U (en) Protecting net hanging device for bridge foundation pile construction
CN210598066U (en) High-stability diagonal tension door type scaffold
CN114604786A (en) Tower crane wall attaching structure and construction method thereof
CN211596362U (en) Bailey frame for Bailey bridge
CN211920714U (en) Support system of pull-up and pull-down type external hanging self-climbing tower crane
CN110821167A (en) Construction method for cantilever formwork support
CN217840861U (en) Multi-angle template jacking bracket
CN220888322U (en) Cast-in-situ construction template supporting structure
CN210767918U (en) Hook seat for protection net of cantilever plate
JP3745905B2 (en) How to build stays on the rooftop tower
CN204920242U (en) Transmission line tala line installation specialized tool that acts as go -between
CN217489577U (en) Safety rope tying and hanging device
CN218843715U (en) Straight steel beam mounting structure
CN212129861U (en) Overhanging scaffold for construction engineering
CN220790525U (en) Suspended operation platform device for edge
CN215055396U (en) Triangular support structure encorbelments
CN218786779U (en) Pier support overhauls rail
CN217812226U (en) Construction scaffold

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant