CN218060801U - Installation module of prefabricated cabin wallboard and prefabricated cabin - Google Patents

Installation module of prefabricated cabin wallboard and prefabricated cabin Download PDF

Info

Publication number
CN218060801U
CN218060801U CN202221662016.5U CN202221662016U CN218060801U CN 218060801 U CN218060801 U CN 218060801U CN 202221662016 U CN202221662016 U CN 202221662016U CN 218060801 U CN218060801 U CN 218060801U
Authority
CN
China
Prior art keywords
rock wool
skeleton
framework
prefabricated cabin
panel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221662016.5U
Other languages
Chinese (zh)
Inventor
汪童志
余鑫
刘明强
贾妍
黄福德
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ceepower Co ltd
Fujian Ceepower Co ltd
Original Assignee
Ceepower Co ltd
Fujian Ceepower Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ceepower Co ltd, Fujian Ceepower Co ltd filed Critical Ceepower Co ltd
Priority to CN202221662016.5U priority Critical patent/CN218060801U/en
Application granted granted Critical
Publication of CN218060801U publication Critical patent/CN218060801U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/24Structural elements or technologies for improving thermal insulation
    • Y02A30/244Structural elements or technologies for improving thermal insulation using natural or recycled building materials, e.g. straw, wool, clay or used tires

Landscapes

  • Building Environments (AREA)

Abstract

The utility model relates to an installation module of prefabricated cabin wallboard, including rock wool battenboard and skeleton subassembly, the rock wool battenboard passes through the skeleton subassembly and installs on the wall of prefabricated cabin, the skeleton subassembly includes first skeleton, second skeleton and third skeleton, first skeleton is located the upper segment of rock wool battenboard, the second skeleton is located the middle section of rock wool battenboard, the third skeleton is located the hypomere of rock wool battenboard; the lengths of the first framework, the second framework and the third framework in the horizontal direction are the same. Be different from prior art, the utility model discloses can guarantee that the rock wool battenboard is unified in the ascending roughness of vertical side, can all use the wall as the benchmark, guarantee the relative position plane degree, can simplify the installation of rock wool battenboard, guarantee the quality of rock wool battenboard interior trim wall.

Description

Installation module of prefabricated cabin wallboard and prefabricated cabin
Technical Field
The utility model relates to a become fields such as transmission and distribution power consumption, assembled modular building, in particular to prefabricated cabin board's installation module and prefabricated cabin.
Background
The prefabricated cabin type transformer substation is characterized in that the interior wall boards are made of rock wool sandwich boards, so that the requirements of fire prevention, heat preservation and the like can be met, and the material cost is low.
But the mounting means of rock wool battenboard is comparatively complicated at present, and the wall flatness is difficult to control after the installation, and the interior trim wall quality in prefabricated cabin is difficult to guarantee.
In the process of implementing the present invention, the inventor finds the following problems in the prior art:
among the prior art, the mounting means of rock wool battenboard is complicated, and rock wool battenboard needs a plurality of mounting points in vertical direction, and the reference position of a plurality of mounting points is not unified, leads to rock wool battenboard flatness in vertical direction to be difficult to control, and the interior trim wall quality in prefabricated cabin is difficult to guarantee.
SUMMERY OF THE UTILITY MODEL
In view of above-mentioned problem, this application provides an installation module and prefabricated cabin of prefabricated cabin wallboard for solve among the prior art rock wool battenboard and be difficult to control at the ascending roughness in vertical direction, the interior trim wall quality in prefabricated cabin is difficult to the technical problem who guarantees.
To achieve the above object, in a first aspect, the inventors provide an installation module of prefabricated bulkhead plate, comprising:
the rock wool sandwich panel is used for being installed on the wall surface of the prefabricated cabin; and
the rock wool sandwich board is arranged on the wall surface of the prefabricated cabin through the framework assembly, the framework assembly comprises a first framework, a second framework and a third framework, the first framework is located at the upper section of the rock wool sandwich board, the second framework is located at the middle section of the rock wool sandwich board, and the third framework is located at the lower section of the rock wool sandwich board;
wherein, the first skeleton, the second skeleton and the third skeleton are the same in length on the horizontal direction.
Different from the prior art, the technical scheme of the application includes that the skeleton assembly comprises a first skeleton, a second skeleton and a third skeleton, the first skeleton is located at the upper section of the rock wool sandwich board, the second skeleton is located at the middle section of the rock wool sandwich board, and the third skeleton is located at the lower section of the rock wool sandwich board; the lengths of the first framework, the second framework and the third framework in the horizontal direction are the same. So, can guarantee that the upper and middle and lower triplex of rock wool battenboard is the same with the distance between the wall, and rock wool battenboard is unified in the ascending roughness of vertical side, can all use the wall as the benchmark, guarantees the relative position plane degree, can simplify the installation of rock wool battenboard, guarantees the quality of rock wool battenboard interior trim wall.
As an embodiment of the present invention, the first skeleton the second skeleton and the third skeleton all include first connecting portion, second connecting portion and third connecting portion, first connecting portion are used for being connected with the wall in prefabricated cabin, the second connecting portion be used for with the rock wool sandwich panel is connected, first connecting portion pass through the third connecting portion with the second connecting portion are connected. So, first skeleton, second skeleton and third skeleton can be connected with the wall in prefabricated cabin through first connecting portion, are connected with the rock wool battenboard through the second connecting portion, easy to assemble.
As an embodiment of the present invention, the first connecting portion is disposed along a vertical direction, the third connecting portion is disposed along a horizontal direction, the first frame, the second frame and the third frame are three, and the length of the third connecting portion in the horizontal direction is the same. So, can follow vertical direction downwardly extending through first connecting portion, can increase the connection face between first connecting portion and the wall, improve the joint strength between rock wool battenboard and the wall. Set up along the horizontal direction through the third connecting portion, as long as can unify the length of the third connecting portion of first skeleton, second skeleton, third skeleton, just also can guarantee that the rock wool battenboard is the same at the distance between upper, middle and lower three and the corrugated sheet, makes things convenient for the production of first skeleton, second skeleton, third skeleton.
As an embodiment of the utility model, the third skeleton the second connecting portion are the U-shaped structure, the bottom setting of rock wool sandwich panel is in the second connecting portion, the second connecting portion are used for right the bottom of rock wool sandwich panel is carried on spacingly. So, can be through the U-shaped structure of second connecting portion, directly with rock wool battenboard from last to putting into the U-shaped structure down, closely cooperate between rock wool battenboard and the third skeleton to carry on spacingly to the position of rock wool battenboard's bottom, simplify the installation of rock wool battenboard, improve the rock wool battenboard to the efficiency of construction, reduce installation cost.
As an embodiment of the utility model, prefabricated cabin wallboard's installation module includes more than two rock wool battenboard, more than two the rock wool battenboard is arranged along the horizontal direction and is set up, more than two through wallboard connecting piece interconnect between the rock wool battenboard, the wallboard connecting piece is used for right rock wool battenboard's top is carried on spacingly. So, can connect fixedly between the rock wool battenboard of two above through the wallboard connecting piece, simultaneously, the wallboard connecting piece carries on spacingly to the top of two rock wool battenboards, prevents that the rock wool battenboard is not hard up, conveniently installs the rock wool battenboard.
As an embodiment of the utility model, the wallboard connecting piece includes the catching groove, the catching groove sets up two between the rock wool battenboard, the top of rock wool battenboard is located in the catching groove, the catching groove is located two the top of rock wool battenboard, the catching groove is used for two the rock wool battenboard is spacing to the top. So, can closely cooperate between catching groove and two rock wool battenboard, improve the plane degree between two rock wool battenboard, carry on spacingly from lower part and upper portion to the rock wool battenboard, guarantee rock wool battenboard's whole roughness.
As an embodiment of the present invention, the wallboard connector further includes a blocking piece, the blocking piece is disposed on the buckle slot, and the blocking piece is used for fixing the electric wire. So, through install the separation blade additional at the catching groove, improve the wire casing height to a ligature line, the separation blade can play the ligature electric wire, and increases the wire casing, prevents the effect that the electric wire slided out the wire casing.
As an embodiment of the utility model, the second connecting portion of first skeleton upwards extend along vertical direction, the catching groove is used for right rock wool battenboard with the second connecting portion press from both sides tightly fixedly. So, the catching groove is from last to down, with rock wool battenboard and second connecting portion card jail, can be connected rock wool battenboard and second connecting portion through the catching groove and fix, need not to add other parts more, has simplified the installation of rock wool battenboard, has reduced installation cost.
As an embodiment of the present invention, the frame assembly includes two or more second frames, two or more second frames are disposed along the vertical direction, and the rock wool sandwich panel is fixed to the second frames by fasteners, respectively. So, through more than two the second skeleton sets up along vertical direction, can strengthen the support intensity at rock wool battenboard middle part, improves the joint strength between rock wool battenboard and the corrugated sheet.
In order to achieve the above object, in a second aspect, the inventors provide a prefabricated cabin comprising an installation module of prefabricated cabin panels as described in any one of the above mentioned inventors.
Be different from prior art, the distance that can guarantee between the upper, middle and lower three of rock wool battenboard and the wall is the same in the prefabricated cabin of the technical scheme of this application, and rock wool battenboard is unified in the ascending roughness of vertical side, can all use the wall as the benchmark, guarantees the relative position plane degree, can simplify the installation of rock wool battenboard, guarantees the quality of rock wool battenboard interior trim wall.
The above description of the present invention is only an overview of the technical solutions of the present application, and in order to make the technical solutions of the present application more clearly understood by those skilled in the art, the present invention may be further implemented according to the content described in the text and the drawings of the present application, and in order to make the above objects, other objects, features, and advantages of the present application more easily understood, the following description is made in conjunction with the detailed description of the present application and the drawings.
Drawings
The drawings are only for purposes of illustrating the principles, implementations, applications, features, and effects of particular embodiments of the present application, as well as others related thereto, and are not to be construed as limiting the application.
In the drawings of the specification:
FIG. 1 is a schematic structural view of a wall panel of a prefabricated cabin according to an embodiment of the present application;
FIG. 2 is an exploded view of a wall panel of a prefabricated cabin according to one embodiment of the present application;
FIG. 3 is a front view of a wall panel of the prefabricated cabin of one embodiment of the present application;
FIG. 4 is a cross-sectional view of a wall panel of the prefabricated compartment of an embodiment of the present application;
FIG. 5 is an enlarged schematic view at A in FIG. 4;
FIG. 6 is an enlarged schematic view at B of FIG. 4;
FIG. 7 is an enlarged schematic view at C of FIG. 4;
FIG. 8 is a schematic structural diagram of a skeletal assembly in accordance with an embodiment of the present application;
figure 9 is a schematic view of a wall panel connector according to one embodiment of the present application;
fig. 10 is a diagram illustrating an installation process of the prefabricated cabin wall panel according to an embodiment of the present application.
The reference numerals referred to in the above figures are explained below:
1. the corrugated board is made of a corrugated board,
11. the installation of the reference plane is carried out,
2. the rock wool sandwich board is characterized in that,
3. the framework component is arranged on the base plate,
31. a first framework and a second framework which are arranged in parallel,
32. a second framework is arranged on the first framework,
33. a third framework is arranged on the first framework,
34. a first connecting part is arranged at the first side of the base plate,
35. a second connecting part which is connected with the first connecting part,
36. a third connecting part for connecting the first and second connecting parts,
4. a connecting piece of the wall plate is connected with the wall plate,
41. the groove is buckled with the groove body,
42. a baffle plate.
Detailed Description
In order to explain in detail possible application scenarios, technical principles, practical embodiments, and the like of the present application, the following detailed description is given with reference to the accompanying drawings in conjunction with the listed embodiments. The embodiments described herein are merely for more clearly illustrating the technical solutions of the present application, and therefore, the embodiments are only used as examples, and the scope of the present application is not limited thereby.
Reference herein to "an embodiment" means that a particular feature, structure, or characteristic described in connection with the embodiment can be included in at least one embodiment of the application. The appearances of the phrase "an embodiment" in various places in the specification are not necessarily all referring to the same embodiment, nor are separate or related to other embodiments specifically defined. In principle, in the present application, the technical features mentioned in the embodiments can be combined in any manner to form a corresponding implementable technical solution as long as there is no technical contradiction or conflict.
Unless defined otherwise, technical terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this application belongs; the use of relational terms herein is intended only to describe particular embodiments and is not intended to limit the present application.
In the description of the present application, the term "and/or" is a expression for describing a logical relationship between objects, indicating that three relationships may exist, for example, a and/or B, indicating that: there are three cases of A, B, and both A and B. In addition, the character "/" herein generally indicates that the former and latter associated objects are in a logical relationship of "or".
In this application, terms such as "first" and "second" are used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions.
Without further limitation, in this application, the use of "including," "comprising," "having," or other similar expressions in phrases and expressions of "including," "comprising," or "having," is intended to cover a non-exclusive inclusion, and such expressions do not exclude the presence of additional elements in a process, method, or article that includes the recited elements, such that a process, method, or article that includes a list of elements may include not only those elements but also other elements not expressly listed or inherent to such process, method, or article.
As is understood in the "review guidelines," in this application, the terms "greater than," "less than," "more than," and the like are to be understood as excluding the number; the expressions "above", "below", "within" and the like are understood to include the present numbers. Furthermore, the description of embodiments herein of the present application of the term "plurality" means more than two (including two), and the analogous meaning of "plurality" is also to be understood, e.g., "plurality", etc., unless explicitly specified otherwise.
In the description of the embodiments of the present application, spatially relative expressions such as "central," "longitudinal," "lateral," "length," "width," "thickness," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "vertical," "top," "bottom," "inner," "outer," "clockwise," "counterclockwise," "axial," "radial," "circumferential," and the like are used, and the indicated orientations or positional relationships are based on the orientations or positional relationships shown in the specific embodiments or drawings and are for convenience of description of the specific embodiments of the present application or for ease of understanding by the reader only, and do not indicate or imply that a device or component referred to must have a specific position, a specific orientation, or be configured or operated in a specific orientation and therefore should not be construed as limiting the embodiments of the present application.
Unless specifically stated or limited otherwise, the terms "mounted," "connected," "secured," and "disposed" used in the description of the embodiments of the present application are to be construed broadly. For example, the connection can be a fixed connection, a detachable connection, or an integrated arrangement; it can be a mechanical connection, an electrical connection, or a communication connection; they may be directly connected or indirectly connected through an intermediate; which may be communication within two elements or an interaction of two elements. Specific meanings of the above terms in the embodiments of the present application can be understood by those skilled in the art to which the present application pertains in accordance with specific situations.
The prefabricated cabin type transformer substation is characterized in that the interior wall boards are made of rock wool sandwich boards, so that the requirements of fire prevention, heat preservation and the like can be met, and the material cost is low. Among the prior art, the mounting means of rock wool battenboard is complicated, and rock wool battenboard needs a plurality of mounting points in vertical direction, and the reference position of a plurality of mounting points is not unified, leads to rock wool battenboard flatness in vertical direction to be difficult to control, and the interior trim wall quality in prefabricated cabin is difficult to guarantee.
The applicant researches and discovers that the rock wool sandwich panel is installed on the wall surface of the prefabricated cabin through the skeleton assembly, the skeleton assembly comprises a first skeleton, a second skeleton and a third skeleton, the first skeleton is located at the upper section of the rock wool sandwich panel, the second skeleton is located at the middle section of the rock wool sandwich panel, and the third skeleton is located at the lower section of the rock wool sandwich panel; the lengths of the first framework, the second framework and the third framework in the horizontal direction are the same. The distance that can guarantee between the upper and middle and lower three of rock wool battenboard and the wall is the same, and rock wool battenboard is unified in the ascending roughness of vertical side, can all use the wall as the benchmark, guarantees the relative position plane degree, can simplify the installation of rock wool battenboard, guarantees the quality of rock wool battenboard interior trim wall.
This embodiment relates to an installation module and prefabricated cabin of prefabricated cabin wallboard, can use each technical field at prefabricated cabin wallboard installation.
Referring to fig. 1 to 10, according to some embodiments of the present application, the present embodiment relates to an installation module of a prefabricated cabin wall panel, including a rock wool sandwich panel 2 and a skeleton assembly 3, wherein the rock wool sandwich panel 2 is used for being installed on a wall surface of a prefabricated cabin; the rock wool sandwich panel 2 is installed on the wall surface of the prefabricated cabin through the framework component 3, the framework component 3 comprises a first framework 31, a second framework 32 and a third framework 33, the first framework 31 is positioned at the upper section of the rock wool sandwich panel 2, the second framework 32 is positioned at the middle section of the rock wool sandwich panel 2, and the third framework 33 is positioned at the lower section of the rock wool sandwich panel 2; the first frame 31, the second frame 32, and the third frame 33 have the same length in the horizontal direction.
In this embodiment, the wall surface of the prefabricated cabin is corrugated board 1, and the surface of corrugated board 1 is used as installation reference surface 11.
In the embodiment, a heat insulation layer and a wiring layer are formed between the rock wool sandwich board 2 and the corrugated board 1, and the first framework 31, the second framework 32 and the third framework 33 all use a wire groove as an installation framework and can be combined with multiple functions; the first frame 31, the second frame 32 and the third frame 33 are all made of metal channel steel.
According to the embodiment, the material is simple, the installation is convenient, and the cost is reduced and the efficiency is improved; the multifunctional composite structure solves the wiring problem; the rock wool sandwich plates 2 are welded according to a uniform standard, so that the flatness of relative positions is guaranteed; improve the heat preservation and insulation performance.
Can set up the through wires hole on first skeleton 31, second skeleton 32, third skeleton 33 for the line is walked in the cabin, and skeleton width size requires and wire casing width to require the adjustment according to prefabricated cabin wall thickness, and wire casing degree of depth size is according to walking the adjustment of line quantity.
All skeletons are welded on the corrugated board according to the height of the rock wool sandwich board 2, the corrugated board is used as a reference, the flatness of relative positions is ensured, and the skeletons and the corrugated board form a wiring space.
In this embodiment, including first skeleton 31, second skeleton 32 and third skeleton 33 through skeleton subassembly 3, first skeleton 31 is located the upper segment of rock wool sandwich panel 2, and second skeleton 32 is located the middle section of rock wool sandwich panel 2, and third skeleton 33 is located the lower section of rock wool sandwich panel 2, and first skeleton 31, second skeleton 32 and third skeleton 33 are the same in the ascending length of horizontal direction.
So, can guarantee that the distance between the upper and middle and lower three of rock wool battenboard 2 and the wall is the same, rock wool battenboard 2 is unified in the ascending roughness of vertical side, can all use the wall as the benchmark, guarantees the relative position plane degree, can simplify the installation of rock wool battenboard 2, guarantees the quality of rock wool battenboard 2 interior trim wall.
According to some embodiments of the present application, optionally, the first framework 31, the second framework 32 and the third framework 33 each include a first connection portion 34, a second connection portion 35 and a third connection portion 36, the first connection portion 34 is used for being connected with a wall surface of the prefabricated cabin, the second connection portion 35 is used for being connected with the rock wool sandwich panel 2, and the first connection portion 34 is connected with the second connection portion 35 through the third connection portion 36.
So, first skeleton 31, second skeleton 32 and third skeleton 33 can be connected with the wall in prefabricated cabin through first connecting portion 34, are connected with rock wool battenboard 2 through second connecting portion 35, easy to assemble.
According to some embodiments of the present application, optionally, the first connecting portion 34 is disposed along a vertical direction, the third connecting portion 36 is disposed along a horizontal direction, and the three third connecting portions 36 of the first frame 31, the second frame 32, and the third frame 33 have the same length in the horizontal direction.
So, can follow vertical direction downwardly extending through first connecting portion 34, can increase the connection face between first connecting portion 34 and the wall, improve the joint strength between rock wool battenboard 2 and the wall. Set up along the horizontal direction through third connecting portion 36, as long as can unify the length of first skeleton 31, second skeleton 32, third skeleton 33's third connecting portion 36, just also can guarantee that rock wool battenboard 2 is the same at the distance between upper, middle and lower three and corrugated sheet 1, makes things convenient for the production of first skeleton 31, second skeleton 32, third skeleton 33.
According to some embodiments of this application, optionally, the second connecting portion 35 of third skeleton 33 is the U-shaped structure, and the bottom of rock wool sandwich panel 2 sets up in second connecting portion 35, and second connecting portion 35 is used for spacing the bottom of rock wool sandwich panel 2.
So, can be through the U-shaped structure of second connecting portion 35, directly with rock wool battenboard 2 from last to putting into the U-shaped structure down, closely cooperate between rock wool battenboard 2 and the third skeleton 33 to carry on spacingly to the position of rock wool battenboard 2's bottom, simplify the installation of rock wool battenboard 2, improve rock wool battenboard 2 to the efficiency of construction, reduce installation cost.
According to some embodiments of the application, optionally, prefabricated cabin panel's installation module includes rock wool battenboard 2 more than two, and rock wool battenboard 2 more than two is arranged along the horizontal direction and is set up, through 4 interconnect of wallboard connecting piece between the rock wool battenboard 2 more than two, and wallboard connecting piece 4 is used for spacing the top of rock wool battenboard 2.
So, can connect fixedly between rock wool battenboard 2 more than two through wallboard connecting piece 4, simultaneously, wallboard connecting piece 4 carries on spacingly to two rock wool battenboard 2's top, prevents that rock wool battenboard 2 is not hard up, conveniently installs rock wool battenboard 2.
According to some embodiments of the present application, optionally, wallboard connection piece 4 includes catching groove 41, and catching groove 41 sets up between two rock wool sandwich panels 2, and the top of rock wool sandwich panel 2 is located catching groove 41, and catching groove 41 is located the top of two rock wool sandwich panels 2, and catching groove 41 is used for spacing two rock wool sandwich panels 2 to the top.
So, can closely cooperate between 41 and two rock wool battenboard 2 through the catching groove, improve the plane degree between two rock wool battenboard 2, carry on spacingly from lower part and upper portion to rock wool battenboard 2, guarantee rock wool battenboard 2's whole roughness.
According to some embodiments of the present application, optionally, the wall plate connector 4 further comprises a stop piece 42, the stop piece 42 is disposed on the fastening slot 41, and the stop piece 42 is used for fixing the electric wire.
So, through install separation blade 42 additional at catching groove 41, improve the wire casing height to be used for the ligature, separation blade 42 can play the ligature electric wire, and increase the wire casing, prevents the effect of electric wire slip-out wire casing.
According to some embodiments of the present application, optionally, the second connecting portion 35 of the first framework 31 extends upward along the vertical direction, and the fastening groove 41 is used for clamping and fixing the rock wool sandwich panel 2 and the second connecting portion 35.
So, the catching groove 41 is from last to down, with rock wool battenboard 2 and the second connecting portion 35 card jail, can be connected rock wool battenboard 2 and second connecting portion 35 through catching groove 41 and fix, need not to add other parts more, has simplified rock wool battenboard 2's installation, has reduced installation cost.
According to some embodiments of this application, optionally, skeleton subassembly 3 includes more than two second skeletons 32, and more than two second skeletons 32 set up along vertical direction, and rock wool battenboard 2 passes through the fastener respectively with more than two second skeletons 32 fixed connection.
So, set up along vertical direction through second skeleton 32 more than two, can strengthen the support intensity at rock wool battenboard 2 middle part, improve the joint strength between rock wool battenboard 2 and the corrugated sheet 1.
In a second aspect, the present embodiment also relates to a prefabricated cabin comprising an installation module of a prefabricated cabin wall panel according to any one of the above-provided.
The installation principle of prefabricated cabin, as shown in fig. 10, first piece rock wool battenboard 2 falls in the U type inslot of third skeleton 33 from last to down, slide to the back that targets in place, the junction nailing is fixed in the Z type fossil fragments of second skeleton 32, second piece rock wool battenboard 2 falls in the U type inslot of third skeleton 33 from last to down, slide to the back that targets in place, the junction nailing is fixed in the Z type fossil fragments of second skeleton 32, wallboard connecting piece 4 is from last to down, with rock wool battenboard 2 and the wire casing snap of first skeleton 31 to analogize and accomplish the wallboard installation.
The production process of the prefabricated cabin wall body of the embodiment is as follows:
the first step is as follows: skeleton processing
Respectively processing a third framework 33 (specifically, a U-shaped groove framework), a second framework 32 (specifically, a Z-shaped framework) and a first framework 31 (specifically, a wire groove framework); all the frameworks are provided with threading holes for wiring in the cabin, the width dimension of the frameworks is adjusted according to the thickness requirement of the prefabricated cabin wall body and the width requirement of the wire grooves, and the depth dimension of the wire grooves is adjusted according to the number of the wiring;
the second step is that: skeleton welding
All the frameworks are welded on the corrugated board 1 according to the height of the rock wool sandwich board 2, the corrugated board 1 is taken as a reference to ensure the flatness of the relative position, wherein the second framework 32 (specifically, a Z-shaped framework) can be properly added to enhance the middle wall strength of the rock wool sandwich board 2, and the first framework 31 (specifically, a wire groove framework) and the corrugated board 1 form a wiring space;
the third step: fastener manufacturing method
Processing a buckle accessory, welding and manufacturing a wallboard connecting piece 4, and welding and connecting the buckling groove 41 and the blocking piece 42 to form a wallboard buckle; the baffle plate 42 can bind wires, heighten the wire grooves and prevent the wires from sliding out of the wire grooves;
the fourth step: wallboard installation
First piece rock wool battenboard 2 is from last to falling in the U type inslot of third skeleton 33 down, slide to the back that targets in place, the junction nailing is fixed in the Z type fossil fragments of second skeleton 32, second piece rock wool battenboard 2 is from last to falling in the U type inslot of third skeleton 33 down, slide to the back that targets in place, the junction nailing is fixed in the Z type fossil fragments of second skeleton 32, wallboard connecting piece 4 is from last to down, with rock wool battenboard 2 and the wire casing chucking of first skeleton 31, so as to analogize and accomplish the wallboard installation.
Be different from prior art, the distance that can guarantee between the upper, middle and lower three of rock wool battenboard 2 and the wall is the same in the prefabricated cabin of the technical scheme of this application, and rock wool battenboard 2 is unified in the ascending roughness of vertical side, can all use the wall as the benchmark, guarantees the relative position plane degree, can simplify the installation of rock wool battenboard 2, guarantees the quality of rock wool battenboard 2 interior trim wall.
Those skilled in the art will appreciate that although some embodiments herein include some features included in other embodiments, not others, combinations of features of different embodiments are meant to be within the scope of the application and form different embodiments. For example, in the claims, any of the claimed embodiments may be used in any combination.
Finally, it should be noted that: the above embodiments are only used for illustrating the technical solutions of the present application, and not for limiting the same; although the present application has been described in detail with reference to the foregoing embodiments, it should be understood by those of ordinary skill in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some or all of the technical features may be equivalently replaced; such modifications and substitutions do not depart from the spirit and scope of the present disclosure, and the present disclosure should be construed as being covered by the claims and the specification. In particular, the technical features mentioned in the embodiments can be combined in any way as long as there is no structural conflict. The present application is not intended to be limited to the particular embodiments disclosed herein but is to cover all embodiments that may fall within the scope of the appended claims.

Claims (10)

1. An installation module of prefabricated bulkhead panels, comprising:
the rock wool sandwich panel is used for being installed on the wall surface of the prefabricated cabin; and
the rock wool sandwich board is arranged on the wall surface of the prefabricated cabin through the framework assembly, the framework assembly comprises a first framework, a second framework and a third framework, the first framework is located at the upper section of the rock wool sandwich board, the second framework is located at the middle section of the rock wool sandwich board, and the third framework is located at the lower section of the rock wool sandwich board;
wherein, the lengths of the first skeleton, the second skeleton and the third skeleton in the horizontal direction are the same.
2. The prefabricated cabin panel installation module of claim 1, wherein the first, second and third frameworks each include a first connection portion for connecting with a wall surface of a prefabricated cabin, a second connection portion for connecting with the rock wool sandwich panel, and a third connection portion through which the first connection portion is connected with the second connection portion.
3. The prefabricated panel installation module of claim 2, wherein the first connection portion is disposed in a vertical direction, the third connection portion is disposed in a horizontal direction, and three third connection portions of the first frame, the second frame, and the third frame have the same length in the horizontal direction.
4. The prefabricated panel installation module of claim 2, wherein the second connection portion of the third framework is a U-shaped structure, the bottom of the rock wool sandwich panel is disposed in the second connection portion, and the second connection portion is used for limiting the bottom of the rock wool sandwich panel.
5. The prefabricated cabin panel installation module of claim 4, wherein the prefabricated cabin panel installation module comprises more than two rock wool sandwich panels, the more than two rock wool sandwich panels are arranged in a horizontal direction, the more than two rock wool sandwich panels are connected with each other through a panel connecting piece, and the panel connecting piece is used for limiting the top of the rock wool sandwich panels.
6. The prefabricated cabin panel installation module of claim 5, wherein the panel connector comprises a groove disposed between two of the rock wool sandwich panels, wherein the top of the rock wool sandwich panel is disposed in the groove, wherein the groove is disposed at the top of the two rock wool sandwich panels, and wherein the groove is configured to limit the top of the two rock wool sandwich panels.
7. The prefabricated cabin panel installation module of claim 6, wherein the panel connector further comprises a catch disposed on the keyway, the catch being configured to secure an electrical wire.
8. The prefabricated panel installation module of claim 6, wherein the second connection portion of the first framework extends upward in a vertical direction, and the fastening groove is used for clamping and fixing the rock wool sandwich panel and the second connection portion.
9. The prefabricated cabin panel installation module of claim 1, wherein the framework assembly comprises more than two second frameworks, the more than two second frameworks are arranged along a vertical direction, and the rock wool sandwich panel is fixedly connected with the more than two second frameworks through fasteners.
10. A prefabricated cabin comprising an installation module of a prefabricated cabin panel of any one of claims 1 to 9.
CN202221662016.5U 2022-06-29 2022-06-29 Installation module of prefabricated cabin wallboard and prefabricated cabin Active CN218060801U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221662016.5U CN218060801U (en) 2022-06-29 2022-06-29 Installation module of prefabricated cabin wallboard and prefabricated cabin

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221662016.5U CN218060801U (en) 2022-06-29 2022-06-29 Installation module of prefabricated cabin wallboard and prefabricated cabin

Publications (1)

Publication Number Publication Date
CN218060801U true CN218060801U (en) 2022-12-16

Family

ID=84436155

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221662016.5U Active CN218060801U (en) 2022-06-29 2022-06-29 Installation module of prefabricated cabin wallboard and prefabricated cabin

Country Status (1)

Country Link
CN (1) CN218060801U (en)

Similar Documents

Publication Publication Date Title
KR0145175B1 (en) Modular panel well structure
FI96708C (en) Method for fastening wall panels and wall elements
CN218060801U (en) Installation module of prefabricated cabin wallboard and prefabricated cabin
CN110094000A (en) A kind of cold bending thin wall light steel composite wall piece of card key formula connecting structure
CN115224625A (en) Prefabricated cabin for transformer substation and transformer substation
CN215442690U (en) Wallboard for assembly type building and wall system thereof
KR101414521B1 (en) Panel assembly of roof
JP2011001151A (en) Elevator car
CN211499348U (en) Bear formula building curtain and decorate component and building curtain
CN103342270A (en) Wedged type elevator car wall assembling structure and mounting method thereof
CN112854589A (en) High-strength wallboard, manufacturing method and wallboard system thereof
CN217000458U (en) Hidden metal panel, metal roofing and metal outer wall
CN102193598A (en) Electronic device shell
CN208394572U (en) A kind of novel elevator bottom beam edge covering mechanism
CN216787703U (en) Ventilation decorative board fixing device for building
CN215442665U (en) High-strength wallboard and wall system thereof
CN211945826U (en) Ventilation type lift car
CN109184105A (en) A kind of plug-in type assembled wall board
CN215859817U (en) Modularized fireproof door
CN213534086U (en) Color steel plate with heat insulation function
JPS5836877A (en) Elevator cage
CN217580985U (en) Wall hanging plate system
CN213477299U (en) Crossbeam structure that two glasss official working were cut off
CN216428677U (en) Cold-formed thin-walled steel house multilayer T type wall connection structure and connecting component
CN216405999U (en) Cavity type fast-assembling wall surface system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant