CN218027730U - Bored pile combination foundation pit enclosure structure - Google Patents

Bored pile combination foundation pit enclosure structure Download PDF

Info

Publication number
CN218027730U
CN218027730U CN202222287026.1U CN202222287026U CN218027730U CN 218027730 U CN218027730 U CN 218027730U CN 202222287026 U CN202222287026 U CN 202222287026U CN 218027730 U CN218027730 U CN 218027730U
Authority
CN
China
Prior art keywords
foundation pit
pile group
pile
bored pile
bored
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222287026.1U
Other languages
Chinese (zh)
Inventor
卞春明
王云峰
徐铨彪
李本悦
沈晓鸣
孙红霞
卞江宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Architectural Design and Research Institute of Zhejiang University Co Ltd
Original Assignee
Architectural Design and Research Institute of Zhejiang University Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Architectural Design and Research Institute of Zhejiang University Co Ltd filed Critical Architectural Design and Research Institute of Zhejiang University Co Ltd
Priority to CN202222287026.1U priority Critical patent/CN218027730U/en
Application granted granted Critical
Publication of CN218027730U publication Critical patent/CN218027730U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The utility model discloses a bored pile combined foundation pit support structure, which comprises a bored pile group (1) positioned on the outer edge surface of a foundation pit, wherein a waterproof curtain (2) is arranged on the outer side of the bored pile group (1), and a reinforcing pile group (3) is arranged on the inner side of the bored pile group (1); a horizontal concrete supporting beam (4) is also arranged at the top of the bored pile group (1); the horizontal concrete supporting beam is characterized by also comprising a steel structure diagonal brace (6) positioned between the horizontal concrete supporting beam (4) and the foundation pit corbel (5); and a triangular soil stacking layer (7) is also arranged between the drilling cast-in-place pile group (1) and the foundation pit bracket (5). The utility model has the characteristics of can effectively reduce engineering cost.

Description

Bored pile combination foundation pit enclosure structure
Technical Field
The utility model relates to a foundation ditch retaining structure, especially a bored concrete pile combination foundation ditch retaining structure.
Background
The types of the existing foundation pit support structures can be summarized into the following 6 types: the foundation pit support structure comprises a sheet pile type foundation pit support structure, a column type foundation pit support structure, an underground continuous wall foundation pit support structure, a self-standing cement-soil retaining wall foundation pit support structure, a combined type foundation pit support structure and an open caisson (box) method. The steel sheet pile cofferdam is the most common type of sheet pile cofferdam, and the steel sheet pile is a type of section steel with a locking notch, and the section of the steel sheet pile cofferdam has a straight plate shape, a groove shape, a Z shape and the like, has various sizes and interlocking forms, and is commonly in a Laerson type, a Laker Mo Na type and the like. The cast-in-place pile system is a pile formed by forming pile holes in foundation soil through mechanical drilling, steel pipe soil extrusion or manual excavation and the like on an engineering site, placing a reinforcement cage and cast-in-place concrete in the pile holes, and according to different hole forming methods, the cast-in-place pile can be divided into a immersed tube cast-in-place pile, a cast-in-place pile and the like, and the cast-in-place pile is a pile type defined according to the classification of the pile forming method. The combined type is the combination of a cast-in-place pile and a stirring pile, and the combined type enclosure structure has the advantages of being suitable for environments with high requirements on the surrounding environment, less pile top displacement, river water around a foundation pit and the like, but has the defect of high engineering cost. Therefore, the existing combined type enclosure structure has the problem of high manufacturing cost.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a bored concrete pile makes up foundation ditch retaining structure. The utility model has the characteristics of can effectively reduce engineering cost.
The technical scheme of the utility model: the bored pile combined foundation pit support structure comprises a bored pile group positioned on the outer edge surface of a foundation pit, wherein a waterproof curtain is arranged on the outer side of the bored pile group, and a reinforcing pile group is arranged on the inner side of the bored pile group; a horizontal concrete supporting beam is also arranged at the top of the bored pile group; the steel structure inclined strut is positioned between the horizontal concrete supporting beam and the foundation pit bracket; and a triangular soil stacking layer is also arranged between the bored pile group and the foundation pit bracket.
In the cast-in-situ bored pile combined foundation pit support structure, the waterproof curtain is a triaxial cement mixing pile group and/or a biaxial cement mixing pile group.
In the cast-in-situ bored pile combined foundation pit support structure, the reinforcing pile group is a double-shaft cement stirring pile group.
In the cast-in-situ bored pile combined foundation pit support structure, the triangular soil stacking layer is located below the steel structure diagonal brace.
In the cast-in-situ bored pile combined foundation pit support structure, the length of the steel structure diagonal brace is 6-9.4m.
Compared with the prior art, the utility model consists of a bored concrete pile group, a waterproof curtain, a reinforced pile group, a horizontal concrete supporting beam and a steel structure diagonal brace, wherein the bored concrete pile group, the waterproof curtain and the reinforced pile group are positioned on the outer edge surface of the foundation pit; and simultaneously, the utility model discloses a set up the triangle soil and stack the layer and be used for stacking triangle soil between drilling bored concrete pile group and bracket, this structure can reduce the pile bolck displacement at to a great extent under the same condition of excavation degree of depth, and ground deformation reduces greatly behind the messenger pile, avoids causing destruction to the surrounding environment, can also reduce pile body moment of flexure, and then makes the design strength reduction of pile body, and the reduction of design strength is favorable to reducing engineering cost. To sum up, the utility model has the characteristics of can effectively reduce engineering cost.
Drawings
FIG. 1 is a floor plan of a foundation pit enclosure;
FIG. 2 is an enlarged view of a portion of FIG. 1;
FIG. 3 is a floor plan of the pit support;
FIG. 4 is an enlarged view of a portion of FIG. 3;
FIG. 5 is a schematic plan view of a mound of deltoid;
fig. 6 is a partially enlarged view of fig. 5.
The labels in the figures are: 1-bored cast-in-place pile group, 2-waterproof curtain, 3-reinforced pile group, 4-horizontal concrete supporting beam, 5-foundation pit bracket, 6-steel structure diagonal brace and 7-triangular soil stacking layer.
Detailed Description
The following description is made with reference to the accompanying drawings and examples, but not to be construed as limiting the invention.
Examples are given. The bored pile combined foundation pit support structure comprises a bored pile group 1 positioned on the outer edge surface of a foundation pit, a waterproof curtain 2 is arranged on the outer side of the bored pile group 1, and a reinforcing pile group 3 is arranged on the inner side of the bored pile group 1, as shown in figures 1 to 6; the top of the bored pile group 1 is also provided with a horizontal concrete support beam 4; the horizontal concrete supporting beam is characterized by further comprising a steel structure inclined strut 6 positioned between the horizontal concrete supporting beam 4 and the foundation pit corbel 5; and a triangular soil stacking layer 7 is also arranged between the drilling cast-in-place pile group 1 and the foundation pit bracket 5.
The waterproof curtain 2 is a triaxial cement mixing pile group and/or a biaxial cement mixing pile group.
The reinforcing pile group 3 is a double-shaft cement stirring pile group.
The triangular soil stacking layer 7 is positioned below the steel structure inclined strut 6.
The length of the steel structure diagonal brace 6 is 6-9.4m.
The construction process of the foundation pit support structure comprises the following steps:
1) The method comprises the steps of generally surveying a site, removing obstacles, dredging and backfilling a current pond, trimming to a designed ground surface elevation, constructing engineering piles and fender piles (firstly constructing waterproof curtains (triaxial cement mixing piles and biaxial cement mixing piles), then constructing cast-in-situ bored piles, and finally constructing a reinforcing pile group.
2) Horizontal support locations (i.e. horizontal concrete support beams): after the construction of the pile foundation is finished, the pile foundation is excavated to the bottom of the top beam for construction of the top beam and the horizontal concrete supporting beam, and the steel bar stressometers are embedded. After the capping beam and the horizontal concrete supporting beam reach 80% of the design strength, the basement bottom plate and the bearing platform bottom are excavated layer by layer and block according to the design requirements, and then the basement foundation and the bottom plate force transmission belt are constructed.
3) Diagonal bracing portion (steel structural diagonal bracing): and after the pile foundation construction is finished, excavating to the bottom of the coping beam for construction of the coping beam and the bracket. And after the capping beam and the bracket reach 80% of design strength, reserving triangular soil in an area between the bored pile group and the bracket of the foundation pit according to design requirements, jumping and digging in a subarea manner, pouring a cushion layer in time, and then constructing a middle bottom plate, a bearing platform and the bracket of the pit. And arranging a steel structure diagonal brace after the bottom plate and the bracket reach 80% of design strength, wherein the length of the steel structure diagonal brace is about 6-9.4m. After the steel structure inclined strut is arranged, triangular soil is excavated, and then a force transmission belt of the underground chamber foundation and the bottom plate beside the construction pit is constructed.
And after the construction of the foundation pit support structure is finished, continuously constructing the basement outer wall and the basement top plate. And after the outer wall and the top plate of the basement reach 80% of design strength, backfilling plain soil and tamping in layers. The thickness of each layer is not more than 250 mm by manual compaction and not more than 300mm by mechanical compaction, and the waterproof layer is prevented from being damaged. The backfilled soil can not use silt, ploughed soil, frozen soil, expansive soil, domestic garbage and soil with organic matter content more than 5%. The backfill soil compaction coefficient requirement is as follows: the range from the floor cushion layer to the bottom surface of the foundation is not less than 0.94, and the rest parts are not less than 0.92; and finishing the construction of the foundation pit.

Claims (5)

1. Drilling bored concrete pile combination foundation ditch envelope, its characterized in that: the foundation pit water-stopping curtain is characterized by comprising a bored pile group (1) positioned on the outer edge surface of a foundation pit, wherein a water-stopping curtain (2) is arranged on the outer side of the bored pile group (1), and a reinforcing pile group (3) is arranged on the inner side of the bored pile group (1); a horizontal concrete supporting beam (4) is also arranged at the top of the bored pile group (1); the horizontal concrete supporting beam is characterized by also comprising a steel structure diagonal brace (6) positioned between the horizontal concrete supporting beam (4) and the foundation pit corbel (5); and a triangular soil stacking layer (7) is also arranged between the drilling cast-in-place pile group (1) and the foundation pit bracket (5).
2. The cast-in-situ bored pile combined foundation pit support structure of claim 1, wherein: the waterproof curtain (2) is a triaxial cement mixing pile group and/or a biaxial cement mixing pile group.
3. The cast-in-situ bored pile combined foundation pit support structure of claim 1, wherein: the reinforcing pile group (3) is a double-shaft cement stirring pile group.
4. The cast-in-situ bored pile combined foundation pit support structure of claim 1, wherein: the triangular soil stacking layer (7) is positioned below the steel structure inclined strut (6).
5. The cast-in-situ bored pile combined foundation pit support structure of claim 1, wherein: the length of the steel structure diagonal brace (6) is 6-9.4m.
CN202222287026.1U 2022-08-29 2022-08-29 Bored pile combination foundation pit enclosure structure Active CN218027730U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222287026.1U CN218027730U (en) 2022-08-29 2022-08-29 Bored pile combination foundation pit enclosure structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222287026.1U CN218027730U (en) 2022-08-29 2022-08-29 Bored pile combination foundation pit enclosure structure

Publications (1)

Publication Number Publication Date
CN218027730U true CN218027730U (en) 2022-12-13

Family

ID=84352213

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222287026.1U Active CN218027730U (en) 2022-08-29 2022-08-29 Bored pile combination foundation pit enclosure structure

Country Status (1)

Country Link
CN (1) CN218027730U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115233698A (en) * 2022-08-29 2022-10-25 浙江大学建筑设计研究院有限公司 Bored pile combined foundation pit support structure reserved with triangular soil and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115233698A (en) * 2022-08-29 2022-10-25 浙江大学建筑设计研究院有限公司 Bored pile combined foundation pit support structure reserved with triangular soil and construction method

Similar Documents

Publication Publication Date Title
CN1958966A (en) Underground consecutive sinking well type openweb wall body, and construction method
CN110258582B (en) Inclined support foundation pit supporting structure based on steel pipe pile and Lassen steel plate and construction method
CN110777806B (en) Multi-connecting-rod plane frame permanent supporting structure and construction process thereof
CN218027730U (en) Bored pile combination foundation pit enclosure structure
CN108385693B (en) Equal-generation anchor bolt supporting method and system for staged basement supporting
WO2004033843A2 (en) Subterranean structures and methods for constructing subterranean structures
JP4664636B2 (en) Monopile foundation construction method
CN110700270B (en) Construction method for non-drainage earthwork excavation of ultra-deep foundation pit
CN110080234B (en) Method for excavating secondary central island in deep foundation pit of soft soil foundation
CN110117959B (en) Construction method for foundation pit support near river
CN210163910U (en) Pipeline pipe jacking receiving well foundation pit supporting structure
CN111622234A (en) Unloading type thin-wall box-type retaining wall supported by obliquely and vertically combined steel pipe pile and construction process
CN215715515U (en) Municipal pipe network construction supporting integrated structure under unfavorable geological conditions
CN210887256U (en) Straight combined sheet pile-ground wall-connecting type frame of water retaining cofferdam
CN213476893U (en) Supporting structure for spanning large underground pipeline foundation pit
CN115233698A (en) Bored pile combined foundation pit support structure reserved with triangular soil and construction method
CN112962641A (en) Construction method for dismantling riverbank cofferdam structure
CN112609731A (en) Flexible permeable cutting retaining wall and construction method
CN110565666A (en) Construction method of flat combined sheet pile ground connecting wall type water retaining cofferdam
CN209760248U (en) Composite type underwater bearing platform foundation pit support structure
CN211849297U (en) Double-row tubular pile damming cofferdam in shallow water area
CN216865180U (en) Arrangement structure for treating foundation pit support of shore refuse landfill
CN216275592U (en) Anti-settlement structure of retaining wall of prestressed concrete pipe pile foundation
CN214061637U (en) Support-before-dig bored pile and inclined steel pipe enclosure
CN219119242U (en) Pipe jacking working well supporting structure for soft soil area

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant