CN217975397U - Green energy-saving tie beam steel formwork with good water cleaning effect - Google Patents

Green energy-saving tie beam steel formwork with good water cleaning effect Download PDF

Info

Publication number
CN217975397U
CN217975397U CN202221981761.6U CN202221981761U CN217975397U CN 217975397 U CN217975397 U CN 217975397U CN 202221981761 U CN202221981761 U CN 202221981761U CN 217975397 U CN217975397 U CN 217975397U
Authority
CN
China
Prior art keywords
steel form
fixedly connected
steel
block
end fixedly
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202221981761.6U
Other languages
Chinese (zh)
Inventor
黎兵勇
曲猛
肖维
杨哲
高翔
代晓清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan Xingdian Steel Formwork Steel Structure Co ltd
Original Assignee
Yunnan Xingdian Steel Formwork Steel Structure Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunnan Xingdian Steel Formwork Steel Structure Co ltd filed Critical Yunnan Xingdian Steel Formwork Steel Structure Co ltd
Priority to CN202221981761.6U priority Critical patent/CN217975397U/en
Application granted granted Critical
Publication of CN217975397U publication Critical patent/CN217975397U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model belongs to the technical field of the roof beam steel form and specifically relates to an effectual green energy-conserving tie beam steel form of clear water, including the steel form, the spacing inserted bar of left end fixedly connected with of steel form, the outside block of spacing inserted bar has the fixture block, the left end fixedly connected with fixed block of fixture block, the other end fixedly connected with commentaries on classics piece of fixed block, the outside of commentaries on classics piece is rotated and is connected with the horizontal pole, and horizontal pole and steel form fixed connection, one side fixedly connected with spring of fixed block, the other end fixedly connected with connecting plate of spring, and connecting plate and steel form fixed connection, the utility model discloses in, through spacing inserted bar, fixture block, fixed plate and the spring that set up, a plurality of steel forms splice into a whole each other through spacing inserted bar, need reutilization, directly stimulate the drawblock and dismantle, improve the installation flexibility of roof beam steel form, solve the post-weld reutilization, need cut roof beam steel form, very inconvenient problem.

Description

Effectual green energy-conserving tie beam steel form of clear water
Technical Field
The utility model relates to a roof beam steel form field specifically is an effectual green energy-conserving tie beam steel form of clear water.
Background
The steel template is a steel template for concrete pouring molding, and comprises a wood template, a plywood template and the like besides the steel template. The steel form is widely applied to building engineering due to the characteristics of multiple use, attractive concrete pouring and forming and the like.
The steel form forming must be carried out on a forming die, and bolts should be screwed in advance for bolt holes for combination assembly and during combination assembly, so that the sizes of the bolt holes or other adjacent parts are prevented from being misplaced during assembly.
The reinforcing welding of the rib skeleton net of the steel template can be performed under the forming die, and the reinforcing welding of the rib skeleton net needs to be corrected and then is performed on the forming die to combine the steel template panel.
The length of green energy-conserving tie beam steel form is fixed, when needing to splice the use, can weld the roof beam steel form, this kind of connected mode is after connecting the completion, if need the reutilization, need cut the roof beam steel form, it is very inconvenient, reduce the installation flexibility of roof beam steel form, the connection support structure is not possessed on the upper portion of roof beam steel form, lead to in the use, the roof beam steel form bears pressure too big, it cracks to appear the roof beam steel form, can't carry out the plasticity.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide an effectual green energy-conserving tie beam steel form of clear water to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above purpose, the utility model provides a following technical scheme:
the utility model provides an effectual green energy-conserving tie beam steel form of clear water, includes the steel form, the left end fixedly connected with spacing inserted bar of steel form, the outside block of spacing inserted bar has the fixture block, the left end fixedly connected with fixed block of fixture block, the other end fixedly connected with commentaries on classics piece of fixed block, the outside of commentaries on classics piece is rotated and is connected with the horizontal pole, and horizontal pole and steel form fixed connection, one side fixedly connected with spring of fixed block, the other end fixedly connected with connecting plate of spring, and connecting plate and steel form fixed connection, the inside intermediate position of steel form is rotated and is connected with the connection pivot
Preferably, the other end of the fixing block is fixedly connected with a pulling block, and the fixing block is embedded in an inner groove of the steel template.
Preferably, the steel form is the setting of splicing each other, is located the right side spacing inserted bar is located the spacing inslot portion of steel form.
Preferably, the top of steel form rotates and is connected with the support, the other end fixedly connected with locating piece of support, the inboard laminating of locating piece has the reference column, the bottom fixedly connected with girder steel of reference column, and girder steel and support laminating.
Preferably, the inner side of the positioning column is provided with a bolt, the bolt is in threaded connection with the positioning column, the top end of the bolt is fixedly connected with a safety helmet, and the safety helmet is sleeved with the positioning column.
Compared with the prior art, the beneficial effects of the utility model are that:
1. in the utility model, through the arranged limiting insertion rods, the clamping blocks, the fixing plates and the springs, a plurality of steel templates are spliced into a whole through the limiting insertion rods, secondary utilization is needed, the pulling blocks are directly pulled to be disassembled, the mounting flexibility of the beam steel template is improved, and the problem that the beam steel template is inconvenient to cut due to secondary utilization after welding is solved;
2. the utility model discloses in, through support, locating piece, girder steel and the bolt that sets up, the support formation connection support structure of opening strengthens the bulk joint strength of steel form, maintains the plasticity effect, and it is too big to solve beam steel form bearing pressure, appears the problem that beam steel form slotted.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a schematic view of the structure at A of FIG. 1 according to the present invention;
FIG. 3 is a schematic view of the mounting structure of the pull block of the present invention;
FIG. 4 is a schematic view of the installation structure of the steel form of the present invention;
fig. 5 is a schematic view of the mounting structure of the bolt of the present invention;
fig. 6 is a schematic view of the installation structure of the positioning block of the present invention.
In the figure: 1-steel moulding plate, 2-limiting inserted rod, 3-clamping block, 4-fixing plate, 5-rotating block, 6-cross rod, 7-spring, 8-connecting plate, 9-pulling block, 10-connecting rotating shaft, 11-bracket, 12-positioning block, 13-steel beam, 14-positioning column, 15-bolt and 16-safety helmet.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-6, the present invention provides a technical solution:
the utility model provides an effectual green energy-conserving tie beam steel form of clear water, including steel form 1, steel form 1's the spacing inserted bar 2 of left end fixedly connected with, the outside block of spacing inserted bar 2 has fixture block 3, the left end fixedly connected with fixed block 4 of fixture block 3, be favorable to fixed block 4 to carry out the location with spacing inserted bar 2 through fixture block 3 and be connected, fixed block 4's other end fixedly connected with commentaries on classics piece 5, the outside of commentaries on classics piece 5 is rotated and is connected with horizontal pole 6, and horizontal pole 6 and steel form 1 fixed connection, be favorable to controlling the rotation of fixed plate 4, open or closed very simple, one side fixedly connected with spring 7 of fixed block 4, spring 7's other end fixedly connected with connecting plate 8, and connecting plate 8 and steel form 1 fixed connection, steel form 1's inside intermediate position rotates and is connected with connection pivot 10, be favorable to connecting pivot 10 and connect the control of steel form 1 and open or be closed.
The other end of the fixed block 4 is fixedly connected with a pulling block 9, the fixed block 4 is embedded in the inner groove of the steel template 1, the pulling block 9 is convenient to pull the fixed block 4 to be opened in the groove of the steel template 1, and a stress point is provided; the steel templates 1 are spliced with each other, and the limiting inserted bar 2 positioned on the right side is positioned in the limiting groove of the steel templates 1, so that the steel templates 1 are spliced and connected with each other conveniently to form a long steel template 1 structure; the top end of the steel template 1 is rotatably connected with a support 11, the other end of the support 11 is fixedly connected with a positioning block 12, the inner side of the positioning block 12 is attached with a positioning column 14, the bottom end of the positioning column 14 is fixedly connected with a steel beam 13, the steel beam 13 is attached to the support 11, the support 11 is convenient to open, the positioning block 12 at the other end of the support 11 is controlled to be clamped to the outer side of the positioning column 14, the steel beam 13 is connected and installed, and the connection strength is improved; the inboard of reference column 14 is equipped with bolt 15, and bolt 15 and reference column 14 screwed connection, the top fixedly connected with safety helmet 16 of bolt 15, and safety helmet 16 cup joints with reference column 14, and the outside of reference column 14 is installed through bolt 15 to safety helmet 16 of being convenient for, improves the stability of connecting, prevents the condition of dislocation.
The working process comprises the following steps: need use longer steel form 1 to carry out construction operation, the staff transports a plurality of steel form 1 to the construction area, take out a steel form 1 as the main part, insert spacing inserted bar 2 on another steel form 1 to the spacing inslot portion of main part steel form 1, spacing inserted bar 2 promotes fixture block 3 and drives fixed plate 5 extension spring 7 and open, until spacing inserted bar 2 removes the opposite side of card income fixture block 3, connecting plate 8 pulling spring 7 resets, fixed plate 4 is through turning block 5 and horizontal pole 6 at the inside rotation of recess, carry out the location connection to spacing inserted bar 2, thereby connect two steel form 1 of installation and form wholly, can be as required, install a plurality of steel form 1, before the use, rotate and open support 11 on steel form 1 top and open, after moving girder steel 13 to the top middle part of steel form 1, butt joint block 12 of support 11 other end block 14 outside to girder steel 13, take out safety helmet 16, insert bolt 15 in safety helmet 16 to reference column 14, the spiral installation is connected together, after the use is accomplished, dismantle steel form 1, pull out behind the completion steel form 1, pull out the recess 4 outside of pulling, the pull out two independent fixture block 2, use of the pull rod 2 of the fixture block 3.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. The utility model provides an effectual green energy-conserving tie beam steel form of clear water, includes steel form (1), its characterized in that: the utility model discloses a steel form, including steel form (1), the left end fixedly connected with of steel form (1) spacing inserted bar (2), the outside block of spacing inserted bar (2) has fixture block (3), the left end fixedly connected with fixed block (4) of fixture block (3), the other end fixedly connected with commentaries on classics piece (5) of fixed block (4), the outside of commentaries on classics piece (5) is rotated and is connected with horizontal pole (6), and horizontal pole (6) and steel form (1) fixed connection, one side fixedly connected with spring (7) of fixed block (4), the other end fixedly connected with connecting plate (8) of spring (7), and connecting plate (8) and steel form (1) fixed connection, the inside intermediate position of steel form (1) is rotated and is connected with connection pivot (10).
2. The green energy-saving tie beam steel formwork with good clear water effect according to claim 1, which is characterized in that: the other end of the fixing block (4) is fixedly connected with a pulling block (9), and the fixing block (4) is embedded in an inner groove of the steel molding plate (1).
3. The green energy-saving tie beam steel formwork with good clear water effect according to claim 1, which is characterized in that: the steel form (1) is spliced with each other, and the limiting inserted rod (2) on the right side is located in a limiting groove of the steel form (1).
4. The green energy-saving tie beam steel formwork with good clear water effect according to claim 1, characterized in that: the top of steel form (1) is rotated and is connected with support (11), the other end fixedly connected with locating piece (12) of support (11), the inboard laminating of locating piece (12) has reference column (14), the bottom fixedly connected with girder steel (13) of reference column (14), and girder steel (13) and support (11) laminating.
5. The green energy-saving tie beam steel formwork with good clear water effect of claim 4, wherein: the safety helmet is characterized in that a bolt (15) is arranged on the inner side of the positioning column (14), the bolt (15) is in threaded connection with the positioning column (14), a safety helmet (16) is fixedly connected to the top end of the bolt (15), and the safety helmet (16) is sleeved with the positioning column (14).
CN202221981761.6U 2022-07-29 2022-07-29 Green energy-saving tie beam steel formwork with good water cleaning effect Expired - Fee Related CN217975397U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221981761.6U CN217975397U (en) 2022-07-29 2022-07-29 Green energy-saving tie beam steel formwork with good water cleaning effect

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221981761.6U CN217975397U (en) 2022-07-29 2022-07-29 Green energy-saving tie beam steel formwork with good water cleaning effect

Publications (1)

Publication Number Publication Date
CN217975397U true CN217975397U (en) 2022-12-06

Family

ID=84282476

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221981761.6U Expired - Fee Related CN217975397U (en) 2022-07-29 2022-07-29 Green energy-saving tie beam steel formwork with good water cleaning effect

Country Status (1)

Country Link
CN (1) CN217975397U (en)

Similar Documents

Publication Publication Date Title
CN211622592U (en) Template assembly for construction of deformation joint of building structure
CN207582956U (en) A kind of one-time formed constructing device of concrete window tongue and groove
CN203080911U (en) Inner formwork for concrete walls at deformation joint
CN203373968U (en) Filler wall constructional column formwork structure
CN106150087A (en) A kind of combined frame column template and construction method thereof
CN217975397U (en) Green energy-saving tie beam steel formwork with good water cleaning effect
CN112376896B (en) Aluminum-wood mixed formwork applied to building construction
CN207598259U (en) A kind of end molding block apparatus for lining trolley filling concrete
CN212406103U (en) Tool type super-gradient inclined roof construction template
CN116575738A (en) Wall positioning device for assembled building and application method thereof
CN114086758B (en) Loose-spliced bare concrete arc wall formwork and installation method thereof
CN206722138U (en) A kind of vertical splice bar slurry anchor connection node of fabricated shear wall exterior wall
CN206158763U (en) Install convenient tunnel invert end template
CN214302897U (en) Can have enough to meet need early constructional column pan feeding mouth of tearing open
CN112012472B (en) Building aluminum formwork aluminum profile product
CN210086296U (en) Opposite-top supporting system for subway side wall construction
CN209637208U (en) A kind of ruggedized construction that returns back to top for post-cast strip cantilever
CN111576879A (en) Construction method for plugging screw hole of outer vertical face shear wall
CN217151224U (en) Novel beam column joint template reinforcing device
CN205840314U (en) A kind of assembled inner-outer wall composite shuttering mortar leakage prevention device
CN216339045U (en) Slidingtype anticollision barrier template
CN220954645U (en) Adjustable and reusable hole template reinforcing assembly
CN210389618U (en) Bridge deck maintenance canopy
CN220790559U (en) Outer pre-buried wall spare that links of frame
CN221545582U (en) Composite construction's interlock stake structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20221206