CN217974039U - Bridge deck structure - Google Patents

Bridge deck structure Download PDF

Info

Publication number
CN217974039U
CN217974039U CN202221772776.1U CN202221772776U CN217974039U CN 217974039 U CN217974039 U CN 217974039U CN 202221772776 U CN202221772776 U CN 202221772776U CN 217974039 U CN217974039 U CN 217974039U
Authority
CN
China
Prior art keywords
slab
prefabricated
edge
slabs
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221772776.1U
Other languages
Chinese (zh)
Inventor
康玲
牟廷敏
范碧琨
阮飞鹏
张翼
王欢
邹圻
李伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Department of Transportation Highway Planning Prospecting and Design Research Institute
Original Assignee
Sichuan Department of Transportation Highway Planning Prospecting and Design Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Department of Transportation Highway Planning Prospecting and Design Research Institute filed Critical Sichuan Department of Transportation Highway Planning Prospecting and Design Research Institute
Priority to CN202221772776.1U priority Critical patent/CN217974039U/en
Application granted granted Critical
Publication of CN217974039U publication Critical patent/CN217974039U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a decking structure, include: the prefabricated slab comprises an upper layer and a lower layer, wherein the upper layer is a cast-in-place concrete slab, the lower layer comprises a plurality of prefabricated slabs, the prefabricated slabs are plain concrete slabs, edge-covered section steel is arranged on at least two slab edges of the prefabricated slabs along the transverse bridge direction, the thickness of each prefabricated slab is 2-4 cm, and the prefabricated slabs are concrete members with the compressive strength of more than or equal to 150MPa and the bending tensile strength of more than or equal to 20 MPa. The utility model discloses a decking structure is through using the high tenacity concrete that excels in and the shaped steel technique of borduring, realized reducing the thickness of precast slab to 2-4 centimetres, through the reduction of precast slab thickness, the cast in situ concrete plate thickness on upper strata has been increased, cast in situ concrete plate's cross-sectional height has been increased promptly, thereby cast in situ concrete plate's bearing capacity has been improved, and then the structural rigidity and the structural strength of combination formula decking have been improved, make its whole bearing capacity promote, prevent that the decking from ftracturing, the safety of bridge has been guaranteed.

Description

一种桥面板结构A bridge deck structure

技术领域technical field

本实用新型涉及桥面板技术领域,特别是指一种桥面板结构。The utility model relates to the technical field of bridge decks, in particular to a bridge deck structure.

背景技术Background technique

桥梁的主要结构包括墩柱、盖梁、主梁、桥面板,其中桥面板是重要的受力构件,桥面板包括组合式桥面板,组合式桥面板由上层的现浇混凝土板和下层的预制底板构成,其中,预制底板分两种:预制钢板和预制混凝土板,预制钢板涉及到钢结构焊接加工、安装、防腐等多个专业工序,导致预制钢板做预制底板的施工过程复杂,工期长,并且钢材成本高昂;而一般传统的预制混凝土板采用钢筋混凝土板,满足承载力和刚度要求的结构厚度在5厘米以上,甚至达到10厘米,结构重量大、安装困难,等厚的预制钢筋混凝土板结合等高的预制主梁,难以形成设计要求的横向坡度,只能通过现浇混凝土板来调整形成横坡,当遇到横坡较大的情况时,沿桥梁横向相邻的两块预制钢筋混凝土板拼接处的现浇混凝土板厚度不足3厘米,不满足规范对最小净保护层厚度的要求,这样形成的组合式桥面板的整体性差、承载能力低、耐久性不足,在其承受车辆等上部荷载后,容易出现开裂的情况,进而影响桥梁结构的安全。The main structure of the bridge includes piers, cap girders, main girders, and bridge decks. The bridge deck is an important force-bearing component. The bridge deck includes a combined bridge deck. There are two types of prefabricated bottom slabs: prefabricated steel plates and prefabricated concrete slabs. Prefabricated steel plates involve multiple professional processes such as steel structure welding, installation, and anti-corrosion, which makes the construction process of prefabricated steel plates for prefabricated bottom plates complicated and long. And the cost of steel is high; while traditional prefabricated concrete slabs generally use reinforced concrete slabs, the thickness of the structure that meets the requirements of bearing capacity and stiffness is more than 5 cm, or even 10 cm, and the structure is heavy and difficult to install. Combined with the prefabricated main girder of equal height, it is difficult to form the transverse slope required by the design, and the transverse slope can only be adjusted through the cast-in-place concrete slab. When the transverse slope is large, the two adjacent prefabricated steel bars The thickness of the cast-in-place concrete slab at the joint of the concrete slab is less than 3 cm, which does not meet the requirements of the code for the minimum net protective layer thickness. The combined bridge deck formed in this way has poor integrity, low bearing capacity, and insufficient durability. After the upper part is loaded, it is prone to cracking, which will affect the safety of the bridge structure.

基于以上情况,亟需一种桥面板结构,以解决传统的组合式桥面板承载力不够,容易开裂的问题。Based on the above situation, there is an urgent need for a bridge deck structure to solve the problems of insufficient bearing capacity and easy cracking of traditional combined bridge decks.

实用新型内容Utility model content

本实用新型的目的是提供一种桥面板结构,以解决传统的组合式桥面板承载力不够,容易开裂的问题。The purpose of this utility model is to provide a bridge deck structure to solve the problems of insufficient bearing capacity and easy cracking of traditional combined bridge decks.

为了达成目的,本实用新型提供一种桥面板结构,包括:In order to achieve the purpose, the utility model provides a bridge deck structure, including:

上层和下层,上层为现浇混凝土板,下层包括若干个预制板,所述预制板为素混凝土板,所述预制板的厚度为2-4厘米,所述预制板至少沿横桥向的两个板边设置有包边型钢,所述包边型钢沿对应所述板边通长设置,所述包边型钢包括下翼缘和腹板,所述下翼缘的底面和所述预制板的底面齐平,所述腹板的高度大于或等于所述预制板的厚度,所述预制板为抗压强度大于或等于150MPa、弯拉强度大于或等于20MPa的混凝土构件。The upper layer and the lower layer, the upper layer is a cast-in-place concrete slab, and the lower layer includes several prefabricated slabs, the prefabricated slabs are plain concrete slabs, the thickness of the prefabricated slabs is 2-4 cm, and the prefabricated slabs are at least along the two sides of the transverse bridge. Edge-wrapping steel is provided on each edge of the plate, and the edge-wrapping steel is arranged along the entire length of the corresponding edge of the plate. The edge-wrapping steel includes a lower flange and a web, and the bottom surface of the lower flange and the prefabricated plate The bottom surface is flush, the height of the web is greater than or equal to the thickness of the prefabricated slab, and the prefabricated slab is a concrete member with a compressive strength greater than or equal to 150MPa and a bending and tensile strength greater than or equal to 20MPa.

桥面板结构包括上层和下层,上层为现浇混凝土板,下层包括若干个预制板。预制板是预制而成,施工现场安装结构本身,无需安装、拆卸额外的模板,无需绑扎钢筋,简化了施工步骤,缩短了工期;预制板标准化生产有利于预制板质量控制;预制板为素混凝土板,其内不设置钢筋,从而使预制板厚度能够减小为2-4厘米,配合抗压强度大于或等于150MPa、弯拉强度大于或等于20MPa的混凝土浇筑而成,从而使减小厚度到2-4厘米时,还能保持足够的强度和刚度,为了弥补预制板无法设置钢筋带来的抗拉强度不够,在预制板的板边设置有包边型钢,包边型钢用于覆盖住预制板的所有板边或沿桥梁横向的板边,包边型钢的两端与其所覆盖的板边的两端相重合,包边型钢包括:下翼缘和腹板,下翼缘的底面与预制板的底面同平面,腹板的高度大于或等于预制板的厚度,包边型钢自身具备较高的强度和刚度,与预制板结合在一起,其构造技术能保证钢和混凝土共同受力,起到了加强预制板的弯拉强度和刚度的作用,提升预制板在荷载作用下抗弯曲变形能力和抗破坏能力,保证了结构安全。The bridge deck structure includes an upper floor and a lower floor, the upper floor is a cast-in-place concrete slab, and the lower floor consists of several prefabricated slabs. The prefabricated slab is prefabricated, and the structure itself is installed on the construction site without installing or dismantling additional formwork or tying steel bars, which simplifies the construction steps and shortens the construction period; the standardized production of the prefabricated slab is conducive to the quality control of the prefabricated slab; the prefabricated slab is plain concrete The slab does not have steel bars inside, so that the thickness of the prefabricated slab can be reduced to 2-4 cm, and it is poured with concrete with a compressive strength greater than or equal to 150MPa and a bending and tensile strength greater than or equal to 20MPa, so that the thickness can be reduced to When it is 2-4 cm, it can still maintain sufficient strength and rigidity. In order to make up for the insufficient tensile strength caused by the inability to install steel bars on the prefabricated slab, edge-wrapped steel is provided on the edge of the prefabricated slab, and the edge-wrapped steel is used to cover the prefabricated For all the edges of the slab or the slab edges along the transverse direction of the bridge, the two ends of the edge-wrapped steel are coincident with the two ends of the covered slab. The edge-wrapped steel includes: the lower flange and the web, the bottom surface of the lower flange and the prefabricated The bottom surface of the slab is on the same plane, and the height of the web is greater than or equal to the thickness of the prefabricated slab. The edge-wrapped steel itself has high strength and rigidity, and is combined with the prefabricated slab. To strengthen the bending and tensile strength and stiffness of the prefabricated slab, improve the bending deformation resistance and damage resistance of the prefabricated slab under load, and ensure the structural safety.

通过预制板的厚度降低,增加了上层的现浇混凝土板的厚度,即增加了现浇混凝土板的截面高度,从而提高了现浇混凝土板的承载力,进而提高了组合式桥面板的刚度和强度,使其整体承载力提升,防止桥面板开裂,保证了桥梁的安全。By reducing the thickness of the prefabricated slab, the thickness of the upper cast-in-place concrete slab is increased, that is, the cross-section height of the cast-in-place concrete slab is increased, thereby improving the bearing capacity of the cast-in-place concrete slab, and further improving the stiffness and stiffness of the combined bridge deck. Strength, so that the overall bearing capacity is improved, the bridge deck is prevented from cracking, and the safety of the bridge is ensured.

优选地,所述包边型钢仅布置在两个沿横桥向的板边。Preferably, the edge-wrapping steel is only arranged on two plate edges along the transverse bridge direction.

预制板架设在主梁上,包边型钢仅布置在两个沿横桥向的板边,根据预制板与主梁支撑关系,桥梁横向即是预制板的主受力方向,包边型钢布置在预制板主受力方向的板边,与高强高韧的预制板结合在一起,其构造技术能保证钢和混凝土共同受力,起到了加强预制板的弯拉强度和刚度的作用,提升预制板在荷载作用下抗弯曲变形能力和抗破坏能力,保证了结构安全。The prefabricated slab is erected on the main girder, and the edge-wrapped steel is only arranged on two slab edges along the transverse bridge direction. According to the support relationship between the prefabricated slab and the main beam, the transverse direction of the bridge is the main force direction of the prefabricated slab, and the edge-wrapped steel is arranged on The edge of the prefabricated slab in the main stress direction is combined with the high-strength and high-toughness prefabricated slab. Its construction technology can ensure the joint stress of steel and concrete, which plays a role in strengthening the bending and tensile strength and rigidity of the prefabricated slab, and improves the prefabricated slab. The ability to resist bending deformation and damage under load ensures the safety of the structure.

优选地,沿桥梁纵向相邻的两个所述预制板通过包边型钢连接。Preferably, two prefabricated panels adjacent to each other in the longitudinal direction of the bridge are connected by hemming steel.

沿桥梁方向纵向相邻的两个预制板通过包边型钢连接在一起,进而使若干个预制板连接起来形成整个桥面板的底板,安装过程快速高效,缩短了工期。Two prefabricated panels longitudinally adjacent to each other along the bridge direction are connected together by edge-wrapping steel, and then several prefabricated panels are connected to form the bottom plate of the entire bridge deck. The installation process is fast and efficient, and the construction period is shortened.

优选地,相邻两个所述预制板上的所述包边型钢焊接相连或螺栓连接。Preferably, the hemming section steels on two adjacent prefabricated panels are connected by welding or bolts.

相邻两个预制板上的包边型钢通过焊接相连或者螺栓连接,可以实现多个预制板的快速拼接,提高了施工效率,缩短了工期,并且焊接连接牢固可靠,为桥面板的质量提供了保证;并且包边型钢外缘整齐,焊接连接紧密不会漏浆,保证了现浇混凝土板的浇筑成型的质量。The edge-wrapped steel on two adjacent prefabricated slabs is connected by welding or bolts, which can realize the rapid splicing of multiple prefabricated slabs, improve the construction efficiency, shorten the construction period, and the welded connection is firm and reliable, which provides a guarantee for the quality of the bridge deck. Guarantee; and the outer edge of the edge-wrapped steel is neat, and the welding connection is tight without grout leakage, which ensures the quality of the pouring and molding of the cast-in-place concrete slab.

优选地,所述包边型钢上的纵向间隔设置有若干个孔洞。Preferably, several holes are arranged longitudinally at intervals on the edge-wrapping steel.

当包边型钢选用槽钢时,包边型钢的上下翼缘、腹板均沿包边型钢的纵向间隔设置有若干孔洞;当包边型钢选用角钢时,包边型钢的下翼缘、腹板均沿包边型钢的纵向间隔设置有若干孔洞。使得预制板在浇筑成型的过程中,其混凝土进入孔洞,形成混凝土抗剪榫,增强了预制板和包边型钢的连接性能,使得包边型钢和预制板可以更好的共同受力,进一步提高了预制板的弯拉承重能力。When channel steel is used for the edge-wrapped steel, the upper and lower flanges and webs of the edge-wrapped steel are provided with a number of holes along the longitudinal interval of the edge-wrapped steel; A plurality of holes are arranged at longitudinal intervals along the edge-wrapped section steel. During the pouring and forming process of the prefabricated slab, the concrete enters the hole to form a concrete shear tenon, which enhances the connection performance of the prefabricated slab and the edge-wrapped steel, so that the edge-wrapped steel and the prefabricated slab can better jointly bear the force and further improve The flexural and tensile load-bearing capacity of prefabricated panels.

优选地,所述孔洞的孔径为5-10毫米。Preferably, the hole diameter is 5-10 mm.

孔洞的孔径为5-10毫米,使得预制板在浇筑混凝土的时候可以形成足够强度的抗剪榫,进而保证预制板和包边型钢的可靠连接。The hole diameter is 5-10 mm, so that the prefabricated slab can form a shear tenon with sufficient strength when pouring concrete, thereby ensuring the reliable connection between the prefabricated slab and the edge-wrapped steel.

优选地,沿所述包边型钢的纵向相邻的两个所述孔洞的中心间距为3-6厘米。Preferably, the center-to-center distance between two adjacent holes along the longitudinal direction of the wrapping steel is 3-6 cm.

沿包边型钢的纵向相邻的两个孔洞的中心间距为3-6厘米,使得预制板上的抗剪榫的有足够的分布密度,进而保证预制板和包边型钢的可靠连接。The distance between the centers of two adjacent holes along the longitudinal direction of the edge-wrapped steel is 3-6 cm, so that the shear tenon on the prefabricated panel has sufficient distribution density, thereby ensuring the reliable connection between the prefabricated panel and the edge-wrapped steel.

优选地,所述包边型钢的腹板高度与所述预制板厚度相同。Preferably, the web height of the hemming section steel is the same as the thickness of the prefabricated panel.

包边型钢的腹板高度与所述预制板的厚度相同,在预制预制板的时候,包边型钢即作为预制板浇筑混凝土的边模,包边型钢的厚度即为预制板的厚度,方便了生产过程,并且通过固定厚度包边型钢控制住了预制板的厚度,保证了本预制混凝土板外形的一致性。The web height of the edge-wrapped steel is the same as the thickness of the prefabricated slab. When the prefabricated slab is prefabricated, the edge-wrapped steel is used as the side form for pouring concrete on the prefabricated slab. The thickness of the edge-wrapped steel is the thickness of the prefabricated slab, which is convenient. The production process, and the thickness of the prefabricated slab is controlled by the fixed-thickness hemming steel, which ensures the consistency of the shape of the prefabricated concrete slab.

优选地,所述包边型钢为槽钢,所述槽钢上翼缘的顶面与所述预制板的顶面齐平。Preferably, the edge-wrapping section steel is channel steel, and the top surface of the upper flange of the channel steel is flush with the top surface of the prefabricated panel.

包边型钢选用槽钢,槽钢的腹板紧贴预制板的板边,槽钢的上翼缘顶面和预制板的顶面齐平,下翼缘的底面与预制板的底面齐平,槽钢完整地和预制板贴合在一起,更好的与预制板一起受力工作,槽钢能够提升预制板底部的弯拉强度。The edge-wrapping section steel is made of channel steel, the web of the channel steel is close to the edge of the prefabricated slab, the top surface of the upper flange of the channel steel is flush with the top surface of the prefabricated slab, and the bottom surface of the lower flange is flush with the bottom surface of the prefabricated slab. The channel steel is completely attached to the prefabricated slab, and it can work better with the prefabricated slab. The channel steel can improve the bending and tensile strength of the bottom of the prefabricated slab.

优选地,所述预制板的上表面为拉毛形态。Preferably, the upper surface of the prefabricated panel is in the shape of nap.

预制板在混凝土浇筑完毕后对其上表面进行拉毛处理,使得预制板的上表面粗糙,可以更好的与现浇混凝土板紧密结合在一起,提高了桥梁的耐久性。After the concrete is poured, the upper surface of the prefabricated slab is roughened, so that the upper surface of the precast slab is rough and can be better combined with the cast-in-place concrete slab to improve the durability of the bridge.

本实用新型至少包括以下有益效果:The utility model at least includes the following beneficial effects:

本实用新型的桥面板结构通过使用抗压强度大于或等于150MPa、弯拉强度大于或等于20MPa的高强高韧性混凝土,取消预制板内钢筋,以及设置包边型钢,实现了将预制混凝土板的厚度减少为2-4厘米。首先,预制板满足承重能力和结构刚度要求,其次,通过预制板厚度降低,减轻了自重、安装方便,减小了施工难度和工人劳动强度,最后,增加了上层的一次性整体现浇的现浇混凝土板的厚度,即增加了现浇混凝土板的截面高度,其整体性得到提高,进而提高了预制板和现浇混凝土板组成的组合式桥面板的结构刚度和结构强度。强劲的组合式桥面板可加强单片主梁之间的联系,使离散性的主梁形成整体结构,桥梁的抗扭、抗弯和整体稳定性都得到大幅提升。包边型钢不仅提高了预制板的承载能力,还起到了连接预制板的作用,并且连接紧密,不漏浆,保证了现浇混凝土板的成型质量;包边型钢上的孔洞与预制板上剪力隼咬合,更好的共同受力,预制板的上表面拉毛处理,使得预制板和现浇混凝土板的结合更加紧密,提高了桥梁的耐久性。The bridge deck structure of the utility model realizes reducing the thickness of the prefabricated concrete slab by using high-strength and high-toughness concrete with a compressive strength greater than or equal to 150MPa and a bending and tensile strength greater than or equal to 20MPa, canceling the steel bars in the prefabricated slab, and setting the edge-wrapped steel. Reduced to 2-4 cm. First of all, the prefabricated slab meets the requirements of load-bearing capacity and structural rigidity. Secondly, the thickness of the prefabricated slab is reduced, which reduces the self-weight, facilitates installation, and reduces the difficulty of construction and labor intensity of workers. Finally, the one-time overall cast-in-situ cast-in-place The thickness of the poured concrete slab increases the section height of the cast-in-place concrete slab, and its integrity is improved, thereby improving the structural rigidity and structural strength of the combined bridge deck composed of the prefabricated slab and the cast-in-place concrete slab. The strong combined bridge deck can strengthen the connection between the single main girders, so that the discrete main girders form an overall structure, and the torsional, bending and overall stability of the bridge are greatly improved. The edge-wrapped steel not only improves the bearing capacity of the prefabricated slab, but also plays the role of connecting the prefabricated slab, and the connection is tight without grout leakage, which ensures the molding quality of the cast-in-place concrete slab; The force falcon occlusal, better common force, the upper surface of the precast slab is roughened, which makes the combination of the precast slab and the cast-in-place concrete slab more tightly, and improves the durability of the bridge.

附图说明Description of drawings

图1是本实用新型的桥面板结构的结构示意图。Fig. 1 is a structural schematic diagram of the bridge deck structure of the present invention.

图2是本实用新型的预制板的示意图。Fig. 2 is a schematic diagram of the prefabricated panel of the present invention.

图3是图2的局部放大图。FIG. 3 is a partially enlarged view of FIG. 2 .

图4是本实用新型的预制板的弯拉承载能力试验的数据图。Fig. 4 is a data diagram of the bending and pulling bearing capacity test of the prefabricated panel of the present invention.

附图标记:1-预制板,2-包边型钢,3-孔洞,4-现浇混凝土板。Reference signs: 1-prefabricated slab, 2-wrapping section steel, 3-hole, 4-cast-in-place concrete slab.

具体实施方式detailed description

下面结合附图和实施例对本实用新型的技术内容进行进一步说明:Below in conjunction with accompanying drawing and embodiment the technical content of the present utility model is further described:

实施例一Embodiment one

如图1、2、3所示,桥面板结构包括上层和下层,上层为现浇混凝土板4,下层包括若干个预制板1,若干个预制板1沿纵桥向拼接成列,并根据桥梁的宽度需要,可以横向拼接成多列,形成桥面板结构的下层,预制板1横向拼接的拼缝位于主梁顶面。预制板1根据桥梁受力情况采用抗压强度大于或等于150MPa、弯拉强度大于或等于20MPa的混凝土,混凝土抗压强度大于或等于60MPa即为高强度混凝土,预制板1具备高强高韧的特点,并仅在横桥向的板边设置包边型钢2,包边型钢2选用槽钢,槽钢的上翼缘的顶面与预制板1的顶面同平面,槽钢的下翼缘的底面与预制板1的底面同平面,槽钢的腹板紧贴预制板1的板边的侧面,下翼缘增强了预制板1底部的抗拉强度,腹板提高了预制板1的竖向刚度,上翼缘增强了预制板1顶部抗压强度,包边型钢2与预制板1结合在一起,其构造技术能保证钢和混凝土共同受力,起到了加强预制板1的弯拉强度和刚度的作用,提升预制板1在荷载作用下抗弯曲变形能力和抗破坏能力,从而将预制板1的厚度从传统的5-10厘米减少到2厘米,通过预制板1的厚度降低,增加了上层的现浇混凝土板4的厚度,即增加了现浇混凝土板4的截面高度,从而提高了现浇混凝土板4的承载力,进而提高了组合式桥面板的刚度和强度,使其整体承载力提升,防止桥面板开裂,保证了桥梁的安全。As shown in Figures 1, 2, and 3, the bridge deck structure includes an upper layer and a lower layer. The upper layer is a cast-in-place concrete slab 4, and the lower layer includes several prefabricated slabs 1. The width of the prefabricated panels can be spliced into multiple columns horizontally to form the lower layer of the bridge deck structure, and the joints of the prefabricated panels 1 horizontally spliced are located on the top surface of the main girder. The prefabricated slab 1 adopts concrete with a compressive strength greater than or equal to 150MPa and a bending and tensile strength greater than or equal to 20MPa according to the stress of the bridge. The concrete compressive strength greater than or equal to 60MPa is high-strength concrete. The prefabricated slab 1 has the characteristics of high strength and high toughness , and set the edge-wrapped steel 2 only on the edge of the transverse bridge, the edge-wrapped steel 2 is channel steel, the top surface of the upper flange of the channel steel is in the same plane as the top surface of the prefabricated slab 1, and the lower flange of the channel steel The bottom surface is on the same plane as the bottom surface of the prefabricated slab 1, the web of the channel steel is close to the side of the slab edge of the prefabricated slab 1, the lower flange enhances the tensile strength of the bottom of the prefabricated slab 1, and the web improves the vertical direction of the prefabricated slab 1. Rigidity, the upper flange enhances the compressive strength of the top of the prefabricated slab 1, and the edge-wrapped steel 2 is combined with the prefabricated slab 1. Its construction technology can ensure the joint force of steel and concrete, and strengthen the bending and tensile strength of the prefabricated slab 1. The role of stiffness improves the bending deformation resistance and damage resistance of the prefabricated slab 1 under load, thereby reducing the thickness of the prefabricated slab 1 from the traditional 5-10 cm to 2 cm. By reducing the thickness of the prefabricated slab 1, the The thickness of the cast-in-place concrete slab 4 on the upper layer increases the cross-section height of the cast-in-place concrete slab 4, thereby improving the bearing capacity of the cast-in-place concrete slab 4, thereby increasing the stiffness and strength of the combined bridge deck, so that the overall load-carrying The force is lifted, the bridge deck is prevented from cracking, and the safety of the bridge is ensured.

包边型钢2的规格为:腹板高2厘米,上下翼缘宽度2厘米,厚度2毫米,包边型钢2的腹板和上下翼缘均设有若干孔洞3,孔洞3的孔径为5-10毫米,此方案中优选为7毫米,相邻孔洞3的中心间距为3-6厘米,此方案中优选为4厘米,在预制板1预制过程中,包边型钢2可以作为预制板1的边模,预制板1的混凝土流入孔洞3,形成抗剪榫,使得包边型钢2和预制板1紧密咬合在一起,更好的共同工作;预制板1的形状采用矩形,矩形拼装简单,除纵横方向要放置正确外,无需按其他特定规则进行拼装,大大提高了安装效率,缩短了工期,预制板1可以只生产一种标准规格的桥面板,无需多开发模具,提高了生产效率,降低了生产成本;包边型钢2设置在预制板1沿桥面横向的板边上,即预制板1的主受力方向的板边,提高了预制板1假设在主梁上时的承载力,在预制板1和现浇混凝土板4粘合在一起后,预制板1能够成为桥面板受力的一部分,共同承担桥面荷载;相邻的板预制板1通过包边型钢2焊接相连,即保证了预制板1连接的可靠性,还能保住预制板1连接的密封性,在现浇混凝土板4浇筑的过程中,不会漏浆,保证了现浇混凝土板4的成型质量;预制预制板1的过程中,预制板1的上表面拉毛处理,增加预制板1上表面的粗糙程度,使得现浇混凝土板4和预制板1粘接的更加牢固,提高了桥面结构的耐久性。The specifications of the edge-wrapped steel 2 are: the web is 2 cm high, the width of the upper and lower flanges is 2 cm, and the thickness is 2 mm. The web and the upper and lower flanges of the edge-wrapped steel 2 are all provided with some holes 3, and the aperture of the holes 3 is 5- 10 millimeters, preferably 7 millimeters in this scheme, the center-to-center spacing of adjacent holes 3 is 3-6 centimeters, preferably 4 centimeters in this scheme, in the prefabricated process of prefabricated slab 1, hemming steel 2 can be used as prefabricated slab 1 The concrete of the prefabricated slab 1 flows into the hole 3 to form a shear tenon, so that the edge-wrapped steel 2 and the prefabricated slab 1 are closely occluded and work together better; the shape of the prefabricated slab 1 is rectangular, and the rectangular assembly is simple. The vertical and horizontal directions must be placed correctly, and there is no need to assemble according to other specific rules, which greatly improves the installation efficiency and shortens the construction period. The production cost is reduced; the edge-wrapped steel 2 is arranged on the edge of the prefabricated slab 1 along the transverse direction of the bridge deck, that is, the slab edge of the main stress direction of the prefabricated slab 1, which improves the bearing capacity of the prefabricated slab 1 when it is assumed to be on the main girder. After the prefabricated slab 1 and the cast-in-place concrete slab 4 are bonded together, the prefabricated slab 1 can become a part of the bridge deck to bear the load of the bridge deck; the adjacent prefabricated slabs 1 are connected by welding with the edge-wrapped steel 2, namely The reliability of the connection of the prefabricated slab 1 is guaranteed, and the sealing of the connection of the prefabricated slab 1 can also be kept. During the pouring process of the cast-in-place concrete slab 4, there will be no grout leakage, which ensures the molding quality of the cast-in-place concrete slab 4; During the slab 1 process, the upper surface of the precast slab 1 is roughened to increase the roughness of the upper surface of the precast slab 1, so that the cast-in-place concrete slab 4 and the precast slab 1 are bonded more firmly, and the durability of the bridge deck structure is improved.

包边型钢2还可选用为角钢,角钢的下翼缘底面与预制板1底面同平面,角钢的腹板紧贴预制板1的板边的侧面,下翼缘增强预制板1底部的抗拉强度,腹板提升预制板1的竖向刚度,角钢上同样设置有孔洞3,用以在预制板1上形成抗剪榫,增强预制板1与角钢的连接。The edge-wrapped steel 2 can also be selected as angle steel, the bottom of the lower flange of the angle steel is on the same plane as the bottom of the prefabricated panel 1, the web of the angle steel is close to the side of the edge of the prefabricated panel 1, and the lower flange strengthens the tensile strength of the bottom of the prefabricated panel 1. Intensity, the web enhances the vertical stiffness of the prefabricated slab 1, and the angle steel is also provided with holes 3, which are used to form a shear tenon on the prefabricated slab 1 and strengthen the connection between the prefabricated slab 1 and the angle steel.

沿桥梁纵向相邻的预制板1通过包边型钢2连接,包边型钢2通采用螺栓连接,包边型钢2上设置有连接耳,螺栓穿过连接耳将相邻的包边型钢2连接起来,不涉及焊接的特殊工种,施工难度降低,连接速度快,缩短了工期,并且螺栓连接的强度大,稳定可靠,提高了工程质量。Adjacent prefabricated panels 1 along the longitudinal direction of the bridge are connected by hemming steel 2, and the hemming steel 2 is connected by bolts, and the hemming steel 2 is provided with connecting ears, and the bolts pass through the connecting ears to connect adjacent hemming steels 2 , special type of work that does not involve welding, the construction difficulty is reduced, the connection speed is fast, the construction period is shortened, and the bolt connection is strong, stable and reliable, and the project quality is improved.

孔洞3还可以沿包边型钢2的纵向仅间隔设置在包边型钢2的腹板上。使得预制板1在浇筑成型的过程中,其混凝土进入孔洞3,形成混凝土抗剪榫,增强了预制板1和包边型钢2的连接性能,使得包边型钢2和预制板1可以更好的共同受力,提高了本预制混凝土板的耐久度。The holes 3 can also be arranged only at intervals on the web of the hemming steel 2 along the longitudinal direction of the hemming steel 2 . During the pouring process of the prefabricated slab 1, its concrete enters the hole 3 to form a concrete shear tenon, which enhances the connection performance between the prefabricated slab 1 and the edge-wrapped steel 2, so that the edge-wrapped steel 2 and the prefabricated slab 1 can be better Joint stress improves the durability of the prefabricated concrete slab.

孔洞3还可以沿包边型钢2的纵向仅间隔设置在包边型钢2的翼缘上。使得预制板1在浇筑成型的过程中,其混凝土进入孔洞3,形成混凝土抗剪榫,增强了预制板1和包边型钢2的连接性能,使得包边型钢2和预制板1可以更好的共同受力,提高了本预制混凝土板的耐久度。The holes 3 can also be arranged only at intervals along the longitudinal direction of the hemming shaped steel 2 on the flange of the hemming shaped steel 2 . During the pouring process of the prefabricated slab 1, its concrete enters the hole 3 to form a concrete shear tenon, which enhances the connection performance between the prefabricated slab 1 and the edge-wrapped steel 2, so that the edge-wrapped steel 2 and the prefabricated slab 1 can be better Joint stress improves the durability of the prefabricated concrete slab.

包边型钢2还可以设置在预制板1的四边,大大增加了预制板1的强度和刚度,进一步增加了桥面板的强度和刚度。The edge-wrapped steel 2 can also be arranged on the four sides of the prefabricated slab 1, which greatly increases the strength and rigidity of the prefabricated slab 1 and further increases the strength and rigidity of the bridge deck.

包边型钢2还可以设置在预制板1的沿横桥的两个板边以及沿纵桥向的一个板边,大大增加了预制板1的强度和刚度,进一步增加了桥面板的强度和刚度。The edge-wrapping steel 2 can also be arranged on two plate edges along the transverse bridge and one plate edge along the longitudinal bridge direction of the prefabricated slab 1, which greatly increases the strength and rigidity of the prefabricated slab 1 and further increases the strength and rigidity of the bridge deck .

预制板弯拉承载能力试验数据,如图4所示:本实验的实验对象是:规格为100厘米*50厘米*2厘米的预制板1,试验目的是:该预制板1分别在有设置包边型钢2与未设置包边型钢2的情况下的弯拉承载能力的对比,(包边型钢2规格为:腹板高2厘米,上下翼缘宽度2厘米,厚度2毫米,包边型钢2的腹板及上下翼缘均设置有孔洞3,孔洞3的孔径为7毫米,沿包边型钢2的纵向相邻的两个孔洞3的中心间距为4厘米。包边型钢2的设置方式如图2所示)。试验结果为:设置包边型钢2的预制板1的弯拉极限承载能力为8.3kN,未设置包边型钢2的预制板1的弯拉极限承载能力为3.5kN,前者为后者的2.4倍,足以证明包边型钢2使得预制板1的弯拉承载能力大幅度提升。The test data of the bending and tensile bearing capacity of the prefabricated slab is shown in Figure 4: the experimental object of this experiment is: a prefabricated slab 1 with a specification of 100 cm * 50 cm * 2 cm, and the purpose of the test is: the prefabricated slab 1 is installed in a package The comparison of the bending and tensile bearing capacity of the edge-shaped steel 2 and that without the edge-wrapped steel 2, (the specifications of the edge-wrapped steel 2 are: the web height is 2 cm, the width of the upper and lower flanges is 2 cm, and the thickness is 2 mm, and the edge-wrapped steel 2 The web and the upper and lower flanges of the web are all provided with holes 3, and the aperture of the holes 3 is 7 millimeters, and the center-to-center spacing of two adjacent holes 3 along the longitudinal direction of the edge-wrapping steel 2 is 4 centimeters. The setting mode of the edge-wrapping steel 2 is as follows Figure 2). The test results are: the bending and tensile ultimate load-bearing capacity of the prefabricated panel 1 with edge-wrapped steel 2 is 8.3kN, and the bending-tensile ultimate load-bearing capacity of the prefabricated panel 1 without edge-wrapped steel 2 is 3.5kN, the former is 2.4 times of the latter , which is enough to prove that the edge-wrapped steel 2 greatly improves the bending and tensile bearing capacity of the prefabricated panel 1 .

需要理解的是,本实用新型并不局限于上述特定实施方式,本领域技术人员可以在权利要求的范围内做出各种形式的变形和修改,这并不影响本实用新型的实质内容。It should be understood that the utility model is not limited to the above-mentioned specific embodiments, and those skilled in the art can make various forms of deformation and modification within the scope of the claims, which do not affect the essence of the utility model.

Claims (10)

1. A deck slab structure comprising: upper strata and lower floor, its characterized in that: the prefabricated slab structure is characterized in that the upper layer is a cast-in-place concrete slab (4), the lower layer comprises a plurality of prefabricated slabs (1), the prefabricated slabs (1) are plain concrete slabs, the thickness of the prefabricated slabs (1) is 2-4 cm, at least two slab edges of the prefabricated slabs (1) in the transverse bridge direction are provided with edge-wrapped section steel (2), the edge-wrapped section steel (2) is arranged along the length corresponding to the slab edges, the edge-wrapped section steel (2) comprises a lower flange and a web plate, the bottom surface of the lower flange is flush with the bottom surface of the prefabricated slabs, the height of the web plate is larger than or equal to the thickness of the prefabricated slabs (1), and the prefabricated slabs (1) are concrete members with the compressive strength larger than or equal to 150MPa and the bending tensile strength larger than or equal to 20 MPa.
2. Bridge deck structure according to claim 1, characterized in that said profiled edge cladding bars (2) are arranged only at two plate edges in the transverse direction.
3. Bridge deck structure according to claim 2, characterized in that two of said precast slabs (1) adjacent in the longitudinal direction of the bridge are connected by a profiled bar (2) with a border.
4. Bridge deck structure according to claim 3, characterized in that said profiled edge sections (2) of two adjacent precast slabs (1) are welded or bolted.
5. Bridge deck structure according to claim 1, characterized in that a number of holes (3) are provided in the profiled edge section (2) at longitudinal intervals.
6. Bridge deck structure according to claim 5, characterized in that said holes (3) have a diameter of 5-10 mm.
7. Bridge deck structure according to claim 6, characterized in that the centre-to-centre spacing of two said holes (3) adjacent in the longitudinal direction of said profiled section (2) is 3-6 cm.
8. Bridge deck structure according to claim 1, characterized in that the web height of said profiled edge sections (2) is the same as the thickness of said precast slabs (1).
9. The deck panel structure according to claim 8, characterised in that the channel section steel (2) is a channel steel, and the top surface of the upper flange of the channel steel is flush with the top surface of the precast slab (1).
10. Bridge deck structure according to any of claims 1-9, characterized in that the upper surface of said precast slab (1) is of napped form.
CN202221772776.1U 2022-07-11 2022-07-11 Bridge deck structure Active CN217974039U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221772776.1U CN217974039U (en) 2022-07-11 2022-07-11 Bridge deck structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221772776.1U CN217974039U (en) 2022-07-11 2022-07-11 Bridge deck structure

Publications (1)

Publication Number Publication Date
CN217974039U true CN217974039U (en) 2022-12-06

Family

ID=84277275

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221772776.1U Active CN217974039U (en) 2022-07-11 2022-07-11 Bridge deck structure

Country Status (1)

Country Link
CN (1) CN217974039U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115058968A (en) * 2022-07-11 2022-09-16 四川省公路规划勘察设计研究院有限公司 a bridge deck structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115058968A (en) * 2022-07-11 2022-09-16 四川省公路规划勘察设计研究院有限公司 a bridge deck structure

Similar Documents

Publication Publication Date Title
CN105002816B (en) Prefabricated and assembled fish-belly I-shaped prestressed steel-concrete composite continuous girder bridge and its construction method
CN113202219B (en) Fully prefabricated assembled steel-concrete composite floor system and design calculation method
CN114592436B (en) Pier capping beam lower support system and construction method thereof
CN108978434B (en) Bracket-free industrialized construction method of steel-concrete combined continuous box girder bridge
CN107476476A (en) Combined construction method of long-span steel bar truss floor bearing plate and reinforced concrete beam
CN105064196A (en) Prefabricated and assembled fish-belly I-shaped prestressed steel-concrete composite simple supported girder bridge and construction method thereof
CN111305066A (en) Hybrid combination beam steel-concrete combination section and mounting method thereof
CN111254800A (en) A composite beam suitable for urban bridges and its construction method
CN109881587B (en) Integral installation method of main tower upper cross beam support in strong wind environment
CN207686092U (en) A kind of assembled overlapped hollow floor system
CN112962416A (en) Steel plate girder bridge suitable for mountain area construction and construction method thereof
CN211522899U (en) Long-span steel-concrete composite beam convenient to erect by bridge girder erection machine
CN217974039U (en) Bridge deck structure
CN217974005U (en) Combined box girder structure
CN110184903B (en) A truss-type prefabricated pipe column assembled bridge pier
CN205188793U (en) Prefabricated fish belly I shape prestressing force steel and concrete composite continuous bridge of assembling
CN110644662A (en) Prefabricated flat slab composite slab based on stress and splitting method thereof
CN212426749U (en) Hybrid reinforced concrete joint section
CN116771182B (en) Building structure of electronic factory building and construction method thereof
CN209703805U (en) A new type of composite floor suitable for H-shaped steel beams in steel structures
CN218345930U (en) Bridge structure
CN206503063U (en) Prefabricated assembled Wavelike steel webplate T beam bridges
CN215629484U (en) A transverse reinforcement device for a T-beam bridge
CN212388355U (en) A bridge deck structure of a steel truss bridge
CN109853806A (en) It overlaps concrete steel ladder mouth and splices two-way floor

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant