CN217949071U - Utility tunnel excavation supporting tubular pile and steel waist roof beam connection structure - Google Patents
Utility tunnel excavation supporting tubular pile and steel waist roof beam connection structure Download PDFInfo
- Publication number
- CN217949071U CN217949071U CN202222483871.6U CN202222483871U CN217949071U CN 217949071 U CN217949071 U CN 217949071U CN 202222483871 U CN202222483871 U CN 202222483871U CN 217949071 U CN217949071 U CN 217949071U
- Authority
- CN
- China
- Prior art keywords
- steel
- steel waist
- tubular pile
- waist beam
- pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Abstract
The utility model provides a comprehensive pipe gallery foundation pit supporting tubular pile and steel waist beam connecting structure, which comprises a tubular pile, a pre-buried sleeve, a steel waist beam, a steel bracket and a steel support; the pipe pile is of a precast reinforced concrete pile structure, a round steel plate is further arranged in the pipe pile to serve as a supporting plate, a concrete filling core is filled on the supporting plate, a layer of embedded sleeve is embedded outside the middle section of the pipe pile, one side of the embedded sleeve is connected with a steel waist beam in a welding mode, and gaps between the embedded sleeve and the steel waist beam are filled and filled with concrete; the bottom surface of the steel waist beam is connected with a steel corbel in a welding mode, the side surface of the steel corbel is fixedly connected with the embedded sleeve, and a stiffening rib which is perpendicular to the extending direction of the steel waist beam is arranged in the steel waist beam; one side of the steel waist beam back to the tubular pile is fixedly connected with a steel support.
Description
Technical Field
The utility model relates to a municipal works field especially relates to a utility tunnel excavation supporting tubular pile and steel waist roof beam connection structure.
Background
The utility tunnel is an important ring in municipal engineering, namely, a tunnel space is built under the city, various engineering pipelines such as electric power, communication, gas, heat supply, water supply and drainage and the like are integrated, a special overhaul port, a special hoisting port and a special monitoring system are arranged, unified planning, unified design, unified construction and management are implemented, and the utility tunnel is an important infrastructure and a 'life line' for guaranteeing city operation. Wherein generally through built-in fitting welded connection between utility tunnel tubular pile basis and the piping lane support, shift play appears easily when meetting great load and longitudinal vibration, probably leads to appearing the clearance, influences piping lane structure safety.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to prior art's defect and not enough, provide a municipal works utility tunnel tubular pile and steel waist roof beam connection structure, solve generally through built-in fitting welded connection between utility tunnel tubular pile basis and the piping lane support, shift the drunkenness appears easily when meetting great load and longitudinal vibration, probably lead to appearing the clearance, influence the problem of piping lane structure safety.
In order to achieve the purpose, the utility model adopts the technical proposal that: a connection structure of a comprehensive pipe gallery foundation pit supporting tubular pile and a steel waist beam comprises a tubular pile, a pre-buried sleeve, a steel waist beam, a steel corbel and a steel support; the pipe pile is of a precast reinforced concrete row pile structure, a round steel plate is arranged in the pipe pile and serves as a supporting plate, and a concrete filling core is filled on the supporting plate; a layer of embedded sleeve is embedded outside the middle section of the pipe pile, one side of the embedded sleeve is connected with a steel waist beam in a welding mode, and gaps between the embedded sleeve and the steel waist beam are filled and filled with concrete; the bottom surface of the steel waist beam is welded and connected with a steel corbel, the side surface of the steel corbel is fixedly connected with the embedded sleeve, and a stiffening rib which is vertical to the extension direction of the steel waist beam is arranged in the steel waist beam; one side of the steel waist beam back to the tubular pile is fixedly connected with a steel support.
Preferably, the horizontal spacing between the stiffening ribs is not more than 100mm, and the side edges of the stiffening ribs and the steel waist beam are in full-welded connection.
Preferably, the thickness of the embedded sleeve is not less than 8mm, and the length of the embedded sleeve is not less than 500mm.
Preferably, the thickness of the steel corbels is not less than 10mm, and the horizontal distance between the steel corbels is not more than 400mm.
The utility model has the advantages that: the structure forms stable and reliable connection to the tubular pile and the steel support through the steel waist beam, and simultaneously strengthens the bearing and shearing resistance of the steel waist beam by the steel corbels and the stiffening ribs, thereby reducing the risk of displacement and play.
Drawings
The accompanying drawings, which are included to provide a further understanding of the invention and are incorporated in and constitute a part of this application, illustrate embodiment(s) of the invention and together with the description serve to explain the principles of the invention.
Fig. 1 is a schematic view of a connection structure of a municipal engineering comprehensive pipe gallery tubular pile and a steel waist beam, and fig. 2 is a schematic view of a-a section.
Wherein: the concrete pile comprises a tubular pile 1, a supporting plate 11, a pre-embedded sleeve 2, concrete filling 21, a steel waist beam 3, a stiffening rib 31, a steel corbel 4 and a steel support 5.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
As shown in the figure, the connection structure of the comprehensive pipe gallery foundation pit supporting pipe pile and the steel waist beam comprises a pipe pile 1, a pre-buried sleeve 2, a steel waist beam 3, a steel bracket 4 and a steel support 5; the tubular pile 1 is a reinforced concrete filling row pile foundation structure, a round steel plate is further arranged in the tubular pile 1 to serve as a supporting plate 11, and a concrete filling core is filled on the supporting plate 11; a layer of embedded sleeve 2 is embedded outside the middle section of the tubular pile 1, one side of the embedded sleeve 2 is connected with a steel waist beam 3 in a welding mode, and gaps between the embedded sleeve 2 and the steel waist beam 3 are filled with concrete 21; the bottom surface of the steel waist beam 3 is connected with a steel bracket 4 in a welding way, the side surface of the steel bracket 4 is fixedly connected with the embedded sleeve 2, and a stiffening rib 31 which is vertical to the extension direction of the steel waist beam 3 is arranged in the steel waist beam 3; and one side of the steel waist beam 3, which is back to the tubular pile 1, is fixedly connected with a steel support 5.
In specific implementation, the horizontal distance between the stiffening ribs 31 is 100mm, and the side edges of the stiffening ribs 31 are in full-welded connection with the steel waist beam 3.
When the concrete implementation, the thickness of embedded sleeve 2 is 8mm, and embedded sleeve 2's length is 650mm.
In specific implementation, the thickness of the steel corbels 4 is 10mm, and the horizontal distance between the steel corbels 4 is 400mm.
Claims (4)
1. A connection structure of a comprehensive pipe gallery foundation pit supporting tubular pile and a steel waist beam comprises the tubular pile, a pre-buried sleeve, the steel waist beam, a steel corbel and a steel support; the tubular pile is for prefabricating reinforced concrete pile structure, still is provided with the round steel plate in this tubular pile as the layer board, and it has the concrete to fill out the core, its characterized in that to fill on the layer board: a layer of embedded sleeve is embedded outside the middle section of the pipe pile, one side of the embedded sleeve is connected with a steel waist beam in a welding mode, and gaps between the embedded sleeve and the steel waist beam are filled and filled with concrete; the bottom surface of the steel waist beam is welded and connected with a steel corbel, the side surface of the steel corbel is fixedly connected with the embedded sleeve, and a stiffening rib which is vertical to the extension direction of the steel waist beam is arranged in the steel waist beam; one side of the steel waist beam back to the tubular pile is fixedly connected with a steel support.
2. The utility model discloses a utility tunnel excavation supporting tubular pile and steel waist roof beam connection structure of claim 1, its characterized in that: the horizontal distance between the stiffening ribs is not more than 100mm, and the sides of the stiffening ribs are in full-welding connection with the steel waist beam.
3. The utility model discloses a utility tunnel excavation supporting tubular pile and steel waist roof beam connection structure of claim 1, its characterized in that: the thickness of the embedded sleeve is not less than 8mm, and the length of the embedded sleeve is not less than 500mm.
4. The utility model discloses a utility tunnel excavation supporting tubular pile and steel waist roof beam connection structure of claim 1, its characterized in that: the thickness of steel corbels is no less than 10mm, and the horizontal interval between the steel corbels is not more than 400mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222483871.6U CN217949071U (en) | 2022-09-19 | 2022-09-19 | Utility tunnel excavation supporting tubular pile and steel waist roof beam connection structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222483871.6U CN217949071U (en) | 2022-09-19 | 2022-09-19 | Utility tunnel excavation supporting tubular pile and steel waist roof beam connection structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN217949071U true CN217949071U (en) | 2022-12-02 |
Family
ID=84212604
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202222483871.6U Active CN217949071U (en) | 2022-09-19 | 2022-09-19 | Utility tunnel excavation supporting tubular pile and steel waist roof beam connection structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN217949071U (en) |
-
2022
- 2022-09-19 CN CN202222483871.6U patent/CN217949071U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103233459B (en) | A kind of construction method of two-in-one double steel plate Combined concrete diaphragm wall | |
CN107460888B (en) | Mounting structure and method for concrete prefabricated pipe gallery | |
CN106381886A (en) | Partially-prefabricated assembled steel and concrete combined utility tunnel | |
CN111997194A (en) | Fabricated concrete primary and secondary beam structure and dry-type connecting method thereof | |
CN201502060U (en) | Bored pile double pile casing system | |
CN217949071U (en) | Utility tunnel excavation supporting tubular pile and steel waist roof beam connection structure | |
CN103643681A (en) | Subway station foundation ditch inverse constructed supporting structure and construction method thereof | |
CN210395437U (en) | Utility tunnel and prefabricated pipe thereof with self-repairing function | |
CN107152034A (en) | A kind of pipe gallery and its construction method | |
CN217325391U (en) | Construction tool for high-speed rail line deep foundation pit secant pile | |
CN210887303U (en) | Coincide assembled utility tunnel structure | |
CN210482379U (en) | Highway underpass pipe gallery structure | |
CN218233537U (en) | Single double-wall steel cofferdam for bridge construction | |
CN217683557U (en) | Prefabricated sleeper beam of municipal works concrete pipe | |
CN217949134U (en) | Municipal works utility tunnel stake wall connection structure that shears | |
CN218540775U (en) | Special well seat of rectangle assembled inspection shaft | |
CN214657234U (en) | Reinforced concrete inspection shaft | |
CN213417893U (en) | Assembled utility tunnel | |
CN217003419U (en) | Calandria location prefabricated module and calandria device | |
CN212175853U (en) | Assembled piping lane | |
CN212224131U (en) | Assembly type concrete collecting and draining trough with kerbs | |
CN220100859U (en) | Single-row grouting sleeve type water culture pond wall | |
CN212427505U (en) | Assembled concrete column beam dry-type connecting structure | |
CN217782295U (en) | Simple and easy apron is contained | |
CN210622813U (en) | Underground pressure shield water delivery tunnel lining structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |