CN217870927U - Assembled work platform - Google Patents

Assembled work platform Download PDF

Info

Publication number
CN217870927U
CN217870927U CN202222134882.3U CN202222134882U CN217870927U CN 217870927 U CN217870927 U CN 217870927U CN 202222134882 U CN202222134882 U CN 202222134882U CN 217870927 U CN217870927 U CN 217870927U
Authority
CN
China
Prior art keywords
locking
block
fixing
groove
supporting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222134882.3U
Other languages
Chinese (zh)
Inventor
方凯
沈毓陶
杜文皓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Lianghuai Construction Co ltd
Original Assignee
Anhui Lianghuai Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Lianghuai Construction Co ltd filed Critical Anhui Lianghuai Construction Co ltd
Priority to CN202222134882.3U priority Critical patent/CN217870927U/en
Application granted granted Critical
Publication of CN217870927U publication Critical patent/CN217870927U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The application discloses assembled work platform belongs to the work platform field, and it includes a plurality of supporting shoes, subaerial having seted up and having supported the groove, is provided with the pipeline on supporting the lateral wall in groove, a plurality of supporting shoes all with the pipeline offsets, every all be provided with on the lateral wall of supporting shoe be used for with adjacent the fixed subassembly of supporting shoe is fixed. This application has and resets through setting up, can remove the fixing between two adjacent supporting shoes to the completion carries out the purpose dismantled with a plurality of supporting shoes, and then can reduce the effect of building material's waste when building operation platform.

Description

Assembled work platform
Technical Field
The application relates to the field of operation platforms, in particular to an assembly type operation platform.
Background
Working wells are required to be arranged in the construction of tunnels or railways of municipal works and the construction of water supply and drainage works, oil well works and mine works, and the working wells provide a constructed underground passage for the underground works; before the working well is opened, a stable and firm working platform is provided on the ground for mechanical equipment for opening the working well.
Under the normal condition, when the operation platform is built during construction, concrete is used for direct pouring and forming, so that the operation platform which is directly poured cannot be dismantled, and building materials are wasted.
SUMMERY OF THE UTILITY MODEL
In order to reduce the waste of building materials when the operation platform is built, the application provides an assembled operation platform.
The application provides an assembled work platform adopts following technical scheme:
an assembly type work platform comprises a plurality of supporting blocks, wherein a fixing component used for being fixed with the adjacent supporting block is arranged on the side wall of each supporting block;
the fixing assembly comprises a spring and a fixing block, a first fixing groove is formed in the supporting block, the fixing block is connected to the side wall of the first fixing groove in a sliding mode, one end of the spring is fixedly connected with the side wall of the first fixing groove, and the other end of the spring is fixedly connected with the fixing block; second fixing grooves are formed in the adjacent supporting blocks, and the fixing blocks are in inserted fit with the second fixing grooves; and a reset piece for adjusting the reset of the fixed block is also arranged on the side wall of the fixed block.
By adopting the technical scheme, in the process of simultaneously installing a plurality of supporting blocks, a worker firstly hangs one supporting block through a crane to abut against a pipeline, then pulls a reset piece, the reset piece moves to drive a fixing block to move, the fixing block moves to compress a spring, so that the fixing block slides towards a first fixing groove, then one side of a second fixing groove on the other supporting block is put down close to the fixing block on the supporting block, when the second fixing groove on the side wall of the other supporting block is aligned with the first fixing groove, the external force applied to the reset piece is relieved, at the moment, under the action of the elastic force of the spring, the spring pushes the fixing block to be in splicing fit with the second fixing groove, so that the installation of the second supporting block is completed, and then the installation of the plurality of supporting blocks is completed in the same way; through setting up the piece that resets, can remove the fixed between two adjacent supporting shoes to accomplish the purpose of dismantling a plurality of supporting shoes, and then can reduce the waste of building material when building the operation platform.
Preferably, the reset piece is a reset rod, a reset groove is formed in the supporting block, the reset groove is communicated with the first fixing groove, the reset rod is connected to the side wall of the reset groove in a sliding mode, one end of the reset rod is fixedly connected with the fixing block, and the other end of the reset rod is located outside the reset groove.
Through adopting above-mentioned technical scheme, at the in-process that removes the fixed block, the staff promotes the release link earlier and removes, and the release link slides along the lateral wall in reset groove, and the release link removes the lateral wall that drives the fixed block and slides along first fixed slot, through setting up the release link, is convenient for reach the purpose fixed with two adjacent supporting shoes of dismantlement.
Preferably, still be provided with the dead lever in the first fixed slot, the one end fixed connection of dead lever in on the lateral wall of first fixed slot, the spring housing is located on the dead lever, the third fixed slot has been seted up on the fixed block, the other end of dead lever can with the cooperation of pegging graft of third fixed slot.
By adopting the technical scheme, in the process that the fixed block moves into the first fixed groove, the fixed block compresses the spring, the spring is compressed along the axial direction of the fixed rod, and meanwhile, the fixed rod is in inserted fit with the third fixed groove on the fixed block; when the external force action on the reset rod is removed, the spring pushes the fixing block to move under the action of the elastic force of the spring, the fixing block moves towards one side close to the second fixing groove, the fixing rod is separated from the third fixing groove, and meanwhile, the spring restores to deform along the axial direction of the fixing rod; through setting up the dead lever, can play the effect of protection spring.
Preferably, the fixed block is further provided with an inclined plane.
Through adopting above-mentioned technical scheme, utilize the inclined plane, reduced the fixed block and the second fixed slot degree of difficulty of pegging graft the cooperation.
Preferably, each support block is provided with a plurality of first locking holes, and a locking component for locking the support block is arranged corresponding to each first locking hole;
the locking subassembly all includes locking block and locking crab-bolt, locking block fixed connection in on the supporting shoe, the second locking hole has been seted up on the locking block, the locking crab-bolt is worn to locate the second locking hole with first locking hole sets up, still be provided with in the locking crab-bolt and be used for restricting the locating part that the locking crab-bolt upwards pulled up.
Through adopting above-mentioned technical scheme, at the in-process with every backup pad locking, the staff corresponds every first locking hole earlier, with the first locking hole of second locking hole alignment on the locking piece, later with locking piece fixed connection in the backup pad, wear to locate second locking hole and second locking hole simultaneously with the locking crab-bolt, will lock the crab-bolt and fix mutually with the locking piece through the locating part.
Preferably, a locking cavity is formed in the locking block, the limiting members are elastic limiting strips, the number of the elastic limiting strips is two, one end of each of the two elastic limiting strips is fixedly connected with the locking anchor bolt, and the other end of each elastic limiting strip abuts against the side wall of the locking cavity;
corresponding to each elastic limit strip, an adjusting piece for adjusting the elastic limit strips to reset is further arranged in the locking block.
Through adopting the above-mentioned technical scheme, wear to locate the second fixed orifices in-process with the locking crab-bolt, the one end that the locking crab-bolt was kept away from to two elasticity spacing strips on the locking crab-bolt offsets with the lateral wall of fixed block simultaneously, make the one end of two elasticity spacing strips remove to being close to fixed crab-bolt axis one side simultaneously, two elasticity spacing strips can get into the locking intracavity through the second fixed orifices simultaneously, then under the effect of elasticity spacing strip, two elasticity spacing strips remove to keeping away from fixed crab-bolt axis one side simultaneously, make two elasticity spacing strips offset with the lateral wall in locking chamber simultaneously, thereby make the locking crab-bolt can not upwards pull up again, thereby reach the mesh of injecing the locking crab-bolt position.
Preferably, the adjusting member is an adjusting rod, the side wall of the locking block is provided with an adjusting hole, the adjusting rod is slidably connected to the side wall of the adjusting hole, and one end of the adjusting rod, which is located in the locking cavity, abuts against the elastic limiting strip.
Through adopting above-mentioned technical scheme, when needing to remove the butt of two spacing strips of elasticity and locking chamber lateral wall, the staff promotes the one side that the regulation pole is located the locking chamber outside for one side that the regulation pole is located the locking chamber promotes the spacing strip of elasticity and is close to being close to the locking crab-bolt axis, pulls the locking crab-bolt after that, makes two spacing strips of elasticity on the locking crab-bolt can shift out the locking chamber in, thereby is convenient for reach the purpose of adjusting the spacing strip of elasticity and reseing.
Preferably, the side wall of the locking anchor bolt is provided with an adjusting groove, and the elastic limiting strip can be matched with the adjusting groove.
Through adopting above-mentioned technical scheme, set up the adjustment tank, reduced the degree of difficulty of accomodating of the spacing strip of elasticity.
In summary, the present application includes at least one of the following beneficial technical effects:
1. in the process of installing a plurality of supporting blocks simultaneously, a worker firstly hangs one supporting block to abut against a pipeline through a crane, then pulls a reset piece, the reset piece moves to drive a fixing block to move, the fixing block moves to compress a spring, so that the fixing block slides into a first fixing groove, then one side of a second fixing groove on the other supporting block is put down close to the fixing block on the supporting block, when the second fixing groove on the side wall of the other supporting block is aligned with the first fixing groove, the external force applied to the reset piece is relieved, at the moment, under the action of the elastic force of the spring, the spring pushes the fixing block to be in plug-in fit with the second fixing groove, so that the installation of the second supporting block is completed, and then the plurality of supporting blocks are installed in the same mode; by arranging the resetting piece, the fixation between two adjacent supporting blocks can be released, so that the purpose of disassembling the supporting blocks is fulfilled, and the waste of building materials during the construction of the operation platform can be reduced;
2. in the process that the fixed block moves into the first fixed groove, the fixed block compresses the spring, the spring is compressed along the axial direction of the fixed rod, and meanwhile, the fixed rod is in inserted fit with the third fixed groove on the fixed block; when the external force action on the reset rod is removed, the spring pushes the fixing block to move under the action of the elastic force of the spring, the fixing block moves towards one side close to the second fixing groove, the fixing rod is separated from the third fixing groove, and meanwhile the spring restores to deform along the axis direction of the fixing rod; the fixing rod is arranged, so that the spring can be protected;
3. wear to locate the second fixed orifices in-process with the locking crab-bolt, the one end that the locking crab-bolt was kept away from to two elasticity spacing strips on the locking crab-bolt offsets with the lateral wall of fixed block simultaneously, make the one end of two elasticity spacing strips move to being close to fixed crab-bolt axis one side simultaneously, two elasticity spacing strips can get into the locking intracavity through the second fixed orifices simultaneously, under the effect of elasticity spacing strip, make two elasticity spacing strips offset with the lateral wall in locking chamber simultaneously, thereby make the locking crab-bolt can not upwards be pulled up again, thereby reach the purpose of injecing the locking crab-bolt position.
Drawings
Fig. 1 is a schematic structural diagram of the whole of the embodiment of the present application.
FIG. 2 is a schematic view of the structure of the piping and support blocks of the embodiments of the present application.
FIG. 3 is a schematic view of a highlighted fixing assembly according to an embodiment of the present application.
FIG. 4 is a schematic view of the embodiment of the present application highlighting the structure of the locking assembly.
Description of reference numerals: 1. a supporting block; 11. a support groove; 12. a pipeline; 2. a fixing assembly; 21. a spring, 22 and a fixed block; 221. a cross section; 23. a first fixing groove; 24. a second fixing groove; 3. a reset member; 31. a reset lever; 32. a reset groove; 4. a fixing rod; 41. a third fixing groove; 5. a locking assembly; 51. a first locking hole; 52. a locking block; 53. a locking cavity; 54. a second locking hole; 55. locking an anchor bolt; 6. a limiting member; 61. an elastic limit strip; 7. an adjustment member; 71. adjusting a rod; 72. an adjustment hole; 73. a connecting portion; 74. a limiting part; 75. and (4) adjusting the groove.
Detailed Description
The present application is described in further detail below with reference to figures 1-4.
The embodiment of the application discloses an assembly type operation platform. Referring to fig. 1 and 2, the assembly type work platform includes a plurality of support blocks 1, four support blocks are provided in this embodiment, a support groove 11 is provided at a construction position of the ground work well, a cross section 221 of the support groove 11 is circular, a pipeline 12 is provided in the support groove 11, an outer circumferential surface of the pipeline 12 abuts against a side wall of the support groove 11, the four support blocks 1 are simultaneously in lap joint with a pipe orifice side wall of the pipeline 12, and each support block 1 is provided with a fixing component 2 for fixing the adjacent support block 1.
Through setting up four supporting shoes 1, install four supporting shoes 1 through the mode of concatenation, can provide an operation platform for the work of seting up the working well, reduced because 11 inner walls of supporting channel because the soil quality is soft can take place the possibility of collapsing.
As shown in fig. 2 and 3, the fixing assembly 2 includes springs 21 and fixing blocks 22, a first fixing groove 23 is formed in one side of one support block 1, the first fixing groove 23 extends in a direction perpendicular to an axis of the support groove 11, the fixing block 22 is slidably connected to a sidewall of the first fixing groove 23, one end of each spring 21 is fixedly connected to a sidewall of the first fixing groove 23, the other end of each spring 21 is fixedly connected to the fixing block 22, a second fixing groove 24 is formed in a side of the adjacent support block 1 close to the fixing block 22, the second fixing groove 24 extends in a direction perpendicular to the axis of the support groove 11, and the fixing block 22 is in inserted fit with the second fixing groove 24; the fixing block 22 is provided with an inclined surface at a side close to the second fixing groove 24, and the inclined surface is inclined upward from a side close to the spring 21 to a side far from the spring 21.
The fixing block 22 is provided with a reset part 3 for adjusting the position of the fixing block 22, the reset part 3 is a reset rod 31, the supporting block 1 is provided with a reset groove 32, the reset groove 32 is communicated with the first fixing groove 23, the reset rod 31 is slidably connected to the side wall of the reset groove 32, one end of the reset rod 31 is fixedly connected with the fixing block 22, and the other end of the reset rod 31 is positioned outside the reset groove 32;
corresponding every spring 21, all being provided with dead lever 4 in every first fixed slot 23, the one end fixed connection of dead lever 4 is on the lateral wall of first fixed slot 23, and on dead lever 4 was located to spring 21 cover, third fixed slot 41 had been seted up on the fixed block 22, and the other end of dead lever 4 can be pegged graft the cooperation with third fixed slot 41.
The four supporting blocks 1 are spliced into one operation platform by arranging the fixing component 2, and meanwhile, the fixing block 22 can be separated from the first fixing groove 23 by arranging the resetting part 3, so that each supporting block 1 can be detached and reused in other work well opening work; through setting up dead lever 4, can protect spring 21 not to take place excessive deformation, extension spring 21's life.
As shown in fig. 2 and 4, two sets of locking assemblies 5 for locking the positions of the supporting blocks 1 are arranged on each supporting block 1; the locking assemblies 5 comprise locking blocks 52 and locking anchors 55, two groups of locking assemblies 5 are arranged on each supporting block 1, the locking blocks 52 are fixedly connected to the supporting blocks 1, two first locking holes 51 are formed in the supporting blocks 1, second locking holes 54 are formed in the locking blocks 52, each first locking hole 51 and each second locking hole 54 are circular, each first locking hole 51 and each second locking hole 54 are coaxially arranged, and the locking anchors 55 penetrate through the first locking holes 51 and the second locking holes 54 and are inserted into the side walls of the supporting grooves 11;
a locking cavity 53 is formed in the locking block 52, a limiting piece 6 is arranged on the locking anchor bolt 55, the limiting piece 6 is an elastic limiting strip 61, two elastic limiting strips 61 are arranged, one end of each elastic limiting strip 61 is fixedly connected to the side wall of the locking anchor bolt 55, the two elastic limiting strips 61 are arranged obliquely and upwards, and the other end of each elastic limiting plate is abutted against the side wall of the locking cavity 53; two adjusting grooves 75 are formed in the locking anchor bolt 55 corresponding to the two elastic limiting strips 61, and the two elastic limiting strips 61 can be in one-to-one correspondence with the two adjusting grooves 75.
Corresponding to each elastic limiting strip 61, an adjusting piece 7 for adjusting the resetting of the elastic limiting strip 61 is arranged on the locking block 52, the adjusting piece 7 is an adjusting rod 71, the adjusting rod 71 comprises a connecting portion 73 and a limiting portion 74, an adjusting hole 72 is formed in the side wall of the locking cavity 53, the connecting portion 73 is connected to the side wall of the adjusting hole 72 in a sliding mode, the connecting portion 73 is located on one side outside the locking cavity 53 and fixedly connected with the limiting portion 74, and one side, located in the locking cavity 53, of the connecting portion 73 abuts against the elastic limiting strip 61.
By arranging the locking assembly 5, each supporting block 1 can be fixed, so that the possibility that the supporting block 1 is loosened from the side wall of the supporting groove 11 is reduced; by arranging the limiting piece 6, the locking anchor bolt 55 can only move downwards in the process of fixing the supporting block 1 by using the locking anchor bolt 55; through setting up adjusting part 7, when locking crab-bolt 55 needs to be dismantled, through promoting regulation pole 71 with the spacing strip 61 of elasticity to being close to the axis removal of locking crab-bolt 55 for the spacing strip 61 of elasticity no longer offsets with the lateral wall in locking chamber 53, makes locking crab-bolt 55 can upwards be drawn, thereby can relieve the locking effect of locking Assembly 5.
The implementation principle of the assembly type operation platform in the embodiment of the application is as follows: in the process of installing a plurality of supporting blocks 1 simultaneously, a worker firstly hangs one supporting block 1 to abut against a pipeline 12 through a crane, then pulls a reset part 3, the reset part 3 moves to drive a fixing block 22 to move, the fixing block 22 moves to compress a spring 21, the fixing block 22 slides towards a first fixing groove 23, then one side of a second fixing groove 24 on the other supporting block 1 is put down close to the fixing block 22 on the supporting block 1, when the second fixing groove 24 on the side wall of the other supporting block 1 is aligned with the first fixing groove 23, the external force applied to the reset part 3 is removed, at the moment, under the action of the elastic force of the spring 21, the spring 21 pushes the fixing block 22 to be in inserted connection with the second fixing groove 24, so that the installation of the second supporting block 1 is completed, and then the installation of the plurality of supporting blocks 1 is completed in the same way; through setting up the piece 3 that resets, can remove the fixed between two adjacent supporting shoe 1 to accomplish the purpose of dismantling a plurality of supporting shoes 1, and then can reduce the waste of building material when building the operation platform.
The above are preferred embodiments of the present application, and the scope of protection of the present application is not limited thereto, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (8)

1. The utility model provides an assembled work platform which characterized in that: the supporting device comprises a plurality of supporting blocks (1), wherein a fixing component (2) for fixing the supporting blocks (1) adjacent to each other is arranged on the side wall of each supporting block (1);
the fixing component (2) comprises a spring (21) and a fixing block (22), a first fixing groove (23) is formed in the supporting block (1), the fixing block (22) is connected to the side wall of the first fixing groove (23) in a sliding mode, one end of the spring (21) is fixedly connected with the side wall of the first fixing groove (23), and the other end of the spring (21) is fixedly connected with the fixing block (22); a second fixing groove (24) is formed in each adjacent supporting block (1), and the fixing blocks (22) are in inserting fit with the second fixing grooves (24); and a reset piece (3) for adjusting the reset of the fixed block (22) is also arranged on the side wall of the fixed block (22).
2. A fabricated work platform according to claim 1, wherein: reset piece (3) are release link (31), reset groove (32) have been seted up on supporting shoe (1), reset groove (32) with first fixed slot (23) are linked together, release link (31) sliding connection in on the lateral wall of reset groove (32), the one end of release link (31) with fixed block (22) fixed connection, the other end of release link (31) is located set up outside reset groove (32).
3. A fabricated work platform according to claim 2, wherein: still be provided with dead lever (4) in first fixed slot (23), the one end fixed connection of dead lever (4) in on the lateral wall of first fixed slot (23), spring (21) cover is located on dead lever (4), third fixed slot (41) have been seted up on fixed block (22), the other end of dead lever (4) can with the cooperation of pegging graft of third fixed slot (41).
4. A fabricated work platform according to claim 2, wherein: an inclined plane is arranged on the fixing block (22).
5. A fabricated work platform according to claim 1, wherein: a plurality of first locking holes (51) are formed in each supporting block (1), and a locking component (5) used for locking the supporting block (1) is arranged corresponding to each first locking hole (51);
locking subassembly (5) all include locking block (52) and locking crab-bolt (55), locking block (52) fixed connection in on supporting shoe (1), second locking hole (54) have been seted up on locking block (52), locking crab-bolt (55) wear to locate second locking hole (54) with first locking hole (51) set up, still be provided with in locking crab-bolt (55) and be used for restricting locating part (6) that locking crab-bolt (55) upwards pulled up.
6. A fabricated work platform according to claim 5, wherein: a locking cavity (53) is formed in the locking block (52), the limiting pieces (6) are two elastic limiting strips (61), one end of each of the two elastic limiting strips (61) is fixedly connected with the locking anchor bolt (55), and the other end of each elastic limiting strip (61) abuts against the side wall of the locking cavity (53);
corresponding to each elastic limiting strip (61), an adjusting piece (7) used for adjusting the elastic limiting strips (61) to reset is further arranged in the locking block (52).
7. A fabricated work platform according to claim 6, wherein: the adjusting piece (7) is an adjusting rod (71), an adjusting hole (72) is formed in the side wall of the locking block (52), the adjusting rod (71) is connected to the side wall of the adjusting hole (72) in a sliding mode, and one end of the adjusting rod (71) in the locking cavity (53) is abutted to the elastic limiting strip (61).
8. A fabricated work platform according to claim 6, wherein: the lateral wall of the locking anchor bolt (55) is provided with an adjusting groove (75), and the elastic limiting strip (61) can be matched with the adjusting groove (75).
CN202222134882.3U 2022-08-12 2022-08-12 Assembled work platform Active CN217870927U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222134882.3U CN217870927U (en) 2022-08-12 2022-08-12 Assembled work platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222134882.3U CN217870927U (en) 2022-08-12 2022-08-12 Assembled work platform

Publications (1)

Publication Number Publication Date
CN217870927U true CN217870927U (en) 2022-11-22

Family

ID=84077257

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222134882.3U Active CN217870927U (en) 2022-08-12 2022-08-12 Assembled work platform

Country Status (1)

Country Link
CN (1) CN217870927U (en)

Similar Documents

Publication Publication Date Title
CN210422618U (en) Supporting structure of trenchless pipeline repairing operation well
CN204849776U (en) Loose structure and bearing structure among bearing structure
JP2002081070A (en) Slide type earth retaining timbering system
CN112459082B (en) Foundation pit slope collapse prevention structure and building method thereof
CN217870927U (en) Assembled work platform
KR100966148B1 (en) Ground adhering soil nailing structure and ground reinforcement method using the same
KR101175112B1 (en) Multipurpose nailing anchor and construction method thereof
CN109653192A (en) Assembled underground continuous wall and its construction method
CN218437099U (en) Foundation ditch quick installation supporting construction
JP5789201B2 (en) Building foundation slope restoration method and building foundation structure
CN211647234U (en) Overhanging type scaffold
CN113846712B (en) Foundation pit construction quality detection system and detection method
KR101300078B1 (en) Variable supporting device for sheathing work pile
KR100799328B1 (en) Extractable nail structure and reinforce steel-bar extraction method using the same
KR102123666B1 (en) Implant pile installer in architecture foundation system and a universal implant pile method
CN217651815U (en) Foundation pit supporting structure in shaft construction
KR200274837Y1 (en) Hume pipe mounting structure using concrete board without form
CN220301351U (en) Cutting slope prosthetic protector
KR101183926B1 (en) Multipurpose nailing anchor and construction method thereof
CN216586589U (en) Pile foundation hole protection device
CN112376580A (en) Foundation structure
CN220767907U (en) Water conservancy side slope protective structure
KR100507597B1 (en) Formwork supporting apparatus for hanging type formwork system and formwork using the same
CN214574067U (en) Precipitation well structure for building construction
CN114775635B (en) Building foundation pit maintaining plate

Legal Events

Date Code Title Description
GR01 Patent grant