CN217841542U - Anchor eye drilling equipment for civil engineering - Google Patents

Anchor eye drilling equipment for civil engineering Download PDF

Info

Publication number
CN217841542U
CN217841542U CN202221372136.1U CN202221372136U CN217841542U CN 217841542 U CN217841542 U CN 217841542U CN 202221372136 U CN202221372136 U CN 202221372136U CN 217841542 U CN217841542 U CN 217841542U
Authority
CN
China
Prior art keywords
platform
civil engineering
lifting platform
drilling
lead screw
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202221372136.1U
Other languages
Chinese (zh)
Inventor
孙旭东
周广钒
宗烁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Tanki Industry & Commerce Group Co ltd
Original Assignee
Shandong Tanki Industry & Commerce Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Tanki Industry & Commerce Group Co ltd filed Critical Shandong Tanki Industry & Commerce Group Co ltd
Priority to CN202221372136.1U priority Critical patent/CN217841542U/en
Application granted granted Critical
Publication of CN217841542U publication Critical patent/CN217841542U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model relates to the technical field of civil engineering, in particular to an anchor hole drilling device for civil engineering, which comprises a base, wherein a lifting platform is fixedly arranged at the top of one side of the base, a first motor is fixedly arranged at the top of the lifting platform, and an adjusting mechanism is arranged inside the lifting platform; the shaft bracket is arranged at the top of one side of the base, which is far away from the lifting platform, a platform is movably arranged on the inner side of the top of the shaft bracket through a rotating shaft, and one side of the platform, which is far away from the shaft bracket, is connected with an adjusting mechanism; the pushing mechanism is arranged at the top of one side, close to the lifting platform, of the platform, and the sliding table is fixedly connected to one end, far away from the lifting platform, of the pushing mechanism. The utility model discloses a set up the base, this device can adjust the angle of platform through adjustment mechanism when using, and after the angle modulation was accomplished, drive the slip table through the pushing mechanism and slide, the second motor of installation on the slip table can drive drilling rod and drill bit trompil to reach the mesh of being convenient for adjust and trompil.

Description

Anchor eye drilling equipment for civil engineering
Technical Field
The utility model relates to a civil engineering technical field specifically is an anchor eye drilling equipment for civil engineering.
Background
Civil engineering construction, i.e. the construction of civil construction engineering, covers the construction of buildings, structures and engineering works in facilities and places in engineering ranges such as buildings, roads, railways, airports, bridges, water conservancy projects, ports, tunnels, water supply and drainage projects, protection projects and the like in all categories such as ground, underground, land, above water and under water, and not only includes various technical activities such as surveying, designing, constructing, maintaining and managing in the engineering construction process.
Need cut the anchor eye through drilling equipment during civil engineering, common drilling equipment does not possess angle modulation function on the market, when the angle that needs change the rig, needs manually with the rig according to the angle installation that needs, such operation is more loaded down with trivial details, consequently needs design an anchor eye drilling equipment for civil engineering.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide an anchor eye drilling equipment for civil engineering to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme:
anchor eye drilling equipment is used in civil engineering, anchor eye drilling equipment includes for civil engineering
The lifting platform is fixedly installed at the top of one side of the base, the first motor is fixedly installed at the top of the lifting platform, and an adjusting mechanism is arranged inside the lifting platform;
the shaft bracket is arranged at the top of one side of the base, which is far away from the lifting platform, a platform is movably arranged on the inner side of the top of the shaft bracket through a rotating shaft, and one side of the platform, which is far away from the shaft bracket, is connected with an adjusting mechanism;
the pushing mechanism is arranged at the top of one side, close to the lifting platform, of the platform, the pushing mechanism is far away from the sliding table, the sliding table is fixedly connected to one end of the lifting platform, the second motor is fixedly mounted at the top of the sliding table, and the drilling mechanism is fixedly mounted at the top of one side, far away from the pushing mechanism, of the platform.
Preferably, the adjusting mechanism comprises a screw rod, a screw rod and a shaft seat, the screw rod is movably mounted at the top end and the bottom end of the inner part of the lifting platform through a bearing, the top end of the screw rod is fixedly connected with an output shaft of the first motor, the screw rod is in threaded connection with the outer part of the screw rod, one side of the screw rod is fixedly connected with the shaft seat, a connecting piece is movably mounted at one end, far away from the screw rod, of the shaft seat through a rotating shaft, and one end, far away from the shaft seat, of the connecting piece is fixedly connected with the platform;
preferably, the pushing mechanism comprises a rack, an electric cylinder and a push rod, the electric cylinder is fixedly installed at the top of one side, close to the lifting platform, of the platform through the rack, and the output shaft end of the electric cylinder is connected with the sliding table through the push rod;
preferably, the drilling mechanism comprises a drill rod and a drill bit, a bracket is fixedly mounted at the top of one side, away from the lifting platform, of the platform, the drill rod is movably mounted at the top of the bracket through a guide sleeve, one end of the drill rod is fixedly connected with an output shaft of a second motor, and one end, away from the second motor, of the drill rod is fixedly connected with the drill bit;
preferably, sliding grooves are formed in the outer sides of two ends of the top of the platform, and four corners of the bottom end of the sliding table are movably connected with the sliding grooves through pulleys;
preferably, a supporting column is fixedly installed at the top end of one side, close to the lifting platform, of the base.
Compared with the prior art, the beneficial effects of the utility model are that:
1. this anchor eye drilling equipment for civil engineering through setting up adjustment mechanism, starts first motor during the regulation, drives the lead screw rotation after first motor starts, drives the lead screw straight line after the lead screw rotates and rises, drives the connecting piece through the axle bed and rises when the lead screw rises, and one side that drives the platform when the connecting piece rises lifts, and when platform one side lifted, the opposite side rotated along the pedestal and descends to change the inclination of platform to reach the angle regulation's of being convenient for purpose.
2. This anchor eye drilling equipment for civil engineering through setting up drilling mechanism, starts the second motor of slip table top installation, and it is rotatory to drive the drilling rod after the second motor starts, drives the drill bit when the drilling rod is rotatory and excavates appointed position, when rotatory, can make the drilling rod drive the drill bit rotation and go deep into and carry out the trompil through the pushing mechanism to reach the mesh of being convenient for drill.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is an enlarged schematic view of the present invention at A in FIG. 1;
FIG. 3 is an enlarged schematic view of the present invention at B of FIG. 1;
fig. 4 is an enlarged schematic view of the present invention at C in fig. 1.
In the figure: 1. a base; 2. a lifting platform; 3. a first motor; 4. an adjustment mechanism; 5. a pedestal; 6. a platform; 7. a pushing mechanism; 8. a sliding table; 9. a second motor; 10. a screw rod; 11. a lead screw; 12. a shaft seat; 13. a connecting member; 14. a frame; 15. an electric cylinder; 16. a push rod; 17. a drill stem; 18. a drill bit; 19. a bracket; 20. a chute; 21. a pulley; 22. a support column; 23. a drilling mechanism.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it is to be understood that the terms "top", "bottom", "inner", "outer", and the like refer to orientations or positional relationships based on those shown in the drawings, and are used only for convenience of description and simplicity of description, and do not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus should not be construed as limiting the present invention.
In the description of this patent, it is noted that unless otherwise specifically stated or limited, the terms "mounted," "connected," and "disposed" are to be construed broadly and can include, for example, fixedly connected, disposed, detachably connected, disposed, or integrally connected and disposed. The specific meaning of the above terms in this patent may be understood by those of ordinary skill in the art as appropriate.
Furthermore, the terms "first", "second" and "first" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of the present invention, "a plurality" means two or more unless specifically limited otherwise.
Referring to fig. 1-4, the present invention provides a technical solution:
anchor eye drilling equipment is used in civil engineering, anchor eye drilling equipment includes for civil engineering
The lifting device comprises a base 1, wherein a lifting platform 2 is fixedly installed at the top of one side of the base 1, a first motor 3 is fixedly installed at the top of the lifting platform 2, and an adjusting mechanism 4 is arranged inside the lifting platform 2;
the shaft bracket 5 is arranged at the top of one side, away from the lifting platform 2, of the base 1, a platform 6 is movably arranged on the inner side of the top of the shaft bracket 5 through a rotating shaft, and one side, away from the shaft bracket 5, of the platform 6 is connected with the adjusting mechanism 4;
the pushing mechanism 7 is arranged at the top of one side, close to the lifting platform 2, of the platform 6, the sliding platform 8 is fixedly connected to one end, far away from the lifting platform 2, of the pushing mechanism 7, the second motor 9 is fixedly installed at the top of the sliding platform 8, and the drilling mechanism 23 is fixedly installed at the top of one side, far away from the pushing mechanism 7, of the platform 6;
through the above scheme, through setting up base 1, this device can adjust the angle of platform 6 through adjustment mechanism 4 when using, and after the angle modulation was accomplished, drive slip table 8 through pushing away mechanism 7 and slide, the second motor 9 of installation can drive drilling rod 17 and the 18 trompils of drill bit on the slip table 8 to reach the mesh of being convenient for adjust and trompil.
In this embodiment, preferably, the adjusting mechanism 4 includes a screw rod 10, a screw rod 11 and a shaft seat 12, the screw rod 10 is movably mounted at the top end and the bottom end inside the lifting platform 2 through a bearing, the top end of the screw rod 10 is fixedly connected with an output shaft of the first motor 3, the screw rod 11 is connected with an external thread of the screw rod 10, one side of the screw rod 11 is fixedly connected with the shaft seat 12, a connecting piece 13 is movably mounted at one end of the shaft seat 12 far away from the screw rod 11 through a rotating shaft, and one end of the connecting piece 13 far away from the shaft seat 12 is fixedly connected with the platform 6;
through the scheme, the adjusting mechanism 4 is arranged, the first motor 3 is started during adjustment, the first motor 3 drives the screw rod 10 to rotate after being started, the screw rod 10 drives the screw rod 11 to linearly rise after rotating, the connecting piece 13 is driven to rise through the shaft seat 12 when the screw rod 11 rises, one side of the platform 6 is driven to rise when the connecting piece 13 rises, and the other side rotates and descends along the shaft bracket 5 to change the inclination angle of the platform 6 when one side of the platform 6 rises, so that the aim of conveniently adjusting the angle is fulfilled;
in this embodiment, preferably, the pushing mechanism 7 includes a frame 14, an electric cylinder 15 and a push rod 16, the electric cylinder 15 is fixedly installed on the top of one side of the platform 6 close to the lifting platform 2 through the frame 14, and an output shaft end of the electric cylinder 15 is connected with the sliding table 8 through the push rod 16;
through the scheme, the pushing mechanism 7 and the installed electric cylinder 15 are arranged, the electric cylinder 15 drives the push rod 16 to linearly push after being started, the push rod 16 drives the sliding table 8 to slide towards one side after being linearly pushed, so that the drilling mechanism 23 drills an anchor hole, the electric cylinder 15 is started again after the drilling is finished, and the sliding table 8 is driven to be retracted, so that the purpose of facilitating sliding is achieved;
in this embodiment, preferably, the drilling mechanism 23 includes a drill rod 17 and a drill bit 18, a bracket 19 is fixedly installed at the top of one side of the platform 6 away from the lifting table 2, the drill rod 17 is movably installed at the top of the bracket 19 through a guide sleeve, one end of the drill rod 17 is fixedly connected with an output shaft of the second motor 9, and one end of the drill rod 17 away from the second motor 9 is fixedly connected with the drill bit 18;
through the scheme, the drilling mechanism 23 is arranged, the second motor 9 arranged at the top of the sliding table 8 is started, the second motor 9 drives the drill rod 17 to rotate after being started, the drill bit 18 is driven to drill the appointed position when the drill rod 17 rotates, and the drill rod 17 can drive the drill bit 18 to rotate to deeply drill holes through the pushing mechanism 7 when the drill rod 17 rotates, so that the purpose of facilitating drilling is achieved;
in this embodiment, preferably, the outer sides of the two ends of the top of the platform 6 are both provided with sliding chutes 20, and four corners of the bottom end of the sliding table 8 are both movably connected with the sliding chutes 20 through pulleys 21;
through the scheme, the purpose of arranging the pulleys 21 is that when the sliding table 8 slides transversely, the pulleys 21 at four corners of the bottom end of the sliding table 8 slide along the sliding groove 20, so that the sliding table 8 can slide conveniently;
in this embodiment, preferably, a supporting column 22 is fixedly installed at the top end of one side of the base 1 close to the lifting platform 2;
through above-mentioned scheme, the purpose that sets up support column 22 is when needs keep horizontal angle drilling, adjusts platform 6 to horizontal angle through adjustment mechanism 4, and platform 6 is close to one side bottom of elevating platform 2 and is lifted through support column 22 for platform 6 keeps the level to put.
The anchor eye drilling equipment for civil engineering of this embodiment is when using, can adjust the angle of platform 6 through adjustment mechanism 4, start first motor 3 during the regulation, first motor 3 drives lead screw 10 after starting and rotates, lead screw 10 drives lead screw 11 straight line after rotating and rises, lead screw 11 drives connecting piece 13 through axle bed 12 and rises when rising, connecting piece 13 drives one side of platform 6 and lifts when rising, when platform 6 one side lifts, the opposite side descends along the rotation of pedestal 5 and goes to change the inclination of platform 6, start the electronic jar 15 of frame 14 top installation after the angle modulation is accomplished, electronic jar 15 drives push rod 16 straight line after starting and promotes, drive slip table 8 and slide towards one side after the push rod 16 straight line promotes, start the second motor 9 of slip table 8 top installation simultaneously, it is rotatory to drive drilling rod 17 after the start, drive drill bit 18 when the drilling rod 17 is rotatory and carve appointed position, when rotatory, can make drilling rod 17 drive drilling bit 18 to go deep into and carry out the trompil deeply through pushing mechanism 7.
The foregoing shows and describes the general principles, essential features, and advantages of the invention. It should be understood by those skilled in the art that the present invention is not limited by the above embodiments, and the description in the above embodiments and the description is only preferred examples of the present invention, and is not intended to limit the present invention, and that the present invention can have various changes and modifications without departing from the spirit and scope of the present invention, and these changes and modifications all fall into the scope of the claimed invention. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (6)

1. The utility model provides an anchor eye drilling equipment for civil engineering which characterized in that: the anchor hole drilling device for civil engineering construction comprises
The device comprises a base (1), wherein a lifting platform (2) is fixedly installed at the top of one side of the base (1), a first motor (3) is fixedly installed at the top of the lifting platform (2), and an adjusting mechanism (4) is arranged inside the lifting platform (2);
the lifting platform comprises a pedestal (1), a shaft bracket (5), a platform (6) and an adjusting mechanism (4), wherein the shaft bracket (5) is arranged at the top of one side of the pedestal (1) far away from the lifting platform (2), the inner side of the top of the shaft bracket (5) is movably provided with the platform (6) through a rotating shaft, and one side of the platform (6) far away from the shaft bracket (5) is connected with the adjusting mechanism (4);
push mechanism (7), push mechanism (7) set up in one side top that platform (6) are close to elevating platform (2), one end fixedly connected with slip table (8) of elevating platform (2) are kept away from in push mechanism (7), the top fixed mounting of slip table (8) has second motor (9), one side top fixed mounting that push mechanism (7) were kept away from in platform (6) has drilling mechanism (23).
2. The anchor eye drilling device for civil engineering according to claim 1, wherein: adjustment mechanism (4) are including lead screw (10), lead screw (11) and axle bed (12), bearing movable mounting lead screw (10) is passed through to the inside top and the bottom of elevating platform (2), the output shaft of the first motor of top fixed connection (3) of lead screw (10), outside threaded connection lead screw (11) of lead screw (10), one side fixed connection axle bed (12) of lead screw (11), the one end that lead screw (11) were kept away from in axle bed (12) has connecting piece (13) through pivot movable mounting, one end fixed connection platform (6) of axle bed (12) are kept away from in connecting piece (13).
3. The anchor eye drilling device for civil engineering according to claim 1, wherein: the pushing mechanism (7) comprises a rack (14), an electric cylinder (15) and a push rod (16), the top of one side, close to the lifting platform (2), of the platform (6) is fixedly provided with the electric cylinder (15) through the rack (14), and the output shaft end of the electric cylinder (15) is connected with the sliding table (8) through the push rod (16).
4. The anchor eye drilling device for civil engineering according to claim 1, wherein: drilling mechanism (23) are including drilling rod (17) and drill bit (18), one side top fixed mounting that elevating platform (2) were kept away from in platform (6) has bracket (19), uide bushing movable mounting drilling rod (17) are passed through at the top of bracket (19), the output shaft of the one end fixed connection second motor (9) of drilling rod (17), one end fixed connection drill bit (18) of second motor (9) are kept away from in drilling rod (17).
5. The anchor eye drilling equipment for civil engineering of claim 1, wherein: sliding grooves (20) are formed in the outer sides of two ends of the top of the platform (6), and four corners of the bottom end of the sliding table (8) are movably connected with the sliding grooves (20) through pulleys (21).
6. The anchor eye drilling equipment for civil engineering of claim 1, wherein: the base (1) is close to one side top fixed mounting of elevating platform (2) has support column (22).
CN202221372136.1U 2022-06-02 2022-06-02 Anchor eye drilling equipment for civil engineering Expired - Fee Related CN217841542U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221372136.1U CN217841542U (en) 2022-06-02 2022-06-02 Anchor eye drilling equipment for civil engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221372136.1U CN217841542U (en) 2022-06-02 2022-06-02 Anchor eye drilling equipment for civil engineering

Publications (1)

Publication Number Publication Date
CN217841542U true CN217841542U (en) 2022-11-18

Family

ID=84021778

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221372136.1U Expired - Fee Related CN217841542U (en) 2022-06-02 2022-06-02 Anchor eye drilling equipment for civil engineering

Country Status (1)

Country Link
CN (1) CN217841542U (en)

Similar Documents

Publication Publication Date Title
CN217841542U (en) Anchor eye drilling equipment for civil engineering
CN214769062U (en) Drilling equipment that multi-angle was adjusted
CN213710450U (en) Prefabricated part based on highlight laser positioning technology
CN112814562A (en) Coal mine geological drilling device
CN210975835U (en) A excavation supporting device for construction
CN218787098U (en) Deviation device is prevented with probing to geotechnical engineering reconnaissance
CN216110619U (en) Oil field instrument fishing device that falls in pit
CN215979200U (en) Oil-water well oil layer fixed-point deep penetration horizontal drilling device with adjustable size
CN113513346B (en) Novel anchor rope drilling device
CN112360353A (en) Drilling rod fixing device is used in geotechnical engineering reconnaissance
CN113006689A (en) Rapid drilling device and drilling method for resource exploration
CN220932409U (en) Sampling device
CN219834832U (en) Land leveling device convenient to adjust
CN213656079U (en) On-spot mapping device of railway engineering cost
CN214997432U (en) Drilling equipment of construction usefulness in underground mine that facilitates use
CN220705632U (en) Anchor drilling machine capable of realizing stable positioning
CN218231682U (en) Swinging arm hoisting frame for gallery
CN220039866U (en) Civil engineering geology sampling device
CN220889638U (en) Support arrangement for civil engineering is with strutting arrangement
CN219121753U (en) Rock and soil sampler
CN220689929U (en) Pipe burying device for mining blasting
CN220822343U (en) Portable electric box
CN221119853U (en) Piling machinery and drilling bucket thereof
CN220955475U (en) Ore drilling device
CN219711438U (en) Static drilling root planting pile construction equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20221118