CN217781885U - Can satisfy pier stores pylon construction equipment of quick drilling under water - Google Patents

Can satisfy pier stores pylon construction equipment of quick drilling under water Download PDF

Info

Publication number
CN217781885U
CN217781885U CN202221357948.9U CN202221357948U CN217781885U CN 217781885 U CN217781885 U CN 217781885U CN 202221357948 U CN202221357948 U CN 202221357948U CN 217781885 U CN217781885 U CN 217781885U
Authority
CN
China
Prior art keywords
underwater
wharf
platform
operation platform
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221357948.9U
Other languages
Chinese (zh)
Inventor
唐雄
王昭
葛朋钊
唐国庆
唐秋君
石军文
左祥
罗来伟
彭冲
苏金
郑秋幸
王坤
周其浩
乔维宇
刘梦迪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 5 Co Ltd
Original Assignee
Sinohydro Bureau 5 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 5 Co Ltd filed Critical Sinohydro Bureau 5 Co Ltd
Priority to CN202221357948.9U priority Critical patent/CN217781885U/en
Application granted granted Critical
Publication of CN217781885U publication Critical patent/CN217781885U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model belongs to the field of underwater construction equipment, in particular to a wharf hanger construction device capable of meeting the requirement of underwater rapid drilling, which comprises an underwater operation platform, wherein the underwater operation platform comprises a bottom platform, stand columns and cross beams, the bottom platform is a square frame surrounded by bottom section steel, a plurality of stand columns are vertically arranged on the square frame, a steel plate is laid on the bottom platform, the steel plate is also arranged between adjacent stand columns, and the adjacent stand columns are connected and fixed through a plurality of cross beams; the platform is provided with an operation window at the construction side, the edge of the window is reinforced by profile steel and is coated with waterproof rubber; each upright post at the construction side of the underwater operation platform extends upwards and is fixed with a transverse support rod to form an inverted L-shaped structure, and one end of the support rod close to the wharf is connected with a hook; this device can closely laminate pier wall position of being under water, has satisfied staff and working facilities under water operational environment demand, need not to reform transform the construction to near the structure of pier wall when using the installation, is applicable to the operational environment of various differences.

Description

Can satisfy pier stores pylon construction equipment of quick drilling under water
Technical Field
The utility model belongs to construction equipment field under water, in particular to can satisfy pier stores pylon construction equipment of quick drilling under water.
Background
The installation of the auxiliary facilities under the wharf wall generally comprises two methods, one method is that the traditional underwater operation is used, a diver operates an underwater operation machine under water to carry out installation and construction, people with diving quality and construction experience need to operate simultaneously, the underwater operation has high safety requirement and large operation difficulty, the installation of the facilities needs higher installation precision, and the installation precision is difficult to ensure under the influence of water flow; and secondly, professional equipment or devices are used, so that the positions of the attached facilities at the lower part of the wharf wall are anhydrous, and enough space is provided for operation and construction.
The attached facilities such as the anti-collision pier and the ladder climbing structure on the wharf wall are partially or completely arranged underwater, so that personnel cannot use machinery and equipment to arrange the attached facilities underwater, and a hanging frame device capable of meeting the underwater operation space conditions is needed to complete the arrangement of the underwater attached facilities on the wharf wall. When the hanger device is used, the wharf wall is long along the line, and the hanger needs to be moved after an accessory is installed, so that the limitation and the technical defect of the installation operation space of the accessory under the wharf wall on site are overcome, and the hanger device is simple in structure, easy and simple to manufacture, simple and convenient to install on site, simple to move and high in applicability.
SUMMERY OF THE UTILITY MODEL
The utility model aims to solve the technical problem that a can provide pier wall underwater operation space, installation set up simple, can shift to the pier stores pylon construction equipment that can satisfy quick drilling under water of next operation position fast.
In order to solve the technical problem, the utility model discloses a technical scheme is: a wharf hanger construction device capable of meeting underwater rapid drilling comprises an underwater operation platform, wherein the underwater operation platform comprises a bottom platform, stand columns and cross beams, the bottom platform is a square frame surrounded by bottom section steel, a plurality of stand columns are vertically arranged on the square frame, a steel plate is laid on the bottom platform, the steel plate is also arranged between adjacent stand columns, and the adjacent stand columns are connected and fixed through the cross beams; an operation window is arranged on the construction side of the underwater operation platform, the edge of the operation window is reinforced by profile steel, and waterproof rubber is coated on the profile steel; each upright post on the construction side of the underwater operation platform extends upwards and is fixed with a transverse support rod to form an inverted L-shaped structure, and one end of the support rod, which is close to the wharf, is connected with a hook; the underwater operation platform is also internally provided with a drainage pump and a drainage pipe, one end of the drainage pipe is connected with the drainage pump, and the other end of the drainage pipe is arranged outside the underwater operation platform. This pier stores pylon construction equipment passes through bottom platform, stand, crossbeam, steel sheet constitution top open-ended cuboid framework, and the operation window that is used for constructor operation is offered to one side that is close to the construction side, guarantees the water tightness of whole device when underwater operation through shaped steel and waterproof rubber on the operation window. The hook is placed on the inner wall of the cable trench of the wharf wall, and the angle between the support rod and the hook is adjusted, so that the wharf hanger construction device is integrally and tightly attached to the wharf wall operation position, and the rapid and convenient construction of workers is guaranteed. The device inevitably can make water flow into inside the device by the operation window in the installation, and the installation makes oozing water through between drain pump and drain pipe gets rid of pier stores pylon construction equipment outside, prevents that construction equipment and constructor from receiving the influence of infiltration.
Further, the bracing piece below is provided with the square timber, because the device can lead to bracing piece deformation fracture because the atress is uneven when installing on the pier wall for the device mounted position takes place the displacement, so set up the square timber and guarantee that the bracing piece atress is even, guarantees the stability of whole device in the work progress.
Furthermore, the support rod is connected with the hook through a bolt. Through the angle between bolt adjustment bracing piece and couple, make the whole swift convenience of staff's construction of closely laminating on pier wall operation position of pier stores pylon construction equipment.
Furthermore, a hanging ring is arranged on the supporting rod. This device catches on rings through using lifting equipment and hoists to the construction position in the installation, convenient and fast, and the installation is simple and easy.
Furthermore, a safe crawling ladder is further arranged in the underwater operation platform, so that workers and working equipment can conveniently enter and exit the underwater operation platform.
Compared with the prior art, the beneficial effects of the utility model are that:
1. this device can closely laminate pier wall position of being under water, has satisfied staff and working facilities at the operational environment demand under water, need not to reform transform the construction to near structure of pier wall when using the installation, is applicable to the operational environment of various differences, has overcome the shortcoming of the operation space restriction of the installation of the attached facility of the part under water of on-the-spot pier wall.
2. Convenient dismantlement removes, and after accomplishing a position construction, only need relax the couple and use lift by crane equipment with it remove to next station fixed can, along with hoist and mount, use up can hang from, convenient and fast easy to carry out arranges that can effectively accelerate the construction progress, improves engineering efficiency of construction.
Drawings
Fig. 1 is the utility model relates to a can satisfy pier stores pylon constructional device overall structure picture of quick drilling under water.
Fig. 2 is the utility model relates to a can satisfy pier stores pylon construction equipment overall structure who drills fast under water and remove steel sheet drawing.
Fig. 3 is the utility model relates to a can satisfy pier stores pylon constructional device top view of quick drilling under water.
Fig. 4 is the utility model relates to a can satisfy pier stores pylon constructional device elevation of quick drilling under water.
Fig. 5 is the utility model relates to a can satisfy pier stores pylon constructional device drilling installation region picture of quick drilling under water.
In the figure: 1-a bottom platform; 2-upright post; 3-a cross beam; 4-a steel plate; 5-an operation window; 6-section steel; 7-waterproof rubber; 8-a support bar; 9-hooking; 10-draining pump; 11-a drain pipe; 12-square wood; 13-a bolt; 14-a hoisting ring; 15-safe ladder climbing; 16-cable trench; 17-quay wall.
Detailed Description
To make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the embodiments of the present invention are clearly and completely described below in combination with the technical solution of the embodiments of the present invention, and obviously, the described embodiments are some, but not all embodiments of the present invention. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative efforts belong to the protection scope of the present invention.
The present invention will be described in further detail with reference to the accompanying drawings and specific embodiments.
The utility model relates to a wharf hanger construction device capable of meeting underwater rapid drilling, as shown in figures 1-4, the device comprises an underwater operation platform, wherein the underwater operation platform comprises a bottom platform 1, stand columns 2 and cross beams 3, the bottom platform 1 is a square frame formed by enclosing bottom section steel, a plurality of stand columns 2 are vertically arranged on the square frame, a steel plate 4 is laid on the bottom platform 1, a steel plate 4 is also arranged between adjacent stand columns 2, and the adjacent stand columns 2 are also connected and fixed through a plurality of cross beams 3; an operation window 5 is arranged on the construction side of the underwater operation platform, the edge of the operation window 5 is reinforced by using section steel 6, and waterproof rubber 7 is coated on the section steel 6; each upright post 2 at the construction side of the underwater operation platform extends upwards and is fixed with a transverse support rod 8 to form an inverted L-shaped structure, and one end of the support rod 8 close to the wharf is connected with a hook 9; the inside drain pump 10 and the drain pipe 11 that still are provided with of underwater operation platform, drain pipe 11 one end is connected drain pump 10, and the other end sets up in the underwater operation platform outside. A square timber 12 is arranged below the support rod 8. The support bar 8 and the hook 9 are connected through a bolt 13. The support bar 8 is provided with a hanging ring 14. A safety ladder stand 15 is also arranged in the underwater operation platform.
As shown in fig. 5, when the device is installed specifically, hoisting is carried out to the construction position by hooking a hoisting ring 14 through hoisting equipment, a hook 9 is placed on the inner wall of a cable duct 16 of a wharf wall 17, the angle between a support rod 8 and the hook 9 is adjusted through a bolt 13, so that the wharf hanger construction device is integrally and tightly attached to the operation position of the wharf wall 17, water seepage entering the wharf hanger construction device in the installation process is eliminated through a drainage pump 10 and a drainage pipe 11, and then constructors and construction equipment are arranged to enter the wharf hanger construction device through a safety ladder stand 15 for construction operation.
As shown in fig. 1 to 4, the number of work windows 5 in the present apparatus is three. For the behavior that adapts to various different wharf walls, can also further improve the device, if become operation window 5 quantity into one, set up the bolt on the platform 1 of bottom, can realize connecting side by side of a plurality of wharf stores pylon construction devices, according to the size of concrete construction scope, carry out in advance and connect pier stores pylon construction device before pier stores pylon construction device hoists, connect and carry out disposable hoist and mount after the installation is accomplished, wharf stores pylon construction device's hoist and mount efficiency has been improved effectively, improve lifting equipment's availability factor, and satisfy multiunit staff and carry out drilling operation simultaneously, drilling efficiency has greatly been improved.
This device can also further improve, each stand 2 of the side of being under water operation platform construction all upwards extends the replacement for the telescopic link, the length of the different adjustment telescopic links according to the operation position of under water, make pier stores pylon construction equipment satisfy the operational environment of different depths of water, wharf stores pylon construction equipment's suitable for operational environment has further been improved, can also install the surface of water inductor additional in 1 inboard of bottom platform simultaneously, the control when carrying out the inside drainage of device, realize the remote operation of the inside drainage of device.
The above embodiments are only used to illustrate the technical solution of the present invention, and not to limit it; although the present invention has been described in detail with reference to the foregoing embodiments, it should be understood by those skilled in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some technical features may be equivalently replaced; such modifications and substitutions do not depart from the spirit and scope of the present invention in its corresponding aspects.

Claims (5)

1. A wharf hanger construction device capable of meeting underwater rapid drilling is characterized by comprising an underwater operation platform, wherein the underwater operation platform comprises a bottom platform (1), stand columns (2) and a cross beam (3), the bottom platform (1) is a square frame formed by enclosing bottom section steel, and a plurality of stand columns (2) are vertically arranged on the square frame; a steel plate (4) is laid on the bottom platform (1), and a steel plate (4) is also arranged between the adjacent upright columns (2); the adjacent upright posts (2) are also connected and fixed through a plurality of cross beams (3); an operation window (5) is arranged on the construction side of the underwater operation platform, the edge of the operation window (5) is reinforced by using section steel (6), and waterproof rubber (7) is coated on the section steel (6); each upright post (2) on the construction side of the underwater operation platform extends upwards and is fixedly provided with a transverse supporting rod (8) to form an inverted L-shaped structure, and one end, close to a wharf, of each supporting rod (8) is connected with a hook (9); the underwater operation platform is characterized in that a drainage pump (10) and a drainage pipe (11) are further arranged inside the underwater operation platform, one end of the drainage pipe (11) is connected with the drainage pump (10), and the other end of the drainage pipe is arranged on the outer side of the underwater operation platform.
2. The wharf rack construction device capable of meeting underwater rapid drilling requirements is characterized in that a square timber (12) is arranged below the supporting rod (8).
3. The wharf rack construction device capable of realizing underwater rapid drilling according to claim 1, wherein the support rod (8) and the hook (9) are connected through a bolt (13).
4. The wharf rack construction device capable of realizing underwater rapid drilling according to claim 1, wherein the support rod (8) is provided with a hanging ring (14).
5. The wharf rack construction device capable of realizing underwater rapid drilling according to claim 1, wherein a safety ladder (15) is further arranged in the underwater operation platform.
CN202221357948.9U 2022-06-01 2022-06-01 Can satisfy pier stores pylon construction equipment of quick drilling under water Active CN217781885U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221357948.9U CN217781885U (en) 2022-06-01 2022-06-01 Can satisfy pier stores pylon construction equipment of quick drilling under water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221357948.9U CN217781885U (en) 2022-06-01 2022-06-01 Can satisfy pier stores pylon construction equipment of quick drilling under water

Publications (1)

Publication Number Publication Date
CN217781885U true CN217781885U (en) 2022-11-11

Family

ID=83911760

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221357948.9U Active CN217781885U (en) 2022-06-01 2022-06-01 Can satisfy pier stores pylon construction equipment of quick drilling under water

Country Status (1)

Country Link
CN (1) CN217781885U (en)

Similar Documents

Publication Publication Date Title
CN101435276B (en) Cabin top steel beam hydraulic hoisting and positioning apparatus of cylinder cabin structure building and construction method thereof
WO2011087234A2 (en) Lifting method for formwork working platform
CN104975719A (en) Novel material distribution device and floor concrete casting construction method of novel material distribution device
CN203654702U (en) Operating platform for construction of reinforced concrete chimney
CN210636796U (en) High-rise elevator shaft jacking formwork system
CN217781885U (en) Can satisfy pier stores pylon construction equipment of quick drilling under water
CN108277994B (en) Method for quickly dismantling safety protection shed of overhead high-speed rail operation line
US2890082A (en) Hoisting attachment for tubular steel scaffolds
CN216662305U (en) Super high-rise tower crane bottom attached hydraulic self-climbing hard protection platform
CN216108092U (en) Construction system for installing steel bar formwork of building pier column
CN212154622U (en) Outer wall plate mounting ladder stand for steel structure factory building
CN210561720U (en) Pier stud maintenance repair operation platform
CN209760761U (en) Construction platform and elevator core section of thick bamboo construction structures in a core section of thick bamboo
CN207513201U (en) A kind of roofing cornices installation mobile device
CN215564411U (en) Sliding construction device for high-rise cylindrical building
CN107700854B (en) Steel plate wall sliding installation device and installation method for super high-rise core tube
CN201686458U (en) Movable operating platform used for quickly processing welding seam at end opening of steel box girder
CN105003074A (en) Commercial building construction system and construction method thereof
CN219316360U (en) Stair operation platform tool
KR20090129574A (en) Climbing scaffolding and method thereof
CN113896124B (en) Attached hydraulic self-climbing hard protection platform at bottom of super high-rise tower crane, mounting process and climbing method thereof
CN211714542U (en) Movable operating platform used in pipeline well
CN214243486U (en) Supplementary gallows structure of large-scale steel column of vertical installation of narrow hoisting hole
KR102392381B1 (en) Moving platform device and facility including the same
RU2006114858A (en) METHOD FOR REPAIR AND RECONSTRUCTION OF ALTITUDE REINFORCED CONCRETE CONSTRUCTIONS WITH VARIABLE Taper, FOR EXAMPLE, COOLING AND INDUSTRIAL PIPES

Legal Events

Date Code Title Description
GR01 Patent grant