CN217752828U - High-efficient plastic conduit welding machine that pipeline erection engineering used - Google Patents

High-efficient plastic conduit welding machine that pipeline erection engineering used Download PDF

Info

Publication number
CN217752828U
CN217752828U CN202221978168.6U CN202221978168U CN217752828U CN 217752828 U CN217752828 U CN 217752828U CN 202221978168 U CN202221978168 U CN 202221978168U CN 217752828 U CN217752828 U CN 217752828U
Authority
CN
China
Prior art keywords
pipe clamp
pipeline
supporting
clamp portion
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221978168.6U
Other languages
Chinese (zh)
Inventor
王文龙
田建荣
张轩
徐杰
张腾中
张�浩
吴午杰
王亚琴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi First Construction Group Co Ltd
Shanxi Construction Investment Group Co Ltd
Original Assignee
Shanxi First Construction Group Co Ltd
Shanxi Construction Investment Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi First Construction Group Co Ltd, Shanxi Construction Investment Group Co Ltd filed Critical Shanxi First Construction Group Co Ltd
Priority to CN202221978168.6U priority Critical patent/CN217752828U/en
Application granted granted Critical
Publication of CN217752828U publication Critical patent/CN217752828U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model relates to the technical field of pipeline welding, and discloses a high-efficiency plastic pipeline welding machine for pipeline installation engineering, which comprises a supporting base, wherein a hot melting machine and two symmetrically arranged pipeline fixing devices are arranged on the supporting base, and each pipeline fixing device comprises a height adjusting unit, a horizontal moving unit and a pipeline fixing unit; the height adjusting unit comprises a lifting cylinder arranged on a supporting base, a supporting platform is arranged on a piston rod of the lifting cylinder, and elastic supporting components are arranged at four corners of the bottom of the supporting platform respectively; the horizontal moving unit comprises a sliding seat, a lead screw supporting seat, a transmission lead screw and a servo motor; the pipeline fixing unit comprises a first support frame, a second support frame and a plurality of pipe clamp assemblies, wherein the first support frame, the second support frame and the plurality of pipe clamp assemblies are installed on a sliding seat. The utility model discloses can be under the prerequisite of guaranteeing pipeline welding quality, the welding installation of high-efficient, quick completion pipeline.

Description

High-efficient plastic conduit welding machine that pipeline erection engineering used
Technical Field
The utility model relates to a pipeline welding technical field especially relates to an efficient plastic conduit welding machine.
Background
The working principle of the plastic pipe hot melting welding machine is that after two plastic pipe joints to be welded are heated and melted, the two plastic pipes are oppositely pushed to be butted and fixed in position through external force, and the two melted joints are cooled and solidified into a whole.
At present, when a plastic pipeline is installed, the pipeline is generally welded through an electrothermal fusion belt, the plastic pipeline with two ends needing to be connected together is welded together manually after being melted, workers are generally required to manually place the plastic pipeline on two sides of a melting machine, the melting machine cannot switch the plastic pipelines with different diameters in time, the two sections of melted pipelines are meshed together manually by the workers, and therefore the efficiency is low and the pipeline welding quality is not high; in addition, the plastic pipeline melted at high temperature has certain potential safety hazard to workers, and welding is very inconvenient.
SUMMERY OF THE UTILITY MODEL
In view of this, the utility model aims at providing an efficient plastic conduit welding machine can be under the prerequisite of guaranteeing pipeline welding quality, and the welding installation of pipeline is accomplished to high efficiency, fast, and the guarantee farmland task of supplying water can be accomplished as scheduled.
In order to achieve the purpose of the utility model, the technical proposal is as follows:
the efficient plastic pipeline welding machine for pipeline installation engineering comprises a supporting base, wherein a hot melting machine and two symmetrically arranged pipeline fixing devices are arranged on the supporting base, and each pipeline fixing device comprises a height adjusting unit, a horizontal moving unit and a pipeline fixing unit;
the height adjusting unit comprises a lifting cylinder arranged on a supporting base, a supporting platform is arranged on a piston rod of the lifting cylinder, and elastic supporting components are arranged at four corners of the bottom of the supporting platform respectively;
the horizontal moving unit comprises a sliding seat, screw rod supporting seats, a transmission screw rod and a servo motor, wherein the screw rod supporting seats are provided with two screw rods which are respectively installed at two ends of a supporting platform, the transmission screw rod is installed between the two screw rod supporting seats, an output shaft of the servo motor is connected with the transmission screw rod, guide rails are arranged on two sides of the transmission screw rod in parallel, the sliding seat is sleeved on the transmission screw rod, and the transmission screw rod is driven by the servo motor to move so as to drive the sliding seat to slide left and right along the guide rails;
the pipeline fixing unit comprises a first support frame, a second support frame and a plurality of pipe clamp assemblies, wherein the first support frame, the second support frame and the plurality of pipe clamp assemblies are installed on the sliding seat, each pipe clamp assembly comprises a first pipe clamp portion and a second pipe clamp portion, the first pipe clamp portion and the second pipe clamp portion can be enclosed to form a locking cavity, the first pipe clamp portion and the second pipe clamp portion can be opened relatively, one end of the second pipe clamp portion is sleeved on the first support frame, the locking assembly is arranged between the other end of the second pipe clamp portion and the first pipe clamp portion, and the bottom middle portion of the second pipe clamp portion is sleeved on the second support frame.
As a further improvement, be equipped with the position control device who is used for adjusting the hot melt machine position on the support base, position control device includes guide bar and regulation seat, the guide bar is fixed on supporting the base and is followed the length direction setting that supports the base, it slides and sets up to adjust the seat on the guide bar, the hot melt machine is installed on the regulation seat.
As a further improvement of the utility model, be provided with the standing groove that is used for placing the hot melt machine on adjusting the seat.
As the utility model discloses a further improvement, be equipped with spacing subassembly on the regulation seat, spacing subassembly is including fixing the screw sleeve on adjusting the seat, it is equipped with the screw hole with the corresponding position department of screw sleeve on the seat to adjust, be equipped with spacing bolt in the screw sleeve, the front end of spacing bolt supports tightly with the guide bar after passing screw sleeve, screw hole in proper order.
As a further improvement, the elastic supporting component comprises a supporting rod and a supporting cylinder, the upper end of the supporting rod is fixedly connected with the bottom of the supporting platform, the lower end of the supporting rod is movably arranged inside the supporting cylinder, and the bottom of the supporting rod and the bottom of the inside of the supporting cylinder are provided with the traction spring, the supporting cylinder is fixedly arranged on the supporting base, when the lifting cylinder drives the supporting platform to lift upwards, the supporting rod moves upwards inside the supporting cylinder, and the traction spring is stretched, so that the supporting platform can be kept more stable when rising to the moving height.
As a further improvement, the locking assembly comprises a locking bolt which is rotatably arranged at the other end of the second pipe clamping part, a bayonet is arranged on the first pipe clamping part, a locking nut is sleeved on the locking bolt through a thread, the upper end of the locking bolt is positioned in the bayonet through rotating the locking bolt, and then the locking bolt is locked through the locking nut.
As a further improvement, the first pipe clamp portion is provided with a jacking component, the jacking component comprises two at least symmetrical jacking bolts, and the front end of each jacking bolt is connected with an arc-shaped top plate after passing through a threaded hole in the first pipe clamp portion.
The utility model has the advantages that: the utility model discloses can be under the prerequisite of guaranteeing pipeline welding quality, high-efficient, accomplish the welding installation of pipeline fast, the guarantee piping erection task can be accomplished as scheduled. The construction operation of water conservancy pipeline all has not neglected engineering in each fields such as city pipe network, agriculture and industry and accounts for than, the utility model discloses a popularization will improve the efficiency of construction greatly, reduce construction cost.
Drawings
The accompanying drawings, which are incorporated in and constitute a part of this application, are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification. In the drawings:
FIG. 1 is a schematic view of the present invention;
fig. 2 is a schematic view of a second view structure of the present invention;
FIG. 3 is an enlarged view of the structure of portion A of FIG. 2;
FIG. 4 is a schematic structural view of the pipe clamp assembly of the present invention;
fig. 5 is a schematic structural diagram of a pipe clamp assembly in embodiment 2 of the present invention.
In the figure: 1. the device comprises a supporting base, 2, a hot melting machine, 3, a pipeline fixing device, 4, a position adjusting device, 5, a first plastic pipe, 301 lifting air cylinders, 302, a supporting platform, 303 elastic supporting components, 304, a sliding seat, 305, a screw supporting seat, 306, a transmission screw, 307, a servo motor, 308, a guide rail, 309, a first supporting frame, 310, a second supporting frame, 311, a pipe clamp component, 312, a first pipe clamp part, 313, a second pipe clamp part, 314, a locking component, 315, a supporting rod, 316, a supporting cylinder, 317, a locking bolt, 318, a bayonet, 319, a locking nut, 320, a jacking component, 321, a jacking bolt, 322, an arc top plate, 401, an adjusting seat, 402, an adjusting seat, 403, a limiting component, 404, a threaded sleeve, 405 and a limiting bolt.
Detailed Description
It should be noted that, in the present application, the embodiments and features of the embodiments may be combined with each other without conflict. The present invention will be described in detail below with reference to the accompanying drawings in conjunction with embodiments.
In order to make the technical solutions of the present application better understood by those skilled in the art, the technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the drawings in the embodiments of the present application, and it is obvious that the described embodiments are only some embodiments of the present application, and not all embodiments. All other embodiments obtained by a person of ordinary skill in the art based on the embodiments in the present application without making any creative effort shall fall within the protection scope of the present application.
Example 1
As shown in fig. 1-4, the high-efficiency plastic pipeline welding machine for pipeline installation engineering comprises a supporting base 1, wherein a hot melting machine 2 and two symmetrically arranged pipeline fixing devices 3 are arranged on the supporting base 1, and each pipeline fixing device 3 comprises a height adjusting unit, a horizontal moving unit and a pipeline fixing unit;
the height adjusting unit comprises a lifting cylinder 301 arranged on the supporting base 1, a supporting platform 302 is arranged on a piston rod of the lifting cylinder 301, and elastic supporting components 303 are respectively arranged at four corners of the bottom of the supporting platform 302;
the horizontal moving unit comprises a sliding seat 304, screw rod supporting seats 305, a transmission screw rod 306 and a servo motor 307, wherein the screw rod supporting seats 305 are provided with two screw rod supporting seats which are respectively arranged at two ends of the supporting platform 302, the transmission screw rod 306 is arranged between the two screw rod supporting seats 305, an output shaft of the servo motor 307 is connected with the transmission screw rod 306, guide rails 308 are arranged at two sides of the transmission screw rod 306 in parallel, the sliding seat 304 is sleeved on the transmission screw rod 306, and the servo motor 307 drives the transmission screw rod 306 to move so as to drive the sliding seat 304 to slide left and right along the guide rails 308;
the pipeline fixing unit comprises a first support frame 309, a second support frame 310 and a plurality of pipe clamp assemblies 311 which are installed on a sliding base 304, each pipe clamp assembly 311 comprises a first pipe clamp portion 312 and a second pipe clamp portion 313 which can be enclosed into a locking cavity, the first pipe clamp portion 312 and the second pipe clamp portion 313 can be opened relatively, one end of the second pipe clamp portion 313 is sleeved on the first support frame 309, a locking assembly 314 is arranged between the other end of the second pipe clamp portion and the first pipe clamp portion 312, and the bottom middle portion of the second pipe clamp portion 313 is sleeved on the second support frame 310.
Support and be equipped with position control device 4 that is used for adjusting 2 positions of hot melt machine on the base 1, position control device 4 includes guide bar 401 and regulation seat 402, guide bar 401 is fixed and is set up along the length direction who supports base 1 on supporting base 1, it slides and sets up to adjust seat 402 on the guide bar 401, hot melt machine 2 installs adjust on the seat 402.
The adjusting base 402 is provided with a placing groove for placing the hot melting machine 2.
The adjustable support is characterized in that a limiting component 403 is arranged on the adjusting seat 402, the limiting component 403 comprises a threaded sleeve 404 fixed on the adjusting seat 402, a threaded hole is formed in the position, corresponding to the threaded sleeve 404, of the adjusting seat 402, a limiting bolt 405 is arranged in the threaded sleeve 404, and the front end of the limiting bolt 405 penetrates through the threaded sleeve 404 and the threaded hole in sequence and then abuts against the guide rod 401 tightly.
The elastic support assembly 303 comprises a support rod 315 and a support cylinder 316, the upper end of the support rod 315 is fixedly connected with the bottom of the support platform 302, the lower end is movably located inside the support cylinder 316, a pulling spring is arranged between the support rod 315 and the bottom end inside the support cylinder 316, the support cylinder 316 is fixedly mounted on the support base 1, when the lifting cylinder 301 drives the support platform 302 to lift upwards, the support rod 315 moves upwards inside the support cylinder 316, and at the moment, the pulling spring is stretched, so that the support platform 302 can be kept more stable when lifted to a moving height.
The locking assembly 314 comprises a locking bolt 317 rotatably arranged at the other end of the second pipe clamping portion 313, a bayonet 318 is arranged on the first pipe clamping portion 312, a locking nut 319 is sleeved on the locking bolt 317 through threads, the upper end of the locking bolt 317 is positioned in the bayonet 318 through rotation, and then the locking bolt is locked through the locking nut 319.
Example 2
Based on the structure of embodiment 1, in embodiment 2, as shown in fig. 5, a tightening assembly 320 is disposed on the first pipe clamping portion 312, the tightening assembly 320 includes at least two symmetrically disposed tightening bolts 321, a front end of the tightening bolt 321 passes through a threaded hole on the first pipe clamping portion 312 and is connected to an arc-shaped top plate 322, and the setting of the tightening assembly 320 facilitates fixing of a small-diameter pipe.
The utility model discloses when using, the pipeline fixing device 3 that sets up through two symmetries will treat welded first plastic tubing 5 and second plastic tubing 6 respectively fixedly, make the face of treating of first plastic tubing 5 and second plastic tubing 6 directly push up hot melt machine 2 through altitude mixture control unit and horizontal migration unit and make and treat the face round mouth melting, then hot melt machine 2 shifts up, through two horizontal migration units with first plastic tubing 5 and 6 alignment pressurizations of second plastic tubing, realize the welding of first plastic tubing 5 and second plastic tubing 6.
The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention, and various modifications and changes may be made by those skilled in the art. Any modification, equivalent replacement, improvement, component separation or combination made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (7)

1. High-efficient plastic conduit welding machine that pipeline installation engineering used, its characterized in that: the hot melting machine and the two symmetrically arranged pipeline fixing devices are arranged on the supporting base, and each pipeline fixing device comprises a height adjusting unit, a horizontal moving unit and a pipeline fixing unit;
the height adjusting unit comprises a lifting cylinder arranged on a supporting base, a supporting platform is arranged on a piston rod of the lifting cylinder, and elastic supporting components are arranged at four corners of the bottom of the supporting platform respectively;
the horizontal moving unit comprises a sliding seat, screw rod supporting seats, a transmission screw rod and a servo motor, wherein the screw rod supporting seats are provided with two screw rods which are respectively installed at two ends of a supporting platform, the transmission screw rod is installed between the two screw rod supporting seats, an output shaft of the servo motor is connected with the transmission screw rod, guide rails are arranged on two sides of the transmission screw rod in parallel, the sliding seat is sleeved on the transmission screw rod, and the transmission screw rod is driven by the servo motor to move so as to drive the sliding seat to slide left and right along the guide rails;
the pipeline fixing unit comprises a first support frame, a second support frame and a plurality of pipe clamp assemblies, wherein the first support frame, the second support frame and the plurality of pipe clamp assemblies are installed on the sliding seat, each pipe clamp assembly comprises a first pipe clamp portion and a second pipe clamp portion, the first pipe clamp portion and the second pipe clamp portion can be enclosed to form a locking cavity, the first pipe clamp portion and the second pipe clamp portion can be opened relatively, one end of the second pipe clamp portion is sleeved on the first support frame, the locking assembly is arranged between the other end of the second pipe clamp portion and the first pipe clamp portion, and the bottom middle portion of the second pipe clamp portion is sleeved on the second support frame.
2. The efficient plastic pipeline welding machine for pipeline installation engineering according to claim 1, wherein: the hot melting machine is characterized in that a position adjusting device used for adjusting the position of the hot melting machine is arranged on the supporting base and comprises a guide rod and an adjusting seat, the guide rod is fixed on the supporting base and arranged along the length direction of the supporting base, the adjusting seat is arranged on the guide rod in a sliding mode, and the hot melting machine is installed on the adjusting seat.
3. The efficient plastic pipeline welding machine for pipeline installation engineering as claimed in claim 2, wherein: and a placing groove for placing the hot melting machine is formed in the adjusting seat.
4. A high efficiency plastic pipe welder for pipe installation work according to claim 2 or 3, characterized in that: the adjusting seat is provided with a limiting assembly, the limiting assembly comprises a threaded sleeve fixed on the adjusting seat, a threaded hole is formed in the position, corresponding to the threaded sleeve, of the adjusting seat, a limiting bolt is arranged in the threaded sleeve, and the front end of the limiting bolt is tightly abutted to the guide rod after penetrating through the threaded sleeve and the threaded hole in sequence.
5. The efficient plastic pipeline welding machine for pipeline installation engineering according to claim 1, wherein: the elastic support assembly comprises a support rod and a support cylinder, the upper end of the support rod is fixedly connected with the bottom of the support platform, the lower end of the support rod is movably located inside the support cylinder, a traction spring is arranged between the support rod and the bottom of the inside of the support cylinder, and the support cylinder is fixedly installed on the support base.
6. The efficient plastic pipeline welding machine for pipeline installation engineering according to claim 1, wherein: locking Assembly includes rotatable setting locking bolt on second pipe strap portion other end, be equipped with the bayonet socket in the first pipe strap portion, the threaded sleeve is equipped with lock nut on the locking bolt.
7. The efficient plastic pipeline welding machine for pipeline installation engineering according to claim 1, wherein: the pipe clamp is characterized in that a jacking assembly is arranged on the first pipe clamp portion and comprises at least two symmetrically arranged jacking bolts, and the front ends of the jacking bolts penetrate through threaded holes in the first pipe clamp portion and then are connected with arc-shaped top plates.
CN202221978168.6U 2022-07-28 2022-07-28 High-efficient plastic conduit welding machine that pipeline erection engineering used Active CN217752828U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221978168.6U CN217752828U (en) 2022-07-28 2022-07-28 High-efficient plastic conduit welding machine that pipeline erection engineering used

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221978168.6U CN217752828U (en) 2022-07-28 2022-07-28 High-efficient plastic conduit welding machine that pipeline erection engineering used

Publications (1)

Publication Number Publication Date
CN217752828U true CN217752828U (en) 2022-11-08

Family

ID=83877316

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221978168.6U Active CN217752828U (en) 2022-07-28 2022-07-28 High-efficient plastic conduit welding machine that pipeline erection engineering used

Country Status (1)

Country Link
CN (1) CN217752828U (en)

Similar Documents

Publication Publication Date Title
WO2023019711A1 (en) Automatic welding equipment
CN203726056U (en) Auxiliary support device for sidewise-mounting welding of large structures
CN110822169B (en) Pipeline laying device for road engineering and laying method thereof
CN102632319A (en) Numerically-controlled radiator automatic welding machine
CN106112360A (en) A kind of H profile steel quick centering group founds machine double spot-welding equipment
CN212286455U (en) Positioning and clamping device for mechanical welding
CN110039236A (en) A kind of welding fixture of the guide rail of attachment type raise scaffold
CN105710518A (en) Hollow bolt ball welding tool
CN211102477U (en) Pipeline aligning device
CN210334872U (en) Welding platform for super-huge steel members
CN217752828U (en) High-efficient plastic conduit welding machine that pipeline erection engineering used
CN107186416A (en) A kind of component of machine weld clamp device
CN108237303B (en) Rail narrow-gap arc welding machine and welding method thereof
CN104108177A (en) Thermofusion welding method of polyethylene (PE) gas valve central stand column and thermofusion welding device
CN205464583U (en) Horizontal cutting equipment
CN115283893A (en) Steel pipe welding device and welding process
CN210649301U (en) Workstation convenient to short steel pipe welding operation
CN209078177U (en) New energy water-cooled plate water nozzle internal expanding fastening apparatus
CN209478799U (en) A kind of electric melting pipe fittings mold core wrapping wire lifting device
CN219818569U (en) Vertical support frame splice welding device
CN205703085U (en) A kind of auxiliary positioner of Adjustable Range
CN220278756U (en) Lifting and rotating tool for repair welding of standard joint
CN220945266U (en) Stable bearing clamp
CN220226771U (en) Lifting type screwing machine device with adjustable size
CN206883038U (en) A kind of top plate component welder

Legal Events

Date Code Title Description
GR01 Patent grant