CN217711807U - Upper bearing type inhaul cable construction bearing device - Google Patents
Upper bearing type inhaul cable construction bearing device Download PDFInfo
- Publication number
- CN217711807U CN217711807U CN202221467824.6U CN202221467824U CN217711807U CN 217711807 U CN217711807 U CN 217711807U CN 202221467824 U CN202221467824 U CN 202221467824U CN 217711807 U CN217711807 U CN 217711807U
- Authority
- CN
- China
- Prior art keywords
- truss
- cable
- building
- superimposed sheet
- positioning
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Abstract
The structure is characterized in that the upper supporting type stay rope construction bearing device is arranged between building beams, truss composite slabs are laid between the building beams, positioning columns corresponding to the truss composite slabs are arranged on the building beams, stay ropes with tensioning devices are arranged between the positioning columns and the trusses corresponding to the truss composite slabs, the positions of bottom plates of the truss composite slabs are adjusted by adjusting the tensioning devices, the bottom plates are bent downwards when concrete is prevented from being poured, a supporting frame is not required to be arranged at the bottoms of the truss composite slabs, the construction quality is guaranteed, unnecessary construction operation steps are reduced, and the efficiency of floor construction is greatly improved.
Description
Technical Field
The utility model belongs to the technical field of the construction technology and specifically relates to a take-up cable construction bearing device.
Background
When the building construction of floor slab is carried out, usually be the prefabricated superimposed sheet of overlap joint on the building crossbeam, then carry out the pouring of concrete, form holistic floor slab finally, but if the span between the building crossbeam is great, then make the superimposed sheet produce the situation of downwarping very easily at the in-process of pouring concrete, can't guarantee construction quality, the method of solving this problem at present installs the support frame additional in the bottom of superimposed sheet, the height of support frame sets up according to the height of floor, its stability often is not enough for too high support frame, and also need additionally carry out the dismouting operation of support frame in the manufacture process of floor slab, the construction of giving the floor slab has brought the trouble of different degree.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a take up formula cable construction bearing device installs the cable that has overspeed device tensioner between the reference column on truss superimposed sheet and building crossbeam, and the truss superimposed sheet takes place the condition of downwarping when avoiding concreting through adjusting overspeed device tensioner, under the prerequisite that does not use the support frame, solves the problem among the prior art.
The utility model provides a technical scheme that its technical problem adopted is: a take up formula cable construction load-bearing device, including a plurality of rows of building crossbeam that set up side by side, be equipped with the truss superimposed sheet between per two building crossbeams, the truss superimposed sheet is including a plurality of trusses that set up on bottom plate and the bottom plate, and the bottom plate is located the building crossbeam, corresponding to the position at truss superimposed sheet both ends, all installs corresponding positioning seat on the building crossbeam, and the periphery of positioning seat is equipped with the lag, and the lag is located the building crossbeam, the detachable reference column is installed in the cooperation on the positioning seat, and the reference column is located inside the lag, all installs two cables that have overspeed device tensioner on the every truss, and the one end of cable is connected with the last chord of truss, and the other end of cable is connected with the upper end of reference column, and two cables of every truss are connected with the upper end of the reference column at this truss superimposed sheet both ends respectively. The protection sleeve is a rectangular sleeve, the length direction of the rectangular sleeve is arranged along the length direction of the building beam, matched through holes are formed in the positioning column and the positioning seat, the bolt penetrates through the through holes and is provided with a fastening nut in a matched mode, the axial direction of the bolt is arranged along the length direction of the rectangular sleeve, and the bolt can stretch into a space between the rectangular sleeve and the positioning column. One end of the inhaul cable is provided with a lantern ring, the lantern ring is sleeved on the upper chord and the rib of the truss, the upper end of the positioning column is provided with a hanging ring, and the other end of the inhaul cable is provided with a hook matched with the hanging ring.
The utility model has the positive effects that: a hold formula cable construction load-bearing device and construction method on, lay the truss superimposed sheet between the building crossbeam, and set up the reference column corresponding with the truss superimposed sheet on the building crossbeam, the cable that the installation has overspeed device tensioner between reference column and the truss that corresponds the truss superimposed sheet, adjust the position of truss superimposed sheet bottom plate through adjusting overspeed device tensioner, the bottom plate takes place the condition of downwarping when avoiding concreting, need not to set up the support frame bottom the truss superimposed sheet, construction quality has not only been guaranteed, inessential construction operating procedure has still been reduced, the efficiency of floor construction has been improved by a wide margin.
Drawings
Fig. 1 is a schematic structural diagram of the present invention (a schematic state after the bottom plate is adjusted in step (5));
FIG. 2 is a top view of FIG. 1;
FIG. 3 is an enlarged view taken along line A-A of FIG. 1;
fig. 4 is a schematic structural diagram of the steel bar net and the poured concrete in the step 6 and the step 7;
FIG. 5 is a schematic structural diagram of pouring concrete into the protective sleeve after the positioning columns are detached in the steps 8 and 9;
fig. 6 is another structural embodiment of the connection between the guy cable and the location post and truss.
Detailed Description
Hold formula cable construction load-bearing device, as shown in fig. 1 and fig. 2, including a plurality of rows of building crossbeam 1 that set up side by side, be equipped with the truss superimposed sheet between per two building crossbeam 1, the truss superimposed sheet is including a plurality of trusses 4 that set up on bottom plate 3 and the bottom plate 3, bottom plate 3 is located building crossbeam 1, truss 4 arranges along the length direction who erects the superimposed sheet, sets up with building crossbeam 1's length direction mutually perpendicularly. Corresponding to the position at truss superimposed sheet both ends, all install corresponding positioning seat 2 on building crossbeam 1, the periphery of positioning seat 2 is equipped with lag 5, and lag 5 is located building crossbeam 1. The positioning seat 2 is provided with a detachable positioning column 6 in a matching mode, and the positioning column 6 is located inside the protecting sleeve 5. All install two cables 8 that have overspeed device tensioner 7 on every truss 4, the one end of cable 8 is connected with truss 4's last quarter, and the other end of cable 8 is connected with the upper end of reference column 6, and two cables 8 of every truss 4 are connected with the upper end of the reference column 6 at truss superimposed sheet both ends at this truss 4 place respectively. That is to say, every truss superimposed sheet is not only its both ends receive the support of building crossbeam 1, also makes whole truss superimposed sheet obtain ascending pulling force through two cables 8 on every truss 4, makes the bottom plate 3 of truss superimposed sheet be in same horizontal position, can offset the action of gravity on most concrete layer when concrete placement in later stage to avoid truss superimposed sheet to receive the stress and produce the deformation of downwarping, guarantee the normal clear of construction. The tension force applied to the truss composite slab can be changed by adjusting the tension device 7, so that the requirement of pouring concrete with different weights can be met.
Further, the protection sleeve 5 is a rectangular sleeve, the length direction of the rectangular sleeve is arranged along the length direction of the building beam 1, the positioning column 6 and the positioning seat 2 are provided with matched through holes, the bolt 9 penetrates through the through holes and is provided with a fastening nut 10 in a matched mode, as shown in fig. 3, the axial direction of the bolt 9 is arranged along the length direction of the rectangular sleeve, and the bolt 9 can extend into a space between the rectangular sleeve and the positioning column 6. Bolt 9 has improved the joint strength of reference column 6 and positioning seat 2 to a certain extent with fastening nut 10's setting, also is convenient for realize dismantling fixedly between reference column 6 and the positioning seat 2, and wherein the length direction distance of rectangle cover slightly is greater than for the twice of bolt 9 length to stretch into bolt 9 at first between rectangle cover and the reference column 6, then carrying out the interlude of through-hole and fastening nut 10's cooperation installation.
Further, in order to install the guy cable 8 with the tensioning device 7 between the positioning column 6 and the truss composite slab, as shown in fig. 6, one end of the guy cable 8 is provided with a sleeve ring 12, the sleeve ring 12 is sleeved on the upper chord and the rib of the truss 4 so as to realize the fixed connection with the truss 4, the upper end of the positioning column 6 is provided with a hanging ring 13, the other end of the guy cable 8 is provided with a hook 14 matched with the hanging ring 13, and the guy cable 8 and the positioning column 6 can be fixedly connected by being hung on the hanging ring 13 through the hook 14.
A construction method of a bearing device for the construction of a top bearing type inhaul cable comprises the following steps:
(1) a plurality of positioning seats 2 are arranged in the length direction of the building beams 1, truss composite slabs with the same number as the positioning seats 2 are laid between every two building beams 1, the truss composite slabs are in one-to-one correspondence with the positioning seats 2, and each truss composite slab comprises a bottom plate 3 and a plurality of trusses 4 arranged on the bottom plate 3. 3 overlap joints of bottom plate are between two building crossbeams 1, and the both ends of truss superimposed sheet all are equipped with corresponding positioning seat 2, and setting up of truss 4 can make the fastening more that concrete layer and bottom plate 3 combine when concreting in the later stage. If the building cross beam 1 is a metal beam, the positioning seat 2 is welded and fixed on the building cross beam 1, if the building cross beam 1 is a concrete precast beam, a convex embedded metal piece needs to be arranged in the building cross beam 1 during manufacturing, and the positioning seat 2 and the embedded metal piece are welded and fixed.
(2) And (3) placing a protective sleeve 5 on the periphery of each positioning seat 2 installed in the step (1), wherein the protective sleeve 5 is positioned on the building cross beam 1 and between the two truss composite slabs.
(3) And (3) a positioning column 6 is arranged on the positioning seat 2, so that the positioning column 6 is positioned in the protective sleeve 5 placed in the step (2).
(4) Every 4 last installation two inhaul cables 8 that have overspeed device tensioner 7 of truss, two inhaul cables 8 of every truss 4 are connected with the upper end of the reference column 6 at this truss 4 place truss superimposed sheet both ends respectively. Through adjusting tensioning device 7 can adjust the 8 lengths of cable between reference column 6 and truss 4 to and the position that whole truss superimposed sheet bottom plate 3 is located, take place the circumstances of bending downwards when avoiding appearing concrete placement.
(5) And adjusting a tensioning device 7 on each inhaul cable 8 to enable the heights of the middle parts of the bottom plates 3 of all the truss composite slabs and the two ends of the bottom plates 3 to be the same. The integral truss composite slab is kept at the same horizontal position before concrete pouring, and bending deformation of the middle part of the truss composite slab in the length direction is avoided when concrete is poured.
(6) And (3) laying reinforcing meshes 11 on the truss composite slab and the building cross beam 1 so as to further improve the building strength of the constructed floor slab.
(7) And (5) pouring concrete on each truss composite slab and the building crossbeam 1, so that the reinforcing mesh 11 and the truss 4 paved in the step (6) are embedded in the concrete, and the height of the poured concrete is not higher than that of the protective sleeve 5. As shown in fig. 4, the casting height of the concrete can be aligned with the height of the protective sleeve 5, and except for the space inside the protective sleeve 5, the building beams 1 and the truss composite slab are both cast with concrete, so as to facilitate the later dismantling operation of the positioning columns 6 in the protective sleeve 5.
(8) And (5) after the concrete poured in the step (7) is solidified, forming a cast-in-place layer, shearing off the stay cable 8 at the surface position of the cast-in-place layer, and dismantling the positioning column 6.
(9) And (5) pouring concrete into the protective sleeve 5 until the concrete is level with the cast-in-place layer formed in the step (8), and obtaining the laminated floor after the concrete is solidified. As shown in fig. 5, after the positioning columns 6 are removed, the building beam 1 and the truss composite slab form a level concrete pouring layer, i.e. a floor slab to be constructed. If the height of the protective sleeve 5 is higher than that of the cast-in-place layer after the pouring is finished, the position of the redundant height of the protective sleeve 5 can be manually cut off after the concrete is solidified.
Further, in order to ensure the connection strength between the positioning column 6 and the positioning seat 2, after the positioning column 6 is installed in the step (3), positioning pins are inserted into the positioning column 6 and the positioning seat 2, wherein through holes matched with the positioning pins are formed in the positioning column 6 and the positioning seat 2.
Furthermore, the positioning pin is a bolt 9, and after the positioning column 6 is mounted on the positioning seat 2, the bolt 9 penetrates through the positioning column 6 and the through hole of the positioning seat 2, and a fastening nut 10 is screwed on the bolt 9 in a matching manner, so that the positioning seat 2 is fixedly connected with the positioning column 6.
Technical scheme of the utility model not be restricted to the utility model the within range of embodiment. The technical contents not described in detail in the present application are all known technologies.
Claims (3)
1. The utility model provides a deck cable construction load-bearing device which characterized in that: including a plurality of rows of building crossbeam (1) that set up side by side, be equipped with the truss superimposed sheet between per two building crossbeam (1), the truss superimposed sheet is including a plurality of trusses (4) that set up on bottom plate (3) and bottom plate (3), bottom plate (3) are located building crossbeam (1), corresponding to the position at truss superimposed sheet both ends, all install corresponding positioning seat (2) on building crossbeam (1), the periphery of positioning seat (2) is equipped with lag (5), lag (5) are located building crossbeam (1), detachable reference column (6) are installed in the cooperation on positioning seat (2), reference column (6) are located lag (5) inside, all install two cable (8) that have overspeed device tensioner (7) on every truss (4), the one end of cable (8) is connected with the last string of truss (4), the other end of cable (8) is connected with the upper end of reference column (6), two truss (8) of every truss (4) are connected with the reference column (6) at the both ends of this truss (4) place superimposed sheet upper end respectively.
2. The bolster construction load bearing device of claim 1, wherein: the protection sleeve (5) is a rectangular sleeve, the length direction of the rectangular sleeve is arranged along the length direction of the building beam (1), matched through holes are formed in the positioning column (6) and the positioning seat (2), the bolt (9) penetrates through the through holes and is matched with the through holes to install the fastening nut (10), the axial direction of the bolt (9) is arranged along the length direction of the rectangular sleeve, and the bolt (9) can stretch into the space between the rectangular sleeve and the positioning column (6).
3. The deck type guy construction load bearing device of claim 1, wherein: one end of the inhaul cable (8) is provided with a lantern ring (12), the lantern ring (12) is sleeved on the upper chord and the rib of the truss (4), the upper end of the positioning column (6) is provided with a hanging ring (13), and the other end of the inhaul cable (8) is provided with a hook (14) matched with the hanging ring (13).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202221467824.6U CN217711807U (en) | 2022-06-13 | 2022-06-13 | Upper bearing type inhaul cable construction bearing device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202221467824.6U CN217711807U (en) | 2022-06-13 | 2022-06-13 | Upper bearing type inhaul cable construction bearing device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN217711807U true CN217711807U (en) | 2022-11-01 |
Family
ID=83800544
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202221467824.6U Active CN217711807U (en) | 2022-06-13 | 2022-06-13 | Upper bearing type inhaul cable construction bearing device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN217711807U (en) |
-
2022
- 2022-06-13 CN CN202221467824.6U patent/CN217711807U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105113388B (en) | Formwork and bracket combining structure of vase pier of viaduct and application method | |
CN101787732B (en) | Cable-stayed multi-layer framework structure and construction control method thereof | |
CN114427258B (en) | High-altitude large-span cantilever concrete member disassembly-free construction system and construction method | |
CN113931313B (en) | Construction method of super high-rise core tube horizontal structure | |
CN110965474A (en) | Construction method of cable tower cross beam | |
CN207159827U (en) | No. 1 plate installation and positioning structure in No. 0 block of Wavelike steel webplate bridge | |
CN112832368A (en) | Quick construction process for cantilever beam at ultrahigh position | |
CN105780922A (en) | Construction method for segmental formwork hoisting system of large-span steel reinforced concrete transfer truss | |
CN113914223A (en) | High-pier arc-shaped upper cross beam light-weight bracket system and mounting method thereof | |
CN217711807U (en) | Upper bearing type inhaul cable construction bearing device | |
CN107326812A (en) | No. 1 plate installation and positioning structure and operating method in No. 0 block of Wavelike steel webplate bridge | |
CN111519545A (en) | Pier and capping beam integrated construction platform and construction method thereof | |
CN108518071B (en) | Installation method of double-layer large-span steel structure corridor | |
CN207296399U (en) | Continuous placing is molded overall assembled stair template system | |
CN216616865U (en) | High-efficient construction system of super high-rise structure of encorbelmenting | |
CN114991496A (en) | Bearing type inhaul cable construction bearing device and construction method | |
CN108797350B (en) | Tower column inner and outer stiff skeleton device and construction method thereof | |
CN115162752A (en) | Top-bearing rope-pulling construction bearing device and construction method | |
CN111196566A (en) | Construction structure and construction method of super high-rise inner climbing tower crane | |
CN107630409B (en) | Supporting structure for temporary T-shaped structure suspension casting construction and manufacturing method thereof | |
CN205476466U (en) | Formwork system is hoisted in segmentation of large -span shaped steel concrete conversion truss | |
CN115976980B (en) | Installation method of continuous beam segment reinforcement cage | |
CN219430545U (en) | Operation platform for utilizing stiffness framework for tower column head section | |
CN212771954U (en) | Pier and bent cap integral type construction platform | |
CN115538678B (en) | Construction method for small side surface platform of large-angle overhanging view platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |