CN217711782U - Concrete placement auxiliary device - Google Patents

Concrete placement auxiliary device Download PDF

Info

Publication number
CN217711782U
CN217711782U CN202221812938.XU CN202221812938U CN217711782U CN 217711782 U CN217711782 U CN 217711782U CN 202221812938 U CN202221812938 U CN 202221812938U CN 217711782 U CN217711782 U CN 217711782U
Authority
CN
China
Prior art keywords
pipe
auxiliary device
fixedly connected
hopper
shell
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221812938.XU
Other languages
Chinese (zh)
Inventor
王明明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202221812938.XU priority Critical patent/CN217711782U/en
Application granted granted Critical
Publication of CN217711782U publication Critical patent/CN217711782U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model relates to a pour equipment technical field, concretely relates to concrete placement auxiliary device, which comprises a hopper, the bottom of hopper has linked firmly the conveyer pipe, the outside of hopper is provided with supporting mechanism, the outside of conveyer pipe one end is provided with pushing mechanism, supporting mechanism is including bearing the shell, the inside wall that bears the shell top contacts with the lateral wall of hopper bottom, the bottom that bears the shell lateral wall has linked firmly the knee. The utility model discloses in, be provided with pushing mechanism through the outside in conveyer pipe one end, utilize clamp, spacing pipe and stand pipe to be convenient for fix the position of conveyer pipe one end, and through starter motor, utilize motor, circle piece, screw rod, screwed pipe, spacing groove and gag lever post to cooperate the use to make screwed pipe, knee and bear the weight of the shell and remove, and then make this concrete placement auxiliary device can adjust the height of hopper as required, improved this concrete placement auxiliary device's application scope.

Description

Concrete placement auxiliary device
Technical Field
The utility model relates to a pour equipment technical field, concretely relates to concrete placement auxiliary device.
Background
When water supply and drainage pipeline engineering is carried out, manual layered excavation and layered wall protection construction are adopted for some circular working wells, receiving wells and inspection wells, wherein when side wall concrete pouring is carried out, simple devices such as chutes and corrugated pipes are often adopted for pouring construction, but the construction method needs manual shoulder carrying, so that the manual labor is increased, the operation is not easy, the labor cost is increased, and the situations of super-pouring sprinkling, less post-pouring supplement and the like are easy to occur due to easy and unstable manual operation.
Some concrete pouring auxiliary devices also appear in the prior art, for example, a Chinese patent with the application number of 202021162946.5 discloses a concrete pouring auxiliary device, which relates to the technical field of building components, and comprises a material conveying assembly and a supporting assembly; the material conveying assembly comprises a hopper and a material pipe, an inlet of the material pipe is communicated with the hopper, and an outlet of the material pipe deviates from the inlet in the transverse direction and extends downwards along the direction far away from the inlet; the supporting assembly comprises an upright post and a supporting frame, the bottom of the upright post is used for being relatively fixed with the construction ground, and the supporting frame is fixedly connected to the upright post; the supporting assembly is used for supporting the material pipe.
Although this technical scheme can fix the material pipe, reduces staff's intensity of labour, has avoided because of manual operation unstability, the condition such as watering spills and mends after watering less appears. However, such concrete placement assistance device's rigidity is not convenient for adjust more the in service behavior, and the result of use is relatively poor.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a: in order to solve current concrete placement auxiliary device's rigidity of position, the service behavior adjusts more not convenient for, and the relatively poor problem of result of use provides a concrete placement auxiliary device.
The purpose of the utility model can be realized by the following technical scheme:
a concrete pouring auxiliary device comprises a hopper, wherein a conveying pipe is fixedly connected to the bottom of the hopper, a supporting mechanism is arranged on the outer side of the hopper, a pushing mechanism is arranged on the outer side of one end of the conveying pipe, the supporting mechanism comprises a bearing shell, the inner side wall of the top of the bearing shell is in contact with the outer side wall of the bottom of the hopper, a bent rod is fixedly connected to the bottom of the outer side wall of the bearing shell, a spiral pipe is fixedly connected to the bottom of the bent rod, a plurality of limiting rods are fixedly connected to the top of the outer side wall of the spiral pipe at equal angles relative to the central line of the spiral pipe, a screw rod is connected to the inner side of the spiral pipe in a screwing mode, a round pipe is arranged on the outer side of the screw rod, a plurality of limiting grooves are formed in the inner side wall of the round pipe at equal angles relative to the central line of the round pipe, the limiting rods are in sliding connection with the limiting grooves at corresponding positions, a rectangular shell is arranged at the bottom of the spiral pipe, and a motor is fixedly connected to the middle position at the top of the rectangular shell, the output end of the motor is fixedly connected with the round block, the top of the round block is fixedly connected with the bottom of the screw rod, the middle position of the top of the rectangular shell is fixedly connected with the fixed shell, the middle position of the top of the fixed shell is provided with the round hole, the position of the top of the fixed shell, which corresponds to the round hole, is fixedly connected with the connecting pipe, the top of the connecting pipe is fixedly connected with the bottom of the round pipe, when the concrete pouring auxiliary device is used, the hopper is supported and fixed by the bearing shell, the round block and the screw rod are driven to rotate by the motor through starting the motor, the screw pipe is connected with the screw rod in a screwing manner, and the screw pipe is limited by the limiting groove and the limiting rod, so that the screw pipe moves, the height of the bearing shell can be adjusted according to requirements by the concrete pouring auxiliary device, the application range of the concrete pouring auxiliary device is improved, and the hopper, the conveying pipe and the pushing mechanism are convenient for conveying concrete to a proper position for pouring, the use effect of this concrete placement auxiliary device has been improved, has avoided artifical transport conveyer pipe, has reduced staff's intensity of labour.
The inner diameter of the connecting pipe is the same as that of the round pipe, and the inner diameter of the connecting pipe is larger than the outer diameter of the screw rod.
The circular block is arranged on the bottom of the rectangular shell, and the outer diameter of the circular block is larger than that of the screw rod.
Further, the equal sliding connection in both ends of rectangle shell has the movable plate, the intermediate position department of movable plate one end sets up threaded hole, the one end of movable plate is provided with fixing bolt, and fixing bolt one end closes soon with the screw hole that corresponds position department and is connected, fixing bolt's one end has linked firmly the extrusion piece, through removing the movable plate to suitable position department to through the fixing bolt of screwing, thereby make the extrusion piece with place ground extrusion contact, and then be convenient for fix the position of supporting mechanism.
The rectangular shell is characterized in that two ends of two sides of the rectangular shell are fixedly connected with a first limiting block, two sides of the other end of the movable plate are fixedly connected with a second limiting block, the second limiting block is opposite to the first limiting block at the corresponding position, and the first limiting block and the second limiting block are utilized to avoid the separation of the movable plate and the rectangular shell.
Further lie in, pushing mechanism includes the L template, four corner position departments of L template horizontal segment have all linked firmly four universal wheel two, the intermediate position department of L template horizontal segment one end has linked firmly the bracing piece, and the top of bracing piece has linked firmly the stand pipe, the top of stand pipe is provided with spacing pipe, spacing outside of tubes lateral wall has linked firmly dead lever one, and the one end of dead lever one links firmly with the L template, be provided with the clamp between the top of spacing socle portion and stand pipe.
The push mechanism is characterized in that the top of the vertical section of the L-shaped plate is fixedly connected with a push handle, the outer side wall of the push handle is fixedly sleeved with a rubber sleeve, and the push handle and the rubber sleeve are used for facilitating the movement of the push mechanism.
The utility model has the advantages that:
1. through being provided with pushing mechanism in the outside of conveyer pipe one end, utilize the clamp, spacing pipe and stand pipe are convenient for fix the position of conveyer pipe one end, and through starter motor, utilize the motor, the circle piece, the screw rod, the screwed pipe, spacing groove and gag lever post cooperate the use, thereby make the screwed pipe, the knee removes with bearing shell, and then make the height that this concrete placement auxiliary device can adjust the hopper as required, this concrete placement auxiliary device's application scope has been improved, and utilize universal wheel one to be convenient for supporting mechanism and hopper to remove to suitable position department, recycle and push away the one end that pushing mechanism and conveyer pipe are convenient for with universal wheel two and remove to suitable position department, thereby utilize hopper and conveyer pipe to be convenient for pour concrete transport to suitable position department, the result of use of this concrete placement auxiliary device has been improved, manual handling conveyer pipe has been avoided, staff's intensity of labour has been reduced.
Drawings
The present invention will be further described with reference to the accompanying drawings.
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a schematic structural view of the supporting mechanism of the present invention;
FIG. 3 is an enlarged view of a portion of FIG. 2 at A;
FIG. 4 is an enlarged view of a portion of FIG. 2 at B;
fig. 5 is a schematic structural view of the middle pushing mechanism of the present invention.
In the figure: 100. a hopper; 110. a delivery pipe; 200. a support mechanism; 210. a load-bearing housing; 211. bending a rod; 220. a circular tube; 221. a limiting groove; 230. a screw; 240. a solenoid; 241. a limiting rod; 250. a motor; 260. a stationary case; 261. a connecting pipe; 270. a rectangular shell; 271. a first universal wheel; 272. a first limiting block; 280. moving the plate; 281. a threaded hole; 282. a second limiting block; 290. fixing the bolt; 291. extruding the block; 300. a pushing mechanism; 310. an L-shaped plate; 320. a second universal wheel; 330. a push handle; 340. fixing a rod I; 341. a limiting pipe; 350. clamping a hoop; 360. a support bar; 361. a guide tube.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely below with reference to the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by a person of ordinary skill in the art without creative efforts belong to the protection scope of the present invention.
Referring to fig. 1-5, a concrete pouring auxiliary device includes a hopper 100, a conveying pipe 110 is fixedly connected to the bottom of the hopper 100, a supporting mechanism 200 is disposed on the outer side of the hopper 100, a pushing mechanism 300 is disposed on the outer side of one end of the conveying pipe 110, the supporting mechanism 200 includes a bearing shell 210, the inner side wall of the top of the bearing shell 210 contacts with the outer side wall of the bottom of the hopper 100, a curved rod 211 is fixedly connected to the bottom of the outer side wall of the bearing shell 210, a spiral pipe 240 is fixedly connected to the bottom of the curved rod 211, a plurality of limiting rods 241 are fixedly connected to the top of the outer side wall of the spiral pipe 240 at equal angles with respect to the central line thereof, a screw rod 230 is rotatably connected to the inside of the spiral pipe 240, a circular pipe 220 is disposed on the outer side of the screw rod 230, a plurality of limiting grooves 221 are disposed on the inner side wall of the circular pipe 220 at equal angles with respect to the central line thereof, the limiting rods 241 are slidably connected to the limiting grooves 221 at corresponding positions, a rectangular shell 270 is disposed at the bottom of the spiral pipe 240, when the concrete pouring auxiliary device is used, the bearing shell 210 is used for supporting and fixing the hopper 100, the motor 250 is started to drive the round block and the screw rod 230 to rotate, the spiral pipe 240 is in screwed connection with the screw rod 230, the limiting groove 221 and the limiting rod 241 are used for limiting the spiral pipe 240, so that the spiral pipe 240 can move, the concrete pouring auxiliary device can adjust the height of the bearing shell 210 as required, and the application range of the concrete pouring auxiliary device is improved, hopper 100, conveyer pipe 110 and pushing mechanism 300 are convenient for carry the concrete to suitable position department and pour again, have improved this concrete placement auxiliary device's result of use, have avoided artifical transport conveyer pipe 110, have reduced staff's intensity of labour.
The inner diameter of the connecting pipe 261 is the same as the inner diameter of the circular pipe 220, the inner diameter of the connecting pipe 261 is larger than the outer diameter of the screw 230, the outer diameter of the circular block is larger than the outer diameter of the screw 230, the first universal wheel 271 is fixedly connected to four corner positions at the bottom of the rectangular shell 270, the rectangular shell 270 is convenient to move by means of the first universal wheel 271, the moving plate 280 is slidably connected to two ends inside the rectangular shell 270, a threaded hole 281 is formed in the middle of one end of the moving plate 280, a fixing bolt 290 is arranged at one end of the moving plate 280, one end of the fixing bolt 290 is rotatably connected with the threaded hole 281 at the corresponding position, an extrusion block 291 is fixedly connected to one end of the fixing bolt 290, the moving plate 280 is moved to the proper position and is rotated by means of the fixing bolt 290, so that the extrusion block 291 is in extrusion contact with the ground, and therefore the position of the supporting mechanism 200 is convenient to fix, the two ends of two sides of the rectangular shell 270 are fixedly connected with a first limit block 272, two limits 282 are fixedly connected to two ends of the other end of the moving plate 280, and two limits 272 are opposite to the first limit 272, and the first limit block 272 and the rectangular shell 270 are prevented from being separated from the moving plate 280.
Pushing mechanism 300 includes L template 310, four corner position departments of L template 310 horizontal segment all link firmly four universal wheel two 320, the intermediate position department of L template 310 horizontal segment one end links firmly bracing piece 360, and the top of bracing piece 360 links firmly stand pipe 361, the top of stand pipe 361 is provided with spacing pipe 341, the lateral wall of spacing pipe 341 links firmly dead lever one 340, and the one end of dead lever one 340 links firmly with L template 310, be provided with clamp 350 between spacing pipe 341 bottom and the top of stand pipe 361, the top of the vertical section of L template 310 links firmly pushes away handle 330, the lateral wall of pushing away handle 330 cup joints and is fixed with the rubber sleeve, utilize to push away handle 330 and rubber sleeve and be convenient for remove pushing mechanism 300.
The working principle is as follows: when the concrete pouring auxiliary device is used, the hopper 100 is supported and fixed by the bearing shell 210, one end of the conveying pipe 110 penetrates through the bottom of the bearing shell 210, penetrates through the limiting pipe 341 and the guide pipe 361 and extends to the bottom of the guide pipe 361, the clamp 350 is locked, the clamp 350 is in pressing contact with the outer side wall of the conveying pipe 110, the clamp 350 is limited by the limiting pipe 341 and the guide pipe 361, the position of one end of the conveying pipe 110 is fixed, the motor 250 is started to drive the round block and the screw 230 to rotate, the screw 240 is in screwing connection with the screw 230, the screw 240 is limited by the limiting groove 221 and the limiting rod 241, the screw 240 is moved, the height of the bearing shell 210 can be adjusted as required, the supporting mechanism 200 and the hopper 100 are convenient to move to the proper position by the first universal wheel 271, one ends of the pushing mechanisms 300 and 110 are convenient to move to the proper positions by the pushing handles 330 and the second universal wheels 320, the labor intensity of concrete pouring of a worker is improved, and the conveying efficiency of the conveying pipe is improved.
In the description herein, references to the description of "one embodiment," "an example," "a specific example," etc., mean that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the invention. In this specification, the schematic representations of the terms used above do not necessarily refer to the same embodiment or example. Furthermore, the particular features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.
The foregoing is illustrative and explanatory only, and various modifications, additions and substitutions as described for the specific embodiments described herein may be made by those skilled in the art without departing from the scope of the invention or exceeding the scope of the invention as defined in the claims.

Claims (7)

1. The utility model provides a concrete placement auxiliary device, includes hopper (100), its characterized in that, the bottom of hopper (100) has linked firmly conveyer pipe (110), the outside of hopper (100) is provided with supporting mechanism (200), the outside of conveyer pipe (110) one end is provided with pushing mechanism (300), supporting mechanism (200) are including bearing shell (210), the inside wall at bearing shell (210) top contacts with the lateral wall of hopper (100) bottom, the bottom of bearing shell (210) lateral wall has linked firmly knee (211), the bottom of knee (211) has linked firmly solenoid (240), solenoid (240) lateral wall top has linked firmly a plurality of gag lever posts (241) about its central line isogonism, the inside of solenoid (240) closes soon and is connected with screw rod (230), the outside of screw rod (230) is provided with pipe (220), pipe (220) have seted up a plurality of spacing grooves (221) about its central line isogonism about the inside wall, and gag lever post (241) and the spacing groove (221) sliding connection that corresponds position department, the bottom of solenoid (240) is provided with rectangular shell (270), and the middle part of the motor (250) and the middle part of screw rod (250) have linked firmly the motor, the intermediate position department at rectangle shell (270) top has linked firmly set casing (260), the round hole has been seted up to the intermediate position department at set casing (260) top, the position department that set casing (260) top corresponds the round hole has linked firmly connecting pipe (261), and connecting pipe (261) top links firmly with pipe (220) bottom.
2. A concrete pouring aid according to claim 1, wherein the inner diameter of the connecting pipe (261) is the same as the inner diameter of the round pipe (220), and the inner diameter of the connecting pipe (261) is larger than the outer diameter of the screw (230).
3. The concrete pouring auxiliary device according to claim 1, wherein the outer diameter of the round block is larger than that of the screw rod (230), and first universal wheels (271) are respectively connected to four corner positions of the bottom of the rectangular shell (270).
4. The concrete pouring auxiliary device as claimed in claim 1, wherein a moving plate (280) is slidably connected to each of two ends of the inside of the rectangular shell (270), a threaded hole (281) is formed in a middle position of one end of the moving plate (280), a fixing bolt (290) is arranged at one end of the moving plate (280), one end of the fixing bolt (290) is rotatably connected with the threaded hole (281) in the corresponding position, and an extrusion block (291) is fixedly connected to one end of the fixing bolt (290).
5. A concrete pouring auxiliary device according to claim 4, characterized in that two ends of two sides of the rectangular shell (270) are fixedly connected with a first limit block (272), two sides of the other end of the moving plate (280) are fixedly connected with a second limit block (282), and the second limit block (282) is opposite to the first limit block (272) at the corresponding position.
6. The concrete pouring auxiliary device as claimed in claim 1, wherein the pushing mechanism (300) comprises an L-shaped plate (310), four corner positions of a horizontal section of the L-shaped plate (310) are fixedly connected with four universal wheels II (320), a support rod (360) is fixedly connected with a middle position of one end of the horizontal section of the L-shaped plate (310), a guide pipe (361) is fixedly connected with the top of the support rod (360), a limiting pipe (341) is arranged at the top of the guide pipe (361), a first fixing rod (340) is fixedly connected with the outer side wall of the limiting pipe (341), one end of the first fixing rod (340) is fixedly connected with the L-shaped plate (310), and a clamp (350) is arranged between the bottom of the limiting pipe (341) and the top of the guide pipe (361).
7. A concrete pouring auxiliary device according to claim 6, characterized in that a push handle (330) is fixedly connected to the top of the vertical section of the L-shaped plate (310), and a rubber sleeve is fixedly sleeved on the outer side wall of the push handle (330).
CN202221812938.XU 2022-07-14 2022-07-14 Concrete placement auxiliary device Active CN217711782U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221812938.XU CN217711782U (en) 2022-07-14 2022-07-14 Concrete placement auxiliary device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221812938.XU CN217711782U (en) 2022-07-14 2022-07-14 Concrete placement auxiliary device

Publications (1)

Publication Number Publication Date
CN217711782U true CN217711782U (en) 2022-11-01

Family

ID=83779089

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221812938.XU Active CN217711782U (en) 2022-07-14 2022-07-14 Concrete placement auxiliary device

Country Status (1)

Country Link
CN (1) CN217711782U (en)

Similar Documents

Publication Publication Date Title
CN210885122U (en) Lifting device for pipeline installation
CN217106038U (en) Scaffold for building construction
CN217711782U (en) Concrete placement auxiliary device
CN206605172U (en) A kind of steel pipe butt welding of Elements of Space Grid Truss is with adjustable removable apparatus for correcting
CN111502334A (en) Adjustable steel structure supporting device for concrete supporting beam and construction method
CN109537623B (en) Pipe gallery installation method
CN207405978U (en) A kind of plastic building template
CN220395149U (en) Handling device of movable operation platform
CN219565428U (en) Efficient and convenient circular pipe pier device
CN216743167U (en) Bottom support device for pipeline engineering construction
CN212924291U (en) Forklift type electromechanical engineering pipeline installation lifting device
CN212027140U (en) Steel column bottom grouting device
CN217028139U (en) House building construction is with pouring auxiliary device
CN218145568U (en) Pipe fitting installation lifting devices
CN220320507U (en) Pipe jacking construction device for gas pipeline
CN213196341U (en) Adjustable support device for welding steel structure
CN216690456U (en) Building construction faces limit protection frame fixing device
CN217400805U (en) Operation ladder for communication pipeline construction
CN208977931U (en) A kind of fixed device of high density polyethylene (HDPE) bellows production
CN214240935U (en) Civil engineering construction is pipe fitting temporary stand for place
CN213648163U (en) Auxiliary pipe cutting device for large-diameter reinforced concrete pipe
CN218612421U (en) Adjustable portable pipeline is to mouthful device
CN216340984U (en) Building engineering construction template device
CN217356103U (en) Spiral winding pipeline prosthetic devices
CN214687859U (en) Tractor for plastic pipes

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant