CN217670099U - Concrete pipe pile filling mould - Google Patents

Concrete pipe pile filling mould Download PDF

Info

Publication number
CN217670099U
CN217670099U CN202220197154.4U CN202220197154U CN217670099U CN 217670099 U CN217670099 U CN 217670099U CN 202220197154 U CN202220197154 U CN 202220197154U CN 217670099 U CN217670099 U CN 217670099U
Authority
CN
China
Prior art keywords
mould
concrete
wall
mold
pipe pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220197154.4U
Other languages
Chinese (zh)
Inventor
张学宏
廖胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yangjiang Hengji Building Material Co ltd
Original Assignee
Yangjiang Hengji Building Material Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yangjiang Hengji Building Material Co ltd filed Critical Yangjiang Hengji Building Material Co ltd
Priority to CN202220197154.4U priority Critical patent/CN217670099U/en
Application granted granted Critical
Publication of CN217670099U publication Critical patent/CN217670099U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses a concrete pipe pile filling mould, this tubular pile filling mould aim at solving prior art's concrete pipe pile filling mould, are difficult to realize carrying out the rapid heating to the interior concrete of mould usually to be difficult to realize the technical problem of the quick drawing of patterns of concrete pipe pile. The tubular pile perfusion mold comprises a support body, a lower mold fixedly arranged at the upper end of the support body and an upper mold movably arranged at the upper end of the lower mold; go up mould upper end fixed mounting has evenly distributed's heating box, it has the filling tube to go up mould upper end fixed mounting. This tubular pile fills mould utilizes a plurality of heating wires can realize heating last mould and bed die to can heat the concrete in the mould, open the fourth heating wire and can realize the rapid heating to concrete inside, open the cylinder and make ejector pad upward movement can take out the concrete tubular column of pouring completion, can realize the quick drawing of patterns of concrete tubular column.

Description

Concrete pipe pile filling mould
Technical Field
The utility model belongs to the technical field of concrete pipe pile production, concretely relates to concrete pipe pile filling die.
Background
Concrete pipe pile commonly used in the life is the concrete prefab nowadays, carries out batch production by the mill mostly, at the in-process of concrete pipe pile production, will use the mould, and the shaping of the concrete pipe pile of being convenient for, most adopt to the mode production of pouring concrete in the mould, but present concrete pipe pile pours the mould, is difficult to realize carrying out rapid heating to concrete in the mould usually to be difficult to realize concrete pipe pile's quick drawing of patterns.
At present, the utility model patent of patent No. CN202020320843.0 discloses a concrete pipe pile is with filling mould, including die base, lower bolster, cope match-plate pattern and guide cylinder, the middle part top of die base is provided with the support column, and the top of the left and right sides of die base has all seted up the guide slot, the top of support column is connected with puts the board, and has placed the lower bolster above putting the board, the top of lower bolster is provided with the cope match-plate pattern, and both ends all are provided with sealed lid around lower bolster and the cope match-plate pattern, the inside of sealed lid is provided with the guide cylinder, but present concrete pipe pile filling mould is difficult to realize carrying out rapid heating to concrete in the mould usually to be difficult to realize the quick drawing of patterns of concrete pipe pile.
Therefore, to the above-mentioned present concrete tubular pile perfusion mold, it is usually difficult to realize heating the concrete in the mold fast, and to be difficult to realize the problem of the quick drawing of patterns of concrete tubular pile, it needs to be solved urgently to realize that the concrete tubular pile perfusion mold can realize heating the concrete in the mold fast, can realize the ability of the quick drawing of patterns of concrete tubular pile.
SUMMERY OF THE UTILITY MODEL
(1) Technical problem to be solved
The utility model aims to prior art not enough, the utility model provides a concrete pipe pile filling mould, this tubular pile filling mould aim at solving current concrete pipe pile filling mould, are difficult to realize carrying out the rapid heating to concrete in the mould usually to be difficult to realize concrete pipe pile's the technical problem of the quick drawing of patterns.
(2) Technical scheme
In order to solve the technical problem, the utility model provides a concrete pipe pile pouring mould, which comprises a support body, a lower mould fixedly arranged at the upper end of the support body and an upper mould movably arranged at the upper end of the lower mould; go up mould upper end fixed mounting and have evenly distributed's heating box, it has the injection tube that is used for pouring into the concrete to go up mould upper end fixed mounting, it has first mounting disc to go up mould front end inner wall threaded connection, it has the second mounting disc to go up mould rear end inner wall threaded connection, supporter lower extreme inner wall fixed mounting has the cylinder, the upper end fixed mounting of the telescopic link of cylinder has the ejector pad, first cell body has been seted up in lower mould lower extreme and the lower extreme inner wall run through, ejector pad and first cell body looks adaptation, the wall layer of bed die is hollow structure, fixed mounting has the second fixing base in the wall layer of bed die, the fixed second heating wire that is used for heating the bed die that is provided with on the second fixing base, second mounting disc front end activity is provided with the installation section of thick bamboo.
When the tubular pile pouring mold is used, the bottom plate is placed on the inclined plane with a certain inclination, the upper mold is placed at the upper end of the lower mold, the outer wall of the second threaded column is installed on the installation cylinder in a threaded mode, the reinforcing cage is placed on the outer wall of the installation cylinder, the second installation disc is installed on the inner wall of the rear end of the upper mold and the inner wall of the rear end of the lower mold in a threaded mode, concrete is placed into the mold from the inlet of the front end of the upper mold and the inlet of the front end of the lower mold, meanwhile, the concrete is injected into the upper mold and the inner portion of the lower mold through the injection pipe, then the first threaded column is installed on the inner wall of the front end of the installation cylinder in a threaded mode, the first heating wire, the second heating wire, the third heating wire and the fourth heating wire are started, the concrete can be rapidly heated, after the concrete is solidified for a certain time, the first installation disc and the second installation disc are taken down, the upper mold is lifted by the aid of a crane through the lifting ring, the cylinder is started, the pushing block moves upwards, and the concrete tubular pile can be taken out, and rapid demolding of the concrete tubular pile can be achieved.
Preferably, the bottom plate is fixedly mounted at the lower end of the lower die, first fixing plates are fixedly mounted at the left end and the right end of the lower die respectively, second fixing plates are fixedly mounted at the left end and the right end of the upper die respectively, limiting columns are fixedly mounted at the lower ends of the first fixing plates, through holes which are uniformly distributed are formed in the upper end and the lower end of the lower die in a penetrating mode, and the through holes are matched with the limiting columns.
Preferably, go up mould upper end fixed mounting has the rings of symmetry, heating box inner wall fixed mounting has first fixing base, fixed mounting has first heating wire on the first fixing base. The first electric heating wire is turned on to heat the upper die, so that the concrete in the upper die can be heated.
Preferably, the wall layer of the upper mold is of a hollow structure, a third fixing seat is fixedly mounted in the wall layer of the upper mold, a third heating wire is fixedly mounted on the third fixing seat, a fixing pipe is fixedly mounted at the upper end of the upper mold and in a penetrating manner with the inner wall of the upper end, and the upper end of the fixing pipe is connected with the lower end of the injection pipe. The upper mold can be heated by opening the third heating wire, and concrete can be added into the upper mold and the lower mold through the injection pipe and the fixing pipe.
Preferably, a first fixing column is fixedly mounted at the front end of the first mounting disc, a first threaded column is fixedly mounted at the rear end of the first mounting disc, and the first threaded column is mounted on the inner wall of the front end of the mounting cylinder in a threaded manner. Install first screw thread post screw thread and can realize the quick installation of first mounting disc at the front end inner wall of an installation section of thick bamboo.
Preferably, a second fixing column is fixedly mounted at the rear end of the second mounting disc, a second threaded column is fixedly mounted at the front end of the second mounting disc, and the second threaded column is mounted on the inner wall of the rear end of the mounting cylinder in a threaded manner. And the second threaded column is installed on the inner wall of the rear end of the installation cylinder in a threaded manner, so that the second installation disc can be installed quickly.
Preferably, a fourth fixing seat is fixedly mounted on the inner wall of the mounting cylinder, and a fourth heating wire is fixedly mounted on the fourth fixing seat. The installation cylinder can be heated by opening the fourth heating wire, so that the interior of the concrete can be heated.
(3) Advantageous effects
Compared with the prior art, the beneficial effects of the utility model reside in that: the utility model discloses an utilize first heating wire, second heating wire and third heating wire can realize heating last mould and bed die to can heat the concrete in the mould, open the fourth heating wire and can realize the rapid heating to concrete inside, thereby improve the heating effect to the concrete, open the cylinder and make the ejector pad upward movement can take out the concrete tubular column of pouring the completion, can realize the quick drawing of patterns of concrete tubular column.
Drawings
Fig. 1 is a schematic perspective view of a concrete embodiment of the tubular pile pouring mold of the present invention;
fig. 2 is a sectional view of an upper die and a lower die of one embodiment of the tubular pile pouring die of the present invention;
fig. 3 is a schematic view of a three-dimensional split structure of a first mounting plate, a mounting cylinder and a second mounting plate of a concrete embodiment of the tubular pile pouring mold of the present invention;
fig. 4 is a sectional view of an installation cylinder of a concrete embodiment of the tubular pile pouring mold of the utility model.
The labels in the figures are: 1. a support body; 2. a lower die; 3. an upper die; 4. a base plate; 5. a first fixing plate; 6. a second fixing plate; 7. a first mounting plate; 8. a first fixed column; 9. a heating cartridge; 10. a hoisting ring; 11. a second fixed column; 12. an injection pipe; 13. a first fixed seat; 14. a first heating wire; 15. a cylinder; 16. a push block; 17. a first tank body; 18. a second fixed seat; 19. a second heating wire; 20. a third fixed seat; 21. a third heating wire; 22. fixing the tube; 23. a through hole; 24. a limiting column; 25. a second mounting plate; 26. mounting the cylinder; 27. a first threaded post; 28. a second threaded post; 29. a fourth fixed seat; 30. a fourth heating wire.
Detailed Description
The concrete pipe pile pouring mold in the embodiment is characterized in that a schematic three-dimensional structure diagram is shown in fig. 1, a sectional view of an upper mold 3 and a lower mold 2 is shown in fig. 2, and the pipe pile pouring mold comprises a support body 1, the lower mold 2 fixedly arranged at the upper end of the support body 1 and the upper mold 3 movably arranged at the upper end of the lower mold 2; go up 3 upper ends fixed mounting of mould 3 and have evenly distributed's heating box 9, it has injection pipe 12 that is used for pouring into the concrete to go up 3 upper ends fixed mounting of mould, it has first mounting disc 7 to go up 3 front end inner wall threaded connection of mould, it has second mounting disc 25 to go up 3 rear end inner wall threaded connection of mould, 1 lower extreme inner wall fixed mounting of supporter has cylinder 15, the upper end fixed mounting of the telescopic link of cylinder 15 has ejector pad 16, 2 lower extremes of bed die and lower extreme inner wall run through and have seted up first cell body 17, ejector pad 16 and 17 looks adaptations of first cell body, the wall layer of bed die 2 is hollow structure, fixed mounting has second fixing base 18 in the wall layer of bed die 2, the fixed second heating wire 19 that is used for heating bed die 2 that is provided with on the second fixing base 18, second mounting disc 25 front end activity is provided with a mounting cylinder 26.
For the present embodiment, the push block 16 is made of steel.
In order to realize the quick heating of the concrete in the lower die 2 and the upper die 3, a bottom plate 4 is fixedly mounted at the lower end of the lower die 2, a first fixing plate 5 is fixedly mounted at the left end and the right end of the lower die 2, a second fixing plate 6 is fixedly mounted at the left end and the right end of the upper die 3, a limiting column 24 is fixedly mounted at the lower end of the first fixing plate 5, through holes 23 which are uniformly distributed are formed in the upper end and the lower end of the lower die 2 in a penetrating manner, symmetrical hanging rings 10 are fixedly mounted at the upper end of the upper die 3, a first fixing seat 13 is fixedly mounted on the inner wall of a heating box 9, a first heating wire 14 is fixedly mounted on the first fixing seat 13, the wall layer of the upper die 3 is of a hollow structure, a third fixing seat 20 is fixedly mounted in the wall layer of the upper die 3, a third heating wire 21 is fixedly mounted on the third fixing seat 20, a fixing pipe 22 is fixedly mounted at the upper end and the upper end of the upper fixing pipe 22 in a penetrating manner, and the lower end of the fixing pipe 12 are connected. The lower mold 2 and the upper mold 3 can be heated by turning on the first heating wire 14, the second heating wire 19 and the third heating wire 21, thereby heating the concrete in the mold.
In order to realize the quick seal to the concrete, first mounting disc 7 front end fixed mounting has first fixed column 8, first mounting disc 7 rear end fixed mounting has first screw thread post 27, first screw thread post 27 threaded mounting is in the front end inner wall of an installation section of thick bamboo 26, second mounting disc 25 rear end fixed mounting has second fixed column 11, second mounting disc 25 front end fixed mounting has second screw thread post 28, second screw thread post 28 threaded mounting is in the rear end inner wall of an installation section of thick bamboo 26. The first threaded column 27 is arranged on the inner wall of the front end of the installation cylinder 26, and the second threaded column 28 is arranged on the inner wall of the rear end of the installation cylinder 26, so that the concrete can be quickly sealed.
In order to improve the heating effect on the concrete, a fourth fixing seat 29 is fixedly installed on the inner wall of the installation cylinder 26, and a fourth heating wire 30 is fixedly installed on the fourth fixing seat 29. The fourth heating wire 30 is turned on to heat the installation cylinder 26, so that the concrete can be heated from the inside of the concrete, thereby improving the heating effect on the concrete.
The schematic three-dimensional split structure of the first mounting plate 7, the mounting cylinder 26 and the second mounting plate 25 of the pipe pile pouring mold is shown in fig. 3, and the cross-sectional view of the mounting cylinder 26 is shown in fig. 4.
When the pipe pile pouring mold of the technical scheme is used, the bottom plate 4 is placed on an inclined plane with a certain inclination, the upper mold 3 is placed at the upper end of the lower mold 2, the limiting column 24 is matched with the through hole 23, the outer wall of the second threaded column 28 is installed on the installation cylinder 26 in a threaded manner, the reinforcing cage is placed on the outer wall of the installation cylinder 26, the second installation disc 25 is installed on the inner wall of the rear end of the upper mold 3 and the inner wall of the rear end of the lower mold 2 in a threaded manner, concrete is placed into the mold from the inlet of the front end of the upper mold 3 and the front end of the lower mold 2, meanwhile, the concrete is injected into the upper mold 3 and the inner wall of the lower mold 2 through the injection pipe 12, then the first threaded column 27 is installed on the inner wall of the front end of the installation cylinder 26 in a threaded manner, the first heating wire 14, the second heating wire 19, the third heating wire 21 and the fourth heating wire 30 are started, so that the concrete can be rapidly heated, after the concrete is solidified for a certain time, the first installation disc 7 and the second installation disc 25 are taken down, the upper mold 3 is lifted by the lifting ring 10, the cylinder 15 is started so that the pushing block 16 moves upwards, and the pipe pile can be rapidly taken out of the poured concrete pipe pile.

Claims (7)

1. A concrete pipe pile pouring mould comprises a supporting body, a lower mould fixedly arranged at the upper end of the supporting body and an upper mould movably arranged at the upper end of the lower mould; its characterized in that, last mould upper end fixed mounting has evenly distributed's heating box, it has the injection tube that is used for pouring into the concrete to go up mould upper end fixed mounting, it has first mounting disc to go up mould front end inner wall threaded connection, it has the second mounting disc to go up mould rear end inner wall threaded connection, supporter lower extreme inner wall fixed mounting has the cylinder, the upper end fixed mounting of the telescopic link of cylinder has the ejector pad, first cell body has been seted up in lower mould lower extreme and the lower extreme inner wall run through, ejector pad and first cell body looks adaptation, the wall of bed die is hollow structure, fixed mounting has the second fixing base in the wall of bed die, the fixed second heating wire that is used for heating the bed die that is provided with on the second fixing base, second mounting disc front end activity is provided with the installation section of thick bamboo.
2. The concrete pipe pile pouring mold according to claim 1, wherein a bottom plate is fixedly mounted at the lower end of the lower mold, first fixing plates are fixedly mounted at the left end and the right end of the lower mold, second fixing plates are fixedly mounted at the left end and the right end of the upper mold, limiting columns are fixedly mounted at the lower end of the first fixing plates, through holes are uniformly distributed in the upper end and the lower end of the lower mold, and the through holes are matched with the limiting columns.
3. The concrete pipe pile pouring mold according to claim 1, wherein symmetrical hanging rings are fixedly installed at the upper end of the upper mold, a first fixing seat is fixedly installed on the inner wall of the heating box, and a first heating wire is fixedly installed on the first fixing seat.
4. The concrete pipe pile pouring mold according to claim 1, wherein the wall layer of the upper mold is a hollow structure, a third fixing seat is fixedly installed in the wall layer of the upper mold, a third heating wire is fixedly installed on the third fixing seat, a fixing pipe is fixedly installed on the upper end of the upper mold and the inner wall of the upper end in a penetrating manner, and the upper end of the fixing pipe is connected with the lower end of the injection pipe.
5. The concrete pipe pile pouring mold according to claim 1, wherein a first fixing column is fixedly mounted at the front end of the first mounting plate, a first threaded column is fixedly mounted at the rear end of the first mounting plate, and the first threaded column is threadedly mounted on the inner wall of the front end of the mounting cylinder.
6. The concrete pipe pile pouring mold according to claim 1, wherein a second fixing column is fixedly mounted at the rear end of the second mounting plate, a second threaded column is fixedly mounted at the front end of the second mounting plate, and the second threaded column is threadedly mounted on the inner wall of the rear end of the mounting cylinder.
7. The concrete pipe pile pouring mold according to claim 1, wherein a fourth fixing seat is fixedly installed on the inner wall of the installation cylinder, and a fourth heating wire is fixedly installed on the fourth fixing seat.
CN202220197154.4U 2022-01-24 2022-01-24 Concrete pipe pile filling mould Active CN217670099U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220197154.4U CN217670099U (en) 2022-01-24 2022-01-24 Concrete pipe pile filling mould

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220197154.4U CN217670099U (en) 2022-01-24 2022-01-24 Concrete pipe pile filling mould

Publications (1)

Publication Number Publication Date
CN217670099U true CN217670099U (en) 2022-10-28

Family

ID=83729899

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220197154.4U Active CN217670099U (en) 2022-01-24 2022-01-24 Concrete pipe pile filling mould

Country Status (1)

Country Link
CN (1) CN217670099U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114043604A (en) * 2021-12-07 2022-02-15 衡阳市凯晋锋机械制造有限公司 High-strength special-shaped steel die and pouring method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114043604A (en) * 2021-12-07 2022-02-15 衡阳市凯晋锋机械制造有限公司 High-strength special-shaped steel die and pouring method thereof

Similar Documents

Publication Publication Date Title
CN217670099U (en) Concrete pipe pile filling mould
CN108890872A (en) A kind of precast inspection well mold and its technique for making inspection shaft
CN218365535U (en) Building cement pipe pouring device
CN107471413A (en) Large-scale side contains internal model auto zoom device
CN2923108Y (en) Core ejection mechanism of core injector
CN213648530U (en) Cell-phone shell processing is with injection mold who has automatic demoulding function
CN211923568U (en) Pier stud reinforcement mould
CN216634791U (en) Composite sliding plate brick integrated forming die
CN216801590U (en) Frameless sand pouring basin
CN201195342Y (en) Hollow block mould
CN215164807U (en) Template mounting structure for steel pipe arch rib outer concrete-wrapped hanging basket construction
CN203470843U (en) Hydraulic lifting pattern stripping machine
CN212822545U (en) Automatic molding machine of drawer type is pressed from top to bottom
CN202683968U (en) Large-size slag pot one-step molding die
CN213257024U (en) Forming die for filter end cover
CN201140429Y (en) Die body apparatus of anode carbon block shaping apparatus
CN215660960U (en) Light high-strength gypsum block forming machine
CN214026783U (en) AI wisdom chest mould forming die
CN205364166U (en) Composite wall panel moulding by casting mould platform
CN216230500U (en) Mould with direction function
CN216297904U (en) Sand mold for forming PU seat foaming mold
CN220075002U (en) Combined porous brick mold
CN210850733U (en) Vertical die top die for producing prefabricated parts
CN216065484U (en) Low-pressure casting die utensil
CN215434200U (en) Aerated concrete block production is with mould of being convenient for to come off membrane

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant