CN217602305U - Building engineering site operation safety control rail - Google Patents

Building engineering site operation safety control rail Download PDF

Info

Publication number
CN217602305U
CN217602305U CN202221199878.9U CN202221199878U CN217602305U CN 217602305 U CN217602305 U CN 217602305U CN 202221199878 U CN202221199878 U CN 202221199878U CN 217602305 U CN217602305 U CN 217602305U
Authority
CN
China
Prior art keywords
rigid coupling
base
mount pad
water tank
engineering site
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202221199878.9U
Other languages
Chinese (zh)
Inventor
王安国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202221199878.9U priority Critical patent/CN217602305U/en
Application granted granted Critical
Publication of CN217602305U publication Critical patent/CN217602305U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Emergency Lowering Means (AREA)

Abstract

The utility model discloses a building engineering site operation safety control rail, including two bases, the equal rigid coupling in bottom four corners department of base has the universal wheel, two the base is close to each other one serve respectively the rigid coupling have the mount pad, two even rigid coupling has a plurality of railings between the mount pad, the railing includes slide bar and two links, the link rigid coupling is on the mount pad, and has seted up the spout on the link, slide bar slidable mounting is between two spouts, when this device needs to use, at first removes this device to suitable position, and through the universal wheel, conveniently removes this device, is then under stabilizing mean's effect to further improved the stability that this device placed, thereby fixed two mounting brackets, thereby fixed two mount pads and base, thereby reduced the occupation space of this device, thereby conveniently carry this device.

Description

Building engineering site operation safety control rail
Technical Field
The utility model relates to a site operation safety control rail technical field specifically is a building engineering site operation safety control rail.
Background
The fence is mainly used for protecting and protecting personal safety and equipment and facilities in occasions such as houses, roads, commercial districts, public places, factories, construction sites and the like, is visible everywhere in our lives, and is made of steel materials commonly used, such as: stainless steel, round steel pipe, square steel pipe, etc., and the surface treatment depends on the application place.
However, in the prior art, some safety fences are inconvenient to transport and carry due to large size and incapability of stretching, and the transportation cost and labor force are increased.
Therefore, a safety management fence for construction engineering site construction needs to be designed so as to solve the problems set forth in the foregoing.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a building engineering site operation safety control rail to solve the problem that above-mentioned background art provided.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a building engineering site operation safety control rail, includes two bases, the equal rigid coupling in bottom four corners department of base has the universal wheel, two the base is close to each other one serve respectively the rigid coupling have the mount pad, two even rigid coupling has a plurality of railings between the mount pad, the railing includes slide bar and two links, the link rigid coupling is on the mount pad, and has seted up the spout on the link, slide bar slidable mounting is between two spouts, the spacing groove has been seted up respectively on the inner wall around the spout, the rigid coupling has the stopper that corresponds with the spacing groove on the slide bar, screw hole has been seted up respectively at the both ends of slide bar, the roof both ends of spout respectively threaded connection have the fixing bolt who corresponds with the screw hole, be provided with stabilizing mean on the base, be provided with dust fall mechanism on the mount pad.
Preferably, stabilizing mean includes connecting plate and a plurality of staple, the opening has been seted up on the base, the rigid coupling has the rack that corresponds with the opening on the base, threaded connection has the screw rod on the roof of rack, the screw rod runs through the opening and rotates the installation with the connecting plate, and is a plurality of the even rigid coupling of staple is at the top of connecting plate, the rigid coupling has two gag lever posts on the connecting plate, and gag lever post and rack slidable mounting, the top rigid coupling of screw rod has the disc, the centrifugation end rigid coupling of disc has the crank.
Preferably, dust fall mechanism includes the water tank, the water tank rigid coupling is on the mount pad, and has seted up the screw thread mouth on the roof of water tank, threaded connection has the screw thread lid on the screw thread mouth, the rigid coupling has the water pump on the preceding curb plate of water tank, the inlet tube of water pump extends to in the water tank, and the intercommunication has the hose on the outlet pipe of water pump, the intercommunication has the installation pipe on the hose, the rigid coupling has the shower nozzle on the installation pipe.
Preferably, the front side plate of the water tank is fixedly connected with a mounting frame corresponding to the mounting pipe.
Preferably, the top of the mounting seat is fixedly connected with an illuminating lamp.
Preferably, two fixing frames are fixedly connected to the base at the left end, and a handle is fixedly connected between the two fixing frames.
Compared with the prior art, the beneficial effects of the utility model are that:
(1) When this device needs to be used, at first remove suitable position with this device, and through the universal wheel, conveniently remove this device, then under stabilizing mean's effect, thereby the stability that this device was placed has further been improved, thereby prevent to topple over under the effect of external force, as shown in fig. 1, for the state of having installed, under the effect of a plurality of railings, thereby protection and protection people's safety's effect have been played, simultaneously when the dust of job site is great, through setting up dust fall mechanism, thereby carry out the dust fall to the job site, thereby prevent that the dust is too big, on the one hand influence staff's health, on the other hand has reduced staff's work efficiency, when this device is in the transportation, rotate two fixing bolt that are close to each other, make fixing bolt not on threaded connection to the screw hole, then can make the slide bar slide on the spout, make two bases close to each other, thereby make two mount pads drive the link and be close to each other, when two link contacts each other, two screw holes on the slide bar this moment correspond with two fixing bolt that keep away from each other, rotate two fixing bolt from the screw hole, thereby two mount pads occupy this fixing device and the space, thereby two mount pads take up convenient for this mount, thereby this device to take.
Drawings
Fig. 1 is a sectional view of the present invention;
fig. 2 is a top view of the present invention;
FIG. 3 is a side sectional view of the present invention;
FIG. 4 is a sectional view of the water tank of the present invention;
fig. 5 is a sectional view of the slide rod and the connecting frame of the present invention.
In the figure: 1. a base; 2. placing a rack; 3. a screw; 4. a disc; 5. a crank; 6. a handle; 7. a water tank; 8. a threaded port; 9. a threaded cap; 10. an illuminating lamp; 11. fixing the bolt; 12. a chute; 13. a connecting frame; 14. a slide bar; 15. a mounting base; 16. a connecting plate; 17. fixing nails; 18. an opening; 19. a universal wheel; 20. a limiting rod; 21. a mounting frame; 22. a water pump; 23. a hose; 24. installing a pipe; 25. a spray head; 26. a threaded hole.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-5, the present invention provides a technical solution: a construction site construction safety management fence for building engineering comprises two bases 1, universal wheels 19 are fixedly connected at four corners of the bottom of each base 1, mounting seats 15 are fixedly connected to one ends, close to each other, of the two bases 1 respectively, a plurality of railings are fixedly connected between the two mounting seats 15 uniformly, each railing comprises a sliding rod 14 and two connecting frames 13, each connecting frame 13 is fixedly connected to the corresponding mounting seat 15, each connecting frame 13 is provided with a sliding groove 12, each sliding rod 14 is slidably mounted between the two sliding grooves 12, the front inner wall and the rear inner wall of each sliding groove 12 are respectively provided with a limiting groove, each sliding rod 14 is fixedly connected with a limiting block corresponding to the limiting groove, two ends of each sliding rod 14 are respectively provided with a threaded hole 26, two ends of the top wall of each sliding groove 12 are respectively in threaded connection with a fixing bolt 11 corresponding to the threaded holes 26, a stabilizing mechanism is arranged on each base 1, a dust falling mechanism is arranged on each mounting seat 15, when the device is required to be used, firstly, the device is moved to a proper position, the universal wheels 19 are used for facilitating the movement of the device, then the device is under the action of the stabilizing mechanism, so that the placing stability of the device is further improved, the device is prevented from falling down under the action of external force, as shown in figure 1, in a mounted state, under the action of a plurality of railings, the effects of protecting and protecting the safety of people are achieved, meanwhile, when dust on a construction site is large, the dust is reduced on the construction site by arranging the dust reducing mechanism, so that the excessive dust is prevented, the health of workers is prevented, on one hand, the working efficiency of the workers is reduced, when the device is transported, two fixing bolts 11 which are close to each other are rotated, so that the fixing bolts 11 are not in threaded connection with the threaded holes 26, then, the sliding rods 14 can slide on the sliding grooves 12, and the two bases 1 are close to each other, thereby make two mount pads 15 drive link 13 and be close to each other, when two link 13 contacts each other, two screw holes 26 on the slide bar 14 this moment correspond with two fixing bolt 11 of keeping away from each other, rotate two fixing bolt 11 of keeping away from each other, with fixing bolt 11 threaded connection on screw hole 26 to fix two mounting brackets 21, thereby fix two mount pads 15 and base 1, thereby reduced the occupation space of this device, thereby conveniently carry this device.
Stabilizing mean includes connecting plate 16 and a plurality of staple 17, opening 18 has been seted up on base 1, the rigid coupling has rack 2 corresponding with opening 18 on base 1, threaded connection has screw rod 3 on rack 2's the roof, screw rod 3 runs through opening 18 and rotates the installation with connecting plate 16, the even rigid coupling of a plurality of staple 17 is at the top of connecting plate 16, the rigid coupling has two gag lever post 20 on connecting plate 16, and gag lever post 20 and rack 2 slidable mounting, screw rod 3's top rigid coupling has disc 4, disc 4's centrifugal end rigid coupling has crank 5, after removing suitable position, rotate crank 5, make disc 4 rotate, thereby make screw rod 3 rotate, simultaneously under the effect of gag lever post 20, thereby make connecting plate 16 descend, thereby drive staple 17 and descend, and make staple 17 insert on the soil, under the effect of staple 17, thereby the stability that this device placed has further been improved.
Dust fall mechanism includes water tank 7, 7 rigid couplings of water tank are on mount pad 15, and threaded opening 8 has been seted up on the roof of water tank 7, threaded connection has threaded cover 9 on the threaded opening 8, the rigid coupling has water pump 22 on the preceding curb plate of water tank 7, water pump 22's inlet tube extends to in the water tank 7, and the intercommunication has hose 23 on water pump 22's the outlet pipe, the intercommunication has installation pipe 24 on the hose 23, the rigid coupling has shower nozzle 25 on the installation pipe 24, when the job site has the dust, be equipped with water in the water tank 7, the staff is on hand holding installation pipe 24, start water pump 22 after that, make the water in the water tank 7 enter into on water pump 22's the outlet pipe through water pump 22's inlet tube, finally enter into on hose 23 through water, water enters into installation pipe 24 after that, water sprays out through shower nozzle 25 after that, thereby carry out the dust fall to the job site.
The rigid coupling has the mounting bracket 21 that corresponds with installation pipe 24 on the preceding curb plate of water tank 7, when not using, can place installation pipe 24 on rack 2, and under the effect of shower nozzle 25, has played the effect of spacing installation pipe 24 for more stable being located on rack 2.
The top of the mounting seat 15 is fixedly connected with an illuminating lamp 10 for prompting passersby, and further has a protection effect.
Two fixing frames are fixedly connected to the base 1 at the left end, and a handle 6 is fixedly connected between the two fixing frames, so that the device is further convenient to move.
Those not described in detail in this specification are within the skill of the art.
Although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments or portions thereof without departing from the spirit and scope of the invention.

Claims (6)

1. The utility model provides a building engineering site operation safety control rail which characterized in that: including two bases (1), the equal rigid coupling in bottom four corners department of base (1) has universal wheel (19), two base (1) one end that is close to each other is served rigid coupling respectively and is had mount pad (15), two even rigid coupling has a plurality of railing between mount pad (15), the railing includes slide bar (14) and two link (13), link (13) rigid coupling is on mount pad (15), and has seted up spout (12) on link (13), slide bar (14) slidable mounting is between two spout (12), the spacing groove has been seted up on the front and back inner wall of spout (12) respectively, the rigid coupling has the stopper that corresponds with the spacing groove on slide bar (14), threaded hole (26) have been seted up respectively at the both ends of slide bar (14), the roof both ends of spout (12) threaded connection have fixing bolt (11) that correspond with threaded hole (26) respectively, be provided with stabilizing mean on base (1), be provided with dust fall mechanism on mount pad (15).
2. The construction engineering site construction safety management fence of claim 1, wherein: stabilizing mean includes connecting plate (16) and a plurality of staple (17), opening (18) have been seted up on base (1), the rigid coupling has rack (2) that corresponds with opening (18) on base (1), threaded connection has screw rod (3) on the roof of rack (2), screw rod (3) run through opening (18) and rotate the installation with connecting plate (16), and is a plurality of the even rigid coupling of staple (17) is at the top of connecting plate (16), the rigid coupling has two gag lever posts (20) on connecting plate (16), and gag lever post (20) and rack (2) slidable mounting, the top rigid coupling of screw rod (3) has disc (4), the centrifugation end rigid coupling of disc (4) has crank (5).
3. The construction engineering site construction safety management fence of claim 1, wherein: dust fall mechanism includes water tank (7), water tank (7) rigid coupling is on mount pad (15), and has seted up screw thread mouth (8) on the roof of water tank (7), threaded connection has screw cap (9) on screw thread mouth (8), the rigid coupling has water pump (22) on the preceding curb plate of water tank (7), the inlet tube of water pump (22) extends to in water tank (7), and the intercommunication has hose (23) on the outlet pipe of water pump (22), the intercommunication has installation pipe (24) on hose (23), the rigid coupling has shower nozzle (25) on installation pipe (24).
4. The construction engineering site construction safety management fence of claim 3, wherein: and a mounting frame (21) corresponding to the mounting pipe (24) is fixedly connected to the front side plate of the water tank (7).
5. The construction engineering site construction safety management fence of claim 1, wherein: the top of the mounting seat (15) is fixedly connected with an illuminating lamp (10).
6. The construction engineering site construction safety management fence of claim 1, wherein: two fixing frames are fixedly connected to the base (1) at the left end, and a handle (6) is fixedly connected between the two fixing frames.
CN202221199878.9U 2022-05-19 2022-05-19 Building engineering site operation safety control rail Expired - Fee Related CN217602305U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221199878.9U CN217602305U (en) 2022-05-19 2022-05-19 Building engineering site operation safety control rail

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221199878.9U CN217602305U (en) 2022-05-19 2022-05-19 Building engineering site operation safety control rail

Publications (1)

Publication Number Publication Date
CN217602305U true CN217602305U (en) 2022-10-18

Family

ID=83569289

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221199878.9U Expired - Fee Related CN217602305U (en) 2022-05-19 2022-05-19 Building engineering site operation safety control rail

Country Status (1)

Country Link
CN (1) CN217602305U (en)

Similar Documents

Publication Publication Date Title
CN210636774U (en) Scaffold for building engineering
CN217602305U (en) Building engineering site operation safety control rail
CN113374340A (en) Metal building encloses fender
KR20090118786A (en) Lift and rotational of multipurpose big pole
CN213837627U (en) Construction platform convenient to remove
CN214169856U (en) Safety platform for building scaffold
CN214246528U (en) Scaffold for building construction
CN211174173U (en) Caving coal face end support with pedestrian bridge
CN113697999A (en) Water treatment facilities with disinfection function
CN210003009U (en) construction adjustable rail guard is built in room
CN214885752U (en) A protection construction platform for high-rise building
CN215368356U (en) Fire alarm convenient to install at guardrail
CN206071106U (en) Dismounting Combined multifunctional energy-conservation tea booth
CN112978633A (en) Self-service lifting device for entering and exiting high-rise water tank
CN217054436U (en) Green construction protective structure
CN214659374U (en) Garden guardrail
CN214596599U (en) Public health disinfection sprinkler
CN213062843U (en) Safe scaffold
US6082493A (en) Method and apparatus for suspending worker's scaffolds over the sides of buildings
CN215858957U (en) Combined mounting rack for building intellectualization
CN215167909U (en) Construction equipment scaffold
CN219808680U (en) Split-level balcony section steel support frame
CN211836927U (en) Building site dust collector
CN213391478U (en) Rail guard is used in municipal garden construction
CN214786201U (en) A face limit protector that is used for oblique roofing eaves mouth of encorbelmenting

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20221018

CF01 Termination of patent right due to non-payment of annual fee