CN217589996U CN202220803057.5U CN202220803057U CN217589996U CN 217589996 U CN217589996 U CN 217589996U CN 202220803057 U CN202220803057 U CN 202220803057U CN 217589996 U CN217589996 U CN 217589996U
Authority
CN
China
Prior art keywords
sliding block
transmission line
bevel gear
tool
power transmission
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220803057.5U
Other languages
Chinese (zh)
Inventor
王莹
吴鑫
沙炳衡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202220803057.5U priority Critical patent/CN217589996U/en
Application granted granted Critical
Publication of CN217589996U publication Critical patent/CN217589996U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Transmission Devices (AREA)

Abstract

The utility model provides a pay off instrument that transmission line erect belongs to transmission line and erects technical field. The cable fixing and erecting device comprises a first sliding block and a second sliding block which are in sliding connection with a telegraph pole and are symmetrically arranged, wherein an adjusting mechanism and a fixing mechanism are arranged on the first sliding block and the second sliding block in a matched mode, and a cable fixing and erecting device is arranged on one side, away from each other, of the first sliding block and the second sliding block. The utility model discloses convenient to use, easy operation, the people of operation just can operate through ground, and adjusting device is holistic from top to bottom, can be better carry out the unwrapping wire, the injured risk of the workman that significantly reduces.

Description

Pay-off tool for erecting power transmission line
Technical Field
The utility model provides a pay off instrument that transmission line erect belongs to transmission line and erects technical field.
Background
Along with the continuous construction of new capital construction of country, almost all places have used electricity, and the electric wire needs to be used in the transmission of electricity, and the work that has certain challenge then is put up to the electric wire, has very big influence to people's life safety, and needs adjust and maintain the electric wire at the in-process of setting up of electric wire, and direct contact electric wire is very dangerous, needs to design a device that can avoid direct contact.
SUMMERY OF THE UTILITY MODEL
The utility model discloses a solve above-mentioned problem, the pay off instrument that the transmission line erect that provides. In order to solve the problems, the provided technical scheme is as follows: a pay-off tool for erecting a power transmission line comprises a first sliding block and a second sliding block, wherein the first sliding block and the second sliding block are in sliding connection with a telegraph pole and are symmetrically arranged, an adjusting mechanism and a fixing mechanism are arranged on the first sliding block and the second sliding block in a matched mode, the adjusting mechanism comprises a groove, the groove is located on one side, close to the telegraph pole, of the first sliding block and the second sliding block, a fixing rod is arranged in the groove, a first gear and a pulley are arranged on the fixing rod in the first sliding block, the pulley is in contact with the telegraph pole, a first cavity is formed in the first sliding block, a transmission rod is arranged in the first cavity, a first bevel gear is arranged at the upper end of the transmission rod, a second gear and a second bevel gear are arranged in the first cavity in a rotating mode, the first bevel gear is meshed with the second bevel gear, a chain is arranged between the first gear and the second gear, the fixing mechanism comprises a second cavity symmetrically arranged in the first sliding block and the second sliding block, a third bevel gear is arranged in a rotating mode, a bevel gear is arranged at one end, a fourth bevel gear is arranged at the bottom surface in the third cavity, the bevel gear is arranged at one end, the transmission rod, a slide block extending out of the first sliding block downwards, a polygonal knob is arranged at the lower side of the sliding block, and a knob is arranged at the other side of the sliding block, and a polygonal knob is arranged at the other side, and a knob is arranged at the other side of the sliding block, and a polygonal cable is arranged at the other side, and is arranged at the other side of the slider.
Further, the cable fixing and erecting device comprises supporting plates symmetrically arranged on the first sliding block and the second sliding block, a support is arranged on the opposite surface of each supporting plate, rollers are arranged on the supports, and cables are arranged between the rollers and can provide certain supporting effect for the cables.
Further, the bracket is rotatably connected with the drum.
Furthermore, the supporting plate is provided with a bolt, one end of the bolt extending into the support is provided with a brake disc, the roller can be fixed after adjustment is completed, and the cable on the bottom surface slides.
Furthermore, the polygonal groove is a regular hexagon groove, and the production cost can be reduced due to a common structure on the market.
Furthermore, one side of the first sliding block, which is close to the second sliding block, is provided with a sliding rod, the sliding rod is connected with the second sliding block in an inserting mode, and the connection stability between the first sliding block and the second sliding block can be improved.
Furthermore, the upper ends, close to the telegraph pole, of the first sliding blocks and the second sliding blocks are respectively provided with a roller.
Furthermore, anti-skidding convex points are arranged outside the pulleys to enhance the friction force with the telegraph pole.
The utility model has the advantages that:
the utility model discloses convenient to use, easy operation, the people of operation just can operate through ground, and adjusting device is holistic about, can be better carry out the unwrapping wire, the injured risk of the workman that significantly reduces.
Drawings
Fig. 1 is a schematic structural view of a paying-off tool for erecting a power transmission line of the present invention.
Fig. 2 is a bottom view of the paying out tool for erecting the power transmission line.
Fig. 3 is the utility model relates to a transmission line, bevel gear one and bevel gear two's of unwrapping wire instrument that transmission line erect schematic diagram.
Fig. 4 is a schematic view of the cable fixing and erecting device of the paying-off tool for erecting the power transmission line of the present invention.
Fig. 5 is a schematic diagram of a knob of a pay-off tool for erecting a power transmission line.
As shown in the figure:
1. a first sliding block 2, a second sliding block 3, a groove 4, a fixing rod 5, a first gear 6, a pulley 7, a first cavity 8, a transmission rod 9, a first bevel gear 10, a second gear 11, a second bevel gear 12, a chain 13, a second cavity 14, a double-thread screw rod, 15, a cavity III, 16, a bevel gear III, 17, a bevel gear IV, 18, a knob, 19, a polygonal groove, 20, a support plate, 21, a support, 22, a roller, 23, a cable, 24, a bolt, 25, a brake disc, 26, a sliding rod, 27, a roller, 28 and an anti-skid bump.
Detailed Description
The present invention will be further explained with reference to the accompanying drawings.
According to all the figures:
a pay-off tool for erecting a power transmission line comprises a first sliding block 1 and a second sliding block 2 which are in sliding connection with a telegraph pole and are symmetrically arranged, an adjusting mechanism and a fixing mechanism are arranged on the first sliding block 1 and the second sliding block 2 in a matched mode, the adjusting mechanism comprises a groove 3 which is located on one side, close to the telegraph pole, of the first sliding block 1 and the second sliding block 2, a fixing rod 4 is arranged in the groove 3, a first gear 5 and a second gear 6 are arranged on the fixing rod 4 in the first sliding block 1, the pulley 6 is in contact with the telegraph pole, a first cavity 7 is arranged in the first sliding block 1, a transmission rod 8 is arranged in the first cavity 7, a first bevel gear 9 is arranged at the upper end of the transmission rod 8, a second gear 10 and a second bevel gear 11 are arranged in the first cavity 7 in a rotating mode, the first bevel gear 9 is meshed with the second bevel gear 10, a chain 12 is arranged between the first gear 5 and the second gear 10, the fixing mechanism comprises a second cavity 13 which is symmetrically arranged in the first sliding block 1 and the second sliding block 2, a double-thread screw 14 is arranged between the second cavity 13, three cavities 15 are arranged in the second sliding block 2, a double-thread screw 14 is arranged at one end, a third cavity 16 is arranged at one end, a sliding block 14 extending into the cavity, a polygonal slider 15 is arranged at one end of the slider, a slider 17, a knob 17 is arranged on one side of the slider, a knob 17 extends out of the slider 2, a knob and a knob 17, a knob is arranged on one side of the slider, a knob 17, a knob is arranged on the slider, and a knob 17, and a knob are arranged on the slider 2, and a knob extending out of the slider.
Furthermore, the cable fixing and erecting device comprises a supporting plate 20 symmetrically arranged on the first sliding block 1 and the second sliding block 2, a support 21 is arranged on the opposite surface of the supporting plate 20, a roller 22 is arranged on the support 21, and a cable 23 is arranged between the rollers 22 and can provide a certain supporting effect for the cable 22.
Further, the bracket 21 is rotatably connected to the drum 22.
Furthermore, a bolt 24 is arranged on the support plate 20, a brake disc 25 is arranged at one end of the bolt 24 extending into the support 21, the roller 22 can be fixed after adjustment is completed, and the bottom cable 23 slides.
Furthermore, the polygonal groove 19 is a regular hexagonal groove, and a common structure on the market can reduce the production cost.
Further, a sliding rod 26 is arranged on one side, close to the second sliding block 2, of the first sliding block 1, the sliding rod 26 is connected with the second sliding block 2 in an inserting mode, and therefore the connection stability between the first sliding block 1 and the second sliding block 2 can be improved.
Furthermore, the first sliding block 1 and the second sliding block 2 are provided with rollers 27 near the upper end of the utility pole.
Furthermore, anti-skidding convex points 28 are arranged outside the pulleys 6 to enhance the friction force with the telegraph pole.
The utility model discloses when concrete implementation:
in the early stage, a cable 23 passes through two rollers 22, the rollers 22 are fixed through bolts 24, the cable 23 is fixed, after the fixing is completed, the cable 23 between the telegraph poles does not reach the optimal tight state, and the cable 23 is loosened, namely the cable 23 needs to be in an ideal tight state by adjusting the height difference between a first sliding block 1 and a second sliding block 2, the cable is matched into a polygonal groove 19 on the first sliding block 1 through a special tool, a knob 18 is rotated to drive a transmission rod 8 to rotate, a first bevel gear 9 and a second bevel gear 11 are driven to rotate, a second gear 10 is driven to rotate, a chain 13 is driven to rotate, a first gear 5 is driven to rotate, a pulley 6 is driven to move, pressure is applied through the friction force of the telegraph pole, the cable 23 is adjusted to move up and down, and finally the knob 18 on the second sliding block 2 is rotated to drive a double-thread screw 14 to rotate, the first sliding block 1 and the second sliding block 2 are driven to approach the telegraph poles to clamp the telegraph poles, and the paying-off tasks can be completed.
The present invention and the embodiments thereof have been described above, but the description is not limited thereto, and the embodiment shown in the drawings is only one of the embodiments of the present invention, and the actual structure is not limited thereto. In summary, it should be understood that those skilled in the art should also understand the scope of the present invention without inventively designing the similar structure and embodiments of the present invention without departing from the spirit of the present invention.

Claims (8)

1. The utility model provides a pay off instrument that transmission line erect which characterized in that: the wire pole fixing device comprises a first sliding block and a second sliding block which are in sliding connection with a wire pole and are symmetrically arranged, an adjusting mechanism and a fixing mechanism are arranged on the first sliding block and the second sliding block in a matched mode, the adjusting mechanism comprises a groove which is located on one side, close to the wire pole, of the first sliding block and the second sliding block, a fixing rod is arranged in the groove, a first gear and a pulley are arranged on the fixing rod in the first sliding block, the pulley is in contact with the wire pole, a first cavity is arranged in the first sliding block, a transmission rod is arranged in the first cavity, a first bevel gear is arranged at the upper end of the transmission rod, a second gear and a second bevel gear are arranged in the first cavity in a rotating mode, the first bevel gear is meshed with the second bevel gear, a chain is arranged between the first gear and the second gear, a second double-thread screw rod is arranged between the second cavity, a third bevel gear is arranged at one end, extending into the third cavity, a fourth bevel gear is arranged on the inner bottom surface of the third cavity, the third bevel gear is meshed with the four bevel gear, a knob is arranged at one end, extending out of the first sliding block downwards, a second sliding block is arranged at one side, and a polygonal cable fixing knob is arranged at one side, and a fixing device is arranged at one side, which is far away from the groove.
2. The paying-off tool for power transmission line erection as claimed in claim 1, wherein: the cable fixing and erecting device comprises supporting plates symmetrically arranged on the first sliding block and the second sliding block, a support is arranged on the opposite surface of each supporting plate, a roller is arranged on each support, and a cable is arranged between the rollers.
3. The paying-off tool for erecting the power transmission line according to claim 2, wherein: the bracket is rotatably connected with the roller.
4. The paying-off tool for erecting the power transmission line according to claim 2, wherein: the supporting plate is provided with a bolt, and one end of the bolt extending into the support is provided with a brake disc.
5. The paying-off tool for erecting the power transmission line according to claim 1, wherein: the polygonal groove is a regular hexagon groove.
6. The paying-off tool for erecting the power transmission line according to claim 1, wherein: and a sliding rod is arranged on one side, close to the second sliding block, of the first sliding block and is connected with the second sliding block in an inserting mode.
7. The paying-off tool for power transmission line erection as claimed in claim 1, wherein: and rollers are arranged at the upper ends, close to the telegraph pole, of the first sliding blocks and the second sliding blocks.
8. The paying-off tool for erecting the power transmission line according to claim 1, wherein: antiskid salient points are arranged outside the pulleys.
CN202220803057.5U 2022-04-08 2022-04-08 Pay-off tool for erecting power transmission line Active CN217589996U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220803057.5U CN217589996U (en) 2022-04-08 2022-04-08 Pay-off tool for erecting power transmission line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220803057.5U CN217589996U (en) 2022-04-08 2022-04-08 Pay-off tool for erecting power transmission line

Publications (1)

Publication Number Publication Date
CN217589996U true CN217589996U (en) 2022-10-14

Family

ID=83541079

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220803057.5U Active CN217589996U (en) 2022-04-08 2022-04-08 Pay-off tool for erecting power transmission line

Country Status (1)

Country Link
CN (1) CN217589996U (en)

Similar Documents

Publication Publication Date Title
CN218620225U (en) Electric rotary lifting insulating platform for operation on auxiliary rod
CN113356675B (en) Bearing platform type electric tower installation construction system and installation method
CN217589996U (en) Pay-off tool for erecting power transmission line
CN215291564U (en) Strutting arrangement for construction
CN213171204U (en) Construction equipment hoisting device
CN112623976A (en) Heavy tower crane with transverse supporting and stabilizing equipment
CN217984464U (en) Direction device mechanism for cable laying
CN214740354U (en) Auxiliary adjusting device of cement electric pole
CN212849619U (en) Municipal works cable frame establishes device
CN212456098U (en) Hank mill for electric power engineering suitable for multiple topography
CN211078260U (en) Building is built a wall and is used fragment of brick hoisting device
CN211765612U (en) Handcart for building engineering who facilitates use
CN210703378U (en) Excavator bucket welding set that shifts for excavator
CN220033605U (en) Antiwind electric power construction unwrapping wire ware
CN214590230U (en) Adjustable erection device of cable
CN212535280U (en) Electric power engineering construction is with device of rectifying
CN212648950U (en) Coal mine machine cable machinery moves device certainly
CN220115892U (en) Mounting bracket for communication engineering construction
CN216074983U (en) Construction equipment for water conservancy river course bank protection
CN215681564U (en) Power distribution network overhead line wire drawing device
CN214643459U (en) Pipeline connection fixing device for hydraulic engineering
CN212387603U (en) Hoisting accessory is used in utility tunnel construction
CN216235723U (en) Highway engineering is with construction hoisting accessory
CN217201856U (en) Building engineering material lifting machine
CN214321372U (en) Small low-rotation-speed roller device