CN217583460U - Piping lane multilayer support - Google Patents

Piping lane multilayer support Download PDF

Info

Publication number
CN217583460U
CN217583460U CN202221394681.0U CN202221394681U CN217583460U CN 217583460 U CN217583460 U CN 217583460U CN 202221394681 U CN202221394681 U CN 202221394681U CN 217583460 U CN217583460 U CN 217583460U
Authority
CN
China
Prior art keywords
fixedly connected
support
supporting
piping lane
coupling assembling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221394681.0U
Other languages
Chinese (zh)
Inventor
邢玉书
曹金桥
孙立涛
艾厚宇
孙龙飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Bureau Installation Engineering Co Ltd
Original Assignee
China Construction Second Bureau Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Bureau Installation Engineering Co Ltd filed Critical China Construction Second Bureau Installation Engineering Co Ltd
Priority to CN202221394681.0U priority Critical patent/CN217583460U/en
Application granted granted Critical
Publication of CN217583460U publication Critical patent/CN217583460U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a piping lane multilayer support, including the supporting baseplate, the supporting baseplate is provided with four, four the equal fixedly connected with locating piece in both ends about the supporting baseplate, four the equal fixedly connected with support column in supporting baseplate upper end, four the support column upper end all alternates and is connected with the extension rod, fore-and-aft two the one end that the support column is not relative all alternates and is connected with limit screw, and four limit screw alternate with four extension rods respectively and be connected four the common fixedly connected with supporting component in extension rod upper end, horizontal two equal fixedly connected with gusset plate, two between the gusset plate two fixedly connected with diaphragms, the equidistance is provided with three locating component in supporting component upper end. A piping lane multilayer support, support efficiently, support effectually, stability is high, is fit for the use of pipeline support fixed in-process.

Description

Piping lane multilayer support
Technical Field
The utility model relates to a piping lane support technical field, in particular to piping lane multilayer support.
Background
Pipe corridor, i.e. corridor of pipes. Many pipelines are concentrated together in chemical industry and relevant class factory, arrange along device or factory building outward, generally in the air, prop up with the support, form and corridor similar appearance, also have a few piping lane to be located the underground, have following drawback in current piping lane support use at least: 1. the existing pipe gallery support is mostly of a single-layer structure, and a plurality of pipe galleries are not easy to support, so that the supporting process of the pipe gallery support is influenced; 2. current piping lane support poor stability, the installation is dismantled inconveniently, so, we release a new piping lane multilayer support.
SUMMERY OF THE UTILITY MODEL
The utility model discloses a main aim at provides a piping lane multilayer support can effectively solve the problem among the background art.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a piping lane multilayer support, includes supporting baseplate, supporting baseplate is provided with four, four the equal fixedly connected with locating piece in both ends about the supporting baseplate, four the equal fixedly connected with support column in supporting baseplate upper end, four the support column upper end all alternates and is connected with the extension rod, fore-and-aft two the one end that the support column is not relative all alternates and is connected with limit screw, and four limit screw alternate with four extension rods respectively and be connected, four the common fixedly connected with supporting component in extension rod upper end, horizontal two equal fixedly connected with gusset plate, two between the gusset plate two fixedly connected with diaphragms, the supporting component upper end equidistance is provided with three locating component.
Preferably, the supporting component includes coupling assembling, coupling assembling is provided with threely, three alternate between the coupling assembling and be connected with two supporting screw, and two supporting screw and coupling assembling fixed connection of lower part, upper portion coupling assembling upper end fixedly connected with roof, lower part coupling assembling and four extension rod fixed connection.
Preferably, coupling assembling includes the extension board, extension board upper end four corners all alternates fixedly connected with bracing piece, four the equal fixedly connected with connecting rod in upper end of the support bar, fore-and-aft two the one end that the bracing piece is not relative all alternates and is connected with the bolt, four the connecting rod all alternates with the coupling assembling at middle part and is connected.
Preferably, locating component includes the fixed plate, fixed plate upper end fixedly connected with fixture block, the fixture block is provided with two, the lower part two connecting screw rod of fixture block upper end left part and the equal fixedly connected with in upper end right part, two three draw-in groove has all been opened to the relative one end of fixture block, and the lower part is three the equal fixedly connected with a plurality of spring block of cell wall, a plurality of in the draw-in groove the equal common fixedly connected with snap ring in spring block upper end, the snap ring is provided with six, the three on upper portion the snap ring respectively with the three draw-in groove fixed connection on upper portion, the equal fixedly connected with brace piece in both ends about the fixed plate, fixed plate and supporting component fixed connection.
Preferably, gaps are reserved between the six clamping blocks and the plurality of supporting rods, and the three fixing plates are located between the two supporting screws.
Preferably, gaps are reserved between the two support screws and the six clamping blocks.
Compared with the prior art, the utility model discloses following beneficial effect has:
1. in the utility model, three connecting components are arranged on the supporting component, every two adjacent connecting components are connected together, and the connecting process of the three connecting components is fixed through two supporting screws, so that the stability is improved, the whole pipe gallery bracket has a multilayer structure, a plurality of pipelines are conveniently supported, and the stability is improved;
2. the utility model discloses in, link together two fixture blocks through two sets of fore-and-aft two connecting screw to fix through the nut respectively, can support the pipeline of joint between three fore-and-aft two snap rings of group, improve stability, and whole locating component installation dismantles conveniently convenient to use.
Drawings
Fig. 1 is a schematic view of the overall structure of a multi-layer support for a pipe gallery according to the present invention;
fig. 2 is a schematic view of the overall structure of the supporting component of the multi-layer support of the pipe rack of the present invention;
fig. 3 is a schematic view of the overall structure of the connecting assembly of the multi-layered support for pipe gallery according to the present invention;
figure 4 is the utility model discloses a positioning assembly overall structure schematic diagram of piping lane multilayer support.
In the figure: 1. a support base plate; 2. positioning blocks; 3. a support pillar; 4. a limit screw; 5. an extension rod; 6. a support assembly; 7. a reinforcing plate; 8. a transverse plate; 9. a positioning assembly; 61. a connecting assembly; 62. a support screw; 63. a top plate; 91. a fixing plate; 92. a clamping block; 93. connecting a screw rod; 94. a card slot; 95. a spring block; 96. a snap ring; 97. supporting a block; 611. a support plate; 612. a support bar; 613. a connecting rod; 614. and (4) a bolt.
Detailed Description
Examples
Referring to fig. 1-4, the present invention provides a technical solution:
the utility model provides a piping lane multilayer support, including supporting baseplate 1, supporting baseplate 1 is provided with four, four supporting baseplate 1 left and right sides equal fixedly connected with locating piece 2 in both ends, four 1 upper end equal fixedly connected with support columns 3 of supporting baseplate, four 3 upper ends of support column all alternate and are connected with extension rod 5, the one end that two fore-and-aft support columns 3 are not relative all alternates and is connected with limit screw 4, and four limit screw 4 alternate with four extension rod 5 respectively and be connected, the common fixedly connected with supporting component 6 in four extension rod 5 upper ends, equal fixedly connected with gusset plate 7 between two horizontal support columns 3, two diaphragms 8 of fixedly connected with between two gusset plates 7, the equidistance is provided with three locating component 9 in supporting component 6 upper end.
In this embodiment, the supporting assembly 6 includes three connecting assemblies 61, two supporting screws 62 are inserted and connected between the three connecting assemblies 61, the two supporting screws 62 are fixedly connected with the lower connecting assembly 61, the upper end of the upper connecting assembly 61 is fixedly connected with a top plate 63, and the lower connecting assembly 61 is fixedly connected with the four extension rods 5; the connecting assembly 61 comprises a support plate 611, four corners of the upper end of the support plate 611 are fixedly connected with support rods 612 in an inserted manner, the upper ends of the four support rods 612 are fixedly connected with connecting rods 613 in an inserted manner, the ends, which are not opposite to the two longitudinal support rods 612, are respectively connected with bolts 614 in an inserted manner, and the four connecting rods 613 are respectively connected with the connecting assembly 61 in the middle in an inserted manner; gaps are reserved between the two supporting screws 62 and the six clamping blocks 92, the positioning assembly 9 is supported by arranging the supporting assembly 6, the three connecting assemblies 61 are connected together through the two supporting screws 62, the stability of the whole supporting assembly 6 in the using process is improved, every two adjacent connecting assemblies 61 are connected together, the multi-layer separation of the whole supporting assembly 6 can be completed, the flexibility is improved, the positioning assembly 9 is supported by arranging the connecting assemblies 61, the four supporting rods 612 on the connecting assemblies 61 can support the upper connecting assemblies 61, the connection between every two connecting assemblies 61 can be enhanced by the four connecting rods 613, the four connecting rods 614 are fixed, and the stability between every two adjacent connecting assemblies 61 is improved;
in this embodiment, the positioning assembly 9 includes a fixing plate 91, a fixture block 92 is fixedly connected to the upper end of the fixing plate 91, two fixture blocks 92 are provided, two connecting screws 93 are fixedly connected to the left portion of the upper end and the right portion of the upper end of the lower fixture block 92, three fixture grooves 94 are provided at opposite ends of the two fixture blocks 92, a plurality of spring blocks 95 are fixedly connected to inner groove walls of the three fixture grooves 94 at the lower portion, snap rings 96 are fixedly connected to the upper ends of the spring blocks 95, six snap rings 96 are provided, the three snap rings 96 at the upper portion are fixedly connected to the three fixture grooves 94 at the upper portion, support blocks 97 are fixedly connected to left and right ends of the fixing plate 91, and the fixing plate 91 is fixedly connected to the support assembly 6; all leave the clearance between six fixture blocks 92 and a plurality of bracing piece 612, three fixed plate 91 all is located between two supporting screw 62, support fixedly through setting up locating component 9 to the pipeline, two fixture blocks 92 carry out the joint to the pipeline jointly, two sets of fore-and-aft connecting screw 93 alternate with the fixture block 92 on upper portion and be connected, and fix through the nut, can strengthen the connection between two fixture blocks 92, and the stability is improved, a plurality of spring block 95 in the three draw-in groove 94 of lower part supports three snap ring 96 respectively, support the buffering to the pipeline between two snap ring 96, and the stability is improved, and the installation of whole locating component 9 is dismantled conveniently.
It should be noted that, the utility model relates to a piping lane multilayer support, in the use, at first fix the position of whole piping lane multilayer support through two locating pieces 2 on four supporting baseplate 1 and every supporting baseplate 1, stability is improved, through adjusting the connection length between four support columns 3 and four extension rods 5, and fix through stop screw 4 respectively, can highly adjust the use of whole piping lane multilayer support, link together three coupling assembling 61 through two supporting screw 62, come to carry out the multilayer partition to supporting component 6, be convenient for support three locating component 9, thereby support a plurality of pipelines, stability is improved, two fixture blocks 92 on three locating component 9 and three two vertical two snap rings 96 of three groups on two fixture blocks 92 support the pipeline jointly, stability is improved, a plurality of spring block 95 on three locating component 9 can support the buffering to the pipeline, stability is improved, two sets of vertical two connecting screw 93 can strengthen the connection between per two fixture blocks 92, and three locating component 9 all installs and dismantles conveniently, whole piping lane supporting efficiency is high, support the effect high, the stability is fit for supporting, the fixed pipeline in-process.
The basic principles and the main features of the invention and the advantages of the invention have been shown and described above. It will be understood by those skilled in the art that the present invention is not limited to the above embodiments, and that the foregoing embodiments and descriptions are provided only to illustrate the principles of the present invention without departing from the spirit and scope of the present invention. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (6)

1. A piping lane multilayer support, includes supporting baseplate (1), its characterized in that: supporting baseplate (1) is provided with four, the equal fixedly connected with locating piece (2) in both ends about four supporting baseplate (1), the equal fixedly connected with support column (3) in four supporting baseplate (1) upper ends, four support column (3) upper ends all alternate and are connected with extension rod (5), the one end that two fore-and-aft support column (3) are not relative all alternates and is connected with stop screw (4), and four stop screw (4) alternate with four extension rod (5) respectively and be connected, the common fixedly connected with supporting component (6) in four extension rod (5) upper ends, equal fixedly connected with gusset plate (7) between two horizontal support column (3), two diaphragms (8) of fixedly connected with between two gusset plate (7), supporting component (6) upper end equidistance is provided with three locating component (9).
2. A piping lane multi-layer rack according to claim 1, characterized in that: supporting component (6) are including coupling assembling (61), and coupling assembling (61) are provided with threely, alternate between three coupling assembling (61) and be connected with two supporting screw (62), and two supporting screw (62) and coupling assembling (61) fixed connection of lower part, coupling assembling (61) upper end fixedly connected with roof (63) on upper portion, coupling assembling (61) and four extension rod (5) fixed connection of lower part.
3. A piping lane multi-layer rack according to claim 2, characterized in that: coupling assembling (61) include extension board (611), and extension board (611) upper end four corners all alternates fixedly connected with bracing piece (612), four equal fixedly connected with connecting rods (613) in bracing piece (612) upper end, and the one end that two fore-and-aft bracing pieces (612) are not relative all alternates and is connected with bolt (614), and four connecting rods (613) all alternate with coupling assembling (61) at middle part and are connected.
4. A pipe rack multi-layer rack as claimed in claim 1 wherein: locating component (9) is including fixed plate (91), fixed plate (91) upper end fixedly connected with fixture block (92), fixture block (92) are provided with two, two connecting screw (93) of fixture block (92) upper end left part and the equal fixedly connected with of upper end right part of lower part, three draw-in groove (94) have all been opened to two fixture block (92) relative one end, the equal fixedly connected with a plurality of spring block (95) of cell wall in three draw-in groove (94) of lower part, equal common fixedly connected with snap ring (96) in a plurality of spring block (95) upper end, snap ring (96) are provided with six, three snap ring (96) on upper portion respectively with three draw-in groove (94) fixed connection on upper portion, two piece (97) of equal fixedly connected with in both ends about fixed plate (91), fixed plate (91) and supporting component (6) fixed connection.
5. A piping lane multi-layer rack as claimed in claim 4, wherein: gaps are reserved between the six clamping blocks (92) and the support rods (612), and the three fixing plates (91) are located between the two support screws (62).
6. A piping lane multi-layer rack according to claim 2, characterized in that: gaps are reserved between the two support screws (62) and the six clamping blocks (92).
CN202221394681.0U 2022-06-07 2022-06-07 Piping lane multilayer support Active CN217583460U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221394681.0U CN217583460U (en) 2022-06-07 2022-06-07 Piping lane multilayer support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221394681.0U CN217583460U (en) 2022-06-07 2022-06-07 Piping lane multilayer support

Publications (1)

Publication Number Publication Date
CN217583460U true CN217583460U (en) 2022-10-14

Family

ID=83528078

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221394681.0U Active CN217583460U (en) 2022-06-07 2022-06-07 Piping lane multilayer support

Country Status (1)

Country Link
CN (1) CN217583460U (en)

Similar Documents

Publication Publication Date Title
CN111946902A (en) Modularization combination assembled antidetonation gallows
CN217583460U (en) Piping lane multilayer support
CN207905205U (en) A kind of prefabricated floor construction and its structural system
CN114134934A (en) Assembled pipe gallery support and installation and construction method thereof
CN209818075U (en) Municipal administration tunnel reinforced structure
CN103255837B (en) A kind of removable modular combination room
CN216109594U (en) Construction engineering place construction is with scaffold frame of encorbelmenting of dismouting operation of being convenient for
CN111042328A (en) Distributed modular anti-side K-support type unit multi-layer frame structure
CN216641526U (en) Building structure design roof beam reinforced structure
CN214368183U (en) Arch piping lane support and arch piping lane
CN210867045U (en) Support frame for cable bridge
CN113463754A (en) Assembled branch type cable support prestressed column suitable for multi-angle connection
CN201588357U (en) Weldless exterior wall structure
CN202706656U (en) Keyhole type insertion tent
CN212897607U (en) Tower type supporting truss
CN219638277U (en) Light building structure
CN211137098U (en) Movable type dismantled and assembled construction steel bar rack
CN212251484U (en) A novel gallows for large pipeline
CN211649279U (en) Anti-seismic hanging bracket
CN219362381U (en) Tube panel module roll-over stand
CN219710388U (en) Subway platform frame beam prefabricated structure
CN110242941B (en) Dysprosium lamp holder capable of being used in turnover mode
CN218597455U (en) Heat-insulating bridge structure of steel frame stone curtain wall
CN220377903U (en) Temporary protection device for roof
CN220790260U (en) Curtain wall structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant