CN221610933U - Electromechanical and decoration integrated finished product support and hanger - Google Patents
Electromechanical and decoration integrated finished product support and hanger Download PDFInfo
- Publication number
- CN221610933U CN221610933U CN202323154499.5U CN202323154499U CN221610933U CN 221610933 U CN221610933 U CN 221610933U CN 202323154499 U CN202323154499 U CN 202323154499U CN 221610933 U CN221610933 U CN 221610933U
- Authority
- CN
- China
- Prior art keywords
- cross arm
- electromechanical
- detachably connected
- short
- concrete structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000005034 decoration Methods 0.000 title claims abstract description 19
- 238000009434 installation Methods 0.000 claims abstract description 71
- 229910000831 Steel Inorganic materials 0.000 claims description 14
- 239000010959 steel Substances 0.000 claims description 14
- 230000003014 reinforcing effect Effects 0.000 claims description 2
- 238000010276 construction Methods 0.000 abstract description 12
- 238000004904 shortening Methods 0.000 abstract description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 9
- XAGFODPZIPBFFR-UHFFFAOYSA-N aluminium Chemical compound [Al] XAGFODPZIPBFFR-UHFFFAOYSA-N 0.000 description 6
- 229910052782 aluminium Inorganic materials 0.000 description 6
- 238000004891 communication Methods 0.000 description 4
- 238000010586 diagram Methods 0.000 description 4
- 239000000463 material Substances 0.000 description 4
- 241000700647 Variola virus Species 0.000 description 2
- 239000004411 aluminium Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 2
- 238000005336 cracking Methods 0.000 description 2
- 238000004378 air conditioning Methods 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 239000012634 fragment Substances 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 238000009413 insulation Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 description 1
- 238000009428 plumbing Methods 0.000 description 1
- 239000000126 substance Substances 0.000 description 1
- 239000000758 substrate Substances 0.000 description 1
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
An electromechanical and decoration integrated finished support and hanger is provided to effectively meet the installation requirements of various electromechanical pipeline equipment and various facilities, thereby greatly shortening the construction period and improving the construction efficiency. The concrete structure comprises a plurality of vertical rods which are arranged in parallel, wherein the upper ends of the vertical rods are detachably connected with the concrete structure through mounting supports; a cross arm is arranged between the adjacent vertical rods, and two ends of the cross arm are detachably connected with the lower ends of the vertical rods through connecting pieces; a cross arm is arranged between the transversely adjacent concrete structure and the upright rod, one end of the cross arm is detachably connected with the concrete structure through a mounting support, and the other end of the cross arm is detachably connected with the lower end of the upright rod through a connecting piece; a first-stage installation space is formed above each cross arm.
Description
Technical Field
The utility model belongs to the technical field of constructional engineering, and particularly relates to an electromechanical and decoration integrated finished product support and hanger.
Background
Currently, in the construction of subway stations, various electromechanical plumbing devices such as: the fire-fighting water pipe, the water supply pipe, the air-conditioning water pipe, the air pipe, the communication bridge and the like are respectively installed without considering the installation requirements of various facilities in later decoration, such as suspended ceiling aluminum ceilings, indication boards, lamps, cameras and the like. When the facilities are installed, the facilities are often required to avoid the electromechanical equipment and are installed and fixed in a top concrete structure, the operation is complex, and the construction and installation time is not easy to save and the working efficiency is improved.
Therefore, how to solve the above-mentioned problems of the prior art is a direction of effort by those skilled in the art.
Disclosure of utility model
The utility model aims to solve the technical problem of providing an electromechanical and decoration integrated finished product support and hanger, so as to effectively meet the installation requirements of various electromechanical pipeline equipment and various facilities, thereby greatly shortening the construction period and improving the construction efficiency.
The technical scheme adopted by the utility model for solving the technical problems is as follows:
The utility model relates to an electromechanical and decoration integrated finished product support and hanger, which is characterized in that: the concrete structure comprises a plurality of vertical rods which are arranged in parallel, wherein the upper ends of the vertical rods are detachably connected with the concrete structure through mounting supports; a cross arm is arranged between the adjacent vertical rods, and two ends of the cross arm are detachably connected with the lower ends of the vertical rods through connecting pieces; a cross arm is arranged between the transversely adjacent concrete structure and the upright rod, one end of the cross arm is detachably connected with the concrete structure through a mounting support, and the other end of the cross arm is detachably connected with the lower end of the upright rod through a connecting piece; a first-stage installation space is formed above each cross arm.
In the one-level installation space, set up the cross arm between two vertical poles, this cross arm both ends form detachable connection through connecting piece and pole setting middle part, longitudinally separate this one-level installation space and form two second grade installation spaces.
In the one-level installation space, set up its upper end and form the short pole setting of dismantling the connection through erection bracing and concrete structure between two pole sets, set up the short cross arm between this short pole setting and adjacent pole setting, the short cross arm both ends form the dismantlement with short pole setting lower extreme, pole setting middle part respectively through the connecting piece and are connected, separate the vertical and horizontal three second grade installation space that forms with this one-level installation space.
The short cross arm is arranged between the short vertical rod and the adjacent vertical rod, two ends of the short cross arm are detachably connected with the middle part of the short vertical rod and the vertical rod respectively through connecting pieces, and two three-level installation spaces are formed by longitudinally separating two secondary installation spaces.
The utility model has the beneficial effects that the structure design is reasonable, the installation requirements of various electromechanical pipeline equipment and various facilities are comprehensively considered, various installation spaces can be flexibly formed, and the construction period can be greatly shortened; can be assembled, disassembled and recycled conveniently, and is beneficial to improving the construction efficiency and saving the construction cost.
Drawings
The specification includes the following nine drawings:
FIG. 1 is a schematic view of a first embodiment of the present utility model;
FIG. 2 is a schematic illustration of the structure of a three-hole connector of the present utility model;
FIG. 3 is a schematic view of the structure of the adjustable base of the present utility model;
FIG. 4 is a schematic view of the structure of the fixing base of the present utility model;
FIG. 5 is a schematic diagram of a second embodiment of the present utility model;
FIG. 6 is a schematic view of a four-hole connector of the present utility model;
FIG. 7 is a state diagram of the utility model for auxiliary installation;
figure 8 is a diagram of the connection of the third cross arm to the keel joint;
Fig. 9 is a diagram of the connection of the third cross arm to the finished ceiling grid.
The component names and corresponding labels are shown: a first cross arm 11, a second cross arm 12, a third cross arm 13, a fourth cross arm 14, a first short cross arm 15, a second short cross arm 16, a third short cross arm 17; a first upright 21, a second upright 22, a third upright 23, a short upright 24; four-hole connectors 31, three-hole connectors 32, screw rods 33, keel connectors 34, hollow hanger rods 35 and channel steel fasteners 36; adjustable base 41, base 411, pedestal 412, unable adjustment base 42, expand the bottom crab-bolt 43, fire control water pipe 50, communication bridge 51, tuber pipe 52, camera 53, sign 54, aluminium smallpox 55, feed pipe 56, air conditioner water pipe 57, fitment furred ceiling fossil fragments 58.
Detailed Description
The present utility model is further described by the following structural drawings and examples.
Referring to fig. 1, the electromechanical and decoration integrated finished product support and hanger comprises a plurality of vertical rods which are arranged in parallel, wherein the upper ends of the vertical rods are detachably connected with a concrete structure through mounting supports; a cross arm is arranged between the adjacent vertical rods, and two ends of the cross arm are detachably connected with the lower ends of the vertical rods through connecting pieces; a cross arm is arranged between the transversely adjacent concrete structure and the upright rod, one end of the cross arm is detachably connected with the concrete structure through a mounting support, and the other end of the cross arm is detachably connected with the lower end of the upright rod through a connecting piece; a first-stage installation space is formed above each cross arm.
Referring to fig. 5 and 7, further, in the primary installation space, a cross arm is disposed between the two upright posts, two ends of the cross arm are detachably connected with the middle part of the upright post through a connecting piece, and the primary installation space is longitudinally separated to form two secondary installation spaces.
Referring to fig. 5 and 7, further, in the primary installation space, a short upright rod is arranged between two upright rods, the upper end of the short upright rod is detachably connected with the concrete structure through an installation support, a short cross arm is arranged between the short upright rod and an adjacent upright rod, two ends of the short cross arm are detachably connected with the lower end of the short upright rod and the middle part of the upright rod respectively through connecting pieces, and the primary installation space is longitudinally and transversely separated to form three secondary installation spaces.
Example 1:
Referring to fig. 1, the electromechanical and decoration integrated finished support and hanger comprises a first vertical rod 21, a second vertical rod 22 and a third vertical rod 23 which are arranged in parallel, wherein the upper ends of the first vertical rod 21, the second vertical rod 22 and the third vertical rod 23 are detachably connected with a concrete structure through mounting supports. Wherein, set up first cross arm 11 between first pole setting 21 and horizontal adjacent concrete structure, the one end of first cross arm 11 forms detachable connection with concrete structure through the erection bracing, and the other end forms detachable connection with first pole setting 21 lower extreme through the connecting piece. A second cross arm 12 is arranged between the first upright rod 21 and the second upright rod 22, and two ends of the second cross arm 12 are detachably connected with the lower ends of the first upright rod 21 and the second upright rod 22 through connecting pieces. A third cross arm 13 is arranged between the second upright 22 and the third upright 23, and the third cross arm 13 is detachably connected with the lower ends of the second upright 22 and the third upright 23 through connecting pieces. A first stage installation space (shown as A, B, C in the figure) is formed above the first, second, and third cross arms 11, 12, 13.
Referring to fig. 3 and 4, the mounting bracket includes an adjustable base 41, a fixed base 42. The fixed base 42 is anchored on the concrete structure through a bottom expanding anchor bolt 43, and the upper end of the upright rod is detachably connected with the fixed base 42 through a bolt. The adjustable base 41 is composed of a base 411 and a base 412 which are hinged through a connecting bolt, the base 411 is anchored on a concrete structure through a bottom expanding anchor bolt 43, the upper end of a vertical rod is detachably connected with the base 412 through a bolt, the base 411 can rotate by taking the connecting bolt as an axle center, the angle adjustment between the base 411 and the base 412 is realized, and the locking is carried out through the connecting bolt after the angle adjustment is completed. The adjustable base 41 is arranged to facilitate the connection and fixation of the first upright 21 and the inclined surface of the concrete structure. Referring to fig. 1, fixed bases 42 are provided at the upper ends of the second and third uprights 22 and 23, and an adjustable base 41 is provided at the upper end of the first upright 21.
In the prior art, the advertising board, the aluminum ceiling, the advertising lamp box and the identification system are all fixed by expansion anchor bolts, but according to the specification of J G160-2017 of mechanical anchor bolts for concrete, the expansion anchor bolts are strictly forbidden to be used as connecting pieces of bearing members in the structure of an earthquake-proof fortification area, in members directly bearing power load and on cracked concrete base materials, so the fixation by the expansion anchor bolts is not in accordance with the specification. The support and hanger can adopt the reverse taper chemical anchor bolts and the bottom expanding mechanical anchor bolts to fixedly mount the facilities, can be applied to non-cracking concrete, cracking concrete and scenes bearing earthquake actions, and can meet the standard requirements.
Referring to fig. 2 and 6, the connecting member includes a four-hole connecting member 31 and a three-hole connecting member 32, the main body of the connecting member is an L-shaped connecting plate, through holes for the installation bolts to pass through are formed in the vertical section and the horizontal section of the L-shaped connecting plate, and reinforcing ribs integrally connected with the vertical section and the horizontal section of the L-shaped connecting plate of the four-hole connecting member 31 are formed in the L-shaped connecting plate.
Referring to fig. 1, the first cross arm 11, the second cross arm 12, and the third cross arm 13 are provided with reserved mounting holes for hanging and mounting a suspended ceiling aluminum ceiling, a sign, a lamp, a camera, and the like. The cross arm adopts a single-spliced groove steel structure, the vertical rod can adopt a double-spliced groove steel structure or a single-spliced groove steel structure, and a fixed channel steel end cover is arranged at the lower end of the vertical rod. In this embodiment, the first cross arm 11, the second cross arm 12, and the third cross arm 13 are of a single-spliced-groove steel structure, the first upright 21 and the second upright 22 are of a double-spliced-groove steel structure, and the third upright 23 is of a single-spliced-groove steel structure.
Referring to fig. 1, in this embodiment, in a first-stage installation space a above a first cross arm 11, a fire-fighting water pipe 50 is installed and fixed on the first cross arm 11 by using a common P-type pipe bundle or/and an insulation pipe bundle, and a screw 33 is matched with a reserved installation hole on the first cross arm 11 to implement hoisting of a camera 53. The first-stage installation space B above the second cross arm 12 is used for installation of the communication bridge 51. The primary installation space C above the third cross arm 13 is used for the installation of the air duct 24. The hollow suspender 35 is adopted to match with the reserved mounting holes on the second cross arm 12 and the third cross arm 13, so that the lifting of the indication board 54 can be realized. Through the cooperation of the keel connecting piece 34 and the reserved mounting holes on the first cross arm 11, the second cross arm 12 and the third cross arm 13, the aluminum ceiling 55 can be hoisted.
Example 2:
Referring to fig. 5 and 7, on the basis of the basic structure of embodiment 1, in the first stage installation space B on the second cross arm 11, a fourth cross arm 14 is disposed between the first upright 21 and the second upright 22, and two ends of the fourth cross arm 14 are detachably connected with the middle parts of the first upright 21 and the second upright 22 through connectors, so that the first stage installation space B is longitudinally divided to form two second stage installation spaces B1 and B2.
Further, in the first-stage installation space C above the third cross arm 13, a short upright 24, the upper end of which is detachably connected with the concrete structure through an installation support, is provided between the second upright 22 and the third upright 23. A first short cross arm 15 is arranged between the short upright 24 and the second upright 22, and two ends of the first short cross arm 15 are detachably connected with the lower end of the short upright 24 and the middle part of the second upright 22 respectively through connecting pieces. A second short cross arm 16 is arranged between the short upright rod 24 and the third upright rod 23, and two ends of the second short cross arm 16 are detachably connected with the lower end of the short upright rod 24 and the middle part of the third upright rod 23 respectively through connecting pieces. The primary installation space C is divided longitudinally and transversely to form three secondary installation spaces (marked with C1, (c2+c3), C4 in fig. 5).
Further, a third short cross arm 17 is arranged between the short upright 24 and the second upright 22, two ends of the short third cross arm 17 are detachably connected with the short upright 24 and the second upright 22 respectively through connecting pieces, and two three-stage installation spaces C2 and C3 are formed by longitudinally separating the two-stage installation spaces (C2+C3).
The first-stage installation space A above the first cross arm 11 is a fire-fighting water pipe installation groove; the second-stage installation space B2 above the fourth cross arm 14 above the first cross arm 11 is a first air pipe installation groove, and the second-stage installation space B2 between the second cross arm 12 and the fourth cross arm 14 is a water supply pipe and an air conditioner water pipe installation groove; the second-stage installation space C2 between the third cross arm 13 and the fourth cross arm 14 is a reserved installation groove, the third-stage installation space C2 between the first short cross arm 15 and the third short cross arm 17 and the third-stage installation space C3 above the third short cross arm 17 are all communication bridge installation grooves, and the second-stage installation space C3 above the second short cross arm 16 is a second air pipe installation groove.
The installation of auxiliary facilities such as the indication board 54, the camera 53, the lamp and the like can be realized through the cooperation of the reserved installation hole on the third cross arm 13, the screw rod 33 and the hollow suspender 35, and the installation of the decoration suspended ceiling keel 58 can be realized through the connection of the screw rod 33 and the channel steel fastener 36 with the third cross arm 13 and the connection of the keel connecting piece 34 at the bottom end of the screw rod 33.
According to the embodiment, the installation requirements of various electromechanical pipeline equipment and various auxiliary facilities are comprehensively considered, so that the construction period is shortened, and the working efficiency is improved.
The utility model carries out corresponding supporting product installation by combining a decoration suspended ceiling and the like in the deepening of a bracket scheme, and the electromechanical and decoration integrated finished product supporting and hanging bracket scheme is to select materials with different requirements and different specifications and has a pattern inspection report provided by a national detection mechanism of the corresponding materials; corresponding stress connecting components are designed for the connection of the bracket and facilities such as decoration and fitment; the electromechanical and decoration integrated finished support and hanger can be conveniently detached in construction, is convenient to assemble, is recycled, reduces loss and loss, can effectively save the investment of personnel, machinery and materials, improves the engineering efficiency and saves the construction cost;
The utility model considers the deepening requirements of the electromechanical pipelines and the decoration and carries out corresponding reasonable arrangement, and reserves the fixed installation point positions of the decoration suspended ceiling on the finished product bracket in advance, and the whole process flow from the end to the end of analysis equipment of the system ensures the cooperativity and the logicality of each link.
The utility model considers the load of the decoration suspended ceiling in advance. The integral bearing capacity is achieved through calculating the structural form of the selected bracket, and the integral load requirements of the electromechanical and decoration are met.
The utility model provides a bill-board, aluminium smallpox, advertising light boxes, identification system, camera etc. pass through connecting elements, its mechanical load passes through the component and gives finished product gallows to act on the cross arm with concentrated force's form, the cross arm passes through the connecting piece and gives the pole setting, pole setting support counter-force passes through the crab-bolt and passes through concrete substrate, calculate through professional mechanics software, select the channel-section steel according to the calculation result, the connecting piece, the model of accessory such as crab-bolt, spring nut, make the scheme have theoretical foundation, satisfy the normative requirement simultaneously, accomplish the whole closed loop of scheme calculation.
The foregoing is provided for the purpose of illustrating the principles of the present utility model and is not intended to limit the utility model to the particular structure and application scope of the utility model shown and described, but is to be accorded the full range of possible modifications and equivalent structures.
Claims (8)
1. An electromechanical and decoration integrated finished support and hanger is characterized in that: the concrete structure comprises a plurality of vertical rods which are arranged in parallel, wherein the upper ends of the vertical rods are detachably connected with the concrete structure through mounting supports; a cross arm is arranged between the adjacent vertical rods, and two ends of the cross arm are detachably connected with the lower ends of the vertical rods through connecting pieces; a cross arm is arranged between the transversely adjacent concrete structure and the upright rod, one end of the cross arm is detachably connected with the concrete structure through a mounting support, and the other end of the cross arm is detachably connected with the lower end of the upright rod through a connecting piece; a first-stage installation space is formed above each cross arm.
2. An electromechanical and finishing integrated finished hanger as claimed in claim 1, wherein: in the one-level installation space, set up the cross arm between two vertical poles, this cross arm both ends form detachable connection through connecting piece and pole setting middle part, longitudinally separate this one-level installation space and form two second grade installation spaces.
3. An electromechanical and finishing integrated finished hanger as claimed in claim 2, wherein: in the one-level installation space, set up its upper end and form the short pole setting of dismantling the connection through erection bracing and concrete structure between two pole sets, set up the short cross arm between this short pole setting and adjacent pole setting, the short cross arm both ends form the dismantlement with short pole setting lower extreme, pole setting middle part respectively through the connecting piece and are connected, separate the vertical and horizontal three second grade installation space that forms with this one-level installation space.
4. An electromechanical and finishing integrated finished hanger as claimed in claim 3, wherein: the short cross arm is arranged between the short vertical rod and the adjacent vertical rod, two ends of the short cross arm are detachably connected with the middle part of the short vertical rod and the vertical rod respectively through connecting pieces, and two three-level installation spaces are formed by longitudinally separating two secondary installation spaces.
5. An electromechanical and finishing integrated finished hanger as claimed in claim 1, wherein: the mounting support comprises an adjustable base (41) and a fixed base (42); the fixed base (42) is anchored on the concrete structure through a bottom expanding anchor bolt (43), and the upper end of the vertical rod is detachably connected with the fixed base (42) through a connecting bolt; the adjustable base (41) is composed of a base (411) and a base body (412) which are hinged, the base (411) is anchored on a concrete structure through a bottom expanding anchor bolt (43), and the upper ends of the vertical rods are detachably connected through the base body (412).
6. An electromechanical and finishing integrated finished hanger as claimed in claim 1, wherein: and a reserved mounting hole is formed in the cross arm.
7. An electromechanical and finishing integrated finished hanger as claimed in claim 1, wherein: the cross arm adopts a single-spliced groove steel structure, the vertical rod adopts a double-spliced groove steel structure or a single-spliced groove steel structure, and the lower end of the vertical rod is provided with a fixed channel steel end cover.
8. An electromechanical and finishing integrated finished hanger as claimed in claim 1, wherein: the connecting piece comprises a four-hole connecting piece (31) and a three-hole connecting piece (32), the main body of the connecting piece is an L-shaped connecting plate, through holes for the installation bolts to pass through are formed in the vertical section and the horizontal section of the L-shaped connecting plate, and reinforcing ribs which are integrally connected with the vertical section and the horizontal section of the L-shaped connecting plate are arranged on the L-shaped connecting plate of the four-hole connecting piece (31).
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202323154499.5U CN221610933U (en) | 2023-11-22 | 2023-11-22 | Electromechanical and decoration integrated finished product support and hanger |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202323154499.5U CN221610933U (en) | 2023-11-22 | 2023-11-22 | Electromechanical and decoration integrated finished product support and hanger |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN221610933U true CN221610933U (en) | 2024-08-27 |
Family
ID=92427238
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202323154499.5U Active CN221610933U (en) | 2023-11-22 | 2023-11-22 | Electromechanical and decoration integrated finished product support and hanger |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN221610933U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117346020A (en) * | 2023-11-22 | 2024-01-05 | 四川迈铁龙科技有限公司 | A kind of mechanical, electrical and decoration integrated finished product support and hanger |
-
2023
- 2023-11-22 CN CN202323154499.5U patent/CN221610933U/en active Active
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117346020A (en) * | 2023-11-22 | 2024-01-05 | 四川迈铁龙科技有限公司 | A kind of mechanical, electrical and decoration integrated finished product support and hanger |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN201763002U (en) | Independent adjustable steel supporting device | |
| CN116163461B (en) | Space structure assembled ultra-large color grain metal plate suspended ceiling and construction method | |
| CN114319682A (en) | Connecting node structure of suspended ceiling conversion layer under truss structure and construction method | |
| CN211523685U (en) | Combined three-dimensional adjusting curtain wall system | |
| CN117346020A (en) | A kind of mechanical, electrical and decoration integrated finished product support and hanger | |
| CN212319506U (en) | Intensive installation structure of rail transit elevated station lighting facility and pipeline | |
| CN212249231U (en) | Adjustable beam slab co-supporting type cantilever tripod construction device | |
| CN105133774A (en) | Reverse support system structure and integrated method of design and installation of composite assembled ceiling | |
| CN221276850U (en) | DOME's steel construction system | |
| CN115961729B (en) | Landscape lighting metal curved plate suspended ceiling structure and construction method thereof | |
| CN219261831U (en) | Steel truss web member structure | |
| CN215888894U (en) | Anti-bearing structure of assembled furred ceiling | |
| CN213143566U (en) | Walkway ceiling conversion layer structure | |
| CN103711320B (en) | A kind of high level builds a house the installation method of room modular metal curtain wallboard unit soon | |
| CN110212843B (en) | Reinforcing device of photovoltaic support template and positioning method thereof | |
| CN220133241U (en) | Suspended ceiling anti-supporting structure | |
| CN218375375U (en) | Whole jacking device of rack suitable for different load requirements | |
| CN215716238U (en) | Fire hose fixing frame for prefabricated steel structure residential building | |
| CN217924340U (en) | Novel suspended ceiling conversion layer system | |
| CN104878866A (en) | Ceiling hanging method and ceiling hanging system for project steel structure | |
| CN220318927U (en) | Integrated furred ceiling antidetonation construction structures | |
| CN212897607U (en) | Tower type supporting truss | |
| CN222822513U (en) | A steel structure column that is easy to install | |
| CN219718172U (en) | Inverter support suitable for angle-relaxation type color steel tile roof | |
| CN212960191U (en) | A support for electromechanical pipeline installation for spatial grid structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant |