CN217557629U CN202221066653.6U CN202221066653U CN217557629U CN 217557629 U CN217557629 U CN 217557629U CN 202221066653 U CN202221066653 U CN 202221066653U CN 217557629 U CN217557629 U CN 217557629U
Authority
CN
China
Prior art keywords
wall
fixed
fixing
fixedly connected
scaffold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202221066653.6U
Other languages
Chinese (zh)
Inventor
吴蕾
王露
房凯
孙钧
高洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin No2 Construction Engineering Co ltd
Original Assignee
Tianjin No2 Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin No2 Construction Engineering Co ltd filed Critical Tianjin No2 Construction Engineering Co ltd
Priority to CN202221066653.6U priority Critical patent/CN217557629U/en
Application granted granted Critical
Publication of CN217557629U publication Critical patent/CN217557629U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Electric Cable Installation (AREA)

Abstract

The utility model relates to a construction technical field specifically is a scaffold frame is wall fixing device even, including the fixing bolt cover, wherein, the fixing bolt cover is used for installing on the structure wall, and is specific, and the inside first fixed orifices that quantity is two that is offered to structure wall, fixing bolt cover fixed connection in first fixed orifices inside, the equal threaded connection in inside of two fixing bolt covers has fixing bolt. This scaffold frame is wall fixing device even, with the scaffold frame pole setting through two U-shaped anchorage bars and fastening nut and mounting plate fixed connection, realize the fixed mounting of scaffold frame pole setting, it is quick convenient, and simultaneously, it is rotatory to drive two rotation columns through twisting two rotor plates, two driven bevel gear of two initiative bevel gear drives rotate, thereby make two transmission shafts rotatory in the inside of two fixed blocks and two fixed plates, and then make the movable plate drive the fixed column and take place to remove, realized the scaffold frame pole setting with the interval modulation of structure wall.

Description

Scaffold frame is wall fixing device even
Technical Field
The application relates to the technical field of building construction, in particular to a scaffold wall connecting fixing device.
Background
Along with the development of building industry, apparatus and safety protection articles for use in the work progress demonstrate the trend of regularization, instrument ization, mainly adopt the scaffold frame to do the construction handling frame in main part construction stage outer wall construction, and even wall spare indicates to be connected scaffold frame body and building major structure, can transmit the component of pulling force and pressure, play very important effect in the work progress.
The form of reserving the hitch point or adopting the pillar when current construction often adopts the structure construction, behind the fixed scaffold, when the discovery scaffold frame has the mounting point to appear inclining, needs readjustment scaffold frame and wall body interval, and then needs the fixed scaffold structure of dismouting, and is very inconvenient, so provides a scaffold frame and links wall fixing device and solve the problem that proposes in the aforesaid.
SUMMERY OF THE UTILITY MODEL
To prior art's not enough, this application provides a scaffold frame links wall fixing device, possesses advantages such as adjustable scaffold frame and wall body interval behind the installation scaffold frame, has solved current scaffold frame and has linked wall spare and wall body installation back, if the discovery slope, needs the problem of dismouting scaffold frame structure.
For realizing above-mentioned simple and convenient fixed firm purpose of installation, this application provides following technical scheme: the utility model provides a scaffold frame is wall fixing device even, includes the fixing bolt cover, and wherein, the fixing bolt cover is used for installing on the structure wall, and is concrete, and the inside first fixed orifices that quantity is two that is offered to the structure wall, fixing bolt cover fixed connection inside first fixed orifices, two the equal threaded connection in inside of fixing bolt cover has fixing bolt, two the equal threaded connection in surface of fixing bolt has fixation nut, two fixing bolt's surface is provided with PMKD, the right side swing joint of structure wall has the scaffold frame pole setting, the surface swing joint of scaffold frame pole setting has the fixed column, PMKD's right side surface is provided with adjusting part.
The adjusting assembly comprises a box body, the outer surface of the left side of the box body is fixedly connected with the right side of the fixed base plate, the inner wall of the box body is fixedly connected with a fixed sleeve, the inner part of the fixed sleeve is fixedly connected with a limiting spring, the inner part of the box body is rotationally connected with two rotating columns, the two rotating columns are separated from one side of a rotating plate, the two rotating columns are fixedly connected with a driving bevel gear on one side and are opposite to each other, a transmission shaft is fixedly connected with the outer surface of the right side of each rotating block, the outer surfaces of the two transmission shafts are in threaded connection with a movable plate, the two transmission shafts are far away from two driven bevel gears which are equal in one end and are fixedly connected with the rotating blocks, and the two clamping columns which are equal in one side and are opposite to each movable plate.
This application is through passing through two fixing bolt and two fixation nut and structure wall fixed connection back with PMKD, with the fixed column on scaffold frame pole surface, after entering into fixed sleeve's inside through the inside movable through-hole of box, it is rotatory to drive two rotation columns through twisting two rotor plates, two initiative bevel gear and two driven bevel gear meshes, thereby let two transmission shafts rotatory in the inside of two fixed blocks and two fixed plates, make two movable plates in the condition that has two gag lever posts, let two transmission shafts drive two movable plates and become to remove about by rotary motion, thereby let two calorie posts under the connection of fixed spring, it is firm that the card can be fixed with the scaffold frame inside going into the fixed column.
Furthermore, fixing bolt holes are formed in the two fixing bolt sleeves, the size of each fixing bolt is matched with that of each fixing bolt hole, and the fixing bottom plate is fixedly connected with the structural wall through the two fixing bolts and the two fixing nuts.
The beneficial effect of adopting the further scheme is that: through setting up two fixing bolt holes for when two fixing bolt and two fixation nut get up PMKD and structure wall fixed connection, it is more firm to fix, simultaneously because the existence of fixed thread cover, has avoided appearing not hard up condition when connecting the back and using as far as possible.
Furthermore, the outer surface swing joint of scaffold frame pole setting has quantity to be two U-shaped anchorage bars, two the equal threaded connection of surface of U-shaped anchorage bar has fastening nut.
The beneficial effect of adopting the further scheme is that: through setting up two U-shaped anchorage bars and fastening nut for the surface at the scaffold frame pole setting can be fixed to the mounting plate, makes things convenient for follow-up fixed subassembly's connection.
Furthermore, the outer surfaces of the two U-shaped fastening rods are movably connected with fastening plates, and the outer surfaces of the right sides of the fastening plates are fixedly connected with arc-shaped plates.
The beneficial effect of adopting the above further scheme is: through setting up the arc at the surface of mounting plate for during mounting plate and scaffold frame pole setting fixed connection, the arc can play skid-proof effect, makes its connection more firm.
Further, two the size of U-shaped anchorage bar with the big or small looks adaptation of scaffold frame pole setting, the right side of fixed column with the left side fixed surface of mounting plate is connected, the anchorage bar hole has been seted up to the inside of mounting plate, the radian of arc with the external diameter radian looks adaptation of scaffold frame pole setting, the mounting plate is connected through the fixed surface of two U-shaped anchorage bars and fastening nut and scaffold frame pole setting.
The beneficial effect of adopting the above further scheme is: through the arrangement of the fastening rod holes, when the fastening plate is fixedly connected with the fastening nuts through the two U-shaped fastening rods, the gap between the U-shaped fastening rods and the fastening plate is not too large; through the radian with the arc and the external diameter looks adaptation of scaffold frame pole setting for when mounting plate and scaffold frame pole setting fixed connection, the arc can play skid-proof effect, makes its connection more firm.
Furthermore, the inner wall of the box body is provided with a movable through hole, and the inside of the fixed sleeve is provided with a limit cavity.
The beneficial effect of adopting the further scheme is that: through setting up activity through-hole and spacing cavity for when the fixed column entered into fixed sleeve's inside, can be better be in the centre and be the position.
Furthermore, the inner wall of box has been seted up and has been rotated the post hole, two the size of rotating the post all with two rotate the size looks adaptation of post hole, two the equal fixedly connected with crank of the one side that leaves mutually of rotor plate.
The beneficial effect of adopting the above further scheme is: through setting up rotation post hole and crank for when twisting and moving the rotor plate and drive the rotation post and rotate the inside rotation in rotation post hole, can be better hard, thereby quick come out power transmission, prepare for follow-up.
Further, the top and the equal fixedly connected with fixed plate in bottom of box, two the fixed block and two the transmission shaft hole has all been seted up to the inside of fixed plate, two the size of transmission shaft all with transmission shaft hole size looks adaptation, two the size and two of turning block the size looks adaptation of rotation cavity.
The beneficial effect of adopting the further scheme is that: the transmission shaft connected with the rotating block is ensured to be more stable in rotation by arranging the transmission shaft hole and the two rotating cavities, and the shaking is avoided as much as possible.
Furthermore, two spacing through-holes have all been seted up to the inside of movable plate, the fixed block with two the equal fixedly connected with gag lever post of the relative one side of fixed plate, two the size of gag lever post all with two spacing through-hole size looks adaptation, two the surface of transmission shaft all is seted up threadedly, two the inside of movable plate all is seted up threaded through-hole.
The beneficial effect of adopting the further scheme is that: by arranging the limiting through holes, the two moving plates move more stably when moving left and right, so that the time required for mounting is saved.
Further, the inner wall fixedly connected with quantity of box is two fixed blocks, two the rotation cavity has all been seted up to the inside of fixed block, two the inside of rotating the cavity all rotates and is connected with the turning block.
The beneficial effect of adopting the further scheme is that: through setting up the rotation cavity for the turning block is more stable in the inside rotation that rotates the cavity.
Compared with the prior art, the application provides a scaffold frame is wall fixing device even, possesses following beneficial effect:
1. this scaffold frame is wall fixing device even, through with behind two fixing bolt and two fixation nut and structure wall fixed connection with PMKD, pass through two U-shaped anchorage bar and fastening nut and mounting plate fixed connection with the scaffold frame pole setting, realize the fixed mounting of scaffold frame pole setting, it is quick convenient, and simultaneously, it is rotatory to drive two turnposts through twisting two turnplates, two initiative bevel gear drive two driven bevel gear rotate, thereby make two transmission shafts rotatory in the inside of two fixed blocks and two fixed plates, and then make the movable plate drive the fixed column and take place to control, the interval adjustment with the structure wall of scaffold frame pole setting has been realized.
2. According to the scaffold wall-connecting fixing device, the fastening rod holes are formed, so that when the fastening plate is fixedly connected with the fastening nuts through the two U-shaped fastening rods, the gap between the U-shaped fastening rods and the fastening plate is not too large; through the radian with the arc and the external diameter looks adaptation of scaffold frame pole setting for during mounting plate and scaffold frame pole setting fixed connection, the arc can play skid-proof effect, makes its connection more firm.
Drawings
FIG. 1 is a front cross-sectional view of the structure of the present application;
FIG. 2 is a top view of the U-shaped fixing rod and fastening plate connection structure of the present application.
In the figure: 1. a structural wall; 2. a first fixing hole; 3. fixing a bolt sleeve; 4. fixing the bolt; 5. fixing a nut; 6. fixing a bottom plate; 7. a box body; 8. fixing the sleeve; 9. a limiting spring; 10. rotating the column; 11. a rotating plate; 12. a drive bevel gear; 13. a fixed block; 14. rotating the cavity; 15. rotating the block; 16. a fixing plate; 17. a limiting rod; 18. a drive shaft; 19. moving the plate; 20. a driven bevel gear; 21. clamping the column; 23. fixing a column; 24. erecting a scaffold; 25. a U-shaped fastening rod; 26. fastening a nut; 27. a fastening plate; 28. an arc-shaped plate.
Detailed Description
The technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the drawings in the embodiments of the present application, and it is obvious that the described embodiments are only a part of the embodiments of the present application, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present application.
Referring to fig. 1-2, a scaffold-wall-connecting fixing device in this embodiment includes a structural wall 1, two first fixing holes 2 are formed in the structural wall 1, and fixing bolt sleeves 3 are fixedly connected to the insides of the two first fixing holes 2, where the fixing bolt sleeves 3 are used to be installed on the structural wall 1, specifically, the fixing bolt sleeves 3 are fixedly connected to the insides of the first fixing holes 2, fixing bolt holes are formed in the insides of the two fixing bolt sleeves 3, fixing bolts 4 are respectively connected to the insides of the two fixing bolt sleeves 3, the sizes of the two fixing bolts 4 are matched with the sizes of the two fixing bolt holes, fixing nuts 5 are respectively connected to the outer surfaces of the two fixing bolts 4, fixing bottom plates 6 are movably connected to the outer surfaces of the two fixing bolts 4, the fixing bottom plates 6 are fixedly connected to the structural wall 1 through the two fixing bolts 4 and the two fixing nuts 5, so that when the fixing bottom plates 6 are fixedly connected to the structural wall 1 by the two fixing bolts 4 and the two fixing nuts 5, the fixing bottom plates 6 are more firmly fixed to the structural wall, and the fixing bolt sleeves 3 are prevented from being loosened after being connected.
The right side swing joint of structure wall 1 has scaffold pole setting 24, scaffold pole setting 24's surface swing joint quantity is two U-shaped anchorage bars 25, two U-shaped anchorage bars 25's size and scaffold pole setting 24's size looks adaptation, the equal threaded connection of surface of two U-shaped anchorage bars 25 has fastening nut 26, the surface swing joint of two U-shaped anchorage bars 25 has mounting plate 27, mounting plate 27 is connected with scaffold pole setting 24's surface fixed through two U-shaped anchorage bars 25 and fastening nut 26, through setting up two U-shaped anchorage bars 25 and fastening nut 26, make mounting plate 27 can fix the surface in scaffold pole setting 24, make things convenient for the connection of follow-up fixed subassembly.
Specifically, the fastening plate 27 has a fastening rod hole therein for inserting the U-shaped fastening rod 25.
The right side outer fixed surface of mounting plate 27 is connected with arc 28, and the radian of arc 28 and the external diameter radian looks adaptation of scaffold frame pole setting 24 are through the radian with arc 28 and the external diameter looks butt of scaffold frame pole setting 24 for when mounting plate 27 and scaffold frame pole setting 24 fixed connection, arc 28 can play skid-proof effect, makes its connection more firm.
The outer surface of scaffold pole setting 24 is provided with fixed column 23, and the right side of fixed column 23 and the left side surface fixed connection of mounting plate 27, the right side surface of PMKD 6 is provided with adjusting part.
Adjusting part includes box 7, movable through hole has been seted up to the inner wall of box 7, movable through hole supplies fixed column 23 to slide and alternates, box 7's left side surface and PMKD 6's right side fixed connection, box 7's middle part inner wall horizontal fixedly connected with fixed sleeve 8, spacing cavity has been seted up to fixed sleeve 8's inside, spacing cavity supplies fixed column 23 to slide and alternates, fixed sleeve 8's inside fixedly connected with spacing spring 9, the spacing spring 9 other end and fixed column 23 fixed connection, through setting up movable through hole and spacing cavity, when making fixed column 23 enter into fixed sleeve 8's inside, can be better at the intermediate position.
The inside of box 7 is rotated and is connected with quantity and is two rotation post 10, the rotation post hole has been seted up to the inner wall of box 7, two sizes of rotating post 10 all with two rotation post hole size looks adaptations, two rotation posts 10 are from the equal fixedly connected with rotor plate 11 in one side mutually, two equal fixedly connected with cranks in one side of separating mutually of rotor plate 11, through setting up rotation post hole and crank, make and move rotor plate 11 and drive rotation post 10 when the inside in rotation post hole is rotatory twisting, can be better hard, thereby the quick comes out power transmission, prepare for follow-up well.
The opposite sides of the two rotating columns 10 are fixedly connected with a driving bevel gear 12, the inner wall of the box body 7 is fixedly connected with two fixing blocks 13, rotating cavities 14 are formed in the two fixing blocks 13, the fixing blocks 13 are located in the rotating cavities 14 and are rotatably connected with rotating blocks 15, and the sizes of the two rotating blocks 15 are matched with the sizes of the two rotating cavities 14.
The top and the equal fixedly connected with fixed plate 16 in bottom of box 7, the transmission shaft hole has all been seted up with the inside of two fixed plates 16 to two fixed blocks 13, two fixed blocks 13 and two fixed plates 16 are relative the equal fixedly connected with gag lever post 17 of one side, the equal fixedly connected with transmission shaft 18 in right side surface of two turning blocks 15, transmission shaft 18 alternates in the transmission shaft hole, the size of two transmission shafts 18 all with transmission shaft hole size looks adaptation, it is more stable when rotatory to have guaranteed transmission shaft 18 that turning block 15 is connected through setting up transmission shaft hole and two existence that rotate cavity 14, avoid appearing rocking as far as possible.
The outer surface of two transmission shafts 18 all has seted up the screw thread, the equal threaded connection of outer surface of two transmission shafts 18 has movable plate 19, and spacing through-hole has all been seted up to movable plate 19's inside, and spacing through-hole supplies gag lever post 17 to alternate, and the size of two gag lever posts 17 all with two spacing through-hole size looks adaptations, through setting up spacing through-hole for it is more stable to remove when moving plate 19 removes, thereby practices thrift the required time when the installation.
The interior of the moving plate 19 is provided with threaded through holes in threaded connection with the outer surface of the rotating shaft 18, one ends, far away from the two rotating blocks 15, of the two transmission shafts 18 are fixedly connected with driven bevel gears 20, the driving bevel gears 12 are meshed with the driven bevel gears 20, clamping columns 21 are fixedly connected to the opposite sides of the two moving plates 19, and the clamping columns 21 are fixedly connected with the fixed columns 23. When the clamping column 21 is driven by the moving plate 19 to move left and right, the fixing column 23 is driven to move left and right, and further the distance between the structure wall 1 and the scaffold upright rod 24 is adjusted.
The working principle of the embodiment is as follows:
this scaffold frame is wall fixing device even, through with PMKD 6 through two fixing bolt 4 and two fixation nut 5 with behind 1 fixed connection of structure wall, with scaffold frame pole setting 24 through two U-shaped anchorage bar 25 and fastening nut 26 and mounting plate 27 fixed connection, realize scaffold frame pole setting 24's fixed mounting, it is quick convenient, and simultaneously, it is rotatory to drive two rotation posts 10 through twisting two rotor plates 11, two initiative bevel gear 12 drive two driven bevel gear 20 rotations, thereby make two transmission shaft 18 rotatory in the inside of two fixed blocks 13 and two fixed plates 16, and then make movable plate 19 drive fixed column 23 and take place to remove, realized scaffold frame pole setting 24 with the interval modulation of structure wall 1.
The electrical components present in the document are all electrically connected to a main controller and a power supply, the main controller may be a conventional known device for controlling a computer, and the conventional power connection technology disclosed in the prior art is not described herein.
It should be noted that, in this document, relational terms such as first and second, and the like are used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrases "comprising a," "8230," "8230," or "comprising" does not exclude the presence of additional like elements in a process, method, article, or apparatus that comprises the element.
Although embodiments of the present application have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the application, the scope of which is defined in the appended claims and their equivalents.

Claims (10)

1. The utility model provides a scaffold frame is wall fixing device even, includes structure wall (1), its characterized in that: the structure wall comprises a structure wall (1) and is characterized in that two first fixing holes (2) are formed in the structure wall (1), fixing bolt sleeves (3) are fixedly connected to the insides of the two first fixing holes (2), fixing bolts (4) are connected to the insides of the two fixing bolt sleeves (3) in a threaded manner, fixing nuts (5) are connected to the outer surfaces of the two fixing bolts (4) in a threaded manner, fixing bottom plates (6) are movably connected to the outer surfaces of the two fixing bolts (4), a scaffold upright rod (24) is movably connected to the right side of the structure wall (1), a fixing column (23) is arranged on the outer surface of the scaffold upright rod (24), and an adjusting component is arranged on the outer surface of the right side of the fixing bottom plate (6); the adjusting assembly comprises a box body (7), the outer surface of the left side of the box body (7) is fixedly connected with the right side of the fixed bottom plate (6), the inner wall of the box body (7) is fixedly connected with a fixed sleeve (8), the inner part of the fixed sleeve (8) is fixedly connected with a limiting spring (9), the inner part of the box body (7) is rotatably connected with two rotating columns (10), two rotating columns (10) are fixedly connected with a rotating plate (11) at one side away from one side, two rotating columns (10) are fixedly connected with a driving bevel gear (12) at the opposite side, a fixed block (13) is arranged at one side of the inner wall of the box body (7) away from a hand foot stand, a rotating cavity (14) is formed in the inner wall of the fixed block (13), rotating blocks (15) are arranged in the rotating cavity (14), two fixing blocks (13) and two rotating blocks (15) are arranged, transmission shafts (18) are fixedly connected with the outer surfaces of the right sides of the two rotating blocks (15), the outer surfaces of the two rotating blocks (18) are both fixedly connected with a movable plate (19) in a threaded connection manner, one side of the two transmission shafts (18) away from one end of the fixed block (15) is connected with a movable plate (20), and one side of the two movable plate (21) is connected with a driven bevel gear (21), the clamping column (21) is fixedly connected with the fixing column (23).
2. A scaffolding wall-attachment fixture as claimed in claim 1, in which: fixing bolt holes are formed in the two fixing bolt sleeves (3), the size of each fixing bolt (4) is matched with that of each fixing bolt hole, and the fixing base plate (6) is fixedly connected with the structure wall (1) through the two fixing bolts (4) and the two fixing nuts (5).
3. A scaffold wall attachment as claimed in claim 1, wherein: the outer surface swing joint of scaffold frame pole setting (24) has quantity to be two U-shaped anchorage bars (25), two the equal threaded connection of surface of U-shaped anchorage bar (25) has fastening nut (26).
4. A scaffold wall attachment as claimed in claim 3, wherein: the outer surfaces of the two U-shaped fastening rods (25) are movably connected with fastening plates (27), and the outer surface of the right side of each fastening plate (27) is fixedly connected with an arc-shaped plate (28).
5. A scaffold wall attachment fixing device according to claim 4, wherein: the size of two U-shaped anchorage bar (25) with the big or small looks adaptation of scaffold pole setting (24), the right side of fixed column (23) with the left side fixed surface of mounting plate (27) is connected, the anchorage bar hole has been seted up to the inside of mounting plate (27), the radian of arc (28) with the external diameter radian looks adaptation of scaffold pole setting (24), mounting plate (27) are connected with the fixed surface of scaffold pole setting (24) through two U-shaped anchorage bar (25) and fastening nut (26).
6. A scaffolding wall-attachment fixture as claimed in claim 1, in which: the inner wall of the box body (7) is provided with a movable through hole, the inside of the fixed sleeve (8) is provided with a limit cavity, and the size of the limit spring (9) is matched with that of the limit cavity.
7. A scaffolding wall-attachment fixture as claimed in claim 1, in which: the inner wall of the box body (7) is provided with rotating column holes, the size of the rotating column (10) is matched with that of the rotating column holes, and the two rotating plates (11) are fixedly connected with a crank at the same side.
8. A scaffold wall attachment as claimed in claim 1, wherein: the top and the equal fixedly connected with fixed plate (16) in bottom of box (7), two fixed block (13) and two the transmission shaft hole has all been seted up to the inside of fixed plate (16), two the size of transmission shaft (18) all with transmission shaft hole size looks adaptation, two the size and the two of turning block (15) the size looks adaptation of rotation cavity (14).
9. A scaffold wall attachment as claimed in claim 8, wherein: two limiting through holes have all been seted up to the inside of movable plate (19), two fixed block (13) and two the equal fixedly connected with gag lever post (17) of the relative one side of fixed plate (16), two the size of gag lever post (17) all with two limiting through hole size looks adaptation, two the surface of transmission shaft (18) is all seted up threadedly, two threaded through hole has all been seted up to the inside of movable plate (19).
10. A scaffold wall attachment as claimed in claim 9, wherein: the inner wall fixedly connected with quantity of box (7) is two fixed block (13), two rotation cavity (14), two have all been seted up to the inside of fixed block (13) the inside of rotating cavity (14) all rotates and is connected with turning block (15).
CN202221066653.6U 2022-05-06 2022-05-06 Scaffold frame is wall fixing device even Expired - Fee Related CN217557629U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221066653.6U CN217557629U (en) 2022-05-06 2022-05-06 Scaffold frame is wall fixing device even

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221066653.6U CN217557629U (en) 2022-05-06 2022-05-06 Scaffold frame is wall fixing device even

Publications (1)

Publication Number Publication Date
CN217557629U true CN217557629U (en) 2022-10-11

Family

ID=83474901

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221066653.6U Expired - Fee Related CN217557629U (en) 2022-05-06 2022-05-06 Scaffold frame is wall fixing device even

Country Status (1)

Country Link
CN (1) CN217557629U (en)

Similar Documents

Publication Publication Date Title
CN107524892A (en) A kind of solar energy safety monitoring equipment of installation easy to disassemble
CN110303341B (en) Multifunctional steel structure cutting and drilling device
CN210396193U (en) Temporary supporting device for prefabricated wall
CN104200736B (en) Teaching demonstration experiment table
CN211239765U (en) Fixed adjustable photovoltaic support device
CN211489726U (en) Steel structure machining equipment
CN217557629U (en) Scaffold frame is wall fixing device even
CN211621306U (en) Novel warning for movable building site device
CN211221186U (en) Production system of concrete member
CN212272219U (en) Efficient tunnel construction device
CN210201298U (en) Auxiliary assembly is used in switch board installation
CN220623410U (en) Quick-mounting and orientation device for emergency
CN210264031U (en) Stable aluminum formwork height adjusting device
CN209063016U (en) A kind of steel body PDC drill bit
CN218814365U (en) Novel inner support structure of steel structure building
CN102180230B (en) Height adjusting device for constructing ships
CN209755567U (en) Prefabricated module apparatus for producing of cylinder building
CN213980053U (en) Building construction strutting arrangement
CN215978497U (en) Concrete placement auxiliary device
CN210651037U (en) Building engineering decorative board perforating device
CN214497973U (en) Building structure design wall column base connecting device
CN215618058U (en) Manipulator-assisted mobile positioning device
CN211706513U (en) Agitated vessel based on food processing uses
CN218275800U (en) Make things convenient for interim mounting bracket of electric power facility of dismouting
CN218373847U (en) Engineering pile pulling device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20221011