Automatic cable wiring device for electric power construction Download PDFInfo
- Publication number
- CN217545412U CN217545412U CN202221087728.9U CN202221087728U CN217545412U CN 217545412 U CN217545412 U CN 217545412U CN 202221087728 U CN202221087728 U CN 202221087728U CN 217545412 U CN217545412 U CN 217545412U
- Authority
- CN
- China
- Prior art keywords
- ring
- mounting
- electric power
- power construction
- limiting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 21
- 239000004020 conductor Substances 0.000 claims abstract description 6
- 238000000034 method Methods 0.000 abstract description 6
- 230000000630 rising effect Effects 0.000 abstract 1
- 230000008901 benefit Effects 0.000 description 3
- 238000009434 installation Methods 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000011156 evaluation Methods 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 210000001503 joint Anatomy 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
Images
Landscapes
- Installation Of Indoor Wiring (AREA)
Abstract
The utility model relates to an electric power construction technical field specifically is an automatic wiring arrangement of cable conductor for electric power construction, including hydraulic lift, mounting panel, spacing case, motor case and step motor, the mounting panel is installed to hydraulic lift's jacking end, spacing case is installed to the top face of mounting panel, step motor is all installed to the corresponding both sides face of mounting panel. Can conveniently drag the cable of treating the wiring to the wire pole and erect on the wire pole through spacing ring spare and the fixed ring spare that sets up, make things convenient for the staff construction, and can transport the top with many cables simultaneously through the spacing groove of seting up with the through groove, increased work efficiency, through snap ring and the pulley that sets up, can carry out the injecing in the position to this device at the in-process that this device rises, increased the stability of this device to prevent to take place the slope on the way rising.
Description
Technical Field
The utility model relates to an electric power construction technical field specifically is an automatic wiring arrangement of cable conductor for electric power construction.
Background
The electric power basic construction program is used for planning, coordinating, supervising, controlling and summarizing and evaluating the system operation processes of establishment, feasibility research, evaluation, decision-making, design, equipment purchase, construction, debugging, acceptance inspection, production, capital recovery and the like of a construction project so as to achieve the purposes of ensuring the quality of the investment project, shortening the construction period and improving the investment benefit, and in the process, a cable is an important tool for transmitting electric power, and certain defects exist during cable wiring and are to be perfected;
when the cable is wired, the cable to be wired is usually pulled to the telegraph pole and erected on the telegraph pole manually, so that the labor intensity of workers is increased, the installation efficiency is low, and a plurality of cables cannot be replaced simultaneously.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide an automatic wiring arrangement of cable conductor for electric power construction to solve the problem that proposes among the above-mentioned background art. In order to achieve the above purpose, the utility model provides a following technical scheme: the utility model provides an automatic wiring arrangement of cable conductor for electric power construction, includes hydraulic lift, mounting panel, spacing case, motor case and step motor, the mounting panel is installed to hydraulic lift's jacking end, the spacing case is installed to the top face of mounting panel, step motor, two are all installed to the corresponding both sides face of mounting panel step motor's output is connected with fixed ring spare, the quantity of motor case is two, two the installing frame is installed at the top of motor case, the bottom face of installing frame is vertical installs two electric putter, two the stopper is all installed to electric putter's output, two the slider is all installed to the corresponding both sides face of stopper, two rotate between the stopper and install spacing ring spare, the collar is installed to one side of mounting panel, the snap ring is installed to one side of collar, the fixture block is all installed to one side that the snap ring corresponds with the collar, two the fixture block joint is in the collar, the pulley is all installed to the inner circle of collar and snap ring, the equal threaded mounting ring is installed and is locked to the locking bolt in the corresponding both sides.
Preferably, motor boxes are installed on two corresponding side faces of the installation plate, and step motors are installed inside the two motor boxes respectively.
Preferably, the sliding grooves are formed in two corresponding sides of the limiting box, and the four sliding blocks are respectively slidably mounted in the corresponding sliding grooves.
Preferably, two clamping grooves are formed in one side, corresponding to the clamping ring, of the mounting ring, and the two clamping blocks are clamped in the corresponding clamping grooves respectively.
Preferably, threaded holes are formed in the two sides of the mounting ring, and the two locking bolts are respectively installed in the corresponding threaded holes in a threaded mode.
Preferably, a plurality of through grooves are formed in the two corresponding side faces of the limiting box, the through grooves correspond to each other in position, and a plurality of limiting grooves are formed in the fixed ring piece and the limiting ring piece.
Compared with the prior art, the beneficial effects of the utility model are that:
in the utility model, the cables to be wired can be conveniently pulled to the telegraph pole and erected on the telegraph pole through the arranged limiting ring piece and the fixed ring piece, so that the construction of workers is facilitated, and a plurality of cables can be simultaneously conveyed to the top through the arranged limiting groove and the through groove, so that the working efficiency is increased;
the utility model discloses in, through snap ring and the pulley that sets up, can carry out the injecing on the position to this device at the in-process that this device rises, increased the stability of this device to prevent to rise on the way and take place the slope.
Drawings
Fig. 1 is a schematic perspective view of the present invention;
fig. 2 is a schematic view of the structure of the present invention;
fig. 3 is a schematic left-view structural diagram of the joint between the limiting ring and the limiting block of the present invention;
fig. 4 is a left side view structure diagram of the joint of the snap ring and the mounting ring in the present invention.
In the figure: 1. a hydraulic lift; 2. mounting a plate; 3. a limiting box; 4. a motor case; 5. a stepping motor; 6. a fixed ring member; 7. installing a frame; 8. an electric push rod; 9. a limiting block; 10. a slider; 11. a limiting ring piece; 12. a mounting ring; 13. a snap ring; 14. a clamping block; 15. a pulley; 16. and locking the bolt.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by the staff with ordinary skill in the art without creative work all belong to the protection scope of the present invention.
Referring to fig. 1 to 4, the present invention provides a technical solution: the utility model provides an automatic wiring arrangement of cable conductor for electric power construction, includes hydraulic lift 1, mounting panel 2, spacing case 3, motor case 4 and step motor 5, mounting panel 2 is installed to hydraulic lift 1's jacking end, spacing case 3 is installed to mounting panel 2's top face, step motor 5, two are all installed to the corresponding both sides face of mounting panel 2 step motor 5's output is connected with retaining ring 6, motor case 4's quantity is two, two install mounting frame 7 at motor case 4's top, the vertical two electric putter 8 of installing frame 7's bottom face is installed, two stopper 9, two are all installed to electric putter 8's output slider 10, two slider 10 are all installed to the corresponding both sides face of stopper 9, two rotate between the stopper 9 and install spacing ring 11, mounting ring 12 is installed to one side of mounting panel 2, snap ring 13 is installed to one side of mounting ring 12, snap ring 14, two fixture block 14 joint is all installed to snap ring 13 and one side that mounting ring 12 corresponds, pulley 15 are all installed to the inner circle of mounting ring 12, 16 the both sides that the corresponding lock bolt is all installed to the screw thread mounting ring 12.
In this embodiment, as shown in fig. 1 and 3, motor boxes 4 are installed on two corresponding side surfaces of the installation plate 2, step motors 5 are installed inside the two motor boxes 4, and the motor boxes 4 can protect the step motors 5.
In this embodiment, as shown in fig. 3, sliding grooves are formed in two corresponding sides of the limiting box 3, and four sliding blocks 10 are slidably mounted in the corresponding sliding grooves respectively.
In this embodiment, as shown in fig. 4, two clamping grooves are formed in one side of the mounting ring 12 corresponding to the clamping ring 13, and the two clamping blocks 14 are respectively clamped in the corresponding clamping grooves.
In this embodiment, as shown in fig. 4, threaded holes are formed in both sides of the mounting ring 12, and the two locking bolts 16 are respectively threadedly mounted in the corresponding threaded holes.
In this embodiment, as shown in fig. 1, two corresponding side surfaces of the limiting box 3 are respectively provided with a plurality of through grooves, the through grooves are located in pairs, the fixed ring 6 and the limiting ring 11 are provided with a plurality of limiting grooves, and the through grooves and the limiting grooves can limit cables at the same time.
The utility model discloses a use method and advantage: when the automatic cable wiring device for electric power construction is used, the working process is as follows:
as shown in fig. 1, 2, 3 and 4, when the device is used, firstly, an external power supply is applied to the electric equipment in the device, the device is moved to one side of a telegraph pole, at this time, the mounting ring 12 is close to the telegraph pole, the clamping block 14 on the clamping ring 13 is inserted into the mounting ring 12 in a butt joint mode from the other side, the locking bolt 16 is fixed, at this time, the cable is put into the through groove, penetrates out through the limiting groove between the limiting ring piece 11 and the fixing ring piece 6 and penetrates out through the through groove on the other side of the limiting box 3, at this time, the electric push rod 8 is started, the corresponding limiting block 9 is moved towards the bottom, the limiting ring piece 11 is moved towards the bottom and clamps the cable together with the fixing ring piece 6, at this time, the hydraulic lifter 1 can be started to lift the device, after the cable is conveyed to the top, the stepping motor 5 is started, the cable is rotated out, and the cable is installed by a worker.
The foregoing shows and describes the general principles, essential features, and advantages of the invention. The scope of the invention is defined by the appended claims and equivalents thereof.
Claims (6)
1. The utility model provides an automatic wiring arrangement of cable conductor for electric power construction, includes hydraulic lift (1), mounting panel (2), spacing case (3), motor case (4) and step motor (5), its characterized in that: the jacking end of the hydraulic lifter (1) is provided with a mounting plate (2), the top end surface of the mounting plate (2) is provided with a limit box (3), two corresponding side surfaces of the mounting plate (2) are provided with stepping motors (5), the output ends of the two stepping motors (5) are connected with a fixed ring piece (6), the number of the motor boxes (4) is two, the top parts of the two motor boxes (4) are provided with mounting frames (7), two electric push rods (8) are vertically arranged on the bottom end face of the mounting frame (7), limiting blocks (9) are arranged at the output ends of the two electric push rods (8), sliding blocks (10) are arranged on two corresponding side faces of the two limiting blocks (9), a limiting ring piece (11) is rotatably arranged between the two limiting blocks (9), one side of the mounting plate (2) is provided with a mounting ring (12), a snap ring (13) is arranged on one side of the mounting ring (12), clamping blocks (14) are arranged on one sides of the snap ring (13) corresponding to the mounting ring (12), the two clamping blocks (14) are clamped in the mounting ring (12), pulleys (15) are arranged on the inner rings of the mounting ring (12) and the snap ring (13), and locking bolts (16) are arranged on the two corresponding sides of the mounting ring (12) in a threaded manner.
2. The automatic cabling device for electric power construction according to claim 1, wherein: motor case (4), two are all installed to the corresponding both sides face of mounting panel (2) step motor (5) are installed respectively to the inside of motor case (4).
3. The automatic cabling device for electric power construction according to claim 1, wherein: the two corresponding sides of the limiting box (3) are provided with sliding grooves, and the four sliding blocks (10) are slidably mounted in the corresponding sliding grooves respectively.
4. The automatic cabling device for electric power construction according to claim 1, wherein: two clamping grooves are formed in one side, corresponding to the clamping ring (13), of the mounting ring (12), and the two clamping blocks (14) are clamped in the corresponding clamping grooves respectively.
5. The automatic cabling device for electric power construction according to claim 1, wherein: threaded holes are formed in the two sides of the mounting ring (12), and the two locking bolts (16) are respectively installed in the corresponding threaded holes in a threaded mode.
6. The automatic cabling device for electric power construction according to claim 1, wherein: the two corresponding side surfaces of the limiting box (3) are provided with a plurality of through grooves, the through grooves correspond to each other in position, and the fixed ring piece (6) and the limiting ring piece (11) are provided with a plurality of limiting grooves.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202221087728.9U CN217545412U (en) | 2022-05-07 | 2022-05-07 | Automatic cable wiring device for electric power construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202221087728.9U CN217545412U (en) | 2022-05-07 | 2022-05-07 | Automatic cable wiring device for electric power construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN217545412U true CN217545412U (en) | 2022-10-04 |
Family
ID=83433446
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202221087728.9U Expired - Fee Related CN217545412U (en) | 2022-05-07 | 2022-05-07 | Automatic cable wiring device for electric power construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN217545412U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117566634A (en) * | 2024-01-16 | 2024-02-20 | 沈阳添润信息技术有限公司 | Communication is with holding pole device |
-
2022
- 2022-05-07 CN CN202221087728.9U patent/CN217545412U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117566634A (en) * | 2024-01-16 | 2024-02-20 | 沈阳添润信息技术有限公司 | Communication is with holding pole device |
CN117566634B (en) * | 2024-01-16 | 2024-03-19 | 沈阳添润信息技术有限公司 | Communication is with holding pole device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN217545412U (en) | Automatic cable wiring device for electric power construction | |
CN114362065B (en) | Portable power distribution network live-line drainage wire connecting robot and operation method thereof | |
CN218732808U (en) | Guide wheel with auxiliary power for cable laying | |
CN203289006U (en) | Insulation adjustable yoke plate | |
CN210316214U (en) | Assembled steel construction building dysmorphism post | |
CN212968423U (en) | Ground ring installation device and ground ring installation robot | |
CN214046942U (en) | Portable tree inversion control tool | |
CN206259254U (en) | A kind of coil winding machine coil clamp fixed jig | |
CN111786230B (en) | Grounding ring mounting device, grounding ring mounting robot and grounding ring mounting method | |
CN213812188U (en) | Automatic detection equipment for diameter of steel bar thread head | |
CN209810922U (en) | Full-automatic cold rolling pay-off dolly | |
CN204886031U (en) | Device of supplementary wiring | |
CN212518723U (en) | Servo motor rotor maintenance frock | |
CN208479417U (en) | Workbench is used in a kind of processing of motor stator | |
CN216226713U (en) | Twisted steel processing and sleeve mounting equipment | |
CN218931446U (en) | Lifting platform for power generation equipment assembly | |
CN219987548U (en) | Cutting fluid platform | |
CN220301815U (en) | ALC side fascia mounting tool | |
CN217819739U (en) | Tension detection device for sealing ring production | |
CN217282600U (en) | Piece together motor stator lead-out wire reason line device | |
CN218136106U (en) | Clamp for mounting steel structure | |
CN214246691U (en) | Anti-bending protective appliance for cement rod body | |
CN216471901U (en) | Auxiliary lifting device for hoisting bridge tower | |
CN211351471U (en) | Turning guide device for construction engineering cable erection | |
CN213449582U (en) | Movable safety belt fixing device for edge operation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |