0# block construction structure for installing bracket on bent cap Download PDFInfo
- Publication number
- CN217536689U CN217536689U CN202221180531.XU CN202221180531U CN217536689U CN 217536689 U CN217536689 U CN 217536689U CN 202221180531 U CN202221180531 U CN 202221180531U CN 217536689 U CN217536689 U CN 217536689U
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- bent cap
- bracket
- hollow steel
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
The utility model discloses a 0# piece construction structures of installation bracket on bent cap for the construction of 0# piece, including the bent cap, pre-buried first hollow steel pipe and the hollow steel pipe of second that has relative upper and lower setting in the bent cap just the hollow steel pipe of second is located first hollow steel pipe top, first hollow steel pipe with install round pin stick and finish rolling deformed steel bar respectively in the hollow steel pipe of second, the bracket is all installed just to the bent cap both sides the bracket respectively with the round pin stick with finish rolling deformed steel bar connects. The utility model has the advantages that: a series of problems such as structure height, ground traffic, foundation bearing capacity requirements and the like can be effectively solved, the design condition of the bracket is obtained through analysis and calculation according to the weight of the 0# block and the condition of a cover beam prestress system, the solving method is relatively simple, the construction period is shortened, and the cost is reduced.
Description
Technical Field
The utility model belongs to the technical field of the technique of bent cap construction and specifically relates to a 0# piece construction structures of installation bracket on bent cap.
Background
At present, the construction scheme aiming at the 0# block of the continuous beam on the bent cap mainly comprises two types: firstly, full supports are erected and fully distributed from the ground to the bottom of the structure, the material period is long, the traffic requirement is high, and the overall height of the structure is low; and secondly, the combination of the steel pipe pile, the I-shaped steel and the like is used, so that the requirement on the bearing capacity of the foundation is high, and calculation is required according to actual conditions.
Therefore, there is a need for a 0# block construction structure for a corbel attachment to a capping beam that can solve the above-mentioned problems.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a 0# piece construction structures of installation bracket on bent cap according to above-mentioned prior art not enough, at the pre-buried hollow steel pipe of bent cap design position, wait after the construction of bent cap prestressing force system, the installation round pin stick, finish rolling screw-thread steel, install the bracket in proper order again, members such as sand box, 0# piece is under construction at last, can effectively solve 0# piece construction problem on the bent cap, a series of problems such as structural height, ground is current, ground bearing capacity requirement are synthesized to the while.
The utility model discloses the purpose is realized accomplishing by following technical scheme:
the utility model provides a 0# piece construction structures of installation bracket on bent cap for the construction of 0# piece, its characterized in that: including the bent cap, pre-buried first hollow steel pipe and the second hollow steel pipe that has set up about relative in the bent cap just the second hollow steel pipe is located first hollow steel pipe top, first hollow steel pipe with install round pin stick and finish rolling deformed steel bar respectively in the second hollow steel pipe, the bracket is all installed just to the bent cap both sides the bracket respectively with the round pin stick with the finish rolling deformed steel bar is connected.
And the sand box, the I-steel and the template system are sequentially placed on the bracket from bottom to top.
The 0# block is placed on the template system.
And two ends of the pin rod extend out of the first hollow steel pipe.
The top of the bracket is connected with the finish rolling deformed steel bar, and the bottom of the bracket is connected with the pin rod.
The utility model has the advantages that: a series of problems such as structural height, ground traffic, foundation bearing capacity requirements and the like can be effectively solved, the design condition of the bracket is obtained through analysis and calculation according to the weight of the 0# block and the condition of the cover beam prestress system, the solution is relatively simple, the construction period is shortened, and the cost is reduced.
Drawings
FIG. 1 is a cross-sectional view of the construction structure of the No. 0 block of the present invention;
fig. 2 is an elevation view of the bent cap of the present invention.
Detailed Description
The features of the present invention and other related features are described in further detail below by way of example in conjunction with the accompanying drawings to facilitate understanding by those skilled in the art:
as shown in FIGS. 1-2, reference numerals 1-10 in the drawings respectively denote a bent cap 1, a first hollow steel pipe 2, a pin 3, a second hollow steel pipe 4, finish-rolled deformed steel bars 5, a corbel 6, a sand box 7, I-shaped steel 8, a formwork system 9 and a # 0 block 10.
Example (b): as shown in fig. 1, the present embodiment relates to a 0# block construction structure for mounting a corbel on a capping beam, which is used for construction of a 0# block 10 and mainly comprises the capping beam 1, the corbel 6, a sand box 7, i-steel 8 and a formwork system 9, wherein a first hollow steel pipe 2 and a second hollow steel pipe 4 which are arranged up and down relatively are embedded in the capping beam 1, and the second hollow steel pipe 4 is located above the first hollow steel pipe 2. The first hollow steel pipe 2 and the second hollow steel pipe 4 are internally provided with a pin 3 and finish-rolled deformed steel bars 5 respectively, and two ends of the pin 3 extend out of the first hollow steel pipe 2. The bracket 6 is arranged on two sides of the bent cap 1, the top of the bracket 6 is connected with the finish-rolled deformed steel bar 5, and the bottom of the bracket 6 is connected with the pin rod 3. As shown in fig. 2, in the present embodiment, the capping beam 1 is a # 60 gate pier capping beam.
As shown in fig. 1, a sand box 7, an i-beam 8 and a pattern plate system 9 are sequentially placed on a bracket 6 from bottom to top, the sand box 7 is used for adjusting the position of the pattern plate system 9, the i-beam 8 is used for supporting the pattern plate system 9, the shape and the size of the pattern plate system 9 are matched with those of a 0# block 10, and the 0# block 10 can be placed on the pattern plate system 9.
As shown in fig. 1, the present embodiment also has the following construction method;
1. in the construction process of the bent cap 1, the first hollow steel pipe 2 and the second hollow steel pipe 4 are pre-buried at corresponding positions according to a bracket design drawing.
2. After the integral construction of the bent cap 1 is completed, a pin 3 is installed in a first hollow steel pipe 2, finish rolling deformed steel bars 5 are installed in a second hollow steel pipe 4, and then a bracket 6, a sand box 7, I-shaped steel 8 and a template system 9 are sequentially installed.
3. And finally constructing the continuous beam 0# block 10.
In conclusion, in the embodiment, a series of problems such as structural height, ground traffic, foundation bearing capacity requirements and the like can be effectively solved, the design condition of the bracket is obtained through analysis and calculation according to the weight of the 0# block and the condition of the cover beam prestress system, the solution is relatively simple, the construction period is shortened, and the cost is reduced.
Although the conception and the embodiments of the present invention have been described in detail with reference to the drawings, those skilled in the art will recognize that various changes and modifications can be made therein without departing from the scope of the appended claims, and therefore, the description thereof is not repeated herein.
Claims (5)
1. The utility model provides a 0# piece construction structures of installation bracket on bent cap for the construction of 0# piece, its characterized in that: including the bent cap, pre-buried first hollow steel pipe and the hollow steel pipe of second that has set up about relative in the bent cap just the hollow steel pipe of second is located first hollow steel pipe top, first hollow steel pipe with install round pin stick and finish rolling deformed steel bar respectively in the hollow steel pipe of second, the bracket is all installed just to the bent cap both sides the bracket respectively with the round pin stick with the finish rolling deformed steel bar is connected.
2. The 0# block construction structure for installing the corbel on the bent cap as claimed in claim 1, wherein: and the sand box, the I-steel and the template system are sequentially placed on the bracket from bottom to top.
3. The construction structure of the 0# block for installing the bracket on the bent cap according to claim 2, characterized in that: the 0# block is placed on the template system.
4. The 0# block construction structure for installing the corbel on the bent cap as claimed in claim 1, wherein: and two ends of the pin rod extend out of the first hollow steel pipe.
5. The construction structure of the 0# block for installing the bracket on the bent cap according to claim 1, characterized in that: the top of the bracket is connected with the finish-rolled deformed steel bar, and the bottom of the bracket is connected with the pin rod.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202221180531.XU CN217536689U (en) | 2022-05-17 | 2022-05-17 | 0# block construction structure for installing bracket on bent cap |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202221180531.XU CN217536689U (en) | 2022-05-17 | 2022-05-17 | 0# block construction structure for installing bracket on bent cap |
Publications (1)
Publication Number | Publication Date |
---|---|
CN217536689U true CN217536689U (en) | 2022-10-04 |
Family
ID=83434807
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202221180531.XU Active CN217536689U (en) | 2022-05-17 | 2022-05-17 | 0# block construction structure for installing bracket on bent cap |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN217536689U (en) |
-
2022
- 2022-05-17 CN CN202221180531.XU patent/CN217536689U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107336346B (en) | Beam making pedestal | |
CN106894346B (en) | A kind of the continuous beam bridge construction method | |
CN217536689U (en) | 0# block construction structure for installing bracket on bent cap | |
CN111827090A (en) | Large-size quick assembling steel pipe support | |
CN214613609U (en) | Side span cast-in-situ section support | |
CN216406164U (en) | Under wear suspension type template system of railway bridge sheet structure | |
CN213682477U (en) | Upper cover structure system applied to track operation line | |
CN211772868U (en) | Pier temporary consolidation device in large-span continuous beam | |
CN114412166A (en) | Integrally-moving type cast-in-place concrete roof formwork support and using method thereof | |
CN112095780A (en) | Upper cover structure system applied to track operation line and implementation method thereof | |
CN112376704A (en) | Bolt mounting and fixing frame and construction method thereof | |
CN215369949U (en) | Middle plate and frame body reserved door type channel | |
CN216765568U (en) | Slope adjusting device for embedded steel plate of support | |
CN210361894U (en) | Disconnected case roof beam reinforcing bar positioner festival | |
CN213233165U (en) | Bridge auxiliary pier support installation device | |
CN219280520U (en) | High pier large cantilever bent cap support | |
CN216999361U (en) | Single-column pier cantilever capping beam assembly type bearing support device | |
CN211498467U (en) | Panel type metal anti-throwing screen structure for iron-related engineering | |
CN219653541U (en) | Synchronous steel bent cap pushes away support | |
CN220504665U (en) | Ectopic assembled H-shaped steel tower | |
CN221798190U (en) | Side span cast-in-situ section construction system | |
CN219342870U (en) | Beam supporting structure is assembled to two line bridge festival sections | |
CN216947827U (en) | High-position beam falling buttress structure of steel box girder | |
CN214993135U (en) | Welding platform device for box-type units of steel truss arch bridge | |
CN217352586U (en) | Novel assembled platform system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |