CN217536680U - Be used for pre-buried positioning tool of bridge beam supports bolt - Google Patents

Be used for pre-buried positioning tool of bridge beam supports bolt Download PDF

Info

Publication number
CN217536680U
CN217536680U CN202220827814.2U CN202220827814U CN217536680U CN 217536680 U CN217536680 U CN 217536680U CN 202220827814 U CN202220827814 U CN 202220827814U CN 217536680 U CN217536680 U CN 217536680U
Authority
CN
China
Prior art keywords
plate
locating
sleeve
bolt
positioning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220827814.2U
Other languages
Chinese (zh)
Inventor
黄威
王立国
蔡婷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
China First Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China First Metallurgical Group Co Ltd filed Critical China First Metallurgical Group Co Ltd
Priority to CN202220827814.2U priority Critical patent/CN217536680U/en
Application granted granted Critical
Publication of CN217536680U publication Critical patent/CN217536680U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

A positioning tool for pre-embedding a bridge support bolt relates to the field of bridge construction. This be used for pre-buried positioning tool of bridge beam supports bolt includes the connecting plate, first locating plate and second locating plate, the connecting plate, the regulation hole that extends along its length direction is seted up to first locating plate and second locating plate, first locating hole and second locating hole, the middle part of first locating plate and second locating plate is slip the cover respectively and is equipped with first sleeve and second sleeve, the connecting plate is connected with two connecting bolt that can follow the regulation hole removal, two connecting bolt rotatably run through first sleeve and second sleeve respectively after pass first locating hole and second locating hole and be connected with coupling nut, the both ends of first locating plate and second locating plate are connected with the double-screw bolt that can follow first locating hole and second locating hole removal respectively, the double-screw bolt is connected with set nut. A positioning tool for bridge beam supports bolt is pre-buried can carry out support bolt location fast high-efficiently and pre-buried to practice thrift the manpower and improve the efficiency of construction.

Description

Be used for pre-buried positioning tool of bridge beam supports bolt
Technical Field
The application relates to the field of bridge construction, in particular to a positioning tool for pre-embedding a bridge support bolt.
Background
In the construction process of a bridge, a support base stone is constructed prior to the installation of a bridge support, the common embedding mode of the support base stone bolt in the current construction process is that PVC pipe fittings with the same diameter are respectively and independently fixed on a support base stone reinforcement framework for reserving or embedding support base bolt holes, the quality of the installation and the construction of the bridge support is seriously influenced because of the uneven construction level of constructors, large volume of a single support, large quality, inconvenience in trying to reserve holes and the like, and the positions are required to be manually measured one by one during the construction by adopting the method, so that the positioning is slow, the influence factors are extremely large, the disturbance of the PVC embedded pipe fittings or the support base bolts is easily caused in the concrete pouring process of the support base stone, the difficulty of the support base installation is increased, even the reworking treatment is required, and the construction quality of the support base stone and the support base installation is greatly influenced.
Disclosure of Invention
An object of this application provides a positioning tool for bridge beam supports bolt is pre-buried, and it can carry out support bolt location pre-buried fast high-efficiently to practice thrift the manpower and improve the efficiency of construction, guarantee the support installation quality.
The embodiment of the application is realized as follows:
the application provides a positioning tool for bridge beam supports bolt is pre-buried, it includes connecting plate and parallel arrangement's first locating plate and second locating plate, the regulation hole that extends along its length direction is seted up to the connecting plate, first locating plate and second locating plate are equipped with first locating hole and the second locating hole that extends along length direction respectively, the middle part of first locating plate and second locating plate is the slip cap respectively and is equipped with first sleeve and second sleeve, the connecting plate is connected with two connecting bolt that can follow the regulation hole and remove, two connecting bolt pass corresponding first locating hole and second locating hole and be connected with coupling nut after rotatably running through first sleeve and second sleeve respectively through the screw thread, the both ends of first locating plate and second locating plate are connected with the hollow double-screw bolt that can follow first locating hole and second locating hole removal respectively, the double-screw bolt is connected with positioning nut after passing corresponding first locating hole and second locating hole.
In some optional embodiments, the connecting plate is sleeved with a first rotating sleeve and a second rotating sleeve, and two connecting bolts respectively penetrate through the first rotating sleeve and the second rotating sleeve in a rotatable mode through threads.
In some optional embodiments, the two connecting bolts are respectively connected with a limiting ball head at one end far away from the connecting nut.
In some alternative embodiments, the first rotating sleeve and the second rotating sleeve are each provided with a level bubble.
In some alternative embodiments, the connection plate is provided with a first scale extending along its length.
In some alternative embodiments, the first positioning plate and the second positioning plate are respectively provided with a second scale extending along the length direction thereof.
The beneficial effect of this application is: the application provides a positioning tool for bridge beam supports bolt is pre-buried includes connecting plate and parallel arrangement's first locating plate and second locating plate, the regulating hole that extends along its length direction is seted up to the connecting plate, first locating plate and second locating plate are equipped with first locating hole and the second locating hole that extends along length direction respectively, the middle part of first locating plate and second locating plate is the slip cap respectively and is equipped with first sleeve and second sleeve, the connecting plate is connected with two connecting bolt that can follow the regulating hole and remove, two connecting bolt pass corresponding first locating hole and second locating hole and are connected with coupling nut after rotatably running through first sleeve and second sleeve respectively through the screw thread, the both ends of first locating plate and second locating plate are connected with the hollow double-screw bolt that can follow first locating hole and second locating hole removal respectively, the double-screw bolt is connected with set nut after passing corresponding first locating hole and second locating hole. The application provides a positioning tool for bridge beam supports bolt is pre-buried can carry out support bolt location high efficiency ground pre-buried to practice thrift the manpower and improve the efficiency of construction, guarantee the support installation quality.
Drawings
To more clearly illustrate the technical solutions of the embodiments of the present application, the drawings needed in the embodiments will be briefly described below, it should be understood that the following drawings only illustrate some embodiments of the present application and therefore should not be considered as limiting the scope, and those skilled in the art can also obtain other related drawings based on the drawings without inventive efforts.
Fig. 1 is a schematic structural view of a first view angle of a positioning tool for embedding a bridge support bolt provided in an embodiment of the present application;
fig. 2 is a schematic structural diagram of a second view angle of the positioning tool for embedding a bridge support bolt provided in the embodiment of the present application;
fig. 3 is a schematic structural diagram of a third view angle of the positioning tool for embedding a bridge support bolt provided in the embodiment of the present application;
in the figure: 100. a connecting plate; 110. a first positioning plate; 120. a second positioning plate; 130. an adjustment hole; 140. a first positioning hole; 150. a second positioning hole; 160. a first sleeve; 170. a second sleeve; 180. a connecting bolt; 190. a connecting nut; 200. a stud; 210. positioning a nut; 220. a first rotating sleeve; 230. a second rotating sleeve; 240. a limiting ball head; 250. Horizontally soaking; 260. a support bolt; 270. a first scale; 280. and a second scale.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present application clearer, the technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the drawings in the embodiments of the present application, and it is obvious that the described embodiments are some embodiments of the present application, but not all embodiments. The components of the presently disclosed embodiments, as generally described and illustrated in the figures herein, may be arranged and designed in a wide variety of different configurations.
Thus, the following detailed description of the embodiments of the present application, as presented in the figures, is not intended to limit the scope of the claimed application, but is merely representative of selected embodiments of the application. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present application.
It should be noted that: like reference numbers and letters refer to like items in the following figures, and thus, once an item is defined in one figure, it need not be further defined and explained in subsequent figures.
In the description of the present application, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings or orientations or positional relationships that the products of the application usually place when in use, and are used only for convenience in describing the present application and simplifying the description, but do not indicate or imply that the devices or elements being referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present application. Furthermore, the terms "first," "second," "third," and the like are used solely to distinguish one from another and are not to be construed as indicating or implying relative importance.
Furthermore, the terms "horizontal", "vertical", "overhang" and the like do not imply that the components are required to be absolutely horizontal or overhang, but may be slightly inclined. For example, "horizontal" merely means that the direction is more horizontal than "vertical" and does not mean that the structure must be perfectly horizontal, but may be slightly inclined.
In the description of the present application, it is further noted that, unless expressly stated or limited otherwise, the terms "disposed," "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning either a fixed connection, a removable connection, or an integral connection; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present application can be understood in a specific case by those of ordinary skill in the art.
In this application, unless expressly stated or limited otherwise, the first feature "on" or "under" the second feature may comprise direct contact of the first and second features, or may comprise contact of the first and second features not directly but through another feature in between. Also, the first feature being "on," "above" and "over" the second feature includes the first feature being directly on and obliquely above the second feature, or merely indicating that the first feature is at a higher level than the second feature. A first feature being "under," "below," and "beneath" a second feature includes the first feature being directly under and obliquely below the second feature, or simply meaning that the first feature is at a lesser elevation than the second feature.
The characteristics and performance of the positioning tool for embedding the bridge bearing bolt of the present application are further described in detail with reference to the following embodiments.
As shown in fig. 1, 2 and 3, an embodiment of the present application provides a positioning tool for pre-embedding a bridge beam anchor bolt, which includes a connecting plate 100, and a first positioning plate 110 and a second positioning plate 120 that are arranged in parallel, where the connecting plate 100 is provided with a first scale 270 extending along a length direction of the connecting plate, the first positioning plate 110 and the second positioning plate 120 are respectively provided with a second scale 280 extending along a length direction of the connecting plate, the connecting plate 100 is provided with an adjusting hole 130 extending along a length direction of the connecting plate, the first positioning plate 110 and the second positioning plate 120 are respectively provided with a first positioning hole 140 and a second positioning hole 150 extending along a length direction of the connecting plate, a first sleeve 160 and a second sleeve 170 are respectively slidably sleeved on middle portions of the first positioning plate 110 and the second positioning plate 120, a first rotating sleeve 220 and a second rotating sleeve 230 are sleeved on the connecting plate 100, the connecting plate 100 is connected with two connecting bolts 180 capable of moving along the adjusting hole 130, one end of each connecting bolt 180 respectively penetrates through the first rotating sleeve 220 and the second rotating sleeve 230 in a rotatable manner through a thread, then penetrates through the first sleeve 160 and the second sleeve 170, then penetrates through the corresponding first positioning hole 140 and the second positioning hole 150, and is connected with a connecting nut 190, the other end of each connecting bolt respectively penetrates through the first rotating sleeve 220 and the second rotating sleeve 230 in a rotatable manner through a thread, then is connected with a limiting ball head 240, two ends of the first positioning plate 110 and the second positioning plate 120 are respectively connected with hollow studs 200 capable of moving along the first positioning hole 140 and the second positioning hole 150, the studs 200 penetrate through the corresponding first positioning hole 140 and the second positioning hole 150 and are connected with positioning nuts 210, and the first rotating sleeve 220 and the second rotating sleeve 230 are respectively provided with horizontal bubbles 250.
The application provides a positioning tool for bridge beam supports bolt is pre-buried uses as follows:
when binding a support base cushion skeleton steel bar, attaching a connecting plate 100 of a positioning tool for embedding a bridge support base bolt and a first positioning plate 110 and a second positioning plate 120 which are arranged in parallel to a support base for adjustment, adjusting a horizontal bubble 250 arranged on a first rotating sleeve 220 and a second rotating sleeve 230 to be horizontal so as to ensure that the first positioning plate 110 and the second positioning plate 120 are horizontally arranged and attached to the support base, then loosening two connecting nuts 190, sliding the first rotating sleeve 220 and the second rotating sleeve 230 along an adjusting hole 130 to determine a transverse distance, rotating a first sleeve 160 and a second sleeve 170 connected with the first rotating sleeve 220 and the second rotating sleeve 230, adjusting a horizontal angle between the first positioning plate 110 and the second positioning plate 120 and the connecting plate 100 and screwing the connecting nuts 190, then loosening four positioning nuts 210 and moving the studs 200 along the first positioning hole 140 and the second positioning hole 150 to determine a longitudinal distance, aligning four studs 200 to preset positions of the bolt on the support base respectively, and then screwing the connecting nuts 190 and the positioning nuts 210.
After the installation of the binding support base cushion stone template is completed, a positioning tool for embedding bridge support base bolts is placed on the inner side of the support base cushion stone template, the four support base bolts 260 are respectively inserted into and penetrate through the studs 200, the four support base bolts 260 are positioned at the preset positions of the support base bolts of the support base cushion stone, and the support base cushion stone framework reinforcing steel bars are adjusted to avoid the support base bolts 260.
When the support cushion stone concrete pouring is carried out, the positioning tool for pre-embedding the bridge support bolts is moved away, the tool is placed after the support cushion stone concrete pouring is finished, the horizontal bubble 250 of the adjusting tool is horizontal to the horizontal, so that the first positioning plate 110 and the second positioning plate 120 are horizontally arranged and attached to the top surface of the support cushion stone concrete, the four support bolts 260 are respectively inserted into and penetrate through the studs 200 and are inserted into the support cushion stone concrete, and the four support bolts 260 are positioned at the preset positions of the support bolts of the support cushion stone.
The application provides a positioning tool for bridge beam supports bolt is pre-buried can carry out the support bolt location of different models fast high-efficiently, and easy operation, easily carry. The connecting plate 100 is provided with a first scale 270 extending along the length direction thereof, the first positioning plate 110 and the second positioning plate 120 are respectively provided with a second scale 280 extending along the length direction thereof, and the first scale 270 and the second scale 280 can help an operator to quickly position the relative positions between the connecting plate 100 and the first positioning plate 110 and the second positioning plate 120, so that the positioning is facilitated.
The embodiments described above are some, but not all embodiments of the present application. The detailed description of the embodiments of the present application is not intended to limit the scope of the claimed application, but is merely representative of selected embodiments of the application. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present application.

Claims (6)

1. The utility model provides a positioning tool for bridge beam supports bolt is pre-buried which characterized in that, it includes connecting plate and parallel arrangement's first locating plate and second locating plate, the adjusting hole that extends along its length direction is seted up to the connecting plate, first locating plate with the second locating plate is equipped with first locating hole and second locating hole that extends along length direction respectively, the middle part of first locating plate with the second locating plate is the slip cap respectively and is equipped with first sleeve and second sleeve, the connecting plate is connected with two connecting bolt that can follow the adjusting hole removal, two connecting bolt passes through respectively through the screw thread is rotatable first sleeve with pass behind the second sleeve corresponding first locating hole with the second locating hole and be connected with coupling nut, the both ends of first locating plate and second locating plate are connected with respectively can follow the hollow double-screw bolt that first locating hole and second locating hole removed, the double-screw bolt passes corresponding first locating hole with be connected with coupling nut behind the second locating hole.
2. The positioning tool for embedding the bridge support bolt according to claim 1, wherein a first rotating sleeve and a second rotating sleeve are sleeved on the connecting plate, and the two connecting bolts respectively penetrate through the first rotating sleeve and the second rotating sleeve in a rotatable mode through threads.
3. The positioning tool for embedding the bridge support bolt according to claim 2, wherein one ends of the two connecting bolts, which are far away from the connecting nut, are respectively connected with a limiting ball head.
4. The positioning tool for embedding the bridge support bolt according to claim 2, wherein horizontal bubbles are respectively arranged on the first rotating sleeve and the second rotating sleeve.
5. The positioning tool for embedding the bridge support bolt according to claim 1, wherein the connecting plate is provided with a first scale extending along the length direction of the connecting plate.
6. The positioning tool for embedding the bridge support bolt according to claim 1, wherein the first positioning plate and the second positioning plate are respectively provided with second scales extending along the length direction of the first positioning plate and the second positioning plate.
CN202220827814.2U 2022-04-06 2022-04-06 Be used for pre-buried positioning tool of bridge beam supports bolt Active CN217536680U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220827814.2U CN217536680U (en) 2022-04-06 2022-04-06 Be used for pre-buried positioning tool of bridge beam supports bolt

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220827814.2U CN217536680U (en) 2022-04-06 2022-04-06 Be used for pre-buried positioning tool of bridge beam supports bolt

Publications (1)

Publication Number Publication Date
CN217536680U true CN217536680U (en) 2022-10-04

Family

ID=83430465

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220827814.2U Active CN217536680U (en) 2022-04-06 2022-04-06 Be used for pre-buried positioning tool of bridge beam supports bolt

Country Status (1)

Country Link
CN (1) CN217536680U (en)

Similar Documents

Publication Publication Date Title
CN209636847U (en) A kind of adjustable tower crane built-in fitting accurate positioning tool
CN105040717B (en) Foundation bolt fixing support and installation method
CN102061746B (en) Steel structure assembled embedded part and construction method thereof
CN102561712B (en) Precise positioning frame for large steel columns and equipment foundation fixing bolts and construction method of precise positioning frame
CN204225145U (en) A kind of simple and easy orientation tool for basic embedding anchor bolts
CN106760495B (en) A kind of floor construction method
CN110984397A (en) Self-adjusting building embedded part and embedding method thereof
CN205530322U (en) Fixed steel column foot pre -cast screw's construction equipment
CN204849798U (en) Rag bolt fixed bolster
CN210032663U (en) Positioning device for steel embedded part of batter post
CN204510019U (en) A kind of ramp down angle tall pier and thin wall calf support
CN217536680U (en) Be used for pre-buried positioning tool of bridge beam supports bolt
CN106602984A (en) Photovoltaic support stand column or pile foundation elevation adjusting device and construction method thereof
CN212224683U (en) Positioning device for pre-buried foundation bolt
CN109763572B (en) Device for quickly adjusting embedded verticality of foundation bolt group and operation method of device
CN207847086U (en) A kind of tall and big beam form support frame
CN109440809A (en) A kind of Construction of Steel Structure pre-embedded bolt protective device
CN206189607U (en) Rag bolt location structure
CN109914820A (en) Portable high-accuracy absolute altitude installation of embedded parts tool
CN212507456U (en) A construction appurtenance for concrete thickness control
CN2366484Y (en) Adjustable type supporting apparatus structure able to be early dismantlement
CN212002272U (en) Bidirectional adjustable frame beam template clamp structure
CN208056549U (en) A kind of ultra-flat terrace construction joint formwork also serving as the pneumatic bridge guide rail that shakes
CN110439273A (en) A kind of mold and installation method of telescopic production slope monitoring clump pedestal
CN203923915U (en) The prepared hole die of bridge stone bolt

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant