CN217500201U - Hammering steel pipe pile construction system - Google Patents
Hammering steel pipe pile construction system Download PDFInfo
- Publication number
- CN217500201U CN217500201U CN202221051690.XU CN202221051690U CN217500201U CN 217500201 U CN217500201 U CN 217500201U CN 202221051690 U CN202221051690 U CN 202221051690U CN 217500201 U CN217500201 U CN 217500201U
- Authority
- CN
- China
- Prior art keywords
- pile
- steel pipe
- pipe pile
- tip
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
The utility model provides a steel pipe pile hammering construction system, which comprises a steel pipe pile tip, an outer sleeve, a cylindrical hammer, a fixed pulley, a steel wire rope, a pile frame and a winch; an outer sleeve is welded on the top of the pile tip of the steel pipe pile, and high-strength grouting material with a preset height is paved at the bottom in the pile tip of the steel pipe pile; an existing building is provided with a pile hole, and the pile tip of a steel pipe pile is placed in the pile hole; the pile frame is arranged beside the pile hole, and the fixed pulley is arranged on the pile frame; the steel wire rope is erected on the fixed pulley, one end of the steel wire rope is connected with the winch, and the other end of the steel wire rope is connected with the cylindrical hammer; the columnar hammer is arranged right above the pile tip of the steel pipe pile, and the diameter of the columnar hammer is smaller than the inner diameter of the pile tip of the steel pipe pile. The utility model discloses a hammer steel-pipe pile construction system, under the limited circumstances in job site space or under the existing building can't provide sufficient counter-force or can't provide the condition of counter-force at all, still can carry out the steel-pipe pile sinking construction.
Description
Technical Field
The utility model relates to a building engineering technical field especially relates to a hammer steel-pipe pile construction system.
Background
At present, most of existing buildings are subjected to foundation reinforcement by anchor rod static pressure piles for construction, and the existing buildings are required to provide sufficient counter force for the construction of the anchor rod static pressure piles.
But to most old-fashioned buildings, can't provide the counter-force at all, if adopt with pre-buried stock after the original basis is abolished, newly-increased raft's method, not only can have the risk that causes secondary destruction to existing building structure safety, newly-increased raft still has intensity not enough risk of being pulled apart moreover.
Under the condition that the existing building cannot provide enough counter force or cannot provide counter force at all, how to efficiently, quickly and safely carry out the construction of reinforcing the foundation of the existing building is still to be solved.
Disclosure of Invention
In order to overcome the defects in the prior art, the utility model provides a hammering steel pipe pile construction system, which can carry out steel pipe pile sinking construction under the condition of limited space of a construction site; when the existing building can not provide enough counter force or can not provide counter force at all, the steel pipe pile sinking construction can be carried out.
In order to achieve the purpose, the utility model provides a steel pipe pile hammering construction system, which comprises a steel pipe pile tip, a plurality of outer sleeves, a cylindrical hammer, a plurality of fixed pulleys, a steel wire rope, a pile frame and a winding machine; the outer sleeve is welded to the top of the pile tip of the steel pipe pile, and high-strength grouting material with preset height is paved at the bottom in the pile tip of the steel pipe pile; an existing building is provided with a pile hole, and the pile tip of the steel pipe pile is placed in the pile hole; the pile frame is arranged beside the pile hole, and the fixed pulley is arranged on the pile frame; the steel wire rope is erected on the fixed pulley, one end of the steel wire rope is connected with the winch, and the other end of the steel wire rope is connected with the cylindrical hammer; the columnar hammer is arranged right above the pile tip of the steel pipe pile, and the diameter of the columnar hammer is smaller than the inner diameter of the pile tip of the steel pipe pile.
Preferably, the device also comprises a guide rod and an ejection device; the guide rod is arranged along the central axis of the pile tip of the steel pipe pile, and the top end of the guide rod is connected to the pile frame; a guide hole is formed in the middle of the cylindrical hammer and is freely and slidably sleeved outside the guide rod through the guide hole; the ejection device is fixed on the pile frame or the guide rod right above the cylindrical hammer.
Preferably, a plurality of subsequent piles are further included; the subsequent pile section at the bottommost part is welded with the pile tip of the steel pipe pile through the outer sleeve; when the pile comprises at least two subsequent piles, the adjacent two subsequent piles are welded through the outer sleeve.
Preferably, the preset height is 50 cm.
The utility model discloses owing to adopted above technical scheme, make it have following beneficial effect:
through the matching of the pile tip of the steel pipe pile, the cylindrical hammer, the steel wire rope and the winch; the utility model discloses require extremely low to experimental place space, do not receive the place space restriction, under the limited condition in existing building basement space, can carry out existing building foundation reinforcement construction. Just the utility model discloses need not to carry on pre-buried, after plant the stock or newly-increased raft board, application range is wider, especially to the existing building foundation reinforcement that can't provide sufficient counter-force or can't provide the counter-force at all more suitable, can accomplish the steel-pipe pile construction that the stock static pressure construction method can't be accomplished, safe and reliable.
The utility model discloses be different from general hammering steel-pipe pile construction method, be provided with jettison device, can provide different initial velocities for the cylindricality hammer, can receive great impact force when the initial soil body that gets into of steel-pipe pile.
The utility model discloses the whereabouts direction of control weight that the guide arm can be fine, the stake point atress is even, also can effectually guarantee the steel-pipe pile straightness that hangs down simultaneously.
The pile tip is filled with high-strength grouting material, so that the strength of the pile tip is enhanced, and the pile tip and the pile body are prevented from being separated.
Drawings
Fig. 1 is a schematic structural view of a hammered steel pipe pile construction system in a first construction state according to an embodiment of the present invention;
fig. 2 is the utility model discloses a hammering steel-pipe pile construction system's of second construction state structural schematic diagram.
Detailed Description
The following description of the preferred embodiments of the present invention will be given with reference to the accompanying drawings, fig. 1 and 2, and will make the functions and features of the present invention better understood.
Referring to fig. 1 and 2, a steel pipe pile hammering construction system according to an embodiment of the present invention includes a steel pipe pile toe 1, a plurality of outer sleeves 4, a cylindrical hammer 6, a plurality of fixed pulleys 8, a steel wire rope 9, a pile frame 10, and a winch 11; an outer sleeve 4 is welded on the top of the steel pipe pile tip 1, and a high-strength grouting material 2 with a preset height of 50cm is laid at the bottom in the steel pipe pile tip 1; an existing building is provided with a pile hole 3, and a pile tip 1 of a steel pipe pile is placed in the pile hole 3; the pile frame 10 is arranged beside the pile hole 3, and the fixed pulley 8 is arranged on the pile frame 10; the steel wire rope 9 is erected on the fixed pulley 8, one end of the steel wire rope 9 is connected with the winch 11, and the other end of the steel wire rope 9 is connected with the cylindrical hammer 6; the columnar hammer 6 is arranged right above the steel pipe pile tip 1, and the diameter of the columnar hammer 6 is smaller than the inner diameter of the steel pipe pile tip 1.
The ejection device also comprises a guide rod 5 and an ejection device 7; the guide rod 5 is arranged along the central axis of the pile tip 1 of the steel pipe pile, and the top end of the guide rod is connected to the pile frame 10; a guide hole is formed in the middle of the cylindrical hammer 6 and is freely and slidably sleeved outside the guide rod 5 through the guide hole; the ejection device 7 is fixed on the pile frame 10 or the guide rod 5 right above the cylindrical hammer 6.
Also comprises a plurality of subsequent piles 12; a subsequent pile section 12 at the bottommost part is welded with the pile tip 1 of the steel pipe pile through the outer sleeve 4; when at least two subsequent piles 12 are included, two adjacent subsequent piles 12 are welded by an outer sleeve 4.
The utility model discloses hammer steel-pipe pile construction system, its construction method is as follows:
(1) pile tip manufacturing and processing
Referring to fig. 1, a pile tip 1 of the steel pipe pile is manufactured, and an outer sleeve 4 is welded; paving 50cm of high-strength grouting material 2 at the bottom of the pile tip 1 of the steel pipe pile, and maintaining to the designed strength;
(2) bottom plate opening
(3) pile sinking equipment installation
Installing a pile frame 10 of pile sinking equipment beside a corresponding pile hole 3, and synchronously installing a fixed pulley 8, a steel wire rope 9, a winch 11, an ejection device 7 and a cylindrical hammer 6;
(4) pile tip positioning
Putting the processed steel pipe pile tip 1 into the drilled pile hole 3, installing a guide rod 5, and adjusting the verticality;
(5) pile sinking
In the pile sinking process, a constructor operates the winch 11, the cylindrical hammer 6 obtains a certain initial speed through the ejection device 7, and the cylindrical hammer 6 impacts the high-strength grouting material through the guide rod 5 to enable the pile tip 1 of the steel pipe pile to move downwards; then, operating the winch 11, resetting the cylindrical hammer 6 through the steel wire rope 9, repeating the operation, completing pile sinking of the pile tip 1 of the steel pipe pile, and increasing the length of the guide rod 5 in real time according to actual conditions in the pile sinking process;
(6) pile hanging and splicing
And hoisting the subsequent pile sections 12 to the position right above the pile tip 1 of the steel pipe pile, and welding the subsequent pile sections with the pile tip 1 of the steel pipe pile through the outer sleeve 4.
(7) Pile hanging and splicing
Repeating the step (5) to finish the pile sinking of the subsequent pile sections 12; and (5) sequentially repeating the step (6) and the step (5) to finish the pile sinking of the subsequent pile sections 12 until the designed pile length is reached, and finishing the pile sinking.
The present invention has been described in detail with reference to the embodiments shown in the drawings, and those skilled in the art can make various modifications to the present invention based on the above description. Therefore, certain details of the embodiments should not be construed as limitations of the invention, which are intended to be covered by the following claims.
Claims (4)
1. A steel pipe pile hammering construction system is characterized by comprising a steel pipe pile tip, a plurality of outer sleeves, a cylindrical hammer, a plurality of fixed pulleys, a steel wire rope, a pile frame and a winding machine; the outer sleeve is welded to the top of the pile tip of the steel pipe pile, and high-strength grouting material with preset height is paved at the bottom in the pile tip of the steel pipe pile; an existing building is provided with a pile hole, and the pile tip of the steel pipe pile is placed in the pile hole; the pile frame is arranged beside the pile hole, and the fixed pulley is arranged on the pile frame; the steel wire rope is erected on the fixed pulley, one end of the steel wire rope is connected with the winch, and the other end of the steel wire rope is connected with the cylindrical hammer; the columnar hammer is arranged right above the pile tip of the steel pipe pile, and the diameter of the columnar hammer is smaller than the inner diameter of the pile tip of the steel pipe pile.
2. The hammered steel pipe pile construction system according to claim 1, further comprising a guide rod and an ejector; the guide rod is arranged along the central axis of the pile tip of the steel pipe pile, and the top end of the guide rod is connected to the pile frame; a guide hole is formed in the middle of the cylindrical hammer and is freely and slidably sleeved outside the guide rod through the guide hole; the ejection device is fixed on the pile frame or the guide rod right above the cylindrical hammer.
3. The hammered steel pipe pile construction system according to claim 2, further comprising a plurality of subsequent sections of piles; the subsequent pile section at the bottommost part is welded with the pile tip of the steel pipe pile through the outer sleeve; when the pile comprises at least two subsequent piles, the adjacent two subsequent piles are welded through the outer sleeve.
4. The hammered steel pipe pile construction system according to claim 3, wherein the preset height is 50 cm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202221051690.XU CN217500201U (en) | 2022-05-05 | 2022-05-05 | Hammering steel pipe pile construction system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202221051690.XU CN217500201U (en) | 2022-05-05 | 2022-05-05 | Hammering steel pipe pile construction system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN217500201U true CN217500201U (en) | 2022-09-27 |
Family
ID=83351563
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202221051690.XU Active CN217500201U (en) | 2022-05-05 | 2022-05-05 | Hammering steel pipe pile construction system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN217500201U (en) |
-
2022
- 2022-05-05 CN CN202221051690.XU patent/CN217500201U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107217910A (en) | Supply line's electric pole plants lever apparatus and its plants bar method | |
CN102425166A (en) | Novel pile driving method and equipment for foundation construction treatment | |
CN102654056A (en) | Shield construction method for clearing obstacles by punching rock stratum section | |
CN107700479A (en) | A kind of construction method of large diameter drill hole pile | |
US5359829A (en) | Fabrication and installation of steel reinforcement cages for pier foundations | |
CN217500201U (en) | Hammering steel pipe pile construction system | |
CN202247878U (en) | Novel piling equipment for foundation construction | |
CN106948347A (en) | Pile extracting method and pile pulling system | |
CN117328454A (en) | Method for limiting ultra-long prestressed pipe pile in complex sea-filling land area and sinking pile by hydraulic ram | |
KR20170034801A (en) | pile driver for ground reinforcement pipe | |
CN115142418B (en) | Non-vibration tube drawing anti-cage device for immersed tube filling pile and construction method thereof | |
CN114592517B (en) | Pile body dead weight hammering construction process with enlarged pile shoe | |
US6641333B2 (en) | Method of forming enlarged pile heads | |
KR100474184B1 (en) | Hitting machine to drive sheet pile deeply using auger | |
KR101416865B1 (en) | Construction method of screw file | |
CN112095601A (en) | Steel pipe pile pipe bottom hammering construction method | |
CN106836223B (en) | Pile pulling method | |
EP0084921A1 (en) | Piles | |
JP3760365B2 (en) | Core material erection device | |
CN213741058U (en) | Steel-pipe pile tube bottom hammering construction equipment | |
JP2000154538A (en) | Plumb bob type device for driving steel pipe in inner moat and plumb bob type construction method of driving steel pipe in inner moat | |
CN109989394A (en) | A kind of cast-in-place concrete pile section stake partition and its construction method | |
EP0246046A1 (en) | Support for building structures | |
CN111576396B (en) | Anchor rod type manual hole digging pile and construction method thereof | |
CN111455980B (en) | Prefabricated anti-floating pile structure suitable for underground engineering and construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |