CN217460918U - Hanging device for self-balancing equipment - Google Patents
Hanging device for self-balancing equipment Download PDFInfo
- Publication number
- CN217460918U CN217460918U CN202221533636.9U CN202221533636U CN217460918U CN 217460918 U CN217460918 U CN 217460918U CN 202221533636 U CN202221533636 U CN 202221533636U CN 217460918 U CN217460918 U CN 217460918U
- Authority
- CN
- China
- Prior art keywords
- self
- arc
- column
- hanging device
- balancing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model provides a device is established to self-balancing equipment string, including arc post, stand, back timber and crossbeam. Wherein, the stand is connected respectively at the both ends of arc post, forms the arched frame unit. The number of the arch frame units is at least two, the upright posts of the adjacent arch frame units are connected through the cross beam, and the highest points of the arc posts of the adjacent arch frame units are connected through the top beam. At least one of the arc-shaped columns, the upright columns, the top beams and the cross beams is provided with an installation position for connecting equipment. The self-balancing equipment hanging device is arranged inside the historic site building and has a certain gap with the inner wall surface. The device is integrally placed on the ground, so that damage to a wall body and the ground caused by a traditional fixing mode is avoided, site buildings can be protected, and requirements for hanging and establishing equipment can be met.
Description
Technical Field
The utility model belongs to the technical field of building protection and equipment are built, in particular to self-balancing equipment is hung and is established device.
Background
Along with the continuous development of social economy, the demand of spiritual culture is flourishing day by day, and the ruined building is being combined with modern technologies such as projection, radar and the like as the important embodiment of national traditional culture, and more abundant and various display forms are created. Compared with the modern buildings, the historic site buildings are usually in arch coupon structures, the arch space of the historic site buildings cannot be fixed at the cost of damaging walls or the ground due to cultural protection requirements, and the facility equipment is difficult to be directly fixed on the historic site buildings for use.
Therefore, how to meet the requirement of hanging and installing equipment on the premise of not damaging a building is a key technical problem to be solved urgently by technical personnel in the field.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a self-balancing equipment is hung and is established device under the prerequisite of not destroying the building, can realize that equipment hangs the installation demand.
In order to solve the technical problem, the utility model provides a self-balancing equipment is hung and is established device, include: the device comprises an arc-shaped column, a vertical column, a top beam and a cross beam;
the two ends of the arc-shaped column are respectively connected with the upright column to form an arch-shaped frame unit;
the number of the arched frame units is at least two, the upright columns of the adjacent arched frame units are connected through the cross beam, and the highest points of the arc-shaped columns of the adjacent arched frame units are connected through the top beam;
at least one of the arc-shaped column, the upright column, the top beam and the cross beam is provided with an installation position for connecting equipment;
the self-balancing equipment hanging device is arranged inside the historic site building and has a gap with the inner wall surface.
Optionally, in the self-balancing device hanging apparatus, an arc-shaped column reinforcing beam is arranged on an arc-shaped column in each of the arch frame units;
and/or a post reinforcement beam is positioned between two posts in each of the gantry units.
Optionally, in the self-balancing device hanging device, a cushion is arranged at the bottom end of the upright post.
Optionally, in the self-balancing device hanging apparatus, the mounting position includes a mounting hole, a lifting ring, a buckle, and/or a mounting table.
Optionally, in the self-balancing device hanging apparatus, at least one of the arc-shaped column, the upright column, the top beam, and the cross beam has a hollow cavity for accommodating a device cable.
Optionally, in the self-balancing device hanging apparatus, the upright is a length-adjustable structure.
Optionally, in the self-balancing device hanging device, the beam column of the self-balancing device hanging device is a channel steel.
Optionally, in the self-balancing device hanging device, the beams and the columns in the self-balancing device hanging device are connected by splicing, bolts, buckles or welding.
The utility model provides a device is established to self-balancing equipment string, its beneficial effect lies in:
through the setting, the self-balancing equipment is hung and is established the device and can press close to the wall of ruined building in arch coupon building structure, and direct contact not, does not destroy the building, has effectively provided the supporting role to realize the installation demand of hanging of modern equipment and cable.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required to be used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the provided drawings without creative efforts.
Fig. 1 is the utility model provides a pair of self-balancing equipment hangs and establishes the structural schematic diagram of device.
In the upper drawing:
1-upright column; 2-arc column; 3-a cross beam; 4-arc column reinforcing beam; 5-upright post reinforcing beam; 6-top beam; 7-soft cushion.
Detailed Description
Reference will now be made in detail to embodiments of the present invention, examples of which are illustrated in the accompanying drawings, wherein like reference numerals refer to the same or similar elements or elements having the same or similar function throughout. The embodiments described below with reference to the drawings are exemplary only for the purpose of explaining the present invention, and should not be construed as limiting the present invention.
In the description of the present invention, it should be understood that the orientation or positional relationship indicated with respect to the orientation description, such as up, down, front, rear, left, right, etc., is based on the orientation or positional relationship shown in the drawings, and is only for convenience of description and simplification of description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention.
In the description of the present invention, the meaning of a plurality is more than two, and if there is a description that the first and the second are only used for distinguishing technical features, it is not understood that the relative importance is indicated or implied or the number of the indicated technical features is implicitly indicated or the precedence of the indicated technical features is implicitly indicated.
In the description of the present invention, unless there is an explicit limitation, the words such as setting, installation, connection, etc. should be understood in a broad sense, and those skilled in the art can reasonably determine the specific meanings of the above words in combination with the specific contents of the technical solution.
The core of the utility model is to provide a self-balancing equipment is hung and is established the device, under the prerequisite that does not destroy the building, can realize that equipment hangs the installation demand.
In order to make those skilled in the art better understand the technical solutions provided by the present invention, the present invention will be further described in detail with reference to the accompanying drawings and specific embodiments.
Referring to fig. 1, fig. 1 is a schematic structural diagram of a self-balancing device hanging apparatus provided in the present invention.
The utility model provides a self-balancing equipment is hung and is established device, including arc post 2, stand 1, back timber 6 and crossbeam 3.
Wherein, the two ends of the arc column 2 are respectively connected with the upright posts 1 to form an arch frame unit.
The number of the arch frame units is at least two, the upright posts 1 of the adjacent arch frame units are connected through the cross beam 3, and the highest points of the arc posts 2 of the adjacent arch frame units are connected through the top beam 6.
At least one of the curved columns 2, the uprights 1, the top beams 6 and the cross beams 3 is provided with a mounting location for connecting equipment.
The self-balancing equipment hanging device is arranged inside the historic site building and has a certain gap with the inner wall surface. The device is integrally placed on the ground, so that damage to a wall body and the ground caused by a traditional fixing mode is avoided, site buildings can be protected, and requirements for hanging and establishing equipment can be met.
Through the setting, the self-balancing equipment is hung and is established the device and can press close to the wall of ruined building in arch coupon building structure, and direct contact not, does not destroy the building, has effectively provided the supporting role to realize the installation demand of hanging of modern equipment and cable.
In a specific embodiment, the upright 1 can be made of channel steel and is placed on the ground close to an arched wall surface.
The arched frame unit is formed by connecting an arc column 2 at the upper end with a stand column 1 at the lower end, and in order to improve the structural strength of the arched frame unit, an arc column reinforcing beam 4 is arranged on the arc column 2 in a single arched frame unit, so that the structural stability is maintained under the condition of longitudinal stress of the frame structure, and meanwhile, equipment can be hung. An upright post reinforcing beam 5 is arranged between two upright posts 1 in a single arched frame unit, and the arc-shaped post reinforcing beam 4 and the upright post reinforcing beam 5 are both equivalent to longitudinal beams. The cross beam and the longitudinal beam realize the reinforcing effect in a three-dimensional space.
Of course, the choice of whether to install the reinforcement beam between the arc column 2 and the stud 1 on the gantry unit may be made according to the structural strength or the equipment installation requirements.
Two adjacent arch frame units are connected and fixed by a plurality of sections of cross beams 3 and top beams 6.
In order to realize the anti-skidding and stable effect, the bottom end of the upright post 1 is provided with the soft cushion 7, and the phenomenon that the upright post 1 directly contacts the ground to damage the site building can be avoided. The soft cushion 7 can be made of rubber or sponge and any material capable of playing a role in skid resistance and scratch resistance is within the protection scope of the scheme.
In a specific embodiment, one form of the mounting position is a mounting hole formed in at least one of the arc-shaped column 2, the upright column 1, the top beam 6 and the cross beam 3, and the other form of the mounting position is a hanging ring, a buckle or a mounting table connected to at least one of the arc-shaped column 2, the upright column 1, the top beam 6 and the cross beam 3. Therefore, the wall and the dome are prevented from being directly hung on the wall and the dome, and the wall and the dome are punched and fixed, so that the protective effect is achieved. Of course, the mounting locations may take one of these forms, or alternatively, may take multiple forms on different beams, including but not limited to the forms described above.
The crossbeams 3 are connected with the arched frame units, so that the number of the crossbeams 3 can be increased, the positions can be adjusted, the stability of the frame can be enhanced, and the hanging capacity of the equipment can be expanded.
For example, the beam 3 may be provided with a hole for mounting a projector, a camera, a radar, a spotlight, a display board, an art device, and the like. The width of the top beam 6 is set to be larger than that of the cross beam 3, and it can structurally function as a reinforcing structure, reinforce the connection node between the adjacent arch frame units, functionally lay cables, and install equipment on the surface thereof.
Preferably, at least one of arc post 2, stand 1, back timber 6 and crossbeam 3 has the cavity that is used for holding the equipment cable, and the equipment cable is accomodate in the cavity intracavity of beam column, can make building inner space cleaner and tidier, and the visitor is difficult for stumbling over by the cable.
In order to facilitate self-adaptive adjustment of the height of the hanging device of the self-balancing equipment according to the building height, the stand column 1 is of a length-adjustable structure, if a plurality of stand column 1 units are spliced end to end, the relative displacement of the inner pipe and the outer pipe is adjusted according to the number of the height-adjustable stand column 1 units or the connection of the inner pipe and the outer pipe, and the height adjusting function is achieved. The height change of different use scenes can be adapted by adjusting the number and the length of the straight columns.
The beam columns in the hanging device of the self-balancing device are connected through splicing, bolts, buckles or welding and the like, and the scheme includes but is not limited to the connection mode.
In a specific embodiment, the utility model discloses a self-balancing equipment that can supply equipment to articulate in ancient ruined building arch space hangs establishes device, and it specifically includes and is connected the arched frame unit that forms by multistage arc post 2 and 1 steel of linear type stand, presses close to ancient ruined building's arch passageway wall, and places in subaerially, sets up cushion 7 as fixed and protection with the ground contact. The arched framework units are fixedly connected through a plurality of groups of cross beams 3, and the cross beams 3 can be used for hanging and connecting objects such as equipment, display boards, artistic devices and the like. The top ends of the arched frame units are connected by the top beams 6, so that the structure can be reinforced, and functions of hanging equipment, lamps, arranging cables and the like can be realized. As shown in fig. 1, the three gantry units are connected by a horizontal cross beam 3 and a roof beam 6. The arched frame unit is formed by connecting multistage steel, and the accessible increases and decreases the quantity of bottom stand 1 in order to adapt to the not arch passageway of co-altitude, and the arched frame unit is semi-enclosed channel-section steel, has reserved the buckle on the steel, can be used to lay and fix the cable, and the arch steel column still reserves the trompil, can add crossbeam 3 and reinforcing beam in order to satisfy additional structure stability and add the demand of hanging the equipment of establishing. The whole frame is stressed on the building ground, stress points cannot be generated on the wall of the coupon hole and the dome, the stress points are only generated on the ground, the cushion 7 is installed on the stress points on the ground, the ground is protected, and equipment hanging and installation can be completed under the condition of protecting the original appearance of the historic site building.
The embodiments in the present description are described in a progressive manner, each embodiment focuses on differences from other embodiments, and the same and similar parts among the embodiments are referred to each other.
The principles and embodiments of the present invention have been explained herein using specific examples, and the above descriptions of the embodiments are only used to help understand the method and its core ideas of the present invention. It should be noted that, for those skilled in the art, without departing from the principle of the present invention, the present invention can be further modified and modified, and such modifications and modifications also fall within the protection scope of the appended claims.
Claims (8)
1. The utility model provides a hang from balancing equipment and establish device which characterized in that includes: the device comprises an arc-shaped column, a vertical column, a top beam and a cross beam;
two ends of the arc-shaped column are respectively connected with one upright column to form an arch-shaped frame unit;
the number of the arched frame units is at least two, the upright columns of the adjacent arched frame units are connected through the cross beam, and the highest points of the arc-shaped columns of the adjacent arched frame units are connected through the top beam;
at least one of the arc-shaped column, the upright column, the top beam and the cross beam is provided with an installation position for connecting equipment;
the self-balancing equipment hanging device is arranged inside the historic site building and has a gap with the inner wall surface.
2. The self-balancing equipment hanging device according to claim 1, wherein an arc-shaped column reinforcing beam is arranged on an arc-shaped column in each arch frame unit;
and/or a post reinforcement beam is positioned between two posts in each of the gantry units.
3. The self-balancing device hanging device according to claim 1, wherein a cushion is provided at the bottom end of the upright.
4. The hanging device for self-balancing equipment of claim 1, wherein the mounting locations comprise mounting holes, hanging rings, buckles, and/or mounting platforms.
5. The self-balancing device hanging device according to claim 1, wherein at least one of the arc-shaped column, the upright column, the top beam and the cross beam has a hollow cavity for accommodating a device cable.
6. The self-balancing equipment hanging device of claim 1, wherein the upright is a length adjustable structure.
7. The self-balancing equipment hanging device according to any one of claims 1 to 6, wherein each beam column of the self-balancing equipment hanging device is made of channel steel.
8. The self-balancing equipment hanging device according to any one of claims 1 to 6, wherein the beams and columns in the self-balancing equipment hanging device are connected through splicing, bolts, buckles or welding.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202221533636.9U CN217460918U (en) | 2022-06-17 | 2022-06-17 | Hanging device for self-balancing equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202221533636.9U CN217460918U (en) | 2022-06-17 | 2022-06-17 | Hanging device for self-balancing equipment |
Publications (1)
Publication Number | Publication Date |
---|---|
CN217460918U true CN217460918U (en) | 2022-09-20 |
Family
ID=83238584
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202221533636.9U Active CN217460918U (en) | 2022-06-17 | 2022-06-17 | Hanging device for self-balancing equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN217460918U (en) |
-
2022
- 2022-06-17 CN CN202221533636.9U patent/CN217460918U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN217460918U (en) | Hanging device for self-balancing equipment | |
CN205029274U (en) | Fixed bolster that faces cable | |
CN218509001U (en) | Flower basket type overhanging I-beam | |
CN216690295U (en) | Length-adjustable climbing frame bottom pocket rod | |
CN205282953U (en) | Assembled goods shelves of spatial structure of transformer substation | |
CN209948574U (en) | High-stability wiring rack structure | |
CN204901227U (en) | Display screen installation mount | |
CN209353660U (en) | A kind of portable electric stair shaft workbench | |
CN216240384U (en) | Operation platform assembly with ladder stand suitable for steel structure high altitude installation | |
CN216196493U (en) | Climbing frame and vertical rod connecting device for same | |
CN218581171U (en) | Back-jacking frame and supporting device | |
CN215410928U (en) | Wall-hanging for fire control unit bearing structure | |
CN220203599U (en) | Building construction protective baffle | |
CN213115414U (en) | Do benefit to steel stair platform of workman's construction | |
CN107791226A (en) | More prefabricated components double-row vertical stacking adapters | |
CN218029294U (en) | Steel construction communication computer lab that can build fast | |
CN214508358U (en) | Stable in structure's glass big-arch shelter | |
CN218970567U (en) | Metal scaffold mechanism convenient to dismouting | |
CN210976711U (en) | Double-rod overhead station with guardrail for communication box | |
CN212104879U (en) | Adjustable stair for assembly type building | |
CN220686865U (en) | Assembled high-bearing container house frame | |
CN214189379U (en) | Supporting device of electrified contact net | |
CN210713666U (en) | Clean room | |
CN215645933U (en) | Stainless steel tray type cable bridge | |
CN217479992U (en) | Portable construction stores pylon platform |