CN217424442U CN202221207550.7U CN202221207550U CN217424442U CN 217424442 U CN217424442 U CN 217424442U CN 202221207550 U CN202221207550 U CN 202221207550U CN 217424442 U CN217424442 U CN 217424442U
Authority
CN
China
Prior art keywords
early warning
wind speed
box
groove
monitoring device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221207550.7U
Other languages
Chinese (zh)
Inventor
司建斌
高莉平
赵银亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kunshan Shengang Construction and Installation Engineering Co.,Ltd.
Original Assignee
Henan Riyue Environmental Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Riyue Environmental Technology Co ltd filed Critical Henan Riyue Environmental Technology Co ltd
Priority to CN202221207550.7U priority Critical patent/CN217424442U/en
Application granted granted Critical
Publication of CN217424442U publication Critical patent/CN217424442U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Measuring Fluid Pressure (AREA)
  • Ventilation (AREA)

Abstract

The utility model discloses an air pipe blocks up early warning monitoring facilities, concretely relates to air pipe blocks up early warning monitoring field, including the box, the middle part of box is provided with early warning monitoring facilities body, and the bottom of box is provided with the wind pressure detector, and the bilateral symmetry of box is provided with the wind speed detector, and early warning monitoring facilities body and external alarm, main control system radio connection, the first dead lever of symmetry fixedly connected with around the top of box. The utility model discloses at first through the inside wind pressure of wind pressure detector detection pipeline, through the inside wind speed of wind speed detector detection pipeline, thereby judge whether the pipeline blocks up according to the size of wind pressure and wind speed, and through the wind pressure crescent, the wind speed reduces gradually, can block up the early warning to corresponding pipeline through inside early warning monitoring facilities body sends information to alarm and main control system, thereby realize the effect of monitoring, conveniently carry out accurate maintenance and maintenance to the pipeline, improve the result of use.

Description

Ventilation pipeline blocks up early warning monitoring facilities
Technical Field
The utility model relates to an air pipe blocks up early warning monitoring technology field, more specifically says, the utility model relates to an air pipe blocks up early warning monitoring facilities.
Background
The ventilation pipeline is a metal or composite pipeline for ventilation and air-conditioning engineering of industrial and civil buildings, is a municipal infrastructure for circulating air and reducing the concentration of harmful gases, and generally comprises the following components: clean system air feed back pipe, central air conditioning ventilation pipe, industry air supply and exhaust ventilation pipe, environmental protection system suction and exhaust tuber pipe, mining gas pipe, mining rubber coated cloth dryer etc, and inside in order to avoid outside debris to get into air pipe, generally can be at air pipe's both ends installation perforated plate, because air pipe's export is generally installed in the position that the people are few, when air pipe is stifled, when influencing the ventilation quality, the staff can not in time discover and accurate maintenance, influence air pipe's result of use, consequently just need an air pipe to block up early warning monitoring facilities, current pipe blockage early warning monitoring facilities is installed through the bolt rivet most directness when using, inconvenient dismantlement and maintenance, and comparatively inconvenient during the installation, influence work efficiency.
SUMMERY OF THE UTILITY MODEL
In order to overcome the above-mentioned defect of prior art, the embodiment of the utility model provides an air pipe blocks up early warning monitoring facilities, through the wind speed detector and the wind pressure detector that set up, the cooperation of first dead lever isotructure can conveniently carry out accurate maintenance and maintenance to the pipeline, and easy to assemble dismantles, improves fixed effect and work efficiency to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above purpose, the utility model provides a following technical scheme: an early warning and monitoring device for blocking of an air duct comprises a box body, wherein an early warning and monitoring device body is arranged in the middle of the box body, a wind pressure detector is arranged at the bottom of the box body, wind speed detectors are symmetrically arranged on two sides of the box body, the early warning and monitoring device body is in radio connection with an external alarm and a control host, and first fixing rods are symmetrically and fixedly connected to the periphery of the top of the box body;
a protective pad is arranged on one side, close to the box body, of the first fixing rod, first grooves are formed in two sides of the first fixing rod, and a movable plate is arranged in the middle of each first groove;
a second groove is formed in the middle of the movable plate, a second fixing rod is arranged in the middle of the second groove, and an extrusion block is arranged at the top of the movable plate;
the top of extrusion piece is provided with the dwang, the top fixedly connected with carousel of dwang, the fixed cover in top of dwang is equipped with the limiting plate.
In a preferred embodiment, the early warning monitoring device body is electrically connected with the wind pressure detector and the wind speed detector, the width of the movable plate is the same as that of the first fixed rod, the thickness of the movable plate is matched with the width of the inner cavity of the first groove, sliding grooves are symmetrically formed in two sides of the inner cavity of the first groove, two ends of the second fixed rod extend to the inside of the sliding grooves, the extrusion block is arranged inside the sliding grooves, the length of the inner cavity of the first groove is larger than that of the inner cavity of the sliding grooves, a threaded groove is formed in the inner cavity of the extrusion block, one end of the rotating rod extends to the middle of the extrusion block, a threaded block is fixedly connected to one end of the rotating rod, which is far away from the rotary disk, the threaded block is arranged in the middle of the extrusion block, the wall of the threaded block is in threaded connection with the inner cavity wall of the extrusion block, and a limit groove matched with the limit plate is formed in the top of the inner cavity of the sliding grooves, the dwang runs through the top of first dead lever, the limiting plate sets up the inside at the spacing groove, the carousel sets up the top at first dead lever.
The utility model discloses a technological effect and advantage:
1. the utility model discloses at first detect the wind pressure of pipeline inside through the wind pressure detector, detect the wind speed of pipeline inside through the wind speed detector to judge whether the pipeline blocks up according to the size of wind pressure and wind speed, and through the wind pressure crescent, the wind speed reduces gradually, can send information to inside alarm and the main control system through the early warning monitoring facilities body, block up the early warning to corresponding pipeline, thereby realize the effect of monitoring, conveniently carry out accurate maintenance and maintenance to the pipeline, improve the result of use;
2. the utility model discloses still through running through the aperture inside of perforated plate with first dead lever, then shift out the both ends of fly leaf from the inside of first recess, make the fly leaf perpendicular with first dead lever, can carry out preliminary installation fixed to the box, then rotate the carousel, make the extrusion piece extrude the fly leaf, can accomplish installation and fixed, improve fixed effect, facilitate the installation and use, improve work efficiency;
to sum up, through the above-mentioned interact of a plurality of effects, can conveniently carry out accurate maintenance and maintenance to the pipeline, the easy to assemble dismantlement improves fixed effect and work efficiency.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention.
Fig. 2 is a schematic diagram of a partial enlarged structure at a in fig. 1 according to the present invention.
Fig. 3 is a schematic side view of the first fixing rod of the present invention.
Fig. 4 is a schematic structural view of the rotating rod and the extrusion block of the present invention.
The reference signs are: 1. a box body; 2. a wind pressure detector; 3. a wind speed detector; 4. an early warning monitoring device body; 5. a first fixing lever; 6. a protective pad; 7. a first groove; 8. a movable plate; 9. a second groove; 10. a second fixing bar; 11. extruding the block; 12. rotating the rod; 13. a turntable; 14. a limiting plate; 15. a chute; 16. a thread block.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
The ventilation pipeline blockage early warning and monitoring equipment shown in the attached figures 1-4 comprises a box body 1, wherein an early warning and monitoring equipment body 4 is arranged in the middle of the box body 1, a wind pressure detector 2 is arranged at the bottom of the box body 1, wind speed detectors 3 are symmetrically arranged on two sides of the box body 1, the early warning and monitoring equipment body 4 is in radio connection with an external alarm and a control host, and first fixing rods 5 are symmetrically and fixedly connected to the periphery of the top of the box body 1;
a protective pad 6 is arranged on one side, close to the box body 1, of the first fixing rod 5, first grooves 7 are formed in two sides of the first fixing rod 5, and a movable plate 8 is arranged in the middle of each first groove 7;
a second groove 9 is formed in the middle of the movable plate 8, a second fixed rod 10 is arranged in the middle of the second groove 9, and a squeezing block 11 is arranged at the top of the movable plate 8;
the top of extrusion piece 11 is provided with dwang 12, the top fixedly connected with carousel 13 of dwang 12, and the fixed cover in top of dwang 12 is equipped with limiting plate 14.
As shown in the attached figures 1-4, the early warning monitoring device body 4 is electrically connected with the wind pressure detector 2 and the wind speed detector 3, the width of the movable plate 8 is the same as the width of the first fixing rod 5, the thickness of the movable plate 8 is matched with the width of the inner cavity of the first groove 7, sliding grooves 15 are symmetrically formed in two sides of the inner cavity of the first groove 7, two ends of the second fixing rod 10 extend into the sliding grooves 15, the extrusion block 11 is arranged inside the sliding grooves 15, the length of the inner cavity of the first groove 7 is larger than that of the sliding grooves 15, a threaded groove is formed in the inner cavity of the extrusion block 11, one end of the rotating rod 12 extends to the middle of the extrusion block 11, one end of the rotating rod 12, far away from the rotating disk 13, is fixedly connected with a threaded block 16, the threaded block 16 is arranged in the middle of the extrusion block 11, the wall body of the threaded block 16 is in threaded connection with the inner cavity wall body of the extrusion block 11, a limiting groove matched with the limiting plate 14 is formed in the top of the inner cavity of the sliding grooves 15, the rotating rod 12 penetrates through the top end of the first fixing rod 5, the limiting plate 14 is arranged inside the limiting groove, the rotary disc 13 is arranged at the top of the first fixing rod 5, so that the wind pressure inside the pipeline can be detected through the wind pressure detector 2, the wind speed inside the pipeline can be detected through the wind speed detector 3, whether the pipeline is blocked or not can be judged according to the wind pressure and the wind speed, the wind speed is gradually increased and reduced, information can be sent to the inside of the alarm and the control host through the early warning monitoring equipment body 4, early warning is carried out on the blockage of the corresponding pipeline, the monitoring effect is realized, the pipeline can be conveniently and accurately maintained and overhauled, the using effect is improved, the first fixing rod 5 penetrates through the inner part of the small hole of the porous plate, then the two ends of the movable plate 8 are moved out of the first groove 7, the movable plate 8 is perpendicular to the first fixing rod 5, and the box body 1 can be preliminarily installed and fixed, then, the rotary table 13 is rotated to enable the extrusion block 11 to extrude the movable plate 8, so that installation and fixation can be completed, the fixing effect is improved, the use is convenient, and the working efficiency is improved.
The utility model discloses the theory of operation: when the air outlet porous plate of the ventilating duct is used, only the air outlet porous plate of the ventilating duct needs to be disassembled, the box body 1 is placed on one side of the porous plate, the first fixing rod 5 penetrates through the small hole in the surface of the porous plate, the box body 1 is positioned in the middle of one side of the porous plate, one end of the movable plate 8 is then pushed, two ends of the movable plate 8 are moved out from the inside of the first groove 7 until the movable plate 8 is perpendicular to the first fixing rod 5, the wall body of the movable plate 8 is attached to the wall body of the porous plate, the initial installation of the box body 1 can be completed, the rotary disc 13 is then rotated, the threaded block 16 is driven to rotate through the rotary bar 12, the extrusion block 11 is moved inside the sliding groove 15, the movable plate 8 is extruded until the movable plate 8 extrudes the porous plate, the fixing of the box body 1 can be completed, at the moment, the second fixing rod 10 can slide inside the sliding groove 15, and the flexibility of the movable plate 8 is improved, thereby completing the installation of the box body 1 and improving the working efficiency;
then, one side of the porous plate close to the box body 1 faces the ventilating duct, and the porous plate is arranged at one end of an air outlet of the ventilating duct;
then start through control host computer control early warning monitoring facilities body 4, can the inside wind pressure and the wind speed of real-time supervision air pipe through wind pressure detector 2 and wind speed detector 3, great gradually as the wind pressure, when the wind speed reduces gradually, can detect through early warning monitoring facilities body 4 that the pipeline is stifled to inside sending information to the control host computer, realize real-time supervision, can carry out the early warning through the alarm simultaneously, improve the result of use.
The points to be finally explained are: first, in the description of the present application, it should be noted that, unless otherwise specified and limited, the terms "mounted," "connected," and "connected" should be understood broadly, and may be a mechanical connection or an electrical connection, or a communication between two elements, and may be a direct connection, and "upper," "lower," "left," and "right" are only used to indicate a relative positional relationship, and when the absolute position of the object to be described is changed, the relative positional relationship may be changed;
secondly, the method comprises the following steps: in the drawings of the disclosed embodiments of the present invention, only the structures related to the disclosed embodiments are referred to, and other structures can refer to the common design, and under the condition of no conflict, the same embodiment and different embodiments of the present invention can be combined with each other;
and finally: the above description is only for the preferred embodiment of the present invention and should not be taken as limiting the invention, and any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (6)

1. The utility model provides a ventilation pipe blocks up early warning monitoring facilities, includes box (1), its characterized in that: the wind speed monitoring box is characterized in that an early warning monitoring device body (4) is arranged in the middle of the box body (1), a wind pressure detector (2) is arranged at the bottom of the box body (1), wind speed detectors (3) are symmetrically arranged on two sides of the box body (1), the early warning monitoring device body (4) is in wireless connection with an external alarm and a control host, and first fixing rods (5) are symmetrically and fixedly connected to the periphery of the top of the box body (1);
a protective pad (6) is arranged on one side, close to the box body (1), of the first fixing rod (5), first grooves (7) are formed in two sides of the first fixing rod (5), and a movable plate (8) is arranged in the middle of each first groove (7);
a second groove (9) is formed in the middle of the movable plate (8), a second fixed rod (10) is arranged in the middle of the second groove (9), and a squeezing block (11) is arranged at the top of the movable plate (8);
the top of extrusion piece (11) is provided with dwang (12), the top fixedly connected with carousel (13) of dwang (12), the fixed cover in top of dwang (12) is equipped with limiting plate (14).
2. The ventilation duct blockage early warning and monitoring device according to claim 1, characterized in that: early warning monitoring facilities body (4) are connected with wind pressure detector (2) and wind speed detector (3) electricity, the width of fly leaf (8) is the same with the width of first dead lever (5), the thickness of fly leaf (8) and the inner chamber width looks adaptation of first recess (7).
3. The ventilation duct blockage early warning and monitoring device according to claim 1, characterized in that: the inner cavity bilateral symmetry of first recess (7) has seted up spout (15), the both ends of second dead lever (10) extend to the inside of spout (15), extrusion piece (11) set up the inside at spout (15).
4. The ventilation duct blockage early warning and monitoring device according to claim 1, characterized in that: the inner chamber length of first recess (7) is greater than the inner chamber length of spout (15), the inner chamber of extrusion piece (11) is provided with the thread groove, the one end of dwang (12) extends to the middle part of extrusion piece (11).
5. The ventilation duct blockage early warning and monitoring device according to claim 1, characterized in that: dwang (12) are kept away from one end fixedly connected with screw block (16) of carousel (13), screw block (16) set up the middle part at extrusion piece (11), the wall body of screw block (16) and the inner chamber wall body threaded connection of extrusion piece (11).
6. The ventilation duct blockage early warning and monitoring device according to claim 4, characterized in that: the limiting groove with limiting plate (14) looks adaptation is seted up at the inner chamber top of spout (15), dwang (12) run through the top of first dead lever (5), limiting plate (14) set up the inside at the limiting groove, carousel (13) set up the top at first dead lever (5).
CN202221207550.7U 2022-05-18 2022-05-18 Ventilation pipeline blocks up early warning monitoring facilities Active CN217424442U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221207550.7U CN217424442U (en) 2022-05-18 2022-05-18 Ventilation pipeline blocks up early warning monitoring facilities

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221207550.7U CN217424442U (en) 2022-05-18 2022-05-18 Ventilation pipeline blocks up early warning monitoring facilities

Publications (1)

Publication Number Publication Date
CN217424442U true CN217424442U (en) 2022-09-13

Family

ID=83187271

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221207550.7U Active CN217424442U (en) 2022-05-18 2022-05-18 Ventilation pipeline blocks up early warning monitoring facilities

Country Status (1)

Country Link
CN (1) CN217424442U (en)

Similar Documents

Publication Publication Date Title
CN110067764B (en) Remote switching and intelligent regulation and control device for local ventilator of coal mine and control method
CN217424442U (en) Ventilation pipeline blocks up early warning monitoring facilities
CN108681357A (en) A kind of temperature and humidity controlsystem and control method of substation control buildings
CN114995272A (en) Intelligent centralized control system and method for blasting and air exhaust in tunnel construction
CN205582222U (en) Long -range failure alarm system supplies water
CN106969968A (en) Metal roofing board wind resistance takes off detecting system
CN107081233A (en) A kind of color steel tile processes paint spraying apparatus
CN108939352A (en) A kind of bus main cabin fixed fire extinguishing system with long-range monitoring function
CN209844277U (en) Make things convenient for on-spot electrical control cabinet structure of maintaining
CN109590346B (en) Forming control device of aluminum profile die
CN208606343U (en) A kind of gearing tier building air conditioning power monitoring device
CN218033605U (en) Intelligent control system for energy conservation of central air conditioner
CN208969072U (en) A kind of atmospheric environmental parameters acquisition device based on GPRS
CN204100475U (en) Workshop automatic ventilation equipment
CN209230884U (en) Detection device for disposable PVC glove
CN219682087U (en) Safety monitoring device for intelligent engineering
CN209310150U (en) A kind of fixed device of easy-to-mount hanging outdoor unit of air conditioner
CN207908442U (en) A kind of transformer oil chromatographic on-Line Monitor Device
CN214535190U (en) Wisdom is wisdom energy device for piping lane
CN217100758U (en) Cleaning device of shell pressing machine
CN207315619U (en) A kind of skid type combined type internet energy-saving air compressor station
CN206132608U (en) SF6 on -line monitoring warning optimizing system
CN212372083U (en) Multi-station device for detecting vacuum state of manipulator
CN214166447U (en) Air tightness detection device for fire-fighting equipment
CN211553724U (en) Float glass defect recognition device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240122

Address after: Room 304, Building 4, Shangcheng International Garden, Yushan Town, Kunshan City, Suzhou City, Jiangsu Province, 215300

Patentee after: Xia Yihao

Country or region after: China

Address before: No. 401, 4th Floor, Building 1, No. 88, Jinshui East Road, Zhengzhou Area (Zhengdong), Pilot Free Trade Zone, Zhengzhou City, Henan Province, 450000

Patentee before: Henan Riyue Environmental Technology Co.,Ltd.

Country or region before: China

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240329

Address after: Room 2, 3rd Floor, No. 165 Yucheng South Road, Yushan Town, Kunshan City, Suzhou City, Jiangsu Province, 215300

Patentee after: Kunshan Shengang Construction and Installation Engineering Co.,Ltd.

Country or region after: China

Address before: Room 304, Building 4, Shangcheng International Garden, Yushan Town, Kunshan City, Suzhou City, Jiangsu Province, 215300

Patentee before: Xia Yihao