CN217423751U CN202123405537.0U CN202123405537U CN217423751U CN 217423751 U CN217423751 U CN 217423751U CN 202123405537 U CN202123405537 U CN 202123405537U CN 217423751 U CN217423751 U CN 217423751U
Authority
CN
China
Prior art keywords
wall
main part
water pump
cooler bin
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202123405537.0U
Other languages
Chinese (zh)
Inventor
薛淋兵
周辰婓
杜莹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuxi Xitang Nuclear Equipment Co ltd
Original Assignee
Wuxi Xitang Nuclear Equipment Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuxi Xitang Nuclear Equipment Co ltd filed Critical Wuxi Xitang Nuclear Equipment Co ltd
Priority to CN202123405537.0U priority Critical patent/CN217423751U/en
Application granted granted Critical
Publication of CN217423751U publication Critical patent/CN217423751U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a chemical industry technology tower, including base, intake pipe, heating cabinet, cooler bin and blast pipe, the main part is installed at the top of base, the heating cabinet is installed to the inner wall of main part, the cooler bin is installed to the inside roof of main part, the inductor is installed to the bottom of cooler bin, the guard box is installed to the outer wall of main part. The utility model discloses an install heating cabinet and cooler bin and can adjust the temperature, when temperature variation in the tower, the inside thermal energy gas of packing of inductor begins the inflation, the thermal energy gas all is located one side of closing plate, the trigger bar contacts with the switch, the switch is opened, first water pump begins work afterwards, inside first water pump pumped the coolant liquid of cooler bin inside to the cooler bin, realize cooling function, when needs heat, heating wire and electric plate begin to give off the heat, the fan drives the air flow, make the hot-air enter into the inside of main part through the louvre, realize temperature regulation function.

Description

Chemical process tower
Technical Field
The utility model relates to a chemical tower technical field specifically is a chemical industry technology tower.
Background
The tower equipment is one of important equipment in the production of petroleum, chemical industry, medicine, light industry and the like, gas-liquid or liquid-liquid two phases can be fully contacted in the tower equipment to implement interphase mass transfer, so that the common tower equipment is used for unit operation processes of rectification, absorption, desorption, gas humidification, cooling and the like in the production process, the chemical tower is one of the common chemical equipment, and is specifically divided into a spray tower, a purification tower, a reaction tower and the like according to different use requirements.
The existing chemical tower has the following defects:
patent document CN112304111A discloses a cooling tower for chemical production, the right item of protection "includes the cooling tower body, the four sides of cooling tower body all are seted up flutedly, the inside of four recesses all is provided with heating panel and sealing washer, the middle part on cooling tower body four sides all is provided with fixed establishment, four fixed establishment by the fixed block, bolt and L shape pole are constituteed, one side on cooling tower body top is provided with oral siphon and valve, the positive and equal fixed mounting in middle part at the back in cooling tower body top has the fan. This kind of cooling tower for chemical production, through heat dissipation mechanism, make people can pass through the rotation of control motor output shaft, make the threaded rod can drive adjustable shelf and feed cylinder and reciprocate, when adjustable shelf and feed cylinder rebound, water in adjustable shelf and the feed cylinder can discharge through a plurality of round hole, form the cascade, increase the area of contact of water and wind, accelerate the heat dissipation of water, the radiating efficiency has been promoted, and through the heating panel, accelerated the efficiency that the inside heat of cooling tower body gived off to the external world, but the temperature environment in the tower can not be adjusted to its device, it is not convenient enough.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a chemical industry technology tower to solve the problem that lacks the temperature regulation function that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: a chemical process tower comprises a base, an air inlet pipe, a heating box, a cooling box and an exhaust pipe, wherein a main body is installed at the top of the base, and the heating box is installed on the inner wall of the main body;
the heating box is characterized in that a fan is installed on the inner top wall of the heating box, a heating plate is installed on the inner wall of the heating box, an electric heating wire is installed on the inner wall of the heating plate, and a plurality of heat dissipation holes are formed in the inner bottom wall of the heating box;
the cooling box is installed to the inside roof of main part, the inductor is installed to the bottom of cooling box, the guard box is installed to the outer wall of main part, the intake pipe is installed to the outer wall of main part, the blast pipe is installed at the top of main part.
Preferably, the buckler is installed to the inside diapire of cooler bin, and first water pump is installed to the inside diapire of buckler, and the inlet tube is installed to the input of first water pump, and the outer wall of buckler is extended to the one end of inlet tube, and the outlet pipe is installed to the output of first water pump, and the bottom of cooler bin is extended to the one end of outlet pipe, and the cooling tube is installed to the inner wall of main part, and the one end of cooling tube goes out water piping connection with first water pump, and the other end of cooling tube extends into the inside of cooler bin.
Preferably, the closing plate is installed to the inner wall of inductor, and the trigger bar is installed to the outer wall of closing plate, and the trigger bar runs through the inside of closing plate, and the switch is all installed to the both sides inner wall of inductor, and just two sets of switches pass through wire electric connection with fan, first water pump respectively.
Preferably, a plurality of observation windows are installed at an outer wall of the main body.
Preferably, a plurality of shunt tubes are installed at one end of the air inlet pipe, and exhaust valves are installed on the outer walls of the shunt tubes.
Preferably, the second water pump is installed to the inside diapire of guard box, and the input of second water pump extends into the inside of main part, and the spray pipe is installed to the output of second water pump, and the spray pipe extends into the inside of main part.
Preferably, two sets of fly leaves are installed to the inner wall of blast pipe, and the sealing washer is installed to the inner wall of blast pipe, and the back mounted of blast pipe has the motor, and the output of motor extends into the inside of blast pipe, and the output of motor is installed and is received the spool, and receives the spool and pass through the cable with the fly leaf and be connected.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses an install heating cabinet and cooler bin and can adjust the temperature, when the temperature variation in the tower, the thermal energy gas that inductor inside was filled begins to expand, the thermal energy gas all is located one side of closing plate, the thermal energy gas drives the closing plate and moves, the closing plate drives the trigger bar and moves, then the trigger bar contacts with the switch, the switch is opened, first water pump begins work afterwards, first water pump pumps the coolant liquid inside the cooler bin to the inside of cooler bin, then the coolant liquid gets back to the cooler bin after absorbing the heat, realize the cooling function, when needing to heat, the fan starts, heating wire and electric plate begin to distribute the heat, the fan drives the air flow, make hot-air enter into the inside of main part through the louvre, realize the temperature regulation function;
2. the utility model discloses an install the blast pipe and can adjust the amount of wind, when adjusting the displacement, starter motor, motor rotate and drive the receipts spool and rotate, receive the spool and rotate and drive the cable shrink, the cable shrink drives the fly leaf and rotates to the exhaust aperture of adjustment blast pipe realizes adjusting the function of displacement.
Drawings
Fig. 1 is a schematic view of the appearance structure of the present invention;
fig. 2 is a schematic front view of the structure of the present invention;
FIG. 3 is a schematic view of a part of the structure of the inductor of the present invention;
fig. 4 is a schematic structural view of a top view portion of the exhaust valve of the present invention.
In the figure: 1. a base; 101. a main body; 102. an observation window; 2. an air inlet pipe; 201. a shunt tube; 202. an exhaust valve; 3. a protection box; 301. a second water pump; 302. a spray tube; 4. a heating box; 401. a fan; 402. heating the plate; 5. a cooling tank; 501. a waterproof shell; 502. a first water pump; 503. a cooling tube; 6. an inductor; 601. a sealing plate; 602. a trigger lever; 603. a switch; 7. an exhaust pipe; 701. a movable plate; 702. a motor; 703. and (4) taking up the spool.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "front end", "rear end", "both ends", "one end", "the other end" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element to which the reference is made must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first" and "second" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it should be noted that, unless explicitly stated or limited otherwise, the terms "mounted," "disposed," "connected," and the like are to be construed broadly, such as "connected," which may be a fixed connection, a detachable connection, or an integral connection; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood as a specific case by those skilled in the art.
Example 1: referring to fig. 2 and 3, a chemical process tower comprises a base 1, an air inlet pipe 2, a heating box 4, a cooling box 5 and an exhaust pipe 7, wherein a main body 101 is installed at the top of the base 1, the heating box 4 is installed on the inner wall of the main body 101, a fan 401 is installed on the top wall inside the heating box 4, a heating plate 402 is installed on the inner wall of the heating box 4, heating wires are installed on the inner wall of the heating plate 402, a plurality of heat dissipation holes are formed in the bottom wall inside the heating box 4, the cooling box 5 is installed on the top wall inside the main body 101, an inductor 6 is installed at the bottom of the cooling box 5, a protection box 3 is installed on the outer wall of the main body 101, the air inlet pipe 2 is installed on the outer wall of the main body 101, the exhaust pipe 7 is installed at the top of the main body 101, a waterproof case 501 is installed on the bottom wall inside the cooling box 5, a first water pump 502 is installed on the bottom wall inside the waterproof case 501, an input end of the first water pump 502 is installed with a water inlet pipe, and one end of the water inlet pipe extends out of the outer wall of the waterproof case 501, the output end of the first water pump 502 is provided with a water outlet pipe, one end of the water outlet pipe extends out of the bottom of the cooling box 5, the inner wall of the main body 101 is provided with a cooling pipe 503, one end of the cooling pipe 503 is connected with the water outlet pipe of the first water pump 502, the other end of the cooling pipe 503 extends into the cooling box 5, the inner wall of the inductor 6 is provided with a sealing plate 601, the outer wall of the sealing plate 601 is provided with a trigger rod 602, the trigger rod 602 penetrates through the inside of the sealing plate 601, the inner walls of the two sides of the inductor 6 are provided with switches 603, the two sets of switches 603 are respectively and electrically connected with the fan 401 and the first water pump 502 through conducting wires, when the temperature in the tower changes, the thermal expansion gas filled in the inductor 6 begins to expand, the thermal expansion gas is positioned at one side of the sealing plate 601, the thermal expansion gas drives the sealing plate 601 to move, the sealing plate 601 drives the trigger rod 602 to move, and then the trigger rod 602 is contacted with the switch 603, switch 603 is opened, and first water pump 502 begins work afterwards, and inside first water pump 502 pumped the inside coolant liquid of cooler bin 5 to cooling tube 503, and in the cooler bin 5 was got back to after the coolant liquid absorbed the heat afterwards, the realization cooling function, when needs heat, fan 401 started, and heating wire and hot plate 402 begin to give off the heat, and fan 401 drives the air current for the inside of hot-air entering main part 101 through the louvre realizes the temperature regulation function.
Example 2: referring to fig. 1 and 2, a chemical process tower, a plurality of observation windows 102 are installed on an outer wall of a main body 101, a plurality of shunt pipes 201 are installed at one end of an air inlet pipe 2, an exhaust valve 202 is installed on an outer wall of the shunt pipes 201, a second water pump 301 is installed on an inner bottom wall of a protection box 3, an input end of the second water pump 301 extends into the main body 101, a spray pipe 302 is installed at an output end of the second water pump 301, the spray pipe 302 extends into the main body 101, exhaust gas is discharged into the shunt pipes 201 from the air inlet pipe 2, the exhaust valve 202 is opened, the exhaust gas enters into the main body 101, the second water pump 301 is started, the second water pump 301 pumps purification liquid in the main body 101 into the spray pipe 302, the exhaust gas is sprayed, and the purification function of the exhaust gas is achieved.
Example 3: referring to fig. 2 and 4, in a chemical process tower, two sets of movable plates 701 are installed on an inner wall of an exhaust pipe 7, a sealing ring is installed on the inner wall of the exhaust pipe 7, a motor 702 is installed on a back surface of the exhaust pipe 7, an output end of the motor 702 extends into the exhaust pipe 7, a take-up shaft 703 is installed on an output end of the motor 702, the take-up shaft 703 is connected with the movable plates 701 through a cable, when the air displacement is adjusted, the motor 702 is started, the motor 702 rotates to drive the take-up shaft 703 to rotate, the take-up shaft 703 rotates to drive the cable to contract, and the cable contracts to drive the movable plates 701 to rotate, so that the air displacement of the exhaust pipe 7 is adjusted, and the function of adjusting the air displacement is realized.
The working principle is that when the temperature in the tower changes, the thermal expansion gas filled in the inductor 6 starts to expand and is located on one side of the sealing plate 601, the thermal expansion gas drives the sealing plate 601 to move, the sealing plate 601 drives the trigger rod 602 to move, then the trigger rod 602 contacts with the switch 603, the switch 603 is turned on, then the first water pump 502 starts to work, the first water pump 502 pumps the cooling liquid in the cooling box 5 to the cooling pipe 503, then the cooling liquid absorbs heat and returns to the cooling box 5 to realize the cooling function, when heating is needed, the fan 401 is started, the heating wires and the heating plate 402 start to emit heat, the fan 401 drives air to flow, so that the hot air enters the inside of the main body 101 through the heat dissipation holes to realize the temperature regulation function, when the exhaust amount is regulated, the motor 702 is started, the motor 702 rotates to drive the take-up shaft 703 to rotate to drive the cable to contract, the contraction of the cable drives the movable plate 701 to rotate, so that the exhaust aperture of the exhaust pipe 7 is adjusted, and the function of adjusting the exhaust amount is realized.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (7)

1. The utility model provides a chemical industry technology tower, includes base (1), intake pipe (2), heating cabinet (4), cooler bin (5) and blast pipe (7), its characterized in that: the top of the base (1) is provided with a main body (101), and the inner wall of the main body (101) is provided with a heating box (4);
a fan (401) is mounted on the top wall of the interior of the heating box (4), a heating plate (402) is mounted on the inner wall of the heating box (4), an electric heating wire is mounted on the inner wall of the heating plate (402), and a plurality of heat dissipation holes are formed in the bottom wall of the interior of the heating box (4);
cooling box (5) are installed to the inside roof of main part (101), inductor (6) are installed to the bottom of cooling box (5), guard box (3) are installed to the outer wall of main part (101), intake pipe (2) are installed to the outer wall of main part (101), blast pipe (7) are installed at the top of main part (101).
2. A chemical process tower according to claim 1, wherein: waterproof shell (501) are installed to the inside diapire of cooler bin (5), first water pump (502) are installed to the inside diapire of waterproof shell (501), the inlet tube is installed to the input of first water pump (502), and the outer wall of waterproof shell (501) is extended to the one end of inlet tube, the outlet pipe is installed to the output of first water pump (502), and the one end of outlet pipe extends the bottom of cooler bin (5), cooling tube (503) are installed to the inner wall of main part (101), the one end of cooling tube (503) and the water piping connection of first water pump (502), the other end of cooling tube (503) extends into the inside of cooler bin (5).
3. A chemical process tower according to claim 1, wherein: sealing plate (601) is installed to the inner wall of inductor (6), and trigger bar (602) is installed to the outer wall of sealing plate (601), and trigger bar (602) run through the inside of sealing plate (601), and switch (603) are all installed to the both sides inner wall of inductor (6), and two sets of switch (603) pass through wire electric connection with fan (401), first water pump (502) respectively.
4. A chemical process tower according to claim 1, wherein: a plurality of observation windows (102) are installed on the outer wall of the main body (101).
5. A chemical process tower according to claim 1, wherein: a plurality of shunt tubes (201) are installed to the one end of intake pipe (2), and discharge valve (202) are installed to the outer wall of shunt tubes (201).
6. A chemical process tower according to claim 1, wherein: second water pump (301) is installed to the inside diapire of guard box (3), and the input of second water pump (301) extends into the inside of main part (101), and spray pipe (302) are installed to the output of second water pump (301), and spray pipe (302) extend into the inside of main part (101).
7. A chemical process tower according to claim 1, wherein: two sets of fly leaf (701) are installed to the inner wall of blast pipe (7), and the sealing washer is installed to the inner wall of blast pipe (7), and the back mounted of blast pipe (7) has motor (702), and the output of motor (702) extends into the inside of blast pipe (7), and take-up shaft (703) are installed to the output of motor (702), and take-up shaft (703) pass through the cable with fly leaf (701) and be connected.
CN202123405537.0U 2021-12-30 2021-12-30 Chemical process tower Active CN217423751U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202123405537.0U CN217423751U (en) 2021-12-30 2021-12-30 Chemical process tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202123405537.0U CN217423751U (en) 2021-12-30 2021-12-30 Chemical process tower

Publications (1)

Publication Number Publication Date
CN217423751U true CN217423751U (en) 2022-09-13

Family

ID=83174191

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202123405537.0U Active CN217423751U (en) 2021-12-30 2021-12-30 Chemical process tower

Country Status (1)

Country Link
CN (1) CN217423751U (en)

Similar Documents

Publication Publication Date Title
CN102299491A (en) Vapor chamber for heat radiation of large-current switch cabinet
CN211813433U (en) Oxygenerator with heat dissipation mechanism
GB2596885A (en) Novel container generator set capable of automatically cooling
CN112018639A (en) Switchboard capable of adjusting size of heat dissipation hole based on principle of thermal expansion and cold contraction
CN217423751U (en) Chemical process tower
CN114182844A (en) Anticorrosion structure of building outer wall and construction method thereof
CN111107694B (en) LED driving power supply with strong heat dissipation performance
CN112489947B (en) Multifunctional automatic transformer
CN212231945U (en) Auxiliary cooling experimental device for physical experiment
CN210536533U (en) Production waste heat recovery cyclic utilization device
CN210321185U (en) Portable rotary tube furnace
CN209545363U (en) A kind of motor with intelligent cooling structure
CN210464118U (en) Novel circulating air cooler
CN210111417U (en) Environmental protection comprehensive distribution box
CN209196992U (en) Integrated new energy heating plant for building
CN2311728Y (en) High-temperature air heating blowing defreezing device
CN202121225U (en) Soaking plate applicable to dissipating heat of high-current switch cabinet
CN217129803U (en) High-frequency heating equipment for hydrogen pump gear
CN110671283A (en) Gravity heat pipe type cooling device for wind driven generator
CN220272285U (en) Evaporation cooling type transformer
CN2644988Y (en) Solar energy - air evaporator
CN218206932U (en) Adjustable high-capacity new energy wind turbine generator
CN217979289U (en) Water heater water tank integrated with condenser and novel air energy water heater
CN112038947B (en) High-efficient radiating electric power cabinet
CN216523202U (en) Energy-saving and environment-friendly water vector power cooling tower

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant